Indian Navy-IN has published Rfp For Three Years Repair Rate Contract For Evac Vaccuum Toilet System And Sewage Treatment Plants For In Ships And Yard Crafts At Nsry Karwar Repair/ Routines Of Evac Vaccuum Toilet System And Sewage Treatment Plants For In Ships And Yard Crafts. Submission Date for this Tender is 11-05-2020. Tanks and Cylinders Tenders in Naval Ship Repair Yard Karwar Karnataka. Bidders can get complete Tender details and download the document.
Sr No | CorrigendumDate | Corrignedum | CorrigendumType | NewSubmissionDate |
1 | 04-May-2020 | Bid Auto Extn Corrigendum | Bid Auto Extn Corrigendum | 11-05-2020 |
Name of Work: THREE YEARS RRC FOR EVAC VACUUM TOILET SYSTEM AND SEWAGE TREATMENT PLANTS ONBOARD IN SHIPS AND YARD CRAFTS AT NSRY (KARWAR) | |||||
---|---|---|---|---|---|
Sl. No. | Item Description | Item Code / Make | Quantity | Units | |
1 | 1 | PART 1 - Vacuum Toilet System Evac Vacuum Toilet System - Ejector Type - (INS Aditya, INS Subhadra and INS Suvarna) | |||
2 | 1.1 | Vacuum Pump | |||
3 | 1.11 | Completed Overhauling of Pump | 9 | Nos | |
4 | 1.12 | Completed Overhauling of Motor | 9 | Nos | |
5 | 1.13 | Defect rectification of vacuum pump | 9 | Nos | |
6 | 1.14 | Rewinding of Motor | 9 | Nos | |
7 | 1.15 | Replacement of Pump | 9 | Nos | |
8 | 1.2 | Ejector | |||
9 | 1.21 | Chemical cleaning and overhauling of Ejector | 9 | Nos | |
10 | 1.22 | Removal, chemical cleaning and fitting back of nozzle | 9 | Nos | |
11 | 1.23 | Cleaning /renewal of non return flap | 9 | Nos | |
12 | 1.3 | Collection Tank | |||
13 | 1.31 | Chemical cleaning of Evac collection tank\n(i) Opening of Manhole door and checking the H2S level in the tank.\n(ii) Ventilation of the tank\n(iii) Removal of Sewage Water from the tank\n(iv) Flusing of tank with Sea / fresh water\n(v) Check for any damage to the tank / connecting nozzles\n(vi) Minor cold repair of the tank if any | 9 | Nos | |
14 | 1.32 | Cleaning and checking of Level switch | 9 | Nos | |
15 | 1.33 | Replacement of level switch | 9 | Nos | |
16 | 1.34 | Cleaning of manifold piping and instrument valves | 9 | Nos | |
17 | 1.35 | Cleaning and calibration / setting of Vacuum switch | 9 | Nos | |
18 | 1.4 | System Valves | |||
19 | 1.41 | Overhauling of Gate Valve - Size DN 65 | 9 | Nos | |
20 | 1.42 | Renewal of valve spindle / stem - Size DN 65 | 9 | Nos | |
21 | 1.43 | Renewal of valve seat (Rubber moulded resilient valve seat) - Size DN 65 | 9 | Nos | |
22 | 1.44 | Overhauling of Gate Valve - Size DN 100 | 9 | Nos | |
23 | 1.45 | Renewal of valve spindle / stem - Size DN 100 | 9 | Nos | |
24 | 1.46 | Renewal of valve seat (Rubber moulded resilient valve seat) - Size DN 100 | 9 | Nos | |
25 | 1.47 | Overhauling of Motorised Valve - Size DN 65 | 9 | Nos | |
26 | 1.48 | Replacement of valve | 9 | Nos | |
27 | 1.5 | Control Panel | |||
28 | 1.51 | Overhauling of complete control panel | 9 | Nos | |
29 | 1.52 | Defect rectification of control panel | 9 | Nos | |
30 | 1.53 | Checking of interface with STP | 9 | Nos | |
31 | 2 | Evac Vacuum Toilet System - Onlineflex Type - (INS Makar) | |||
32 | 2.1 | Vacuum Pump | |||
33 | 2.11 | Complete Overhauling of Pump (Onlineflex Pump) | 3 | Nos | |
34 | 2.12 | Complete Overhauling of Motor | 3 | Nos | |
35 | 2.13 | Defect recrification of vacuum pump | 3 | Nos | |
36 | 2.14 | Rewindong of Motor | 3 | Nos | |
37 | 2.15 | Replacement of pump | 3 | Nos | |
38 | 2.2 | System Valves | |||
39 | 2.21 | Overhauling of Ball Valve | 3 | Nos | |
40 | 2.23 | Overhauling of Non Return Valve | 3 | Nos | |
41 | 2.24 | Renewal of valve | 3 | Nos | |
42 | 2.25 | Cleaning of vacuum manifold piping and instrument valves | 3 | Nos | |
43 | 2.26 | Cleaning of catcher unit | 3 | Nos | |
44 | 2.3 | Control Panel | |||
45 | 2.31 | Defect rectification of control panel (Excluding PLC) | 3 | Nos | |
46 | 2.32 | Replacement and Programming of PLC | 3 | Nos | |
47 | 2.33 | Overhauling of complete control panel | 3 | Nos | |
48 | 3 | Evac Vacuum Toilet System, Vacuum Interface Valves and Vacuum Piping (INS Aditya, INS Makar, INS Suvarna & INS Subhadra) | |||
49 | 3.1 | Vacuum Toilet | |||
50 | 3.11 | Complete overhauling of Vacuum toilet | 12 | Nos | |
51 | 3.12 | Defect rectification of vacuum toilet | 12 | Nos | |
52 | 3.13 | Repair / Renewal of toilet foundation (Fabrication work) | 12 | Nos | |
53 | 3.14 | Replacement of Vacuum toilet | 12 | Nos | |
54 | 3.2 | Vacuum Interface Valve | |||
55 | 3.21 | Complete overhauling of Vacuum Interface Valve | 12 | Nos | |
56 | 3.22 | Defect rectification of Vacuum Interface Valve | 12 | Nos | |
57 | 3.23 | Repair / Renewal of Vacuum Interface Valve foundation | 12 | Nos | |
58 | 3.24 | Renewal of Vacuum Interface Valve | 12 | Nos | |
59 | 3.3 | Vacuum Interface Valve (Scupper Type) | |||
60 | 3.31 | Complete overhauling of Vacuum Interface Valve | 12 | Nos | |
61 | 3.32 | Defect rectification of Vacuum Interface Valve | 12 | Nos | |
62 | 3.4 | Vacuum Piping | |||
63 | 3.41 | Repair of vacuum connection (Deck piece) | 12 | Nos | |
64 | 3.42 | Renewal of deck piece (Fabrication work) | 12 | Nos | |
65 | 3.43 | Chemical cleaning of vacuum piping by removal of piping, mechanical and chemical cleaning of piping, Pressure / vacuum testing of piping and fittment (Per Mtr) | 12 | Nos | |
66 | 3.44 | Renewal of vacuum piping (MS schedule 40) excluding piping material (Per Mtr) | 12 | Nos | |
67 | 3.45 | Identification of vacuum leakage in system | 12 | Nos | |
68 | 3.5 | Vacuum Generator Trials | |||
69 | 3.51 | Testing and trials of the Vacuum Generator in Manual and Auto mode | 12 | Nos | |
70 | 4 | PART 2 - Sewage Treatment Plant\nSewage Treatment Plant - ORCA II A 165 with Chlorine Generator (INS Makar) | |||
71 | 4.1 | Treatment Tank | |||
72 | 4.11 | Chemical cleaning of tank\n(i) Opening of tank cover and checking the H2S level in the tank.\n(ii) Ventilation of the tank\n(iii) Removal of Sewage Water from the tank.\n(iv) Flushing of tank with Sea / fresh water\n(v) Check for any damage to the tank / connecting nozzles\n(vi) Minor cold repair of the tank if any | 3 | Nos | |
73 | 4.12 | Internal coating of tank | 3 | Nos | |
74 | 4.13 | Cleaning and checking of Lever switch | 3 | Nos | |
75 | 4.14 | Replacement of level switch | 3 | Nos | |
76 | 4.15 | Cleaning and checking of internal components like spray nozzles, screen | 3 | Nos | |
77 | 4.16 | Cleaning of Sacrificial Anode | 3 | Nos | |
78 | 4.17 | Renewal of Sacrificial Anode | 3 | Nos | |
79 | 4.2 | Sedimentation Tanks | |||
80 | 4.21 | Chemical cleaning of tank\n(i) Opening of tank cover and checking the H2S level in the tank.\n(ii) Ventilation of the tank\n(iii) Removal of Sewage Water from the tank.\n(iv) Flushing of tank with Sea / fresh water\n(v) Check for any damage to the tank / connecting nozzles\n(vi) Minor cold repair of the tank if any | 3 | Nos | |
81 | 4.22 | Internal coating of tank | 3 | Nos | |
82 | 4.23 | Cleaning and checking of float valve | 3 | Nos | |
83 | 4.24 | Replacement of Float valve | 3 | Nos | |
84 | 4.3 | System Valves | |||
85 | 4.31 | Cleaning / Renewal of ball valves / Flow control valve | 3 | Nos | |
86 | 4.32 | Overhauling of Solenoid valve | 3 | Nos | |
87 | 4.33 | Cleaning and Overhauling of STP discharge valve | 3 | Nos | |
88 | 4.34 | Replacement of STP discharge valve | 3 | Nos | |
89 | 4.4 | Sea Water pump, Sludge pump, Flow pump and Discharge pump | |||
90 | 4.41 | Complete Overhauling of Pump | 3 | Nos | |
91 | 4.42 | Complete Overhauling of Motor | 3 | Nos | |
92 | 4.43 | Defect rectification of pump | 3 | Nos | |
93 | 4.44 | Replacement of pump | 3 | Nos | |
94 | 4.45 | Rewinding of Motor | 3 | Nos | |
95 | 4.5 | Dosing pump | |||
96 | 4.51 | Complete Overhauling of Pump | 3 | Nos | |
97 | 4.52 | Defect rectification of pump | 3 | Nos | |
98 | 4.53 | Replacement of pump | 3 | Nos | |
99 | 5 | Sewage Treatment Plant - ORCA II A 165 with Chlorine Generator (INS Makar) | |||
100 | 5.1 | STP Control Panel | |||
101 | 5.11 | Check and clean the electrical components and switches | 3 | Nos | |
102 | 5.12 | Repair of control panel | 3 | Nos | |
103 | 5.13 | Replacement of PLC | 3 | Nos | |
104 | 5.14 | Overhauling of complete control panel | 3 | Nos | |
105 | 5.2 | Chlorine Generator | |||
106 | 5.21 | Overhauling / Defect rectification of Chlorine generator | 3 | Nos | |
107 | 5.3 | Chlorine Generator Control Panel | |||
108 | 5.31 | Repair of control panel | 3 | Nos | |
109 | 5.32 | Overhauling of complete control panel | 3 | Nos | |
110 | 5.4 | STP system piping | |||
111 | 5.41 | Chemical cleaning of STP piping (Internal piping within STP) | 3 | Nos | |
112 | 5.5 | STP Trials | |||
113 | 5.51 | Testing and trials of the STP in Manual and Auto mode | 3 | Nos | |
114 | 6 | Evac Sewage Treatment Plant - Type- ORCA III (INS Aditya and INS Suvarna) | |||
115 | 6.1 | Sedimentation Tank | |||
116 | 6.11 | Chemical cleaning of tank\n(i) Opening of tank cover and checking the H2S level in the tank.\n(ii) Ventilation of the tank\n(iii) Removal of Sewage Water from the tank.\n(iv) Flushing of tank with Sea / fresh water\n(v) Check for any damage to the tank / connecting nozzles\n(vi) Minor cold repair of the tank if any | 3 | Nos | |
117 | 6.12 | Internal coating of tank | 3 | Nos | |
118 | 6.13 | Cleaning and checking of Minim skimmer | 3 | Nos | |
119 | 6.14 | Cleaning and checking of lamella plates | 3 | MM2 | |
120 | 6.2 | Oxidising Tank | |||
121 | 6.21 | Chemical cleaning of tank\n(i) Opening of tank cover and checking the H2S level in the tank.\n(ii) Ventilation of the tank\n(iii) Removal of Sewage Water from the tank.\n(iv) Flushing of tank with Sea / fresh water\n(v) Check for any damage to the tank / connecting nozzles\n(vi) Minor cold repair of the tank if any | 3 | Nos | |
122 | 6.22 | Internal coating of tank | 3 | Nos | |
123 | 6.23 | Cleaning and checking of level switch | 3 | Nos | |
124 | 6.24 | Replacement of level switch | 3 | Nos | |
125 | 7 | Evac Sewage Treatment Plant - Type- ORCA III (INS Aditya and INS Suvarna) | |||
126 | 7.1 | System Valves | |||
127 | 7.11 | Cleaning of ball valves | 6 | Nos | |
128 | 7.12 | Replacement of PVC ball valve | 6 | Nos | |
129 | 7.13 | Defect rectification of electro-pneumatic valve | 6 | Nos | |
130 | 7.14 | Overhauling of electro-pneumatic valve | 6 | Nos | |
131 | 7.15 | Replacement of electro-pneumatic valve | 7 | Nos | |
132 | 7.16 | Defect rectification of solenoid valve | 6 | Nos | |
133 | 7.17 | Overhauling of solenoid valve | 6 | Nos | |
134 | 7.18 | Replacement of solenoid valve | 6 | Nos | |
135 | 7.19 | Cleaning of SS ball valves | 6 | Nos | |
136 | 7.2 | Replacement of SS ball valves | 6 | Nos | |
137 | 7.3 | System Components | |||
138 | 7.31 | Cleaning of brushaway filter | 6 | Nos | |
139 | 7.32 | Renewal of brushaway filter | 6 | Nos | |
140 | 7.33 | Overhauling of brushaway filter | 6 | Nos | |
141 | 7.34 | Cleaning of static mixer | 6 | Nos | |
142 | 7.35 | Renewal of static mixer | 6 | Nos | |
143 | 7.36 | Checking of sacrificial anode | 6 | Nos | |
144 | 7.37 | Renewal of sacrificial anode | 6 | Nos | |
145 | 7.38 | Cleaning of non return valve | 6 | Nos | |
146 | 7.39 | Replacement of non return valve | 6 | Nos | |
147 | 7.4 | Cleaning / Renewal of hypochlorite chemical tank | 6 | Nos | |
148 | 7.5 | Sea water pump, Recirculation / Discharge Pump, Macerator Pump and Sludge pump | |||
149 | 7.51 | Complete Overhauling of Pump | 6 | Nos | |
150 | 7.52 | Complete Overhauling of Motor | 6 | Nos | |
151 | 7.53 | Defect rectification of pump | 6 | Nos | |
152 | 7.54 | Replacement of pump | 6 | Nos | |
153 | 7.55 | Rewinding of Motor | 6 | Nos | |
154 | 7.6 | Hypochlorite dosing pump and Floculant dosing pump | |||
155 | 7.61 | Complete Overhauling of Pump | 6 | Nos | |
156 | 7.62 | Defect rectification of pump | 6 | Nos | |
157 | 7.63 | Replacement of pump | 6 | Nos | |
158 | 7.7 | STP Control Panel | |||
159 | 7.71 | Check and clean the electrical components and switches | 6 | Nos | |
160 | 7.72 | Repair of control panel | 6 | Nos | |
161 | 7.73 | Replacement of PLC | 6 | Nos | |
162 | 7.74 | Replacement and Programming of PLC | 6 | Nos | |
163 | 7.75 | Overhauling ofcomplete control panel | 6 | Nos | |
164 | 7.8 | STP Trials | |||
165 | 7.81 | Testing and trials of the STP in Manual and Auto mode | 6 | Nos | |
166 | 7.9 | STP Tests | |||
167 | 7.91 | Effluent Test as per MARPOL | 6 | Nos | |
168 | 8 | PART 3 - Sewage Treatment Plant (Yard Craft)\nEvac Sewage Treatment Plant - Type- N40CE (Tug Dhiraj, Himmat and Sahas) | |||
169 | 8.1 | Sewage Tank | |||
170 | 8.11 | Chemical cleaning of tank\n(i) Opening of tank cover and checking the H2S level in the tank.\n(ii) Ventilation of the tank\n(iii) Removal of Sewage Water from the tank.\n(iv) Flushing of tank with Sea / fresh water\n(v) Check for any damage to the tank / connecting nozzles\n(vi) Minor cold repair of the tank if any | 9 | Nos | |
171 | 8.12 | Internal coating of tank | 9 | Nos | |
172 | 8.13 | Cleaning and checking of Level Switch | 9 | Nos | |
173 | 8.14 | Replacement of Level Switch | 9 | Nos | |
174 | 8.2 | Effluent Tank | |||
175 | 8.21 | Chemical cleaning of tank\n(i) Opening of tank cover and checking the H2S level in the tank.\n(ii) Ventilation of the tank\n(iii) Removal of Sewage Water from the tank.\n(iv) Flushing of tank with Sea / fresh water\n(v) Check for any damage to the tank / connecting nozzles\n(vi) Minor cold repair of the tank if any | 9 | Nos | |
176 | 8.22 | Internal coating of tank | 9 | Nos | |
177 | 8.23 | Cleaning and checking of Level Switch | 9 | Nos | |
178 | 8.24 | Replacement of Level Switch | 9 | Nos | |
179 | 8.3 | System Valves | |||
180 | 8.31 | Cleaning and overhauling of Solenoid valve | 9 | Nos | |
181 | 8.32 | Replacement of Solenoid valve | 9 | Nos | |
182 | 8.33 | Cleaning and overhauling of motorised Solenoid valve | 9 | Nos | |
183 | 8.34 | Replacement of motorised Solenoid valve | 9 | Nos | |
184 | 8.35 | Cleaning and overhauling of system ball valve | 9 | Nos | |
185 | 8.36 | Replacement of system valve | 9 | Nos | |
186 | 8.4 | STP system piping | |||
187 | 8.41 | Chemical cleaning of STP piping (Internal piping within STP) | 9 | Nos | |
188 | 8.5 | Electrolysis cell | |||
189 | 8.51 | Opening, Overhauling / Defect rectification of Chlorine generator | 9 | Nos | |
190 | 8.52 | Replacement of complete electrolysis cell | 9 | Nos | |
191 | 8.6 | Main pump and Discharge pump | |||
192 | 8.61 | Complete Overhauling of Pump | 9 | Nos | |
193 | 8.62 | Complete Overhauling of Motor | 9 | Nos | |
194 | 8.63 | Defect rectification of pump | 9 | Nos | |
195 | 8.64 | Replacement of pump | 9 | Nos | |
196 | 8.65 | Rewinding of Motor | 9 | Nos | |
197 | 9 | Evac Sewage Treatment Plant - Type- N40CE (Tug Dhiraj, Himmat, Sahas) | |||
198 | 9.1 | STP Control Panel | |||
199 | 9.11 | Check and clean the electrical components and switches | 9 | Nos | |
200 | 9.12 | Repair of control panel | 9 | Nos | |
201 | 9.13 | Overhauling of complete control panel | 9 | Nos | |
202 | 10 | Evac Sewage Treatment Plant - Type- STP 20 (Sullage Barge VI) | |||
203 | 10.1 | Airation Chamber I | |||
204 | 10.11 | Chemical cleaning of tank\n(i) Opening of tank cover and checking the H2S level in the tank.\n(ii) Ventilation of the tank\n(iii) Removal of Sewage Water from the tank.\n(iv) Flushing of tank with Sea / fresh water\n(v) Check for any damage to the tank / connecting nozzles\n(vi) Minor cold repair of the tank if any | 9 | Nos | |
205 | 10.12 | Internal coating of Chamber | 9 | Nos | |
206 | 10.2 | Airation Chamber II | |||
207 | 10.21 | Chemical cleaning of tank\n(i) Opening of tank cover and checking the H2S level in the tank.\n(ii) Ventilation of the tank\n(iii) Removal of Sewage Water from the tank.\n(iv) Flushing of tank with Sea / fresh water\n(v) Check for any damage to the tank / connecting nozzles\n(vi) Minor cold repair of the tank if any | 9 | Nos | |
208 | 10.22 | Internal coating of Chamber | 9 | Nos | |
209 | 10.3 | Settling Chamber | |||
210 | 10.31 | Chemical cleaning of tank\n(i) Opening of tank cover and checking the H2S level in the tank.\n(ii) Ventilation of the tank\n(iii) Removal of Sewage Water from the tank.\n(iv) Flushing of tank with Sea / fresh water\n(v) Check for any damage to the tank / connecting nozzles\n(vi) Minor cold repair of the tank if any | 9 | Nos | |
211 | 10.32 | Internal coating of Chamber | 9 | Nos | |
212 | 10.4 | Disinfection Chamber | |||
213 | 10.41 | Chemical cleaning of tank\n(i) Opening of tank cover and checking the H2S level in the tank.\n(ii) Ventilation of the tank\n(iii) Removal of Sewage Water from the tank.\n(iv) Flushing of tank with Sea / fresh water\n(v) Check for any damage to the tank / connecting nozzles\n(vi) Minor cold repair of the tank if any | 9 | Nos | |
214 | 10.42 | Internal coating of Chamber | 9 | Nos | |
215 | 10.43 | Cleaning and checking of Level Switch | 9 | Nos | |
216 | 10.44 | Replacement of Level Switch | 9 | Nos | |
217 | 11 | Evac Sewage Treatment Plant - Type- STP 20 (Sullage Barge VI) | |||
218 | 11.1 | System Valves | |||
219 | 11.11 | Overhauling of Gate Valve - Size DN 65 | 9 | Nos | |
220 | 11.12 | Renewal of valve spindle / stem - Size DN 65 | 9 | Nos | |
221 | 11.13 | Renewal of valve seat (Rubber moulded resilient valve seat) - Size DN 65 | 9 | Nos | |
222 | 11.14 | Overhauling of Gate Valve - Size DN 50 | 9 | Nos | |
223 | 11.15 | Renewal of valve spindle / stem - Size DN 50 | 9 | Nos | |
224 | 11.16 | Renewal of valve seat (Rubber moulded resilient valve seat) - Size DN 50 | 9 | Nos | |
225 | 11.17 | Replacement of valve | 9 | Nos | |
226 | 11.18 | Cleaning of non returned valve | 9 | Nos | |
227 | 11.19 | Replacement of non returned valve | 9 | Nos | |
228 | 11.2 | STP system piping | |||
229 | 11.21 | Chemical cleaning of STP piping (Internal piping within STP) | 9 | Nos | |
230 | 11.3 | Discharge pump | |||
231 | 11.31 | Complete Overhauling of Pump | 9 | Nos | |
232 | 11.32 | Complete Overhauling of Motor | 9 | Nos | |
233 | 11.33 | Defect rectification of pump | 9 | Nos | |
234 | 11.34 | Replacement of pump | 9 | Nos | |
235 | 11.35 | Rewinding of Motor | 9 | Nos | |
236 | 11.4 | Air Blower | |||
237 | 11.41 | Complete Overhauling of Pump | 9 | Nos | |
238 | 11.42 | Complete Overhauling of Motor | 9 | Nos | |
239 | 11.43 | Defect rectification of pump | 9 | Nos | |
240 | 11.44 | Replacement of pump | 9 | Nos | |
241 | 11.45 | Rewinding of Motor | 9 | Nos | |
242 | 11.5 | Dosing pump | |||
243 | 11.51 | Complete Overhauling of Pump | 9 | Nos | |
244 | 11.52 | Defect rectification of pump | 9 | Nos | |
245 | 11.53 | Replacement of pump | 9 | Nos | |
246 | 11.6 | STP Control Panel | |||
247 | 11.61 | Check and clean the electrical components and switches | 9 | Nos | |
248 | 11.62 | Repair of control panel | 9 | Nos | |
249 | 11.63 | Overhauling of complete control panel | 9 | Nos | |
250 | 11.7 | STP Trials | |||
251 | 11.71 | Testing and trials of the STP in Manual and Auto mode | 9 | Nos | |
252 | 11.8 | STP Tests | |||
253 | 11.81 | Effluent Test as per MARPOL | 9 | Nos | |
254 | 12 | SPARES FOR EVAC VACUUM TOILET SYSTEM AND SEWAGE TREATMENT PLANTS\nINS Aditya - Vacuum Toilet System | |||
255 | 12.1 | Vacuum Toilets | |||
256 | 12.11 | Hose | 3 | Nos | |
257 | 12.2 | Evac SE 044A Pumps and Ejector | |||
258 | 12.21 | Rubber Gasket | 3 | Nos | |
259 | 13 | INS Aditya - Sewage Treatment Plant - ORCA III 100 | |||
260 | 13.1 | ORCA III STP 100 - 6549028 | |||
261 | 13.11 | Cathodic Protection Sacrificial Anode | 3 | Nos | |
262 | 13.12 | Air Pressure Regulator | 3 | Nos | |
263 | 13.13 | Actuator 3/2,1/8 220 AC | 3 | Nos | |
264 | 13.14 | Plug | 3 | Nos | |
265 | 13.15 | Nipple | 3 | Nos | |
266 | 13.2 | 6552393-Macerator Pump, OMCRP 100/4 | |||
267 | 13.21 | Countersunk Screw M8 x 30 D IN 7991 -A2 | 3 | Nos | |
268 | 13.22 | Rotor Disc Retaining Washer | 3 | Nos | |
269 | 13.23 | Cyclone | 3 | Nos | |
270 | 13.24 | O-ring 185x3 70 NBR | 3 | Nos | |
271 | 13.25 | Locking Ring 30 D IN 471 | 3 | Nos | |
272 | 13.3 | 6549080-Sludge Pump, ORSSP 5-2 | |||
273 | 13.31 | Kit, Gaskets Complete | 3 | Nos | |
274 | 13.32 | Kit, Motor Bearing Complete | 3 | Nos | |
275 | 13.33 | Kit, Plug Complete | 3 | Nos | |
276 | 13.34 | Kit, Repair Complete | 3 | Nos | |
277 | 13.4 | 6549083-Recicul/Disch Pump & Seawater Pump | |||
278 | 13.41 | Kit, Plug Complete | 3 | Nos | |
279 | 14 | INS Aditya - Sewage Treatment Plant - ORCA III 15 | |||
280 | 14.41 | ORCA III STP 100 - 6549024 | |||
281 | 14.42 | Cathodic Protection Sacrificial Anode | 3 | Nos | |
282 | 14.43 | Air Pressure Regulator | 3 | Nos | |
283 | 14.44 | Actuator 3/2,1/8 220 AC | 3 | Nos | |
284 | 14.45 | Plug | 3 | Nos | |
285 | 14.46 | Nipple | 3 | Nos | |
286 | 14.5 | Macerator Pump-6552392, OMCRP 100/6 | |||
287 | 14.51 | Countersunk Screw M8 x 30 D IN 7991 -A2 | 3 | Nos | |
288 | 14.52 | Rotor Disc Retaining Washer | 3 | Nos | |
289 | 14.53 | Cyclone | 3 | Nos | |
290 | 14.54 | O-ring 185x3 70 NBR | 3 | Nos | |
291 | 14.55 | Multiple Knife | 3 | Nos | |
292 | 14.56 | Locking Ring 30 D IN 471 | 3 | Nos | |
293 | 14.6 | 6549083-Reciculation/Discharge Pump, Sludge & Seawater Pump | |||
294 | 14.61 | Kit, Gaskets Complete | 3 | Nos | |
295 | 14.62 | Kit, Motor Bearing Complete | 3 | Nos | |
296 | 14.63 | Kit, Plug Complete | 3 | Nos | |
297 | 14.64 | Kit, Repair Complete | 3 | Nos | |
298 | 14.7 | INS Makar - Vacuum Toilet System | |||
299 | 14.71 | Pneumatic Push Button | 3 | Nos | |
300 | 14.72 | Recommended Spare Part Kit | 3 | Nos | |
301 | 14.73 | LOGO 12/24 RC | 3 | Nos | |
302 | 14.74 | LOGO DM8 12/24 R | 3 | Nos | |
303 | 15 | INS Makar - Sewage Treatment Plant - ORCA II A 165 | |||
304 | 15.1 | Transfer Pump | |||
305 | 15.11 | Key | 3 | Nos | |
306 | 15.12 | Coupling | 3 | Nos | |
307 | 15.13 | Screw, Set | 3 | Nos | |
308 | 15.14 | Ring, Snap | 3 | Nos | |
309 | 15.15 | Bearing | 3 | Nos | |
310 | 15.16 | Ring Slinger | 3 | Nos | |
311 | 15.17 | Seal, Mechanical | 3 | Nos | |
312 | 15.18 | Gasket, Adapter plate | 3 | Nos | |
313 | 15.19 | Rotor | 3 | Nos | |
314 | 15.2 | Pin Rotor | 3 | Nos | |
315 | 15.21 | Stator | 3 | Nos | |
316 | 15.22 | Gasket Reducer | 3 | Nos | |
317 | 15.23 | Screw | 3 | Nos | |
318 | 15.24 | Tip Cutter | 3 | Nos | |
319 | 15.25 | Clamp, Cutter | 3 | Nos | |
320 | 15.26 | Screw | 3 | Nos | |
321 | 15.27 | Motor, 1HP, 2850RPM, 380V, 3PH, 50HZ | 3 | Nos | |
322 | 15.3 | INS Subhadra - Vacuum Toilet System | |||
323 | 15.31 | Screw | 3 | Nos | |
324 | 15.32 | O-Ring | 3 | Nos | |
325 | 15.33 | Reducer 1 1/4" -50mm With Vacuum Nipple | 3 | Nos | |
326 | 15.4 | EVAC Vacuum Toilet 910, Floor Model, Trevi | |||
327 | 15.41 | Membrane | 3 | Nos | |
328 | 15.42 | Closing Mechanism | 3 | Nos | |
329 | 15.43 | Screw | 3 | Nos | |
330 | 15.5 | EVAC Vacuum Toilet 910, Floor Model, Trevi | |||
331 | 15.51 | Membrane | 3 | Nos | |
332 | 15.52 | Closing Mechanism | 3 | Nos | |
333 | 16 | INS Suvarna - Sewage Treatment Plant - ORCA III 50 | |||
334 | 16.1 | ORCA III STP 100 - 6549028 | |||
335 | 16.11 | Cathodic Protection Sacrificial Anode | 3 | Nos | |
336 | 16.12 | Air Pressure Regulator | 3 | Nos | |
337 | 16.13 | Actuator 3/2,1/8 220 AC | 3 | Nos | |
338 | 16.14 | Plug | 3 | Nos | |
339 | 16.15 | Nipple | 3 | Nos | |
340 | 16.2 | 6552393-Macerator Pump | |||
341 | 16.21 | Countersunk Screw | 3 | Nos | |
342 | 16.22 | Rotor Disc Retaining Washer | 3 | Nos | |
343 | 16.23 | Cyclone | 3 | Nos | |
344 | 16.24 | O-Ring | 3 | Nos | |
345 | 16.25 | Locking Ring | 3 | Nos | |
346 | 16.3 | 6549083-Sludge Pump Rec/Disc Pump, & Sea water Pump | |||
347 | 16.31 | Kit, Gaskets Complete | 3 | Nos | |
348 | 16.32 | Kit, Motor Bearing Complete | 3 | Nos | |
349 | 16.33 | Kit, Plug Complete | 3 | Nos | |
350 | 16.34 | Kit, Repair Complete | 3 | Nos | |
351 | 16.4 | Sullage Barge VI - Biological STP 20 | |||
352 | 16.41 | Impeller | 3 | Nos | |
353 | 16.42 | Spare Part Kit for Blower | 3 | Nos | |
354 | 16.43 | Motor Protection Circuit Breaker | 3 | Nos | |
355 | 16.44 | Motor Protection Circuit Breaker | 3 | Nos | |
356 | 16.45 | Aux Relay | 3 | Nos | |
357 | 16.46 | Aux Relay Base | 3 | Nos | |
358 | 16.47 | Contactor | 3 | Nos | |
359 | 17 | Tug Himmat, Sahas And Dhiraj | |||
360 | 17.1 | Sewage Treatment Plant - N 25 CE | |||
361 | 17.11 | Ball Valve 8A Screw | 9 | Nos | |
362 | 17.12 | Ball Valve 20A Screw | 9 | Nos | |
363 | 17.13 | Thermo Sensor Hyundai | 9 | Nos | |
364 | 17.14 | Main Pump Bearing | 9 | Nos | |
365 | 17.15 | Main Pump Meachanical Seal | 9 | Nos | |
366 | 17.16 | Main Pump Impeller | 9 | Nos | |
367 | 17.17 | Discharge Pump Bearing | 9 | Nos | |
368 | 17.18 | Discharge Pump Mechanical Seal | 9 | Nos | |
369 | 17.19 | Discharge Pump Impeller | 9 | Nos | |
370 | 17.2 | O-Ring P35 | 9 | Nos | |
371 | 17.21 | Rubber Gasket 12.7 T | 9 | Nos | |
372 | 17.22 | Solenoid Valve 15 A | 9 | Nos | |
373 | 17.23 | Solenoid Valve 15 A | 9 | Nos | |
374 | 17.24 | Level Sensor A Type | 9 | Nos | |
375 | 17.25 | Pressure Gauge 0-1 Kg | 9 | Nos | |
376 | 17.26 | Pressure Gauge 1-6 Kg | 9 | Nos | |
377 | 17.27 | Diode 1600V, 120A | 9 | Nos | |
378 | 17.28 | Fuse 80 A | 9 | Nos | |
379 | 17.29 | Circuit Breake BKM 1P 4A | 9 | Nos | |
380 | 17.3 | Contactor GMC-9 | 9 | Nos | |
381 | 17.31 | Contactor GTH-22 (1.3A) | 9 | Nos | |
382 | 17.32 | Contactor GMC-18 | 9 | Nos | |
383 | 17.33 | Contactor GTH-22 (5A) | 9 | Nos | |
384 | 17.34 | Relay 4 L with Base | 9 | Nos | |
385 | 17.35 | C/H Switch 3 Type | 9 | Nos | |
386 | 17.36 | Push Lamp, Dia 25 mm | 9 | Nos | |
387 | 17.37 | Pilot Lamp, Dia 25 mm | 9 | Nos | |
388 | 17.38 | Pilot Lamp, Dia 25 mm | 9 | Nos | |
389 | 17.39 | Buzzer, Dia 25 mm | 9 | Nos | |
390 | 17.4 | Ammeter DAM 100A DC | 9 | Nos | |
391 | 17.41 | Voltmeter VM 50 V DC | 9 | Nos | |
392 | 17.42 | Aux. contact AU4 (4A) | 9 | Nos | |
393 | 17.43 | Emergency Button | 9 | Nos | |
394 | 17.44 | Check Valve 20A-10K (Flange Type) | 9 | Nos |