| 1 | 1 | Earth work excavation in hard gravelly soil. Stiff black cotton soil, hard red earth, shales, Murram, gravel, stoney earth mixed with small sized boulders etc., complete as per standard specification. | Item Code / 1 | 204 | m³ |
|---|
| 2 | 2 | Earth work excavating and depositing on bank with initial lead of 10m and initial llift of 2.0m in soft disintegrated rock, laterite, soft rock (or) kankar not requiring blasting, as per standard specification, etc., complete. | Item Code / 2 | 26 | m³ |
|---|
| 3 | 3 | Earth work excavating and depositing on Bank with initial lead of 10m and initial lift of 2m in medium rock and dense medium rock not requiring blasting, as per standard specification, etc., complete.. | Item Code / 3 | 13 | m³ |
|---|
| 4 | 4 | Removing hard rock by wedging, chiseling and trimming to proper shape where blasting is prohibited.as per standard specification, etc., complete.. | Item Code / 4 | 13 | m³ |
|---|
| 5 | 5 | Supplying and filling in M.sand for foundation and basement including cost of sand, filling charges as per standard specification (watering & consolidation) with all leads and lifts as per standard specification, etc., complete. | Item Code / 5 | 12.65 | m³ |
|---|
| 6 | 6 | Plain cement concrete in CC 1:3 :6 using 20mm HBG metal, including cost of cement, all materials, labour charges including consolidation, curing, all leads, lifts, as per standard specification etc., complete. | Item Code / 6 | 12.65 | m³ |
|---|
| 7 | 7 | Reinforced cement concrete in C.C. 1:1 ½ :3 mix, using 12 to 20mm HBG machine crushed metal, for Raft concrete & Retaining wall including cost of cement, all materials labour, curing, all leads & lifts, vibrating charges, including cost of centering, shutting, as per standard specification, etc., complete but excluding cost of steel reinforcement | Item Code / 7 | 124.56 | m³ |
|---|
| 8 | 8 | Providing steel reinforcement MS/RTS rods up to 16 mm dia for reinforced concrete works, including cost of steel MS/RTS rods, binding wire, labour charges for cutting, straightening bending as per type design drawing, placing aligning, and tying properly with all leads and lift as per standard specification, etc., complete | Item Code / 8 | 9310 | Kg |
|---|
| 9 | 9 | Supplying and erecting steel centering including necessary supports for plane surfaces for Reinforced Cement Concrete works such as column footings, column pedestals, plinth beams, grade beams, staircase steps, etc. which require only nominal strutting using mild steel sheets of size 90cm x 60cm and 10 BG stiffened with welded mild steel angles of size 25mm x 25mm x 3 mm for boarding, laid over silver oak joists of size 10cm x 6.5cm spaced at about 75cm centre to centre or at suitable intervals etc. complete in all floors complying with standard specifcation. (Payment for centering shall be given after the concrete is laid) | Item Code / 9 | 480 | m2 |
|---|
| 10 | 10 | Plastering with CM 1:3, 20mm thick, including cost of cement, labour, curing, all leads and lifts etc., complete..as per standard specification | Item Code / 10 | 49 | m2 |
|---|
| 11 | 11 | Refilling the foundation and basement with excavated earth other than sand and consolidating in 150mm thick layers, well rammed with all leads and lifts , watering, as per standard specification, etc., complete. | Item Code / 11 | 103 | m³ |
|---|
| 12 | 12 | Disposal of Excess of surplus earth away in low lying area with a lead of 100 Mts including spreading and levelling labour, lead, lift as per standard specification, etc., complete. | Item Code / 12 | 152 | m³ |
|---|
| 13 | 13 | Supplying and laying and fixing of 75mm dia PVC pipe to resist 6Kg/cm2 water pressure to proper alignment & slope for weep holes as required and as directed by the Engineer at site including cost of pipe and fixing in position, testing all matrials solution , lead, lifts etc., complete. | Item Code / 13 | 36 | Rm |
|---|
| 14 | 14 | Providing MS equal angles 65x65x8 MM as fencing post for a length of 2.5 m @2.5m c/c with 2 Nos of 150 mm length MS cleat of 35x35x5 mm as holdfast, 50x6mm flat to hold the chain link fencing using 10x75 mm GI bolt with nut and washers of 7 nos to tie the chainlink, straightening bending as per the instruction of the engineer incharge in the site, placing aligning, and tying properly with all leads and lift etc., complete as per Standard Specification. | Item Code / 14 | 88 | Nos |
|---|
| 15 | 15 | Providing Support angle for fensing post of 2.50 m length with MS equal angles 2 nos 65x65x8 MM @ 10.0 m c/c with 2 Nos of 150 mm length MS cleat of 35x35x5 mm to holdfast the support including GI bolt with 2 Nos of 10x75 mm bolt nut and washers to tie the Fensing post, straightening, bending as per the instruction of the engineer incharge in the site, placing aligning, and tying properly with all leads and lift etc., complete as per Standard Specification. | Item Code / 15 | 64 | Nos |
|---|
| 16 | 16 | Supplying, laying and fixing of GI coated Chain link fencing with mesh size 50x50 size 10 gauge wire of branded make including laying & tensioning cost of all materials labour lead lifts, as per standard specification, etc., complete. | Item Code / 16 | 548 | m2 |
|---|
| 17 | 17 | Supplying,fabricating and fixing in position of MS grills, gates,name boards, handrails and ladder,etc.,at various levels as per approved design of the Engr.including cost of steel and other required materials, labour charges, transportation and fixing, taking grooves in BM/RCC, packing the pockets with CC and painting with one coat metal primer complete. | Item Code / 17 | 700 | Kg |
|---|
| 18 | 18 | Painting 2 coats of Enamel Paint over 1 coat of Red Oxide for Steel Doors & Windows with approved quality & colour including cost of all materials, labour, lead, lift etc., complete. | Item Code / 18 | 28 | m2 |
|---|
| 19 | 19 | Outer colour washing with two coats using ready mixed Weather Proof Exterior Emulsion (First quality - Apex or its equivalent) of approved quality and colour over a coat of exterior emulsion water based primer exterior surfaces including through scrapping, clan removal of dirt, cost of all materials, scaffolding, Labour, Lead, Lift etc., complete and including necessary crack filling paste, putty wherever required. | Item Code / 19 | 445 | m2 |
|---|
| 20 | 20 | Dismantling, transporting and stalking at safe place of existing precast compound wall fensing post and slabs at Work site including cost of loading unloading lead, lift, labour etc., complete. | Item Code / 20 | 218 | m2 |
|---|
| 21 | 21 | Refixing of Precat slab for Compound wall to Height of 1.80 m including cost of transport, erection of precast fensing post at required spacing, fixing of Slabs to uniform levels and aligning to position and packing the slab joints with CM 1:3 including cost of lead, lift, labour etc., complete. | Item Code / 21 | 174 | m2 |
|---|
| 22 | 22 | Casting of precast fensing post and slabs of required size as per site condition in RCC 1:1.5:3 using 12 to 20mm HBG metal for compound wall including cost of cement, all materials, labour curing, vibration, including cost of all leads, lifts as per standard specification | Item Code / 22 | 8 | m3 |
|---|
| 23 | 23 | SGST to be quoted in Percentage (value alone)Ex. 9%, it should be entered as 9 only | Item Code / 23 | 1 | Percentage |
|---|
| 24 | 24 | CGST to be quoted in Percentage (value alone)Ex. 9%, it should be entered as 9 only | Item Code / 24 | 1 | Percentage |
|---|
| 25 | 25 | Inter-state GST @18% for other than Tamil Nadu supplier. If the contractor is within Tamil Nadu may be quoted as \"0\" only | Item Code / 25 | 1 | Percentage |
|---|