Drinking Water Supply and Sanitation Government Departments Closing in 0 days TDR #24449405

Annual Rate Contract For Removing Of Leakage/Choking In Difference Size Of Pipe Line Under Phed Sub Div . Nawalgarh

Issued by Government Departments · Nawalgarh, Rajasthan
Tender Value
10 Lakhs
Estimated cost
Bid Submission
15 Jun 2020
0 days left
EMD
20000
Bank guarantee accepted
Document Fee
500
Non-refundable
Tender Type
Online

Tender Overview

Competition Type
NCB
Bidding Type
Tender
Location / State
Nawalgarh → Rajasthan
EMD Exemption
Not Available
Quantity
Not Available

Project Description

Annual Rate Contract For Removing Of Leakage / Choking In Difference Size Of Pipe Line Under Phed Sub Div . Nawalgarh

BOQ

Name of WORK “RATE CONTRACT FOR REMOVING OF LEAKAGE/CHOKING IN DIFFERENCE SIZE OF PIPE LINE UNDER PHED SUB DN Nawalgarh”
Sl.No.Item DescriptionItem Code / MakeQuantityUnits
11Repairing of leakage in existing Distribution/Rising Main/Transmission Main AC/PVC/HDPE pipe line up to 1.5 mtr depth of sizes as given below by digging out suitable size of pit at site of work including dewatering and providing adequate safety arrangement at site. This will also include cutting of pipe ends, fixing of pipe piece with jointing material to make repair leak proof and then refill the pit from excavated sand by ramming it at sides of pipe & upto ground level for entire job contractor will use his own T&P & labour and will arrange transportation of material required from store. (Required material such as pipe piece, CID Joints shall be provided by Department free of cost)
21.01In all type Soil AC/PVC/HDPE pipe
31.0250/63/75mm1Each
41.0380/90mm1Each
51.04100/110mm1Each
61.06125/140mm1Each
71.07150/160/180mm1Each
81.08200/225mm1Each
91.09250/280mm1Each
101.1300/315mm1Each
111.11350mm1Each
121.12400mm1Each
131.13Add on above item no. 1 for B.T. Road = 5%
141.14Add on above item no. 1 for C.C. Road = 10%
151.15Add on above no. 1 item if depth of pipeline is above 1.5 mtr and up to 3.0 mtr. = 20%
161.16Add on above no. 1 item if depth of pipeline is above 3.0 mtr.= 30%
172Repairing of leakage in existing Distribution/Rising Main/Transmission Main CI/MS/DI pipe line up to 1.5 mtr depth of sizes as given below by digging out suitable size of pit at site of work including dewatering and providing adequate safety arrangement at site. This will also include cutting of pipe ends, fixing of pipe piece with jointing material to make repair leak proof and then refill the pit from excavated sand by ramming it at sides of pipe & upto ground level for entire job contractor will use his own T&P & labour and will arrange transportation of required material from store. (Required material such as pipe piece CID Joints shall be provided by Department free of cost)
182.01In all type Soil
192.0280mm1Each
202.03100mm1Each
212.04125mm1Each
222.05150mm1Each
232.06200mm1Each
242.07250mm1Each
252.08300mm1Each
262.09350mm1Each
272.1400mm1Each
282.11Add on above item no. 2 for B.T. Road = 5%
292.12Add on above item no. 2 for C.C. Road = 10%
302.13Add on above no. 2 item if depth of pipeline is above 1.5 mtr and up to 3.0 mtr. = 20%
312.14Add on above no. 2 item if depth of pipeline is above 3.0 mtr. = 30%
323Minor repair of leakages such as lead caulking, plugging, clamping and ring fixing in existing Distribution/Rising Main/Transmission Main AC/PVC/HDPE/CI/MS/DI pipe line up to 1.5 mtr depth of sizes as given below by digging out suitable size of pit at site of work including dewatering and providing adequate safety arrangement at site to make repair leak proof and then refill the pit from excavated sand by ramming it at sides of pipe & upto ground level for entire job contractor will use his own T&P & labour and will arrange transportation of required material from store. (Required material such as lead wool, white hump, plugs, clamps etc. shall be provided by Department free of cost)
333.01In all type Soil
343.0250/63/75mm1Each
353.0380/90mm1Each
363.04100/110mm1Each
373.05125/140mm1Each
383.06150/160/180mm1Each
393.07200/225mm1Each
403.08250/280mm1Each
413.09300/315mm1Each
423.1350mm1Each
433.11400mm1Each
443.12Add on above item no. 3 for B.T. Road = 5%
453.13Add on above item no. 3 for C.C. Road = 10%
463.14Add on above no. 3 item if depth of pipeline is above 1.5 mtr and up to 3.0 mtr. = 20%
473.15Add on above no. 3 item if depth of pipeline is above 3.0 mtr. = 30%
484Replacement of CI/ DI Double flange sluice valves,non return valves,butter fly valves etc. in existing Distribution/Rising Main/Transmission Main pipe line up to 1.5 mtr depth of sizes as given below by digging out suitable size of pit at site of work including providing and fixing MS Nut and Bolt and rubber gasket, dewatering and providing adequate safety arrangement at site and then refill the pit from excavated sand by ramming it at sides of pipe & upto ground level for entire job contractor will use his own T&P & labour and will arrange transportation of required material from store. (Required material such as Valve, Tail piece, CID Joints etc. shall be provided by Department free of cost)
494.01In all type Soil
504.0280 mm1Each
514.03100 mm1Each
524.04125 mm1Each
534.05150 mm1Each
544.06200 mm1Each
554.07250 mm1Each
564.08300 mm1Each
574.09350 mm1Each
584.1400 mm1Each
594.11Add on above item no. 4 for B.T. Road = 5%
604.12Add on above item no. 4 for CC Road = 10%
614.13Add on above item no. 4 if depth of pipe line is above 1.5 mtr to 3.0 mtr = 20%
624.14Deduct on above item no. 4 if valve is fixed at plinth level / platform i.e. no excavation is required = 20%
635Removal of Choking from pipe line, including tree roots, malba, sand and other by manually or other means, cleaning of line and testing in existing Distribution/Rising Main/Transmission Main AC/PVC/HDPE/uPVC pipe line up to 1.5 mtr depth of sizes as given below by digging out suitable size of pit at site of work including dewatering and providing adequate safety arrangement at site. This will also include cutting of pipe ends, fixing of pipe piece with jointing material and then refill the pit from excavated sand by ramming it at sides of pipe & upto ground level for entire job contractor will use his own T&P & labour and will arrange transportation of required material from store. (Required material such as pipe piece CID Joints shall be provided by Department free of cost)as per satisfaction of EIC. Rates for per pit.
645.01In all type Soil
655.0275 mm1Each
665.0390/80 mm1Each
675.04110/100 mm1Each
685.05140/125 mm1Each
695.06180/160/150 mm1Each
705.07225/200 mm1Each
715.08250 mm1Each
725.09300 mm1Each
735.1Add on above item no. 5 for B.T. Road = 5%
745.11Add on above item no. 5 for CC Road = 10%
755.12Add on above item no. 5 if depth of pipe line is above 1.5 mtr and up to 3.0 mtr.= 20%
765.13Add on above item no. 5 if depth of pipe line is above 3.0 mtr. = 30%
776Removal of Choking from pipe line, including tree roots, malba, sand and other by manually or other means, cleaning of line and testing in existing Distribution/Rising Main/Transmission Main CI/MS/DI pipe line up to 1.5 mtr depth of sizes as given below by digging out suitable size of pit at site of work including dewatering and providing adequate safety arrangement at site. This will also include cutting of pipe ends, fixing of pipe piece with jointing material and then refill the pit from excavated sand by ramming it at sides of pipe & upto ground level for entire job contractor will use his own T&P & labour and will arrange transportation of required material from store. (Required material such as pipe piece CID Joints shall be provided by Department free of cost)as per satisfaction of EIC. Rates for per pit.
786.01In all type Soil
796.0280 mm1Each
806.03100 mm1Each
816.04125 mm1Each
826.05150 mm1Each
836.06225/200 mm1Each
846.07250 mm1Each
856.08300 mm1Each
866.09Add on above item no. 6 for B.T. Road = 5%
876.1Add on above item no. 6 for CC Road = 10%
886.11Add on above item no. 6 if depth of pipe line is above 1.5 mtr up to 3.0 mtr. = 20%
896.12Add on above item no. 6 if depth of pipe line is above 3.0 mtr = 30%
907Disconnection of water connection from existing pipe line in all type of soils up to 1.5 mtr depth by digging out suitable size of pit at site of work, with cutting of service line and refixing of clamp revolving it 180 degree refill the pit from excavated sand by ramming it & upto ground level for entire job contractor will use his own T&P & labour.1Per Job
917.01Add on above item no. 7 for B.T. Road = 5%
927.02Add on above item no. 7 for CC Road = 10%
937.03Add on above item no. 7 if depth of pipe line is above 1.5 mtr and up to 3.0 mtr = 20%
948Removal of sluice valve in existing pipe line up to 1.5 mtr depth by digging out suitable size of pit at site of work including dewatering and providing adequate safety arrangement at site. This will also include cutting of pipe ends, fixing of pipe piece with jointing material to make repair leak proof and then refill the pit from excavated sand by ramming it at sides of pipe & upto ground level for entire job contractor will use his own T&P & labour and will arrange transportation of required material from store. (Required material such as pipe piece CID Joints shall be provided by Department free of cost)
958.01In all type Soil
968.0280 mm dia pipe to 100mm1Each
978.03125 mm dia pipe to 150mm1Each
988.04200 mm dia pipe to 250mm1Each
998.05300 mm dia pipe to 350mm1Each
1008.06400mm1Each
1018.07Add on above item no. 8 for B.T. Road = 5%
1028.08Add on above item no. 8 for CC Road = 10%
1038.09Add on above item no. 8 if depth of pipe line is above 1.5 mtr and up to 3.0 mtr = 20%
1049Work of Inter Connection in AC/PVC/HDPE pipe line up to 1.5 mtr depth by digging out suitable size of pit at site of work including dewatering and providing adequate safety arrangement at site, cutting of existing pipeline, jointing of Tee (complete) and other specials to make inter connection repair leak proof and then refill the pit from excavated sand by ramming it at sides of pipe & upto ground level for entire job contractor will use his own T&P & labour and will arrange transportation of material required from store. (Material such as Tee/ Tee Clamp/rubber sheet/ CID joints required for inter connection shall be provided by the department free of cost).
1059.01In all type Soil
1069.0280 mm to 110 mm1Each
1079.03125 mm to 165 mm1Each
1089.04200 mm to 300 mm1Each
1099.05Add on above item no. 9 for B.T. Road = 5%
1109.06Add on above item no. 9 for CC Road = 10%
1119.07Add on above item no.9 if depth of pipe line is above 1.5 mtr and up to 3.0 mtr = 20%
11210Work of Inter Connection in CI/DI/MS pipe line up to 1.5 mtr depth by digging out suitable size of pit at site of work including dewatering and providing adequate safety arrangement at site, cutting of existing pipeline, jointing of Tee (complete) and other specials to make inter connection repair leak proof and then refill the pit from excavated sand by ramming it at sides of pipe & upto ground level for entire job contractor will use his own T&P & labour and will arrange transportation of material required from store. (Material such as Tee/ Tee Clamp/rubber sheet/ CID joints required for inter connection shall be provided by the department free of cost).
11310.01In all type Soil
11410.0280 mm to 100 mm1Each
11510.03125 mm to 150 mm1Each
11610.04200 mm to 300 mm1Each
11710.05350 mm to 450 mm1Each
11810.06500 mm to 600 mm1Each
11910.07Add on above item no.10 for B.T. Road = 5%
12010.08Add on above item no.10 for CC Road = 10%
12110.09Add on above item no.10 if depth of pipe line is above 1.5 mtr and up to 3.0 mtr = 20%
12211Labour charges for removal of complaint of polluted water supply to the consumers
12311.01Survey of the locality of polluted water supply for preliminary assessment of source of pollution during supply hours1Each survey
12412Labour charges for digging of pit of suitable size for removal of water pollution on existing distribution AC/PVC/uPVC/HDPE pipe lines up to 1.5 mtr depth including cutting of pipe and assessment of direction of flow of polluted water during non supply hours, identifying the source of pollution and repairing of fault in pipe line by fixing of pipe piece with jointing material (pipe and jointing material shall be supplied by department) to make it leak proof and then refilling the pit from excavated sand by ramming it at site of pipe upto ground level. The rate includes all labour charges to complete the work for pipe size
12512.01In all type Soil
12612.0250 to 75 mm1Each
12712.0380-110 mm1Each
12812.04125 to 165 mm1Each
12912.05200 to 300 mm1Each
13012.06350 to 400 mm1Each
13112.07Add on above item no.11.2 for B.T. Road = 5%
13212.08Add on above item no.11.2 for CC Road = 10%
13312.09Add on above item no. 11.2 if depth of pipe line is above 1.5 mtr and up to 3.0 mtr. = 20%
13413Labour charges for digging of pit of suitable size for removal of water pollution on existing distribution CI/DI/MS pipe lines up to 1.5 mtr depth including cutting of pipe and assessment of direction of flow of polluted water during non supply hours, identifying the source of pollution and repairing of fault pipe line by fixing of pipe piece with jointing material (pipe and jointing material shall be supplied by department) to make it leak proof and then refilling the pit from excavated sand by ramming it at site of pipe upto ground level. The rate includes all labour charges to complete the work for pipe size
13513.01In all type Soil
13613.0280-100 mm1Each
13713.03125 to 150 mm1Each
13813.04200 to 300 mm1Each
13913.05350 to 400 mm1Each
14013.06Add on above item 11.3 for B.T. Road = 5%
14113.07Add on above item no. 11.3 for CC Road = 10%
14213.08Add on above item no.11.3 if depth of pipe line is above 1.5 mtr and up to 3.0 mtr.= 20%
14314Restoration of bitumen road by patch work of WBM using crushed / broken aggregate as per the standard specification and consolidation with hand rammer spreading and consolidation of binding material , cleaning of surface of WBM and providing of seal & tack coat as per site condition by using ready cold mix up to the satisfaction of engineer in charge. The rate includes the making of pit in regular shape, all labour, material and T&P charge complete job.1Per Sqm
14415Restoration of cement concrete road including making of pit in regular shape, ramming and consolidation of surface, laying, positioning and compacting cement concrete ( M-20 ) minimum thickness 200 mm upto the satisfaction of engineer incharge. The rate includes the making of pit in regular shape, all labour, material and T&P charge complete job.1Per Sqm

AI Tender Summary

OUR REF NO 24449405
AUTHORITY Government Departments
TENDER VALUE 10 Lakhs
LAST DATE 15-06-2020
Authority
Authority Name Public Health Engineering Department
Work Description Annual Rate Contract For Removing Of Leakage / Choking In Difference Size Of Pipe Line Under Phed Sub Div . Nawalgarh
Basic Detail
Tender No 13/2020-21 City Dn
Bidding Type Tender
Location
City Nawalgarh
State Rajasthan
Key Dates
Publish Date 30 May 2020
Submission Date 15 Jun 2020
Open Date 16 Jun 2020
Finance
Tender Value 10 Lakhs
Tender Fee 500
EMD 20000
Exemption Not Available
Document List
BOQ_326168.xls
Tendernotice_1.pdf
TD13.pdf
9B8AFC2B-8E3A-4268-9D79-27FA98B97977.html

Unlock Full AI Tender Summary

Get instant access to the complete AI-generated analysis — scope, eligibility, timeline & more.

Instant Access Secure Free
Your details are secure and used only for document delivery.

Tender Timeline

May 30, 2020
11:30 IST

Tender Published

Tender notice published.

Completed
Jun 15, 2020
17:00 IST

Bid Submission Deadline

Online submission via eProcurement portal.

Completed
Jun 16, 2020

Bid Opening Date

Technical bids will be opened and evaluated.

Completed

Tender Documents

Download All (ZIP) ↓
xls

BOQ_326168.xls

pdf

Tendernotice_1.pdf

pdf

TD13.pdf

html

9B8AFC2B-8E3A-4268-9D79-27FA98B97977.html

Disclaimer

We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender

TenderDetail
Loading tenders