Two Year Maintenance Contract For Routine / Preventive / Breakdown Maintenance Of Boiler Pressure Parts , Coal And Oil Burner Assemblies , Wind Box , Hp Valves , Safety Valves , Fans , Aphs , Esp , Ducting And Fuel Oil Pumps Etc . For 2X600 Mw, RGTPP, HISAR-Haryana

Haryana Power Generation Corporation Limited-HPGCL has published Two Year Maintenance Contract For Routine / Preventive / Breakdown Maintenance Of Boiler Pressure Parts , Coal And Oil Burner Assemblies , Wind Box , Hp Valves , Safety Valves , Fans , Aphs , Esp , Ducting And Fuel Oil Pumps Etc . For 2X600 Mw. Submission Date for this Tender is 20-06-2020. Boiler Supply Tenders in RGTPP, HISAR Haryana. Bidders can get complete Tender details and download the document.




Tender Notice

24283955
Corrigendum : Two Year Maintenance Contract For Routine / Preventive / Breakdown Maintenance Of Boiler Pressure Parts , Coal And Oil Burner Assemblies , Wind Box , Hp Valves , Safety Valves , Fans , Aphs , Esp , Ducting And Fuel Oil Pumps Etc . For 2X600 Mw
Open Tender
Indian
Haryana
RGTPP, HISAR
20-06-2020

Tender Details

Two Year Maintenance Contract For Routine / Preventive / Breakdown Maintenance Of Boiler Pressure Parts , Coal And Oil Burner Assemblies , Wind Box , Hp Valves , Safety Valves , Fans , Aphs , Esp , Ducting And Fuel Oil Pumps Etc . For 2X600 Mw Unit-I And I

Corrigendum Details

Sr No CorrigendumDate Corrignedum CorrigendumType NewSubmissionDate
1 01-Jun-2020 Corrigendum-I Date Extension-I Date 10-06-2020
2 12-Jun-2020 DateExtensionWithAmendedPQR Technical Bid 20-06-2020

Key Value

Document Fees
INR 1180 /-
EMD
INR 350300.0 /-
Tender Value
Refer document

BOQ Items

Name of Work : TWO YEAR MAINTENANCE CONTRACT FOR ROUTINE / PREVENTIVE / BREAKDOWN MAINTENANCE OF BOILER PRESSURE PARTS, COAL & OIL BURNER ASSEMBLIES, WIND BOX, HP VALVES, SAFETY VALVES, FANS, APH'S, ESP, DUCTING & FUEL OIL PUMPS ETC. FOR 2X600 MW UNIT-I & II AT RGTPP, KHEDAR, HISAR
Sl. No. Item Description Item Code / Make Tentative Frequency/ Quantity for both Units Units
1 1 For Scope of work under Part-A, for First Year :\nLump Sum Monthly Charges for both Units-I&II for Main Scope of work under Part-A (i.e. work of Boiler Pressure Parts, Boiler Rotary Parts & Common Activities as Per Scope of Work at Annexure-III)\n BI01010001010000000000000515BI0100001112 12 Months
2 1.01 For Scope of work under Part-B, for First Year (from 1.02 to 1.70) BI01010001010000000000000515BI0100001125
3 1.02 Mobilization & attending the boiler tube leakage / preventive mtc. of pressure parts tubes in boiler excluding Platen Super Heater area, Divisional Super Heater area, Platen Re Heater area, Finish Reheater area & Panel/wall Reheater area. It includes cutting, welding, fit-up, grinding and replacement of tube of all sizes and thickness involving upto 10 nos. joints. \nNote: \n(i) 3 Nos. Metal Built Ups each having length upto 100 mm will considered as one joint. (ii) Separate payment will be made for scaffolding as per quoted unit rates. \n BI01010001010000000000000515BI0100001125 8 Each
4 1.03 Carrying out HP joint in addition to 10 nos. joints mentioned at Sr. No. 1 above in boiler excluding Platen Super Heater area, Divisional Super Heater area, Platen Reheater area, Finish Reheater area & Panel//wall Reheater area. It includes cutting, welding, fit-up, grinding and welding of one no. joint of tube of all sizes and any thickness of boiler in area covered under Sr. No.1 above. BI01010001010000000000000515BI0100001125 50 Each joint
5 1.04 Metal build up on worn out boiler tubes in boiler excluding Platen Super Heater area, Divisional Super Heater area, Platen Reheater area, Finish Reheater area & Panel/ wall Reheater area half round surface by HP welder upto 100 MM length. BI01010001010000000000000515BI0100001125 100 Each upto 100 MM length
6 1.05 Attending leakage by welding of HP Joints of outside the boiler including replacement of pipe up to 1 Mtr. Length / valve / bends by cutting, welding, grinding and fit-up work for each joint.\nNOTE: In case HP welder capable of doing the above work does not reach RGTPP within 8 Hrs. of verbal/written/ SMS instructions by EIC (i.e. AEE/AE Concerned) or higher authority & hence work could not be started or welder engaged is found incompetent then penalty of Rs.5000/- per day will be imposed on the contractor which will be in addition to other penalty clauses as applicable. Also work will be got carried out through outside agency which will cost approx minimum Rs.20000/- per day at the risk & cost of the contractor and hence deducted from his running bill/s. It is pertinent to mention that above value of risk & cost will be over & above the penalty amount.\n BI01010001010000000000000515BI0100001125 10 Per inch dia. Each joint
7 1.06 Replacements of gasket of man hole of boiler drum including minor repair/grinding, if any BI01010001010000000000000515BI0100001125 2 Each
8 1.07 Repair, rectification & re-fixing of cassette baffles. BI01010001010000000000000515BI0100001125 4 Each
9 1.08 Providing & Re-positioning of twisted shields/ Replacement of shielding plates/shrouds plated on various boiler tubes. BI01010001010000000000000515BI0100001125 200 Nos.
10 1.09 Casting refractory on boiler. BI01010001010000000000000515BI0100001125 4 MT
11 1.1 Providing skin casing with 3mm plate Providing skin casing with 3mm plate BI01010001010000000000000515BI0100001125 10
12 1.11 Providing buck stay pin / repairing of buck stay. BI01010001010000000000000515BI0100001125 6 Each
13 1.12 Providing of scaffolding & platform in the inside/outside boiler area (height X length) with width of 2 nos. Jail (i.e. 2-3 feet approx) BI01010001010000000000000515BI0100001125 400 Sq. Mtr.
14 1.13 Replacement of steam tracing line. BI01010001010000000000000515BI0100001125 20 RM
15 1.14 Internal water washing of goose neck area (i.e. rear arc area) and 2nd pass of boiler. BI01010001010000000000000515BI0100001125 4 Each Boiler
16 1.15 External water washing of boiler from 42 Meters Approx to bottom ring header elevation BI01010001010000000000000515BI0100001125 2 Each Boiler
17 1.16 External water washing of boiler from pent house to zero meter including 2nd pass BI01010001010000000000000515BI0100001125 4 Each Boiler
18 1.17 Checking of Burner Tilt Mechanism and rectification thereof at one corner.\na) Disconnections of all reach rods from burner tilt mechanism as per requirement.\nb) Dismantling of burner tilt mechanism including removal of drive shaft after disconnecting from burner tilt power cylinder. Removal of burner tilt power cylinder from its position if required by C & I mtc. And refitting of same & replacement of burner tilt shear pin/ other pins, if found damaged.\nc) Lubrication of pins, shafts, studs of reach rod etc. As per requirement.\nd) Repair/ replacement of reach rod turn buckle, pivot pins, pins of tilting mechanism as per requirement.\ne) Assembly & refitting of burner tilt mechanism.\nf) Connections of all reach rods to burner tilt mechanism and zero setting of all nozzle tips.\ng) Tilting trail of burner tilt. Ensure free operation of burner tilt upto +/ - 30 degree connecting with power cylinder and trail operation power cylinder. \n BI01010001010000000000000515BI0100001125 4 Each Corner
19 1.18 Rectification of jammed secondary air damper from inside wind box.\na) Cleaning and removing of all the ash accumulated in SADC partition plate in all the four corners and cleaning shafts and bush with diesel/ restoline etc. As per requirement.\nb) Repair/ replacement of damper flaps, bush, glands, links and partition plate of damper compartment as per requirement.\nc) Making damper operation free & smooth.\nd) Providing damper movement indicators over the shaft as per requirement.\ne) Repairing secondary air damper lever & its connection with damper power cylinder if required.\nf) Removal of bush of drive end & non drive end along with bush housing in case of jamming of SADC if required & refitting of same after repairing or replacement by new.\ng) Repairing and replacement of stopper.\nNOTE: Scaffolding if required for above work will be paid extra as per unit rate under item No. 11.\n BI01010001010000000000000515BI0100001125 20 Each damper
20 1.19 Rectification of jammed secondary air damper from outside wind box. BI01010001010000000000000515BI0100001125 50 Each damper
21 1.2 Repairing of scanner guide assembly including its removal from panel, repair/replacement of worn out parts if required and checking its movement with tilting mechanism. BI01010001010000000000000515BI0100001125 20 Each
22 1.21 Servicing / overhauling of oil gun assembly with Igniter including replacement of worn out parts if required. BI01010001010000000000000515BI0100001125 12 Each
23 1.22 Opening/closing of oil gun/coal nozzle/air chamber for inspection BI01010001010000000000000515BI0100001125 60 Each
24 1.23 Removal, refitting & servicing of burner isolating gate with replacement of gaskets etc. at furnace end. \nNOTE: All the associated works such as removal/ locking of fuel inlet elbow, removal of Victaulic coupling etc. Required for completion of above job is included in scope of work.\nIn case work is not started within reasonable time after verbal/ written/ SMS instructions by EIC (i.e. AEE/AE concerned) or higher authority or manpower engaged is found incompetent then penalty of Rs. 5000/- per day will be imposed on the contractor which will be in addition to other penalty clauses as applicable. Also work will be got carried out through outside agency which will cost approx minimum Rs. 30,000/- plus taxes extra as applicable per day at the risk and cost of other agency of the contractor and hence deducted from his running bills. It is pertinent to mention that above value of risk will be over and above the penalty amount.\n BI01010001010000000000000515BI0100001125 10 Each meter
25 1.24 Repairing of boiler seal trough dipping plate which includes lifting/lowering/bolting etc as per requirement. BI01010001010000000000000515BI0100001125 30 Each meter
26 1.25 Repair/replacement of tie rod of any hanger in boiler area. BI01010001010000000000000515BI0100001125 10 Per meter
27 1.26 Replacement of ss wire mesh in seal trough area BI01010001010000000000000515BI0100001125 20 Each
28 1.27 Complete servicing of wall soot blower. BI01010001010000000000000515BI0100001125 10 Each
29 1.28 Repairing/replacement of Chain of long retractable soot blower BI01010001010000000000000515BI0100001125 10 Each
30 1.29 Complete servicing / Repairing of long retractable soot blower including Gear Box including lance, other spares replacement etc if required BI01010001010000000000000515BI0100001125 10 Each
31 1.3 Repair, Servicing, replacement of damaged spares / gaskets & attending steam leakages of valves/ NRVs of size 600 mm & above BI01010001010000000000000515BI0100001125 10 Per inch dia.
32 1.31 Decoupling & coupling after alignment of ID / FD / PA Fan with motor BI01010001010000000000000515BI0100001125 4 Each
33 1.32 Replacement of blade pitch control system ( i.e. Hydraulic Cylinder) of ID/FD/PA Fan BI01010001010000000000000515BI0100001125 4 Each
34 1.33 Opening & Re-fixing of top casing of ID/FD/PA Fan including removal/ replacement of fabric expansion joint of casing. BI01010001010000000000000515BI0100001125 10 Each
35 1.34 Attending oil leakage of bearing housing of ID/FD/PA Fans excluding top cover opening. BI01010001010000000000000515BI0100001125 6 Each
36 1.35 Attending oil leakage of blade pitch control system of ID Fans including removing/ replacement of cover plate BI01010001010000000000000515BI0100001125 4 Each
37 1.36 Replacement of complete set of blades of ID fans excluding top cover opening. BI01010001010000000000000515BI0100001125 4 Each set
38 1.37 Replacement of complete set of blades of both impellers of PA fans excluding top cover opening. BI01010001010000000000000515BI0100001125 2 Each set
39 1.38 Replacement of lube oil pump or coupling of lube oil pump, including opening & re-fixing of Lube oil pump of ID / FD / PA Fan BI01010001010000000000000515BI0100001125 4 Each
40 1.39 Removal of impeller of scanner air fan from motor shaft and its refitting. BI01010001010000000000000515BI0100001125 6 Each
41 1.4 Attending cooler tube leakage of lube oil system of ID/FD/PA fans. BI01010001010000000000000515BI0100001125 4 Each
42 1.41 Cleaning of oil coolers. BI01010001010000000000000515BI0100001125 40 Each
43 1.42 Replacement of oil after thorough cleaning of oil chamber from inside. BI01010001010000000000000515BI0100001125 20 Each
44 1.43 Repairing of steam/ air lance of soot blower by welding BI01010001010000000000000515BI0100001125 8 Each
45 1.44 Cleaning of lube oil coolers. BI01010001010000000000000515BI0100001125 16 Each
46 1.45 Replacement of mechanical seal of lub oil pump of guide/ support bearing including dismantlement & assembly of pump. BI01010001010000000000000515BI0100001125 8 Each
47 1.46 Water washing of APHs through washing system or Fire Fighting line. BI01010001010000000000000515BI0100001125 6 Each Unit (Boiler)
48 1.47 Coupling & decoupling of rapping mechanism gear boxes of ESP. BI01010001010000000000000515BI0100001125 30 Each
49 1.48 Checking of ESP field BI01010001010000000000000515BI0100001125 150 Each
50 1.49 Checking of rapping mechanism of one complete pass BI01010001010000000000000515BI0100001125 16 Each
51 1.5 Removal of snapped emitting electrodes. BI01010001010000000000000515BI0100001125 350 Each
52 1.51 Erection of new emitting electrodes BI01010001010000000000000515BI0100001125 350 Each
53 1.52 Repairing/ replacement of shock bar, Repairing of guide bar BI01010001010000000000000515BI0100001125 40 Each
54 1.53 Replacement of shaft insulator BI01010001010000000000000515BI0100001125 50 Each
55 1.54 Replacement of plain fixed / free bearing BI01010001010000000000000515BI0100001125 80 Each
56 1.55 Re-positioning / removal / replacement of deflection plate. BI01010001010000000000000515BI0100001125 15 Each
57 1.56 Repairing of worn/ damaged manhole BI01010001010000000000000515BI0100001125 10 Each
58 1.57 Cleaning of shaft insulators. BI01010001010000000000000515BI0100001125 256 Each
59 1.58 Attending leakages of ash by welding from inside of hopper including cleaning of surface of hopper for pointing out leakage, formation of temporary platforms if required etc. BI01010001010000000000000515BI0100001125 40 Each
60 1.59 Fabrication, repair & fitment of Flap assembly of Mechanical Ash Level Indicators of ESP hoppers. BI01010001010000000000000515BI0100001125 50 Each
61 1.6 Patch work on ducts up to 300mm x 300mm BI01010001010000000000000515BI0100001125 300 Each
62 1.61 Repairing of duct with welding \n(welding in running meter)\n BI01010001010000000000000515BI0100001125 300 Per meter
63 1.62 Repair / replacement of fabric expansion bellow in air/ flue gas duct or in any other area irrespective of width BI01010001010000000000000515BI0100001125 275 Per meter running length
64 1.63 Replacement of cartridge of HFO / LDO pressurizing pump including replacement of mechanical seal, bearings, if required, including alignment and normalization. BI01010001010000000000000515BI0100001125 2 Each
65 1.64 Replacement of mechanical seals of HFO/ LDO unloading pump/ transfer/ pressurizing pump BI01010001010000000000000515BI0100001125 6 Each Pump
66 1.65 Erection of temporary platform in the different auxiliary's area (Height X Length) up to width of 02 jali's. in addition to the work covered in Part-A. BI01010001010000000000000515BI0100001125 270 Per Sq. Mtr.
67 1.66 Deployment of below mentioned manpower as per requirement for the miscellaneous jobs which are not covered above. \nA gang of 1 no. Tech. & 1 no. Helper for attending any misc. Job for duration of 4 hours. BI01010001010000000000000515BI0100001125 60 Each
68 1.67 Deployment of below mentioned manpower as per requirement for the miscellaneous jobs which are not covered above. \nA gang of 1 no. Rigger. & 1 no. Helper for attending any misc. Job for duration of 4 hours. BI01010001010000000000000515BI0100001125 60 Each
69 1.68 Deployment of below mentioned manpower as per requirement for the miscellaneous jobs which are not covered above:\nA gang of 1 no. Painter & 1 no. Helper for doing any misc. Painting job for duration of 4 hours BI01010001010000000000000515BI0100001125 10 Each
70 1.69 Fabrication & erection of Misc. steel structure BI01010001010000000000000515BI0100001125 20 Per Ton
71 1.7 Removal/re-fixing of any dislocated / bulged skin casing up to 01 Sqr. Meter in boiler. BI01010001010000000000000515BI0100001125 30 Per sqr. Mtr.
72 2 For Scope of work under Part-A, for Second Year :\nLump Sum Monthly Charges for both Units-I&II for Main Scope of work under Part-A (i.e. work of Boiler Pressure Parts, Boiler Rotary Parts & Common Activities as Per Scope of Work at Annexure-III)\n BI01010001010000000000000515BI0100001112 12 Months
73 2.01 For Scope of work under Part-B, for Second Year (from 2.02 to 2.70) BI01010001010000000000000515BI0100001125
74 2.02 Mobilization & attending the boiler tube leakage / preventive mtc. of pressure parts tubes in boiler excluding Platen Super Heater area, Divisional Super Heater area, Platen Re Heater area, Finish Reheater area & Panel/wall Reheater area. It includes cutting, welding, fit-up, grinding and replacement of tube of all sizes and thickness involving upto 10 nos. joints. \nNote: \n(i) 3 Nos. Metal Built Ups each having length upto 100 mm will considered as one joint. (ii) Separate payment will be made for scaffolding as per quoted unit rates. \n BI01010001010000000000000515BI0100001125 8 Each
75 2.03 Carrying out HP joint in addition to 10 nos. joints mentioned at Sr. No. 1 above in boiler excluding Platen Super Heater area, Divisional Super Heater area, Platen Reheater area, Finish Reheater area & Panel//wall Reheater area. It includes cutting, welding, fit-up, grinding and welding of one no. joint of tube of all sizes and any thickness of boiler in area covered under Sr. No.1 above. BI01010001010000000000000515BI0100001125 50 Each joint
76 2.04 Metal build up on worn out boiler tubes in boiler excluding Platen Super Heater area, Divisional Super Heater area, Platen Reheater area, Finish Reheater area & Panel/ wall Reheater area half round surface by HP welder upto 100 MM length. BI01010001010000000000000515BI0100001125 100 Each upto 100 MM length
77 2.05 Attending leakage by welding of HP Joints of outside the boiler including replacement of pipe up to 1 Mtr. Length / valve / bends by cutting, welding, grinding and fit-up work for each joint.\nNOTE: In case HP welder capable of doing the above work does not reach RGTPP within 8 Hrs. of verbal/written/ SMS instructions by EIC (i.e. AEE/AE Concerned) or higher authority & hence work could not be started or welder engaged is found incompetent then penalty of Rs.5000/- per day will be imposed on the contractor which will be in addition to other penalty clauses as applicable. Also work will be got carried out through outside agency which will cost approx minimum Rs.20000/- per day at the risk & cost of the contractor and hence deducted from his running bill/s. It is pertinent to mention that above value of risk & cost will be over & above the penalty amount.\n BI01010001010000000000000515BI0100001125 10 Per inch dia. Each joint
78 2.06 Replacements of gasket of man hole of boiler drum including minor repair/grinding, if any BI01010001010000000000000515BI0100001125 2 Each
79 2.07 Repair, rectification & re-fixing of cassette baffles. BI01010001010000000000000515BI0100001125 4 Each
80 2.08 Providing & Re-positioning of twisted shields/ Replacement of shielding plates/shrouds plated on various boiler tubes. BI01010001010000000000000515BI0100001125 200 Nos.
81 2.09 Casting refractory on boiler. BI01010001010000000000000515BI0100001125 4 MT
82 2.1 Providing skin casing with 3mm plate Providing skin casing with 3mm plate BI01010001010000000000000515BI0100001125 10
83 2.11 Providing buck stay pin / repairing of buck stay. BI01010001010000000000000515BI0100001125 6 Each
84 2.12 Providing of scaffolding & platform in the inside/outside boiler area (height X length) with width of 2 nos. Jail(i.e. 2-3 feet approx) BI01010001010000000000000515BI0100001125 400 Sq. Mtr.
85 2.13 Replacement of steam tracing line. BI01010001010000000000000515BI0100001125 20 RM
86 2.14 Internal water washing of goose neck area (i.e. rear arc area) and 2nd pass of boiler. BI01010001010000000000000515BI0100001125 4 Each Boiler
87 2.15 External water washing of boiler from 42 Meters Approx to bottom ring header elevation BI01010001010000000000000515BI0100001125 2 Each Boiler
88 2.16 External water washing of boiler from pent house to zero meter including 2nd pass BI01010001010000000000000515BI0100001125 4 Each Boiler
89 2.17 Checking of Burner Tilt Mechanism and rectification thereof at one corner.\na) Disconnections of all reach rods from burner tilt mechanism as per requirement.\nb) Dismantling of burner tilt mechanism including removal of drive shaft after disconnecting from burner tilt power cylinder. Removal of burner tilt power cylinder from its position if required by C & I mtc. And refitting of same & replacement of burner tilt shear pin/ other pins, if found damaged.\nc) Lubrication of pins, shafts, studs of reach rod etc. As per requirement.\nd) Repair/ replacement of reach rod turn buckle, pivot pins, pins of tilting mechanism as per requirement.\ne) Assembly & refitting of burner tilt mechanism.\nf) Connections of all reach rods to burner tilt mechanism and zero setting of all nozzle tips.\ng) Tilting trail of burner tilt. Ensure free operation of burner tilt upto +/ - 30 degree connecting with power cylinder and trail operation power cylinder. \n BI01010001010000000000000515BI0100001125 4 Each Corner
90 2.18 Rectification of jammed secondary air damper from inside wind box.\na) Cleaning and removing of all the ash accumulated in SADC partition plate in all the four corners and cleaning shafts and bush with diesel/ restoline etc. As per requirement.\nb) Repair/ replacement of damper flaps, bush, glands, links and partition plate of damper compartment as per requirement.\nc) Making damper operation free & smooth.\nd) Providing damper movement indicators over the shaft as per requirement.\ne) Repairing secondary air damper lever & its connection with damper power cylinder if required.\nf) Removal of bush of drive end & non drive end along with bush housing in case of jamming of SADC if required & refitting of same after repairing or replacement by new.\ng) Repairing and replacement of stopper.\nNOTE: Scaffolding if required for above work will be paid extra as per unit rate under item No. 11.\n BI01010001010000000000000515BI0100001125 20 Each damper
91 2.19 Rectification of jammed secondary air damper from outside wind box. BI01010001010000000000000515BI0100001125 50 Each damper
92 2.2 Repairing of scanner guide assembly including its removal from panel, repair/replacement of worn out parts if required and checking its movement with tilting mechanism. BI01010001010000000000000515BI0100001125 20 Each
93 2.21 Servicing / overhauling of oil gun assembly with Igniter including replacement of worn out parts if required. BI01010001010000000000000515BI0100001125 12 Each
94 2.22 Opening/closing of oil gun/coal nozzle/air chamber for inspection BI01010001010000000000000515BI0100001125 60 Each
95 2.23 Removal, refitting & servicing of burner isolating gate with replacement of gaskets etc. at furnace end. \nNOTE: All the associated works such as removal/ locking of fuel inlet elbow, removal of Victaulic coupling etc. Required for completion of above job is included in scope of work.\nIn case work is not started within reasonable time after verbal/ written/ SMS instructions by EIC (i.e. AEE/AE concerned) or higher authority or manpower engaged is found incompetent then penalty of Rs. 5000/- per day will be imposed on the contractor which will be in addition to other penalty clauses as applicable. Also work will be got carried out through outside agency which will cost approx minimum Rs. 30,000/- plus taxes extra as applicable per day at the risk and cost of other agency of the contractor and hence deducted from his running bills. It is pertinent to mention that above value of risk will be over and above the penalty amount.\n BI01010001010000000000000515BI0100001125 10 Each meter
96 2.24 Repairing of boiler seal trough dipping plate which includes lifting/lowering/bolting etc as per requirement. BI01010001010000000000000515BI0100001125 30 Each meter
97 2.25 Repair/replacement of tie rod of any hanger in boiler area. BI01010001010000000000000515BI0100001125 10 Per meter
98 2.26 Replacement of ss wire mesh in seal trough area BI01010001010000000000000515BI0100001125 20 Each
99 2.27 Complete servicing of wall soot blower. BI01010001010000000000000515BI0100001125 10 Each
100 2.28 Repairing/replacement of Chain of long retractable soot blower BI01010001010000000000000515BI0100001125 10 Each
101 2.29 Complete servicing / Repairing of long retractable soot blower including Gear Box including lance, other spares replacement etc if required BI01010001010000000000000515BI0100001125 10 Each
102 2.3 Repair, Servicing, replacement of damaged spares / gaskets & attending steam leakages of valves/ NRVs of size 600 mm & above BI01010001010000000000000515BI0100001125 10 Per inch dia.
103 2.31 Decoupling & coupling after alignment of ID / FD / PA Fan with motor BI01010001010000000000000515BI0100001125 4 Each
104 2.32 Replacement of blade pitch control system ( i.e. Hydraulic Cylinder) of ID/FD/PA Fan BI01010001010000000000000515BI0100001125 4 Each
105 2.33 Opening & Re-fixing of top casing of ID/FD/PA Fan including removal/ replacement of fabric expansion joint of casing. BI01010001010000000000000515BI0100001125 10 Each
106 2.34 Attending oil leakage of bearing housing of ID/FD/PA Fans excluding top cover opening. BI01010001010000000000000515BI0100001125 6 Each
107 2.35 Attending oil leakage of blade pitch control system of ID Fans including removing/ replacement of cover plate BI01010001010000000000000515BI0100001125 4 Each
108 2.36 Replacement of complete set of blades of ID fans excluding top cover opening. BI01010001010000000000000515BI0100001125 4 Each set
109 2.37 Replacement of complete set of blades of both impellers of PA fans excluding top cover opening. BI01010001010000000000000515BI0100001125 2 Each set
110 2.38 Replacement of lube oil pump or coupling of lube oil pump, including opening & re-fixing of Lube oil pump of ID / FD / PA Fan BI01010001010000000000000515BI0100001125 4 Each
111 2.39 Removal of impeller of scanner air fan from motor shaft and its refitting. BI01010001010000000000000515BI0100001125 6 Each
112 2.4 Attending cooler tube leakage of lube oil system of ID/FD/PA fans. BI01010001010000000000000515BI0100001125 4 Each
113 2.41 Cleaning of oil coolers. BI01010001010000000000000515BI0100001125 40 Each
114 2.42 Replacement of oil after thorough cleaning of oil chamber from inside. BI01010001010000000000000515BI0100001125 20 Each
115 2.43 Repairing of steam/ air lance of soot blower by welding BI01010001010000000000000515BI0100001125 8 Each
116 2.44 Cleaning of lube oil coolers. BI01010001010000000000000515BI0100001125 16 Each
117 2.45 Replacement of mechanical seal of lub oil pump of guide/ support bearing including dismantlement & assembly of pump. BI01010001010000000000000515BI0100001125 8 Each
118 2.46 Water washing of APHs through washing system or Fire Fighting line. BI01010001010000000000000515BI0100001125 6 Each Unit (Boiler)
119 2.47 Coupling & decoupling of rapping mechanism gear boxes of ESP. BI01010001010000000000000515BI0100001125 30 Each
120 2.48 Checking of ESP field BI01010001010000000000000515BI0100001125 150 Each
121 2.49 Checking of rapping mechanism of one complete pass BI01010001010000000000000515BI0100001125 16 Each
122 2.5 Removal of snapped emitting electrodes. BI01010001010000000000000515BI0100001125 350 Each
123 2.51 Erection of new emitting electrodes BI01010001010000000000000515BI0100001125 350 Each
124 2.52 Repairing/ replacement of shock bar, Repairing of guide bar BI01010001010000000000000515BI0100001125 40 Each
125 2.53 Replacement of shaft insulator BI01010001010000000000000515BI0100001125 50 Each
126 2.54 Replacement of plain fixed / free bearing BI01010001010000000000000515BI0100001125 80 Each
127 2.55 Re-positioning / removal / replacement of deflection plate. BI01010001010000000000000515BI0100001125 15 Each
128 2.56 Repairing of worn/ damaged manhole BI01010001010000000000000515BI0100001125 10 Each
129 2.57 Cleaning of shaft insulators. BI01010001010000000000000515BI0100001125 256 Each
130 2.58 Attending leakages of ash by welding from inside of hopper including cleaning of surface of hopper for pointing out leakage, formation of temporary platforms if required etc. BI01010001010000000000000515BI0100001125 40 Each
131 2.59 Fabrication, repair & fitment of Flap assembly of Mechanical Ash Level Indicators of ESP hoppers. BI01010001010000000000000515BI0100001125 50 Each
132 2.6 Patch work on ducts up to 300mm x 300mm BI01010001010000000000000515BI0100001125 300 Each
133 2.61 Repairing of duct with welding \n(welding in running meter)\n BI01010001010000000000000515BI0100001125 300 Per meter
134 2.62 Repair / replacement of fabric expansion bellow in air/ flue gas duct or in any other area irrespective of width BI01010001010000000000000515BI0100001125 275 Per meter running length
135 2.63 Replacement of cartridge of HFO / LDO pressurizing pump including replacement of mechanical seal, bearings, if required, including alignment and normalization. BI01010001010000000000000515BI0100001125 2 Each
136 2.64 Replacement of mechanical seals of HFO/ LDO unloading pump/ transfer/ pressurizing pump BI01010001010000000000000515BI0100001125 6 Each Pump
137 2.65 Erection of temporary platform in the different auxiliary's area (Height X Length) up to width of 02 jali's. in addition to the work covered in Part-A. BI01010001010000000000000515BI0100001125 270 Per Sq. Mtr.
138 2.66 Deployment of below mentioned manpower as per requirement for the miscellaneous jobs which are not covered above. \nA gang of 1 no. Tech. & 1 no. Helper for attending any misc. Job for duration of 4 hours. BI01010001010000000000000515BI0100001125 60 Each
139 2.67 Deployment of below mentioned manpower as per requirement for the miscellaneous jobs which are not covered above. \nA gang of 1 no. Rigger. & 1 no. Helper for attending any misc. Job for duration of 4 hours. BI01010001010000000000000515BI0100001125 60 Each
140 2.68 Deployment of below mentioned manpower as per requirement for the miscellaneous jobs which are not covered above:\nA gang of 1 no. Painter & 1 no. Helper for doing any misc. Painting job for duration of 4 hours BI01010001010000000000000515BI0100001125 10 Each
141 2.69 Fabrication & erection of Misc. steel structure BI01010001010000000000000515BI0100001125 20 Per Ton
142 2.7 Removal/re-fixing of any dislocated / bulged skin casing up to 01 Sqr. Meter in boiler. BI01010001010000000000000515BI0100001125 30 Per sqr. Mtr.
Disclaimer :
We takes all possible care for accurate & authentic tender information, however Users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender.
Tell us about your Product / Services,
We will Find Tenders for you

Copyright © 2024 · All Rights Reserved. Terms of Usage | Privacy Policy

For Tender Information Services Visit : TenderDetail