Orissa Bridge And Construction Corporation Limited has published Consultancy Services For Preparation Of Feasibility Study And Detailed Project Report For Proposed Barbil Bypass Or Ring Road In The Keonjhar District In The State Of Odisha . . Submission Date for this Tender is 16-03-2020. Consultancy Service Tenders in Keonjhar Odisha. Bidders can get complete Tender details and download the document.
Name of Work:Consultancy Services for preparation of Feasibility Study and Detailed Project Report for proposed Barbil Bypass/Ring Road in the Keonjhar District in the State of Odisha. | |||||
---|---|---|---|---|---|
Sl. No. | Item Description | Item Code / Make | Quantity | Units | |
1 | 1 | Professional Staff | |||
2 | 1.01 | Sr. Highway Engineer-\ncum-Team Leader | 4 | Man Month | |
3 | 1.02 | Highway cum Pavement | 2 | Man Month | |
4 | 1.03 | Bridge Engineer | 2 | Man Month | |
5 | 1.04 | Road Safety Engineer | 1 | Man Month | |
6 | 1.05 | Traffic Engineer | 1 | Man Month | |
7 | 1.06 | Material-cum-Geo-technical Engineer | 1 | Man Month | |
8 | 1.07 | Senior Survey Engineer | 2 | Man Month | |
9 | 1.08 | Financial Analyst | 1 | Man Month | |
10 | 1.09 | Environmental Specialist | 1 | Man Month | |
11 | 1.1 | Quantity Surveyor/\nDocumentation Expert | 2 | Man Month | |
12 | 1.11 | RR Expert | 1 | Man Month | |
13 | 2 | Sub-Professional Staff | |||
14 | 2.01 | Quantity Surveyor | 4 | Man Month | |
15 | 2.02 | Survey Engineer | 4 | Man Month | |
16 | 2.03 | Lab Technician | 4 | Man Month | |
17 | 3 | Support Staff | |||
18 | 3.01 | Office Manager (1No) | 4 | Man Month | |
19 | 3.02 | Accountant cum cashier (1No) | 4 | Man Month | |
20 | 3.03 | Dataentry Operator (1No) | 4 | Man Month | |
21 | 3.04 | Office Boy (1No) | 4 | Man Month | |
22 | 4 | Transportation (Fixed costs) | |||
23 | 4.01 | The vehicles provided by the Consultants shall include the cost for rental, drivers, operation, maintenance, repairs, insurance, etc.\n- 3 nos | 12 | Vehicle Month | |
24 | 5 | Duty Travel to Site (Fixed Costs) | |||
25 | 5.1 | Professional Staff | 16 | Man-Days | |
26 | 5.2 | Sub-Professional Staff | 20 | Man-Days | |
27 | 6 | Office Rent (Fixed Costs) | |||
28 | 6.1 | The rent cost includes maintenance, cleaning, repairs, etc.\n | 4 | Month | |
29 | 7 | Office Supplies, Utilities and Communication (Fixed Costs) | |||
30 | 7.01 | Office Supplies Drafting | 4 | Month | |
31 | 7.02 | Supplies Computer | 4 | Month | |
32 | 7.03 | Running Costs | 4 | Month | |
33 | 7.04 | Domestic and International\nCommunication\n | 4 | Month | |
34 | 8 | Office Furniture and Equipment (Rental) | |||
35 | 8.01 | Office Furniture and Equipment (Rental/Hire) | 1 | LS | |
36 | 9 | Reports and Document Printing | |||
37 | 9.01 | Monthly Report (3 per month for four months) | 12 | Nos | |
38 | 9.02 | Inception Report & QAP | 3 | Nos | |
39 | 9.03 | Environment and Social Impact\nScreening Report | 2 | Nos | |
40 | 9.04 | Draft Feasibility Report | 1 | Nos | |
41 | 9.05 | Final Feasibility Report | 3 | Nos | |
42 | 9.06 | Strip Plan with L.A. Reports | 3 | Nos | |
43 | 9.07 | Draft LA and Clearances I Report | 1 | Nos | |
44 | 9.08 | Final LA and Clearances I Report | 3 | Nos | |
45 | 9.09 | Draft Environmental Assessment\nreport & RAP | 1 | Nos | |
46 | 9.1 | Final Environmental Assessment\nreport & RAP | 3 | Nos | |
47 | 9.11 | Draft Detailed Design Report & Drawings etc. | 1 | Nos | |
48 | 9.12 | Draft EMP | 1 | Nos | |
49 | 9.13 | Draft Bidding Documents | 1 | Nos | |
50 | 9.14 | Final Detailed Project Report with Bill of Quantities, Cost\nEstimates, Updated Drawings etc. | 3 | Nos | |
51 | 9.15 | Final EMP | 3 | Nos | |
52 | 9.16 | Final Bidding Documents | 3 | Nos | |
53 | 9.17 | Schedules for land acquisition | 3 | Nos | |
54 | 9.18 | LA & Clearances II Report | 3 | Nos | |
55 | 10 | Topographical Survey (Fixed Rate) | |||
56 | 10.01 | Topographic Survey including hire charges for equipment and supply of survey teams comprising of project survey filed staff etc. inclusive of cost of materials, labourer | 30 | per Km | |
57 | 10.02 | Detailed topographic surveys using mobile/ aerial LiDAR or equivalent technology | 30 | per KM | |
58 | 11 | Investigation (Fixed cost) | |||
59 | 11.01 | Road and Bridge Inventory | 1 | LS | |
60 | 11.02 | BBD Test and Pavement Evaluation | 1 | LS | |
61 | 11.03 | Roughness Survey | 1 | LS | |
62 | 11.04 | Axle Load Survey | 1 | LS | |
63 | 11.05 | Material Survey and Investigation | 1 | LS | |
64 | 11.06 | Sub-grade Investigation | 1 | LS | |
65 | 11.07 | Traffic Survey | 1 | LS | |
66 | 11.08 | Socio-economic & Census Survey/Studies | 1 | LS | |
67 | 11.09 | Land Acquisition Studies | 1 | LS | |
68 | 11.1 | Any other investigations/surveys | 1 | LS | |
69 | 12 | * Sub-Soil Investigation (Boring) | |||
70 | 12.01 | Boring in all type of soils (other than hard rock) | 1500 | Rmt | |
71 | 12.02 | Boring in hard rock | 200 | Rmt |
Copyright © 2024 · All Rights Reserved. Terms of Usage | Privacy Policy