| 1 | 1 | Remuneration for Local Professional Staff key personnel | | | |
|---|
| 2 | 1.01 | :Professional Staff | | | |
|---|
| 3 | 1.02 | Team Leader Cum Senior Bridge Engineer | item3 | 1 | Nos. |
|---|
| 4 | 1.03 | Material-cum-Geotechnical Engineer-Gerlogist | item4 | 1 | Nos. |
|---|
| 5 | 1.04 | Senior Survery Enginer | item5 | 1 | Nos. |
|---|
| 6 | 1.05 | Traffic and Safety Expert | item7 | 1 | Nos. |
|---|
| 7 | 1.06 | Quantity Surveyor / Documentation Expert | item8 | 1 | Nos. |
|---|
| 8 | 2 | Support Staff | | | |
|---|
| 9 | 2.1 | Office Manager | item12 | 1 | Nos. |
|---|
| 10 | 2.2 | Typist | item13 | 1 | Nos. |
|---|
| 11 | 2.3 | Office Boy | item14 | 1 | Nos. |
|---|
| 12 | 3 | Transportation (Fixed costs)\n \nThe vehicles provided by the Consultants shall include the cost for rental, drivers, operation, maintenance, repairs, insurance, etc. | | | |
|---|
| 13 | 3.1 | For Use of Consultants | item16 | 1 | Nos. |
|---|
| 14 | 4 | Duty Travel to Site (Fixed Costs): \n\nTrips | item17 | 1 | Nos. |
|---|
| 15 | 5 | Office Rent (Fixed Costs)\n\nThe rent cost includes, maintenance, Cleaning, repairs, etc. | | | |
|---|
| 16 | 5.1 | 2 Months x_ | item18 | 1 | Nos. |
|---|
| 17 | 6 | Office Supplies, Utilities and Communication (Fixed Costs) | | | |
|---|
| 18 | 6.1 | Office Supplies Drafting | item19 | 1 | Nos. |
|---|
| 19 | 6.2 | Supplies Computer | item20 | 1 | Nos. |
|---|
| 20 | 6.3 | Running Costs | item21 | 1 | Nos. |
|---|
| 21 | 6.4 | Domestic and International Communication | item22 | 1 | Nos. |
|---|
| 22 | 7 | Office Furniture and Equipment (Rental) | | | |
|---|
| 23 | 7.01 | Office Furniture and Equipment (Rental) | item23 | 1 | Nos. |
|---|
| 24 | 8 | Reports and Document Printing | | | |
|---|
| 25 | 8.01 | Monthly reports (3 Copies per Month) | item24 | 3 | Per Months |
|---|
| 26 | 8.02 | Inception Report & QAP | item25 | 3 | Per Months |
|---|
| 27 | 8.03 | Environment and Social Impact Screening Report | item26 | 4 | Per Months |
|---|
| 28 | 8.04 | Draft Feasibility Report | item27 | 4 | Per Months |
|---|
| 29 | 8.05 | Final Feasibility Report | item28 | 6 | Per Months |
|---|
| 30 | 8.06 | Draft Environmental Assessment Report and RAP | item29 | 4 | Per Months |
|---|
| 31 | 8.07 | Final Environment Assessment Report and RAP | item30 | 6 | Per Months |
|---|
| 32 | 8.08 | Draft Detailed Design Report and Drawings etc. | item31 | 4 | Per Months |
|---|
| 33 | 8.09 | Draft EMP | item32 | 4 | Per Months |
|---|
| 34 | 8.1 | Draft Bidding Documents | item33 | 4 | Per Months |
|---|
| 35 | 8.11 | Final Detailed Project Report with Bill of Quantitieis, Cost Estimates, Updated Drawings etc. | item34 | 6 | Per Months |
|---|
| 36 | 8.12 | Final EMP | item35 | 6 | Per Months |
|---|
| 37 | 8.13 | Final Bidding Documents | item36 | 6 | Per Months |
|---|
| 38 | 9 | Survey and Investigation\n(A) Topographical Survey (Fixed Rate) | | | |
|---|
| 39 | 9.1 | Topographic Survey including hire charges for equipment and supply of survey teams comprising of project survey filed staff etc. inclusive of cost of materials, labourer | item42 | 3 | Km |
|---|
| 40 | 9.2 | Detailed topographic surveys using mobile / aerial LiDAR or equivalent technology. | item43 | 3 | Km |
|---|
| 41 | 10 | Investigation (Fixed Cost) | | | |
|---|
| 42 | 10.01 | Road and Bridge Inventory | item44 | 1 | Nos. |
|---|
| 43 | 10.02 | BBD Test and Pavement Evaluation | item45 | 1 | Nos. |
|---|
| 44 | 10.03 | Axle Load Survey | item46 | 1 | Nos. |
|---|
| 45 | 10.04 | Material Survery and Investigation | item47 | 1 | Nos. |
|---|
| 46 | 10.05 | Sub-grade Investigation | item48 | 1 | Nos. |
|---|
| 47 | 10.06 | Traffic Survey | item49 | 1 | Nos. |
|---|
| 48 | 10.07 | Socio-economic & Census Survey/Studies | item50 | 1 | Nos. |
|---|
| 49 | 10.08 | Any other investigations/Surveys | item51 | 1 | Nos. |
|---|
| 50 | 11 | Sub-Soil Investigation (Boring) | | | |
|---|
| 51 | 11.1 | Boring in all type of soils (other than hard rock) | item54 | 1500 | Mtr. |
|---|
| 52 | 12 | Total | | | |
|---|
| 53 | 13 | Bid GST in Percentage (%) | item56 | 1 | Nos. |
|---|