Tender For Graded Bunding Sonala Gut No 10/2,10/3,10/4 Water Shed No Ptb-01/02/10. Tq Sangrampur Dist Buldhana
Tender Overview
Project Description
Tender For Graded Bunding Sonala Gut No 10 / 2, 10 / 3, 10 / 4 Water Shed No Ptb-01 / 02 / 10. Tq Sangrampur Dist Buldhana
Corrigendum
| Sr No | Corrigendum Date | Corrigendum | Type | New Submission Date |
|---|---|---|---|---|
| 1 | 20-Mar-2020 | DateExtension | Date | 30-Mar-2020 |
BOQ
| Name of Work : GRADED BUNDING Sonala GUT NO 10/2,10/3,10/4 Water Shed No PTB-01/02/10. Tq Sangrampur Dist Buldhana | |||||
|---|---|---|---|---|---|
| Sl.No. | Item Description | Item Code / Make | Quantity | Units | |
| 1 | 1 | PART A CONSTRUCTION OF Sonala GRADED BUNDING NO. 1 PTB-01/02/10, (10/2) | BI01010001010000000000000515BI0100001112 | ||
| 2 | 1.01 | CSR 2018-19 Item No. 1: Excavation in all Kinds of soil Including Boulders up to 0.6 m diameter (0.113 cam) for canal, seating of embankment,filter drains/ catch water drains etc., and placing the excabated stuff neatly in dump area of for formation of service road/embankment including cost of all materials, machinery, labour, dressing bed and sides to reqired level and profile etc. complete with lead up to 15 m and all lifts as directed. | BI01010001010000000000000515BI0100001113 | 14110.5 | Cu.mt |
| 3 | 1.02 | CSR 2018-19 Item No. 3 : Item No. 16 : Providing and Constructing 300 mm thick dry rubble stone pitching with pin headers at 2 per sqm using stones and stone chips from approved source including cost of all materials, labour, hand packing / wedging stone chips, finishing etc comlete with lead up to 50 m and all lifts as directed. | BI01010001010000000000000515BI0100001114 | 81 | Cu.mt |
| 4 | 1.03 | Item No. : Provision for work insurance charges at 1% of work cost | BI01010001010000000000000515BI0100001115 | 473592 | Persent |
| 5 | 1.04 | Item No. : Provision for welfare cess at 1% of work cost | BI01010001010000000000000515BI0100001116 | 473592 | Persent |
| 6 | 1.05 | Item No : Charges For Providing Photo copies of Site at Diff stages, Papers for Completion and Handover the work | BI01010001010000000000000515BI0100001117 | 1 | Nos |
| 7 | 2 | PART B CONSTRUCTION OF Sonala GRADED BUNDING NO. 2 PTB-01/02/10, (8/3) | BI01010001010000000000000515BI0100001118 | ||
| 8 | 2.01 | CSR 2018-19 Item No. 1: Excavation in all Kinds of soil Including Boulders up to 0.6 m diameter (0.113 cam) for canal, seating of embankment,filter drains/ catch water drains etc., and placing the excabated stuff neatly in dump area of for formation of service road/embankment including cost of all materials, machinery, labour, dressing bed and sides to reqired level and profile etc. complete with lead up to 15 m and all lifts as directed. | BI01010001010000000000000515BI0100001119 | 10587.9 | Cu.mt |
| 9 | 2.02 | CSR 2018-19 Item No. 3 : Item No. 16 : Providing and Constructing 300 mm thick dry rubble stone pitching with pin headers at 2 per sqm using stones and stone chips from approved source including cost of all materials, labour, hand packing / wedging stone chips, finishing etc comlete with lead up to 50 m and all lifts as directed. | BI01010001010000000000000515BI0100001120 | 67.5 | Cu.mt |
| 10 | 2.03 | Item No. : Provision for work insurance charges at 1% of work cost | BI01010001010000000000000515BI0100001121 | 357072 | Persent |
| 11 | 2.04 | Item No. : Provision for welfare cess at 1% of work cost | BI01010001010000000000000515BI0100001122 | 357072 | Persent |
| 12 | 2.05 | Item No : Charges For Providing Photo copies of Site at Diff stages, Papers for Completion and Handover the work | BI01010001010000000000000515BI0100001123 | 1 | Nos |
| 13 | 3 | PART C CONSTRUCTION OF Sonala GRADED BUNDING NO. 3 PTB-01/02/10, (10/4) | BI01010001010000000000000515BI0100001124 | ||
| 14 | 3.01 | CSR 2018-19 Item No. 1: Excavation in all Kinds of soil Including Boulders up to 0.6 m diameter (0.113 cam) for canal, seating of embankment,filter drains/ catch water drains etc., and placing the excabated stuff neatly in dump area of for formation of service road/embankment including cost of all materials, machinery, labour, dressing bed and sides to reqired level and profile etc. complete with lead up to 15 m and all lifts as directed. | BI01010001010000000000000515BI0100001125 | 14331.6 | Cu.mt |
| 15 | 3.02 | CSR 2018-19 Item No. 3 : Item No. 16 : Providing and Constructing 300 mm thick dry rubble stone pitching with pin headers at 2 per sqm using stones and stone chips from approved source including cost of all materials, labour, hand packing / wedging stone chips, finishing etc comlete with lead up to 50 m and all lifts as directed. | BI01010001010000000000000515BI0100001126 | 83.7 | Cu.mt |
| 16 | 3.03 | Item No. : Provision for work insurance charges at 1% of work cost | BI01010001010000000000000515BI0100001127 | 481375 | Persent |
| 17 | 3.04 | Item No. : Provision for welfare cess at 1% of work cost | BI01010001010000000000000515BI0100001128 | 481375 | Persent |
| 18 | 3.05 | Item No : Charges For Providing Photo copies of Site at Diff stages, Papers for Completion and Handover the work | BI01010001010000000000000515BI0100001129 | 1 | Nos |
AI Tender Summary
Tender Timeline
Tender Published
Tender notice published.
CompletedCorrigendum-1 Issued
Clarifications on tender conditions and amendments issued.
CompletedBid Submission Deadline
Online submission via eProcurement portal.
CompletedBid Opening Date
Technical bids will be opened and evaluated.
CompletedTender Documents
Download All (ZIP) ↓We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender