| 1 | 1 | approach road | BI01010001010000000000000515BI0100001113 | | |
|---|
| 2 | 1.001 | 3.5.2 : Excavation in Soil with Dozer with lead upto 100 m\t\t\t<br>\nExcavation for roadway in soil by mechanical means including cutting and pushing the earth to site of embankment upto a distance of 100 m, including trimming bottom and side slopes in accordance with requirements of lines, grades and cross-sections. | BI01010001010000000000000515BI0100001114 | 136.16 | cum |
|---|
| 3 | 1.002 | od382420/2019_2020 : Dry rubble masonry without concrete levelling course with good quality blasted rubble including packing to compactness and levels for road protection to withstand the dynamic load due to moving traffic including cost and conveyance of all materials ,labour charges etc .complete as per direction of departmental officers at site. | BI01010001010000000000000515BI0100001115 | 407.04 | cum |
|---|
| 4 | 1.003 | 12.5.1.1 : Plain/reinforced cement concrete in substructure complete as per drawings and technical specification Clauses 802, 804, 805, 806, 807, 1202 ans 1204For height upto 5 mI.P.C.C grade M 15(i)Nominal mix (1:2.5:5) | BI01010001010000000000000515BI0100001116 | 44.825 | cum |
|---|
| 5 | 1.004 | 12.5.3 : Plain/reinforced cement concrete in substructure complete as per drawings and technical specification Clauses 802, 804, 805, 806, 807, 1202 ans 1204For height upto 5 m III.R.C.C grade M 20 | BI01010001010000000000000515BI0100001117 | 10.722 | cum |
|---|
| 6 | 1.005 | 12.7 : Supplying, fitting and placing TMT bar reinforcement (Fe 415) in substructrue complete as per drawings and technical specification Clauses 1002, 1005, 1010 & 1202 | BI01010001010000000000000515BI0100001118 | 3.233 | tonne |
|---|
| 7 | 1.006 | 3.14 : Construction of Subgrade and Earthen Shoulders<br>\nConstruction of subgrade and earthen shoulders with approved material obtained from borrow pits with all lifts and leads, transporting to site, spreading, grading to required slope and compacted to meet requirement of Table 300.2 with lead upto 1000 m as per Technical Specification Clause 303.1. | BI01010001010000000000000515BI0100001119 | 944.84 | cum |
|---|
| 8 | 1.007 | od382921/2019_2020 : Filling with Quarry Muck<br>Filling up low lying and water logged areas with local material/ quarry muck, spreading in layers, leveling the top at site and consolidation by ramming, etc complete for improving the CBR value of subgrade<br> | BI01010001010000000000000515BI0100001120 | 83.2 | cum |
|---|
| 9 | 1.008 | od382971/2019_2020 : Item Shifted to Sub head 14 as item 14.73<br>Item Shifted to head 14 as item 14.74<br>Steel work welded in built up sections/framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer using structural steel etc. as required.<br>In gratings, frames, guard bar, ladder, railings, brackets, gates and similar works | BI01010001010000000000000515BI0100001121 | 570 | kg |
|---|