National Aluminium Company Limited-NALCO has published Overhauling Of Critical Pumps Of Power House , Cwph And Cooling Towers Of Unit-1 To 10. Submission Date for this Tender is 10-04-2020. Cooling Tower Tenders in CPP, NALCO, ANGUL Odisha. Bidders can get complete Tender details and download the document.
Name of Work: OVERHAULING OF CRITICAL PUMPS OF POWER HOUSE, CWPH AND COOLING TOWERS OF UNIT#1 TO #10. | |||||
---|---|---|---|---|---|
Sl. No. | Item Description | Item Code / Make | Quantity | Units | |
1 | 1 | O/H of 16"FC valve of cooling tower, as per scope of work. | 200 | NO | |
2 | 2 | Repl. of defective weldment of SR-36 Gea, as per scope of work. | 2 | NO | |
3 | 3 | Repl. of CT 1-6 fan assy, as per scope of work. | 2 | NO | |
4 | 4 | Repl.of driveshaft of CT 1-6 fan, as per scope of work. | 1 | NO | |
5 | 5 | Changing of D.S. rubber bush(1-6), as per scope of work. | 10 | SET | |
6 | 6 | Fan blade end clearance and pitch(1-6), as per scope of work. | 10 | NO | |
7 | 7 | Elimination of Endplay of SR-36 Gearbox, as per scope of work. | 10 | NO | |
8 | 8 | SR-36 Gearbox input shaft oilseal changi, as per scope of work. | 10 | NO | |
9 | 9 | SR-36 Gearbox output shaft 'O' ring, as per scope of work. | 6 | NO | |
10 | 10 | Driveshaft alignment of SR-36 Gearbox, as per scope of work. | 2 | NO | |
11 | 11 | Misc. Welding jobs in CT 1-6, as per scope of work. | 200 | M | |
12 | 12 | Misc.cutting jobs in CT 1-6, as per scope of work. | 200 | M | |
13 | 13 | O/H of Boiler Feed Pump, as per scope of work. | 1 | NO | |
14 | 14 | Mechanical Seal Replacement of BFP, as per scope of work. | 8 | NO | |
15 | 15 | Cartridge Repl./Discharge O-Ring Replace, as per scope of work. | 6 | NO | |
16 | 16 | Alignment,Coupling & Trial Run of the pu, as per scope of work. | 34 | NO | |
17 | 17 | Bearing Inspection of BFP, as per scope of work. | 56 | NO | |
18 | 18 | O/H of Booster Pump, as per scope of work. | 6 | NO | |
19 | 19 | M. Seal /S. Box Gasket Replacement of BP, as per scope of work. | 25 | NO | |
20 | 20 | Alignment,Coupling & Trail Run of BP, as per scope of work. | 22 | NO | |
21 | 21 | Bearing Inspection of BP, as per scope of work. | 56 | NO | |
22 | 22 | Dismantling of B.PUMP and Re-assembly, as per scope of work. | 2 | NO | |
23 | 23 | O/H Condensate Extraction Pump, as per scope of work. | 1 | NO | |
24 | 24 | Stage body dismantling and re-assembly, as per scope of work. | 8 | NO | |
25 | 25 | Alignment,Coupling & Trail Run of CEP, as per scope of work. | 28 | NO | |
26 | 26 | S. Box sleeve Repl. And Brg. Inspection, as per scope of work. | 22 | NO | |
27 | 27 | Gland Replacement of CEP, as per scope of work. | 20 | NO | |
28 | 28 | O/H of CW pump, as per scope of work. | 10 | NO | |
29 | 29 | TBH inspection/repl. Of CW Pump, as per scope of work. | 1 | NO | |
30 | 30 | Stuf.Box inspection/repl.of CW Pump, as per scope of work. | 1 | NO | |
31 | 31 | Alignment,Coupling & Trail Run of CW pum, as per scope of work. | 1 | NO | |
32 | 32 | Gland Replacement Oof CW Pump, as per scope of work. | 2 | NO | |
33 | 33 | O/H of ACW Pump, as per scope of work. | 4 | NO | |
34 | 34 | TBH inspection/repl.of ACW Pump, as per scope of work. | 1 | NO | |
35 | 35 | Stuf.Box inspection/repl.of ACW Pump, as per scope of work. | 1 | NO | |
36 | 36 | Alignment,Coupling & Trail Run of ACW Pu, as per scope of work. | 1 | NO | |
37 | 37 | Gland Replacement of ACW Pump, as per scope of work. | 2 | NO | |
38 | 38 | O/H of Fire Fighting Pump, as per scope of work. | 4 | NO | |
39 | 39 | TBH inspection/repl.of F/F Pump, as per scope of work. | 1 | NO | |
40 | 40 | Stuf.Box inspection/repl.of F/F Pump, as per scope of work. | 1 | NO | |
41 | 41 | Alignment,Coupling & Trail Run of F/F pu, as per scope of work. | 1 | NO | |
42 | 42 | Gland Replacement of F/F Pump, as per scope of work. | 2 | NO | |
43 | 43 | Stage body dismantling and re-assembly, as per scope of work. | 2 | NO | |
44 | 44 | O/H of C.T. pump, as per scope of work. | 6 | NO | |
45 | 45 | TBH inspection/repl.of CT Pump, as per scope of work. | 4 | NO | |
46 | 46 | Alignment,Coupling & Trail Run of CT pum, as per scope of work. | 4 | NO | |
47 | 47 | Gland Replacement of CT Pump, as per scope of work. | 10 | NO | |
48 | 48 | Dismantling and re-assembly of CT Pump, as per scope of work. | 2 | NO | |
49 | 49 | Synthetic enamel painting of P.H., as per scope of work. | 420 | M2 | |
50 | 50 | Chloro rubber painting of CT 1-6, as per scope of work. | 4200 | M2 | |
51 | 51 | Repl.of damaged target nozzles of CT, as per scope of work. | 9000 | NO | |
52 | 52 | O/H of Aux. AOP/EOP/MOP, as per scope of work. | 1 | NO | |
53 | 53 | Insp./Repl. Of coupling bushes of AOP/EO, as per scope of work. | 1 | NO | |
54 | 54 | Insp/Repl. of Bearings AOP/EOP/MOP, as per scope of work. | 1 | NO | |
55 | 55 | O/H of Jacking Oil pump, as per scope of work. | 1 | NO | |
56 | 56 | Repl.of CW/ACW outlet BFV, as per scope of work. | 1 | NO | |
57 | 57 | Overhauling of CW/ACW BFV, as per scope of work. | 2 | NO | |
58 | 58 | Replacement of 400NB pipe, as per scope of work. | 3 | NO | |
59 | 59 | PM of 20/5T CWPH crane, as per scope of work. | 2 | NO | |
60 | 60 | Repl. of CW Inter-connection Valve, as per scope of work. | 1 | NO | |
61 | 61 | O/H of Sluice gate at CT discharge, as per scope of work. | 34 | NO | |
62 | 62 | Repl. of CW/ACW R.E.Joint, as per scope of work. | 3 | NO | |
63 | 63 | OVERHAULING OF DMCW/BOILER FILL PUMP, as per scope of work. | 2 | NO | |
64 | 64 | O/H of 18"FC valve of cooling tower (Uni, as per scope of work. | 124 | NO | |
65 | 65 | Repl. of defective weldment of Gear Box, as per scope of work. | 1 | NO | |
66 | 66 | Repl. of cooling tower fan assy. (Unit 7, as per scope of work. | 4 | NO | |
67 | 67 | Repl.of driveshaft of coolingtower fan (, as per scope of work. | 1 | NO | |
68 | 68 | Changing of Neoprene bonded rubber (Uni, as per scope of work. | 6 | SET | |
69 | 69 | Fan blade end clearance and pitch (Unit, as per scope of work. | 24 | NO | |
70 | 70 | Elimination of End play of Gearbox SR-3, as per scope of work. | 24 | NO | |
71 | 71 | Gearbox SR-32 input shaft oilseal changi, as per scope of work. | 24 | NO | |
72 | 72 | Gearbox SR -32 output shaft 'O' ring (U, as per scope of work. | 2 | NO | |
73 | 73 | Driveshaft alignment at Gearbox SR-32 (U, as per scope of work. | 1 | NO | |
74 | 74 | Misc. Welding jobs in cooling tower (Un, as per scope of work. | 140 | M | |
75 | 75 | Misc.cutting jobs in cooling tower (Uni, as per scope of work. | 100 | M | |
76 | 76 | O/H of Cooling Water Pump at RCPH., as per scope of work. | 4 | NO | |
77 | 77 | TBH inspection/repl.of CW pumps at RCPH, as per scope of work. | 1 | NO | |
78 | 78 | Stuf.Box inspection/repl.RCPH, as per scope of work. | 1 | NO | |
79 | 79 | Alignment,Coupling & Trail Run of CW pum, as per scope of work. | 2 | NO | |
80 | 80 | Gland Replacement of CW p/p at RCPH, as per scope of work. | 2 | NO | |
81 | 81 | O/H of Aux.Cooling Water Pump at RCPH., as per scope of work. | 3 | NO | |
82 | 82 | TBH inspection/repl.of ACW p/p at RCPH, as per scope of work. | 2 | NO | |
83 | 83 | Stuf.Box inspection/repl.RCPH, as per scope of work. | 1 | NO | |
84 | 84 | Alignment,Coupling & Trail Run of ACW p, as per scope of work. | 2 | NO | |
85 | 85 | Gland Replacement of ACW p/p at RCPH, as per scope of work. | 2 | NO | |
86 | 86 | O/H of Firefighting pump at RCPH, as per scope of work. | 3 | NO | |
87 | 87 | TBH inspection/repl.of F/F pump at RCPH, as per scope of work. | 2 | NO | |
88 | 88 | Stuf.Box inspection/repl.of F/F pump at, as per scope of work. | 2 | NO | |
89 | 89 | Alignment,Coupling & Trail Run of F/F pu, as per scope of work. | 2 | NO | |
90 | 90 | Gland Replacementof F/F pump at RCPH, as per scope of work. | 2 | NO | |
91 | 91 | Stage body dismantling and re-assembly R, as per scope of work. | 1 | NO | |
92 | 92 | Synthetic enamel painting Cooling Tower, as per scope of work. | 700 | M2 | |
93 | 93 | Chloro rubber painting at Cooling Tower, as per scope of work. | 4200 | M2 | |
94 | 94 | Repl.of damaged target nozzles of CT (Un, as per scope of work. | 8400 | NO | |
95 | 95 | Repl.of CW/ACW outlet BFV at RCPH., as per scope of work. | 4 | NO | |
96 | 96 | Overhauling of CW/ACW BFV at RCPH., as per scope of work. | 2 | NO | |
97 | 97 | Replacement of 400NB pipe CT (Unit 7 -10, as per scope of work. | 1 | NO | |
98 | 98 | PM,& Loadtesting of 25/5T crane at RCPH, as per scope of work. | 2 | NO | |
99 | 99 | Repl. of RCPH CW Inter-connection Valve, as per scope of work. | 1 | NO | |
100 | 100 | O/H of Sluice gate at CT discharge Uni, as per scope of work. | 36 | NO | |
101 | 101 | Repl. of CW/ACW R.E.Joint at RCPH., as per scope of work. | 3 | NO | |
102 | 102 | O/H of Intake Pump, as per scope of work. | 4 | NO | |
103 | 103 | TBH inspection/repl.of IP., as per scope of work. | 4 | NO | |
104 | 104 | Stuf.Box inspection/repl.of I.pump., as per scope of work. | 2 | NO | |
105 | 105 | Alignment,Coupling & Trail Run of I.Pump, as per scope of work. | 2 | NO | |
106 | 106 | Gland Replacement of I.Pump., as per scope of work. | 2 | NO | |
107 | 107 | Overhauling of VoithHydrocoupling of BFP, as per scope of work. | 4 | NO | |
108 | 108 | Servicing of NRV(600NB) of ACW Pump, as per scope of work. | 6 | NO | |
109 | 109 | Servicing of NRV(1200NB) of CW Pump, as per scope of work. | 5 | NO | |
110 | 110 | Minor overhauling of Cooling Tower Fan, as per scope of work. | 60 | NO |