Plan Fund_Construction Of Playing Ground , Compound Wall And Gate At Womens Polytechnic College , Malaparmba , Kozhikode Construction
Tender Value
22.27 Lakhs
Estimated cost
Bid Submission
26 Mar 2020
0 days left
EMD
50000
Bank guarantee accepted
Document Fee
2760
Non-refundable
Tender Type
Online
Tender Overview
Organization
Tender ID
Competition Type
NCB
Bidding Type
Tender
Location / State
Malaparamba → Kerala
EMD Exemption
Not Available
Quantity
Not Available
Website
Contact Person
Address
Project Description
Plan Fund_Construction Of Playing Ground , Compound Wall And Gate At Womens Polytechnic College , Malaparmba , Kozhikode Construction
BOQ
| Work Name:Construction of Playing Ground ,Compound wall and Gate at Womens Polytechnic College, Malaparmba,Kozhikode | |||||
|---|---|---|---|---|---|
| Sl.No. | Item Description | Item Code / Make | Quantity | Units | |
| 1 | 1 | Detailed Estimate | BI01010001010000000000000515BI0100001113 | ||
| 2 | 1.01 | 2.6.1 : Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including disposal of excavated earth, lead up to 50 m and lift up to 1.5 m, disposed earth to be levelled and neatly dressed.All kinds of soil | BI01010001010000000000000515BI0100001114 | 2500 | cum |
| 3 | 1.02 | 2.8.1 : Earth work in excavation by mechanical means (Hydraulic excavator) /manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m.All kinds of soil | BI01010001010000000000000515BI0100001115 | 134.4 | cum |
| 4 | 1.03 | 4.1.8 : Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40 nominal size) | BI01010001010000000000000515BI0100001116 | 17.227 | cum |
| 5 | 1.04 | od22638/2018_2019 : Dry rubble masonry with hard stone in retaining wall including cost and conveyance of all materials to site and all labour charges etc. complete using departmental materials | BI01010001010000000000000515BI0100001117 | 233.5 | cum |
| 6 | 1.05 | 7.1.1 : Random rubble masonry with hard stone in foundation and plinth including levelling up with cement concrete 1:6:12 (1 cement : 6 coarse sand : 12 graded stone aggregate 20 mm nominal size) up to plinth level with:Cement mortar 1:6 (1 cement : 6 coarse sand) | BI01010001010000000000000515BI0100001118 | 142.575 | cum |
| 7 | 1.06 | 5.2.2 : Reinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. up tot floor five level excluding cost of centering, shuttering, finishing and reinforcement :1:1.5:3( 1 cement : 1.5 coarse sand : 3 graded stone aggregate 20 mm nominal size) | BI01010001010000000000000515BI0100001119 | 5.522 | cum |
| 8 | 1.07 | 5.3 : Reinforced cement concrete work in beams, suspended floors, roofs, having slope up to 15<sup>0</sup> landings, balconies, shelves, chajjas, lintels, bands, plain window sills, staircases and spiral stair cases up to floor five level excluding the cost of centering, shuttering, finishing and reinforcement, with1:1.5:3 (1 cement : 1.5 coarse sand (Zone III) : 3 graded stone aggregate 20 mm nominal size).Reinforced cement concrete work in beams, suspended floors, roofs, having slope up to 15<sup>0</sup> landings, balconies, shelves, chajjas, lintels, bands, plain window sills, staircases and spiral stair cases up to floor five level excluding the cost of centering, shuttering, finishing and reinforcement, with1:1.5:3 (1 cement : 1.5 coarse sand (Zone III) : 3 graded stone aggregate 20 mm nominal size). | BI01010001010000000000000515BI0100001120 | 9.456 | cum |
| 9 | 1.08 | 5.9.2 : Centering and shuttering including strutting, etc. and removal of form for:Walls (any thickness) including attached pilasters, butteresses, plinth and string courses etc. | BI01010001010000000000000515BI0100001121 | 63.2 | sqm |
| 10 | 1.09 | 5.9.3 : Centering and shuttering including strutting, etc. and removal of form for:Suspended floors, roofs, landings, balconies and access platform | BI01010001010000000000000515BI0100001122 | 8.25 | sqm |
| 11 | 1.1 | 5.9.16.1 : Edges of slabs and breaks in floors and wallsUnder 20 cm wide | BI01010001010000000000000515BI0100001123 | 16 | metre |
| 12 | 1.11 | 5.22.6 : Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more | BI01010001010000000000000515BI0100001124 | 1742.14 | kilogram |
| 13 | 1.12 | 50.6.7.2 : Laterate masonry with neatly dressed laterate stone of size 40x20x15cm or nearest size in cement mortar 1:6 for super structure above plinth level up to floor two level including all cost of materials, labour charges etc. | BI01010001010000000000000515BI0100001125 | 16.32 | cum |
| 14 | 1.13 | 13.1.1 : 12 mm cement plaster of mix:1:4 ( 1 cement : 4 fine sand) | BI01010001010000000000000515BI0100001126 | 163.2 | sqm |
| 15 | 1.14 | 13.46.1 : Finishing walls with Acrylic Smooth exterior paint of required shade:New work (Two or more coat applied @ 1.67 ltr/10 sqm over and including priming coat of exterior primer applied @ 2.20 kg/10 sqm) | BI01010001010000000000000515BI0100001127 | 163.2 | sqm |
| 16 | 1.15 | 50.10.1 : Steel work in built up G I tubular ( round, square or rectangular hollow tubes etc.) trusses etc., including cutting, hoisting,fixing in position and applying a priming coat of approved steel primer, including welding and bolted with special shaped washers etc. complete | BI01010001010000000000000515BI0100001128 | 325 | kg |
| 17 | 1.16 | 13.61.1 : Painting with synthetic enamel paint of approved brand and manufacture to give an even shade:Two or more coats on new work | BI01010001010000000000000515BI0100001129 | 36.563 | sqm |
AI Tender Summary
Tender Timeline
Mar 19, 2020
11:30 IST
Tender Published
Tender notice published.
CompletedMar 26, 2020
17:00 IST
Bid Submission Deadline
Online submission via eProcurement portal.
CompletedMar 28, 2020
Bid Opening Date