Ladakh Autonomous Hill Development Council-LAHDC has published Construction Of Footpath With Cycle Track At Amusement Park At Choglamsar. Submission Date for this Tender is 26-02-2020. Footpath Work Tenders in Leh Jammu And Kashmir. Bidders can get complete Tender details and download the document.
Name of Work: construction of Foot Path with cycle track at amuserment park at Choglamsar | |||||
---|---|---|---|---|---|
Sl. No. | Item Description | Item Code / Make | Quantity | Units | |
1 | 1 | Earth work in rough execution banking excavoted earth in layers not exceeding 20 cm in depth ,breaking clods lotering rolling earth layer with half tonne roller or wooden or steel ramments and rolling cury third and top most layer with power roller of minimum 8 tonnersand dressing upin embandment for roads flood banks or filling up ground depressions load upto 50 mts and lift upto 1.5 mtrs in : | 824 | Cum | |
2 | 2 | Dry stone pitching (any thickness) including stones on horzontal | 275 | Cum | |
3 | 3 | Providing and laying in position cement concrete of specified grade excluding the cost of centring and shuttering .All works up to plinth level 1:2:4 ( 1 Cement: 2 Coaase sand: 4 graded stone aggregate 20 mm nominal size. | 136 | Cum | |
4 | 4 | Reinforcement force work including strengthening cutting ,banding placing in position and binding all complete thermo machanically treated bars (TMT) | 8765 | Kg | |
5 | 5 | Providing and laying in position cement concrete of specified grade excluding the cost of centring and shuttering .All works up to plinth level 1:3:6 ( 1 Cement 3 Coarse sand: 6 graded stone aggregate 20 mm nominal size. | 618 | Cum | |
6 | 6 | Centring and shuttering including strutting propping etc and removal of form work for A) Foundation,Footings boses of columns etc for mars concrete. | 4058 | Sqm | |
7 | 7 | Dumping stone including stone in Horizontal Level | 2197 | Cum | |
8 | 8 | Providing and laying at or near ground level factory made kerb stone of M-25 grade cement in position to required the level and curvature pointed with cement mortors 1:3 (1 cement 3 couse sand) including making joints with or without grooves (Thickness of the joints except at sharp curved shall not be more than 5 MM) including massing driange opening wherever required complete etc, as per direction of Engineers in-charge (length of finished kerb doing shall be approved by Engineer-in-charge) | 69 | Cum | |
9 | 9 | Filling available excavoted earth (Excluding rock) in trenches,plinth,sides of foundation etc layers not exceeding 20 cm in depth,consolidating each deposited layer by ramming and watering lead upto som and lift upto 1.5 m | 549 | Cum | |
10 | 10 | Carriage of materials from source to site by machinal transfort including loading-unloading and stocking etc complete A) Stone agg avg lead 12 Km | 679 | Cum | |
11 | 11 | B) Stone avg lead 12 Km | 2473 | Cum | |
12 | 12 | C) Korb stone avg lead 8 KM | 69 | Cum | |
13 | 13 | D) Cement/steel avg lead 4km | 179.55 | m ton | |
14 | 14 | E) sand avg lead 8 km | 339 | Cum |
Copyright © 2024 · All Rights Reserved. Terms of Usage | Privacy Policy