| 1 | 1 | Charges for Docking / un - docking or beaching / un -beaching of the vessel | item1 | 1 | No |
|---|
| 2 | 2 | Dock hire charges (No extra dock hire charges will be entertained) | item2 | 30 | Days |
|---|
| 3 | 3 | Mooring Charges for before and after dry-dock as well as during afloat repair works | item3 | 20 | Days |
|---|
| 4 | 4 | Charges for ultrasonic testing of underwater hull and above water plates, onboard deck etc with Authorized agency. The copy of UT Gauge report shall be submitted to the office after completion of UT testing for the vessel immediately. | item4 | 1200 | Points |
|---|
| 5 | 5 | Dismantling of propellers Port & STBD sides (Make: Madras Marine industries, Dia:700 mm, Pitch:630 mm, P/D:0.9, No of blades:04, Type: Fixed pitch, no: 02), propeller shafts, checking the trueness of the shaft (Make: Madras Marine Industries, Dia:72 mm, Material: Stain less steel, no: 02), propellers, re-metalling, renewal of cut lash bushes etc. and re-fitting of the same along with propellers after balancing properly including labour charges. | item5 | 2 | Set |
|---|
| 6 | 5.1 | Cost of spares (on actual + 10% basis) will be reimbursed | item7 | | |
|---|
| 7 | 6 | Dismantling of rudder (Type:Plate type, Make: Startek shipyard Pvt Ltd,Chennai, Shaft: Dia.70 mm) and rudder stock, inspection of trueness, re-building of the same, making of new bushes, brackets etc. if any and re-fitting of the unit properly including labour charges. | item8 | 2 | Set |
|---|
| 8 | 6.1 | Cost of spares (on actual + 10% basis) will be reimbursed | item9 | | |
|---|
| 9 | 7 | Overhauling of sea suction (in and out) in engine room, onboard deck properly including labour cost. | item10 | 1 | Job |
|---|
| 10 | 7.1 | Cost of spares (on actual + 10% basis) will be reimbursed | item11 | | |
|---|
| 11 | 8 | Provision for renewal of under and above water level hull and onboard deck steel plates of 5 mm thick of ship building quality after cropping and removal of the damaged plates by gas cutting without any damages to other fittings & also section under water portion pipe to assed (to be done after getting ultrasonic test report and recommendation of Surveyor, Port Dept, Govt of Kerala including labour and material Cost. | item12 | 4000 | Kg |
|---|
| 12 | 9 | Chipping, scrapping, wire brushing, buffing, shot blasting etc of external hull plate from keel to water level of the vessel properly (initially clean with fresh water with jet). Painting of the area with 2 coat of marine epoxy, 2 coat of chlorinated rubber antifouling paint including labour and material Cost. | item14 | 100 | Sq.m |
|---|
| 13 | 10 | Surface preparation of entire deck (from water level to deck surface) and super structure including out fittings by chipping, scrapping, wire brushing, buffing, shot blasting etc properly such as onboard deck, anchor winch, anchor cables (after dismantling), air vent pipes, hand pumps, bollards, wheel house, top of galley, railings, hatches, wheel house doors, stern gear compartment inside (rear side of vessel) & other fittings etc including labour and material Cost | item16 | 150 | Sq.m |
|---|
| 14 | 11 | Painting of entire deck (from water level to deck surface) and super structure including out fittings such as onboard deck, anchor winch, air vent pipes, hand pumps, bollards, wheel house, top of galley, railings, hatches, wheel house doors, engine room inside (total sides, top & ladder and floor portion etc), stern gear compartment inside (rear side of vessel) & other fittings etc with 2 coat of epoxy primer and 2 coats of epoxy marine quality enamel of existing colour properly. The exhaust pipe cladding shall be renewed with new one properly (both engines) including labour and material Cost. | item17 | 250 | Sq.m |
|---|
| 15 | 12 | Renewal of damaged fire hand pipe with new one. Including labour and material cost. | item18 | 2 | Mtrs |
|---|
| 16 | 13 | Repair of STBD side main engine silencer pipe leakage and Aux engine exhaust manifold outlet pipe leakage renewal with new pipe including labour and material cost including labour and material cost. | item19 | 1 | Job |
|---|
| 17 | 14 | servicing of the fire engine water pump (is not working properly) and bilge pump (is not working properly water suction and outlet is not giving properly including labour cost. | item20 | 2 | No |
|---|
| 18 | 14.1 | Cost of Spare parts wiil be reimbursed on (Actual+10%) basis | item21 | | |
|---|
| 19 | 15 | Aux engine alternator service, sea water pump service and sea water outlet pipe block repair to be done and make in good working condition and supply of 1 no v belt of suitable size including labour and material cost | item22 | 1 | Job |
|---|
| 20 | 16 | Supply and fitting of Bilge and smoke alrm fitted in engine room and audible to the wheel house.including labour and material cost | item23 | 1 | Job |
|---|
| 21 | 17 | Opening & Cleaning of Diesel tanks of capacity 04 KL (Port:02 Ton,STBD:02 Ton), fresh water tanks of capacity 02 KL (Port:01 Ton, STBD:01 Ton) in Engine room properly with out any dust particles. After cleaning, The oils shall be stored in safe location and re-filled after the cleaning process. The bilge in engine room shall be pumped out and cleaned properly after removing of foot rest plates etc including labour and material Cost. | item24 | 1 | Job |
|---|
| 22 | 18 | Repair & strengthening of hatches (Size:600X600,coaming height:300) for Engine room exit (1 no), stern gear compartment door (1 no) & Accommodation (1 no) by renewal of rubber bleedings with new ones & damaged hatches to be strengthened by plate welding at damaged portions including labour and material Cost. | item25 | 1 | Job |
|---|
| 23 | 19 | New sewage tank to be fitted with 500ltr capacity along with a pump and connection pipes with toilet outlet to the tank, a fitted flang and also supply of hose of required length to pump the waste including labour and material cost. | item26 | 1 | Job |
|---|
| 24 | 20 | Fitting of Zinc Anodes (Location: Hull side shell): Zinc anodes,Type:ZHW-043, Net wt.:3.9 kg, Gross wt.:4.3 kg,Dim: 220X115X30, Qty:12, properly including labour and material Cost. | item27 | 12 | No |
|---|
| 25 | 21 | Fitting of zinc Anodes (Location: Rudder, Kort nozzle & sea chest) Zinc anodes,Type:ZHW-055, Net wt.:5.0 kg, Gross wt.:5.5 kg,Dim: 300x90x40, Qty:10 properly including labour and material Cost. | item28 | 10 | No |
|---|
| 26 | 22 | Re writing of vessel name, logo (IWAI), registration no, Port of registry, GRT on 4 locations of the vessel with size: 200 mm x 200 mm, load line, draft marking etc and on LSA & FFA vessel name, reg no, port of registry to be marked clear visibility including labour and material Cost. | item29 | 1 | Job |
|---|
| 27 | 23 | The following Fire extinguishers to serviced, hydraulic testing & refilling with new one. Labour and material cost | item30 | | |
|---|
| 28 | 23.1 | Foam portable type - 9 lt | item31 | 2 | No |
|---|
| 29 | 23.2 | 9 lt water co2 portable extinguisher | item32 | 2 | No |
|---|
| 30 | 23.3 | Portable DCP extinguisher capacity-10 kg | item33 | 2 | No |
|---|
| 31 | 26 | Service Taxes If any | item13 | | |
|---|