Construction Of Protection Wall Along With Roof Works At Monk Hostel Yiga Choeling Monestery Ghoom Darjeeling, DARJEELING-West Bengal

WEST BENGAL BHUTIA DEVELOPMENT BOARD has published Construction Of Protection Wall Along With Roof Works At Monk Hostel Yiga Choeling Monestery Ghoom Darjeeling. Submission Date for this Tender is 27-03-2020. Shed Construction Tenders in DARJEELING West Bengal. Bidders can get complete Tender details and download the document.




Tender Notice

24003159
Construction Of Protection Wall Along With Roof Works At Monk Hostel Yiga Choeling Monestery Ghoom Darjeeling
Open Tender
Indian
West Bengal
DARJEELING
27-03-2020

Tender Details

Construction Of Protection Wall Along With Roof Works At Monk Hostel Yiga Choeling Monestery Ghoom Darjeeling

Key Value

Document Fees
Refer document
EMD
INR 48411.0 /-
Tender Value
INR 24.20 Lakhs /-

BOQ Items

Name of Work: CONSTRUCTION OF PROTECTION WALL ALONG WITH ROOF WORKS AT MONK HOSTEL YIGA CHOELING MONESTERY GHOOM DARJEELING
Sl. No. Item Description Item Code / Make Quantity Units
1 1 Earth work in excavation of foundation trenches or drains, in all sorts of soil (including mixed soil but excluding laterite or sandstone) including removing, spreading or stacking the spoils within a lead of 75 m. as directed. The item includes necessary trimming the sides of trenches,levelling, dressing and ramming the bottom,bailing out water as required complete. (a) Depth of excavation not exceeding 1,500 BI01010001010000000000000515BI0100001113 264 cum
2 2 Labour for laying 150mm to 200 mm boulder soiling including rough dressing hand packing and ramming down small pieces in the interstics including rolling and preparing the bed to proper level and filling up all joints with sandy clay or earth BI01010001010000000000000515BI0100001114 176 cum
3 3 Cost of stone boulder 150mm size delivered and stacked at site BI01010001010000000000000515BI0100001115 26.4 cum
4 4 Plum concrete with Cement concrete 1:3:6 propotion 40% and stone boulder filling 60% including cost of all materials. BI01010001010000000000000515BI0100001116 169.2 cum
5 5 Plaster (to wall,floor,ceiling etc) with sand and cement mortar including rounding off or chamfreing corners as directed and ranking out joints including throating,noising and drip course,scaffolding where necessary (II) With 1:4 cement mortar (B) 20 mm thick plaster BI01010001010000000000000515BI0100001117 112.8 sqm
6 6 Ordinary cement concrete (mix 1:2:4) with graded stone chips (20 mm nominal size) excluding shuttering and reinforcement BI01010001010000000000000515BI0100001118 36.3 cum
7 7 Ordinary cement concrete (mix 1:1.5:3) with graded stone chips (20 mm nominal size) excluding shuttering and reinforcement BI01010001010000000000000515BI0100001119 27.93 cum
8 8 Reinforcement for reinforced concrete work in all sorts ofstructures including distribution bars, stirrups, binders etc\ninitial straightening and removal of loose rust (if necessary),cutting to requisite length, hooking and bending to correct\nshape, placing in proper position and binding with 16 guage black annealed wire at every inter section,complete as per drawing and direction foundation BI01010001010000000000000515BI0100001120 3.28 MT
9 9 Hire and labour charges for shuttering with centering andnecessary staging upto 4 m using approved stout props and\nthick hard wood planks of approved thickness with requiredbracing for concrete slabs, beams and columns, lintels curvedor straight including BI01010001010000000000000515BI0100001121 202.78 sqm
10 10 Supplying, fitting & fixing circular corrugated Aluminiumsheet (excluding the supporting frame work) of approvedmake & brand in alloy 3105 conforming to IS: 1254-1991fitted and fixed with 55 mm & 25 mm Self tapping screw ,EPDM Washer 16 mm dia & 3 mm th washer etc completewith 150 mm. end lap and one corrugation minimum side lap.(Payment to be made on area of finished work) (Aluminiumsheet to be supplied by contractor). In BI01010001010000000000000515BI0100001122 363 sqm
11 11 Galvanised iron sheet ridging fitted with necessary bolt, screws, washers etc complete. (225 mm end lapping). (A) 300mm laping each way. BI01010001010000000000000515BI0100001123 33 M
12 12 Galvanized iron sheet eaves gutter fitted and fixed with necessary 50 mm X 6 mm.M.S.flat bar clamps bent to design, bolts. Nuts, washers etc. complete. Eaves gutter made of 0.63 mm. sheets.(300mm End lapping). (b) 300 mm.wide gutter. BI01010001010000000000000515BI0100001124 66 M
13 13 Wooden eaves board as per design, fitted and fixed complete:In ground floor BI01010001010000000000000515BI0100001125 33 sqm
14 14 Holding down bolt with nut including 100 x 100 x 6 mm plate washerat bottom fitted complete and packing the hole with cement concreteor cement grout as directed. BI01010001010000000000000515BI0100001126 150 NOS
15 15 12% GST on estimated Cost BI01010001010000000000000515BI0100001127 1 job
16 16 1% Labour welfare cess BI01010001010000000000000515BI0100001128 1 job
17 17 3 % contingency charge BI01010001010000000000000515BI0100001129 1 job
Disclaimer :
We takes all possible care for accurate & authentic tender information, however Users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender.
Tell us about your Product / Services,
We will Find Tenders for you

Copyright © 2024 · All Rights Reserved. Terms of Usage | Privacy Policy

For Tender Information Services Visit : TenderDetail