Petroleum and Natural Gas Boards / Undertakings / PSU Closing in 0 days TDR #23420375

Tender For Mech Jobs For Hgu/Dhdt/Sru Shutdown At Bgr, Iocl

Issued by Boards / Undertakings / PSU · BGR, Dhaligaon, Assam
Tender Value
1.32 Crore
Estimated cost
Bid Submission
04 Feb 2020
0 days left
EMD
1.32 Lakhs
Bank guarantee accepted
Document Fee
Ref. Documents
Non-refundable
Tender Type
Online

Tender Overview

Competition Type
NCB
Bidding Type
Tender
Location / State
BGR, Dhaligaon → Assam
EMD Exemption
Not Available
Quantity
Not Available

Project Description

Tender For Mech Jobs For Hgu / Dhdt / Sru Shutdown At Bgr, Iocl -2 Mech Jobs For Hgu / Dhdt / Sru 3 A Misc Piping & Other Jobs 4 Dismantling Of Carbon Steel / Alloy Steel Piping By Hot Work ( Insulated / Uninsulated ) Dismantling And Removal Of Above Ground, Overhead Under Ground ( Upto Depth Of 5M ) Redundant, Steam Traced Pipelines, Insulated And U Ninsulated, Of Carbon Steel / Alloy Steel By Gas Cutting Or By Grinder From Various Locations Such As Pipe Racks, Columns, Pump House, Vessels, Heaters, Heat Exchangers, Desalter Etc. Upto A Height Of 5 Meters Including, Removal Of Insulation Material, All On Line Instruments, Fittings, Flanges, Valves, Vents, Drains, Branching Etc.; Lowering Down The Same To Ground Level With Due Care So That No Other Piping, Equipment#S, Machinery#S Etc. Is Damaged; Cutting Into Pieces If Required; Segregating For Reclaiming Useful Fittings Such As Bends, Flanges, Valves, Instruments Etc. By Unbolting, Gas Cutting, Cold Cutting Etc.; Transporting And Stacking The Salvageable Useful Materials To Workshop / Instrument Workshop / Store Or As Per The Direction Of The Engineer-In-Charge And Shifting The Scrap Pipes Etc. To Scrap Yard Or Any Other Location Within Refinery Premises And Completing The Job As Per The Instructions Of Engineer-In-Charge. Job Also Includes Supplying Of All Types Of Tools And Tackles, Lifting Arrangements, Equipment, Machineries, All Consumables And Labour Etc. To Complete The Work In All Respects In A Workman Like Manner Including Area Preparation, Taking Clearance For Hot Jobs, Blinding And De-Blinding, Area Cleaning After Completion Of Work, Flushing Wherever Required As Directed By The Engineer-In-Charge. Note : 1. Proper Safety Arrangements For Carrying Out The Job Is Under Contractors Scope And The Same Has To Be Complied With As Per The D Irections Of The Engineer- In-Charge. 2. Salvaging Of Useful Fitting From Redundant Pipe, If Done, Will Be Paid Under Separate Item. 3. Civil Works ( Excavation And Back Filling ) For Underground Dismantling Shall Be Paid Under Separate Item From Civil Sor. Note: For Piping Beyond 5 Mtr. Elevation Above And Below Ground Piping And Upto 10Mtr. Rates Is To Be Escalated By 20%. For More Than 10 Mtr. But Upto 15 Mtr. Rates Is To Be Escalated By 30%. For More Than 15 Mtr But Upto 20 Mtr. Rates To Be Escalated By 40% Respectively. Requirement Of Scaffolding To Be Envisaged And Decided By Engineer In Charge As Per Site Requirement And Scaffolding Item To Be Paid Separately. 5 15 Mm Nb 6 20 Mm Nb 7 25 Mm Nb 8 40 Mm Nb 9 50 Mm Nb 10 80 Mm Nb 11 100 Mm Nb 12 150 Mm Nb 13 200 Mm Nb 14 250 Mm Nb 15 300 Mm Nb 16 350 Mm Nb 17 400 Mm Nb 18 450 Mm Nb 19 500 Mm Nb 20 600 Mm Nb 21 Cold Cutting Of Carbon / Alloy Steel Pipe Lines ( Insulated / Uninsulated ) Cold Cutting And Removal Of Above Ground / Overhead / Underground In Tranches ( Upto 5 Meters Depth ) Insulated Or Uninsulated Pipelines Of Carbon Steel / Alloy Steel / And / Or Any Other Type From Various Location Such As Pipe Racks, Columns, Pump House, Vessels, Heaters, Heat Exchangers, Desalters Etc. Upto A Height Of 5 Meters Including Removal Of Insulation Materials, All On Line Instruments, Fittings, Flanges, Valves, Vents, Drains, Branching Etc.; Lowering Down / Lifting The Same To Ground Level With Due Care So That No Other Piping, Equipment#S, Machinery#S Etc. Is Damaged; Cutting Into Pieces If Required; Segregating For Reclaiming Useful Fittings Such As Bends, Flanges, Valves, Instruments Etc. By Unbolting, Gas Cutting, Cold Cutting Etc. Transporting And Stacking The Salvageable Useful Materials To Workshop / Instrument Workshop / Store Or As Per The Direction Of The Engineer-In-Charge And Shifting The Scrap Pipes Etc. To Scrap Yard Or Any Other Location Within Refinery Premises All Complete As Per The Instructions Of Engineer-In-Charge.°° Job Also Includes Supplying Of All Types Of Tools And Tackles, Lifting Arrangements, Equipment, Machineries, All Consumables And Labour Etc. To Complete The Work In All Respects In A Workman Like Manner Including Area Preparation, Taking Clearance For Hot Jobs, Blinding And Deblinding Area Cleaning After Completion Of Work, Flushing Wherever Required As Directed By The Engineer-In-Charge. Note : 1. Proper Safety Arrangements For Carrying Out The Job Is Under Contractors Scope And The Same Has To Be Complied With As Per The D Irections Of The Engineer- In-Charge. 2. Salvaging Of Useful Fitting From Redundant Pipe, If Done, Will Be Paid Under Separate Item. 3. Civil Works ( Excavation And Back Filling ) For Underground Dismantling Shall Be Paid Under Separate Item From Civil Sor. Note: For Piping Beyond 5 Mtr. Elevation Above And Below Ground Piping And Upto 10Mtr. Rates Is To Be Escalated By 20%. For More Than 10 Mtr. But Upto 15 Mtr. Rates Is To Be Escalated By 30%. For More Than 15 Mtr But Upto 20 Mtr. Rates To Be Escalated By 40% Respectively. Requirement Of Scaffolding To Be Envisaged And Decided By Engineer In Charge As Per Site Requirement And Scaffolding Item To Be Paid Separately. 22 15 Mm Nb 23 20 Mm Nb 24 25 Mm Nb 25 40 Mm Nb 26 50 Mm Nb 27 80 Mm Nb 28 100 Mm Nb 29 150 Mm Nb 30 200 Mm Nb 31 250 Mm Nb 32 300 Mm Nb 33 350 Mm Nb 34 400 Mm Nb 35 450 Mm Nb 36 500 Mm Nb 37 Fixing / Removal Of Flanges / Blind Flanges Of Rating Upto 300# Opening / Fixing Etc. Of Flanges / Blind Flanges / Spool Pieces At The Two Flange Joint ( Rating Upto 300# ) As And When Required For Elbow Reversing, Wedge Opening Etc. Or Any Other Job Including Handling Of Flanges And Preparation Of Gaskets From The Sheet Including Tools And Tackles, Consumables, Supervision Etc. And As Per Direction Of The Engineer-In-Charge. 38 15 Mm 39 20 Mm 40 25 Mm 41 40 Mm 42 50 Mm 43 80 Mm 44 100 Mm 45 150 Mm 46 200 Mm 47 250 Mm 48 300 Mm 49 350 Mm 50 400 Mm 51 450 Mm 52 500 Mm 53 600 Mm 54 Fixing / Removal Of Flanges / Blind Flanges Of Rating More Than 300# And Upto 600# Opening / Fixing Etc. Of Flanges / Blind Flanges / Spool Pieces At The Two Flange Joint ( Rating More Than 300# And Upto 600# ) As And When Required For Elbow Reversing, Wedge Opening Etc. Or Any Other Job Including Handling Of Flanges And Preparation Of Gaskets From The Sheet Including Tools And Tackles, Consumables, Supervision Etc. And As Per Direction Of The Engineer-In-Charge. 55 15 Mm 56 20 Mm 57 25 Mm 58 40 Mm 59 50 Mm 60 80 Mm 61 100 Mm 62 150 Mm 63 200 Mm 64 250 Mm 65 300 Mm 66 350 Mm 67 Dismantling Of Stainless Steel Piping By Hot Work ( Insulated / Uninsulated ) Dismantling And Removal Of Above Ground / Overhead / Underground In Trenches ( Upto 5 M ) Redundant, Steam Traced Pipelines, Insulated And Uninsulated Of Stainless Steel By Grinding / Gouging / Plasma Cutting From Various Locations Such As Pipe Racks, Columns, Pump House, Vessels, Heaters, Heat Exchangers, Desalter Etc. Upto A Height Of 5 Meters Including Removal Of Insulation Materials All On Line Instruments, Fittings, Flanges, Valves, Vents, Drains, Branching Etc.; Lowering Down The Same To Ground Level With Due Care So That No Other Piping, Equipment#S, Machinery#S Etc. Is Damaged; Cutting Into Pieces If Required; Segregating For Reclaiming Useful Fittings Such As Bends, Flanges, Valves, Instruments Etc. By Unbolting, Gas Cutting, Cold Cutting Etc.; Transporting And Stacking The Salvageable Useful Materials To Workshop / Instrument Workshop / Store Or As Per The Direction Of The Engineer-In-Charge And Shifting The Scrap Pipes Etc. To Scrap Yard Or Any Other Location Within Refinery Premises All Complete As Per The Instructions Of Engineer In-Charge. Job Also Includes Supplying Of All Types Of Tools And Tackles, Lifting Arrangements, Equipment, Machineries, All Consumables And Labour Etc. To Complete The Work In All Respects In A Workman Like Manner Including Area Preparation, Taking Clearance For Hot Jobs, Blinding And Deblinding Area Cleaning After Completion Of Work, Flushing Wherever Required As Directed By The Engineer-In-Charge. Note : 1. Proper Safety Arrangements For Carrying Out The Job Is Under Contractors Scope And The Same Has To Be Complied With As Per The D Irections Of The Engineer- In-Charge. 2. Salvaging Of Useful Fitting From Redundant Pipe, If Done, Will Be Paid Under Separate Item. 3. Civil Works ( Excavation And Back Filling ) For Underground Dismantling Shall Be Paid Under Separate Item From Civil Sor. Note: For Piping Beyond 5 Mtr. Elevation Above And Below Ground Piping And Upto 10Mtr. Rates Is To Be Escalated By 20%. For More Than 10 Mtr. But Upto 15 Mtr. Rates Is To Be Escalated By 30%. For More Than 15 Mtr But Upto 20 Mtr. Rates To Be Escalated By 40% Respectively. Requirement Of Scaffolding To Be Envisaged And Decided By Engineer In Charge As Per Site Requirement And Scaffolding Item To Be Paid Separately. 68 20 Mm Nb 69 25 Mm Nb 70 40 Mm Nb 71 50 Mm Nb 72 80 Mm Nb 73 100 Mm Nb 74 150 Mm Nb 75 200 Mm Nb 76 250 Mm Nb 77 Carbon Steel Piping Joints For Hydrocarbon Service ( With Welding Electrode E-6010 / E-7018 ) Transportation Of All Piping Items From Owners Storage Points To Work Site And / Or Pre-Fabrication Yard And To Site After Pre-Fabrication; Cutting, Grinding, Edge Preparation Of Pipes And Fittings, Like Flanges, Elbows, Tees, Reducers Etc. To Match The Mating Edges Of Different Thickness; Fit-Up, Bending, Welding Using Approved Welding Electrodes As Per Owners Quality Requirements Etc. As Per Codes / Specifications, Drawing Etc., Threading, Laying, Erection And Alignment Of Pipes At Ground Level I.E. Upto A Height Of 5 Meters On Sleepers, Pipe Racks Etc. Or Upto 5 Meters Depth In Trenches; Connecting With Equipment, Nozzles, Steam Traps, Strainers, Orifice Assemblies ( Including Tapping Upto First Block Valve ) , Spray Nozzles Rotameters; Tapping For Instrument Connections Like Pressure Gauges, Thermowells, Sample Connections, Vents, Drains Etc. Including Fixing Of All Types Of Sw Valves, Gaskets, Nuts And Bolts, All Inline Instruments, Elbows, Tees, Flanges, Reducers, Full Coupling Or Half Coupling, Earthing Strip Wherever Required; Welding Prefabricated Shoes And Supports ( Including Alignment ) As Per The Drawings, Including Preparation Small Bore Isometric Upto 1.5 Inch Nb, Specifications, Codes Etc. And As Per The Instructions Of The Engineer-In-Charge To His Entire Satisfaction Including Supplying Of All Types Of Tools And Tackles, Lifting Arrangements, Equipment, Machineries, All Consumables And Labour Etc. To Complete The Work In All Respects In A Workman Like Manner Including Area Preparation For Hot Jobs, Area Cleaning After Completion Of Work, Flushing Wherever Required, Cleaning Of Pipes Externally Off All Foreign Materials Like Weld Beads, Clamps Fixtures Etc. Used In Fabrication As Directed By The Engineer-In-Charge. Note : Proper Safety Arrangements For Carrying Out The Job Is Under Contractors Scope And The Same Has To Be Complied With As Per The Dire Ctions Of The Engineer- In-Charge. Note: For Piping Beyond 5 Mtr. Elevation Above And Below Ground Piping And Upto 10Mtr. Rates Is To Be Escalated By 20%. For More Than 10 Mtr. But Upto 15 Mtr. Rates Is To Be Escalated By 30%. For More Than 15 Mtr But Upto 20 Mtr. Rates To Be Escalated By 40% Respectively. Requirement Of Scaffolding To Be Envisaged And Decided By Engineer In Charge As Per Site Requirement And Scaffolding Item To Be Paid Separately. Note: For Piping Where Tig Welding Is Used For Root Run Only, The Rates To Be Escalated By 15% And Where Tig Welding Is Used For Entire Joints The Rates To Be Escalated By 20%. Note: Payment Of Tapping Points Will Also Be Made Extra On Joint Basis, As The Measurement Is On Joint Basis. 78 15 Mm Nb, Schedule Upto 80 79 15 Mm Nb, Schedule Above 80 But Upto 160 80 20 Mm Nb, Schedule Upto 80 81 20 Mm Nb, Schedule Above 80 But Upto 160 82 25 Mm Nb, Schedule Upto 80 83 25 Mm Nb, Schedule Above 80 But Upto 160 84 40 Mm Nb, Schedule Upto 80 85 40 Mm Nb, Schedule Above 80 But Upto 160 86 50 Mm Nb, Schedule More Than 40 But Upto 80 87 50 Mm Nb, Schedule Above 80 But Upto 160 88 80 Mm Nb, Schedule Upto 40 89 80 Mm Nb, Schedule More Than 40 But Upto 80 90 80 Mm Nb, Schedule Above 80 But Upto 160 91 100 Mm Nb, Schedule Upto 40 92 100 Mm Nb, Schedule More Than 40 But Upto 80 93 100 Mm Nb, Schedule Above 80 But Upto 160 94 150 Mm Nb, Schedule Upto 40 95 150 Mm Nb, Schedule More Than 40 But Upto 80 96 150 Mm Nb, Schedule Above 80 But Upto 120 97 200 Mm Nb, Schedule Above 20 But Upto 40 98 200 Mm Nb, Schedule More Than 40 But Upto 80 99 200 Mm Nb, Schedule Above 80 But Upto 120 100 250 Mm Nb, Schedule Above 20 But Upto 40 101 250 Mm Nb, Schedule More Than 40 But Upto 80 102 250 Mm Nb, Schedule Above 80 But Upto 120 103 300 Mm Nb, Schedule Upto 20 104 300 Mm Nb, Schedule Above 20 But Upto 40 105 300 Mm Nb, Schedule More Than 40 But Upto 80 106 350 Mm Nb, Schedule Upto 20 107 350 Mm Nb, Schedule Above 20 But Upto 40 108 350 Mm Nb, Schedule More Than 40 But Upto 80 109 400 Mm Nb, Schedule Upto 20 110 400 Mm Nb, Schedule Above 20 But Upto 40 111 450 Mm Nb, Schedule Upto 20 112 450 Mm Nb, Schedule Above 20 But Upto 40 113 500 Mm Nb, Schedule Upto 20 114 500 Mm Nb, Schedule Above 20 But Upto 40 115 600 Mm Nb, Schedule Upto 20 116 600 Mm Nb, Schedule Above 20 But Upto 40 117 Cs Ppg Joints Nhc Electd E-6013 Transportation Of All Piping Items From Owners Storage Points To Work Site And / Or Pre-Fabrication Yard And To Site After Pre-Fabrication; Cutting, Grinding, Edge Preparation Of Pipes And Fittings, Like Flanges, Elbows, Tees, Reducers Etc. To Match The Mating Edges Of Different Thickness; Fit-Up, Bending, Welding Using Approved Welding Electrodes As Per Owners Quality Requirements Etc. As Per Codes / Specifications, Drawing Etc., Threading, Laying, Erection And Alignment Of Pipes At Ground Level I.E. Upto A Height Of 5 Meters On Sleepers, Pipe Racks Etc. Or Upto 5 Meters Depth In Trenches; Connecting With Equipment, Nozzles, Steam Traps, Strainers, Orifice Assemblies ( Including Tapping Upto First Block Valve ) , Spray Nozzles Rotameters; Tapping For Instrument Connections Like Pressure Gauges, Thermowells, Sample Connections, Vents, Drains Etc. Including Fixing Of All Types Of Sw Valves, Gaskets, Nuts And Bolts, All Inline Instruments, Elbows, Tees, Flanges, Reducers, Full Coupling Or Half Coupling, Earthing Strip Wherever Required; Welding Prefabricated Shoes And Supports ( Including Alignment ) As Per The Drawings, Including Preparation Small Bore Isometric Upto 1.5 Inch Nb, Specifications, Codes Etc. And As Per The Instructions Of The Engineer-In-Charge To His Entire Satisfaction Including Supplying Of All Types Of Tools And Tackles, Lifting Arrangements, Equipment, Machineries, All Consumables And Labour Etc. To Complete The Work In All Respects In A Workman Like Manner Including Area Preparation For Hot Jobs, Area Cleaning After Completion Of Work, Flushing Wherever Required, Cleaning Of Pipes Externally Off All Foreign Materials Like Weld Beads, Clamps Fixtures Etc. Used In Fabrication As Directed By The Engineer-In-Charge. Note : Proper Safety Arrangements For Carrying Out The Job Is Under Contractors Scope And The Same Has To Be Complied With As Per The Dire Ctions Of The Engineer- In-Charge. Note: For Piping Beyond 5 Mtr. Elevation Above And Below Ground Piping And Upto 10Mtr. Rates Is To Be Escalated By 20%. For More Than 10 Mtr. But Upto 15 Mtr. Rates Is To Be Escalated By 30%. For More Than 15 Mtr But Upto 20 Mtr. Rates To Be Escalated By 40% Respectively. Requirement Of Scaffolding To Be Envisaged And Decided By Engineer In Charge As Per Site Requirement And Scaffolding Item To Be Paid Separately. Note: For Piping Where Tig Welding Is Used For Root Run Only, The Rates To Be Escalated By 15% And Where Tig Welding Is Used For Entire Joints The Rates To Be Escalated By 20%. Note: Payment Of Tapping Points Will Also Be Made Extra On Joint Basis, As The Measurement Is On Joint Basis. 118 15 Mm Nb, Schedule Upto 80 119 15 Mm Nb, Schedule Above 80 But Upto 160 120 20 Mm Nb, Schedule Upto 80 121 20 Mm Nb, Schedule Above 80 But Upto 160 122 25 Mm Nb, Schedule Upto 80 123 25 Mm Nb, Schedule Above 80 But Upto 160 124 40 Mm Nb, Schedule Upto 80 125 40 Mm Nb, Schedule Above 80 But Upto 160 126 50 Mm Nb, Schedule More Than 40 But Upto 80 127 50 Mm Nb, Schedule Above 80 But Upto 160 128 80 Mm Nb, Schedule More Than 40 But Upto 80 129 80 Mm Nb, Schedule Above 80 But Upto 160 130 100 Mm Nb, Schedule Upto 40 131 100 Mm Nb, Schedule More Than 40 But Upto 80 132 150 Mm Nb, Schedule Upto 40 133 150 Mm Nb, Schedule More Than 40 But Upto 80 134 200 Mm Nb, Schedule Above 20 But Upto 40 135 200 Mm Nb, Schedule More Than 40 But Upto 80 136 250 Mm Nb, Schedule Above 20 But Upto 40 137 250 Mm Nb, Schedule More Than 40 But Upto 80 138 300 Mm Nb, Schedule Above 20 But Upto 40 139 300 Mm Nb, Schedule More Than 40 But Upto 80 140 400 Mm Nb, Schedule Above 20 But Upto 40 141 400 Mm Nb, Schedule More Than 40 But Upto 80 142 450 Mm Nb, Schedule Above 20 But Upto 40 143 450 Mm Nb, Schedule Above 40 But Upto 80 144 500 Mm Nb, Schedule Above 20 But Upto 40 145 500 Mm Nb, Schedule Above 40 But Upto 80 146 Carbon Steel Piping For Non-Hydrocarbon Service ( With Welding Electrode E-6013 ) Transportation Of All Piping Items From Owners Storage Points To Work Site And / Or Pre-Fabrication Yard And To Site After Pre-Fabrication; Cutting, Grinding, Edge Preparation Of Pipes And Fittings, Like Flanges, Elbows, Tees, Reducers Etc. To Match The Mating Edges Of Different Thickness; Fit-Up, Bending, Welding Using Approved Welding Electrodes As Per Owners Quality Requirements Etc. As Per Codes / Specifications, Drawing Etc., Threading, Laying, Erection And Alignment Of Pipes At Ground Level I.E. Upto A Height Of 5 Meters On Sleepers, Pipe Racks Etc. Or Upto 5 Meters Depth In Trenches; Anchoring Wherever Required, Connecting With Equipment, Nozzles, Steam Traps, Strainers, Orifice Assemblies ( Including Tapping Upto First Block Valve ) , Spray Nozzles Rotameters; Tapping For Instrument Connections Like Pressure Gauges, Thermowells, Sample Connections, Vents, Drains Etc. Including Fixing Of All Types Of Sw Valves, Gaskets, Nuts And Bolts, All Inline Instruments, Elbows, Tees, Flanges, Reducers, Full Coupling Or Half Coupling, Reinforcement Pads, Earthing Strip Wherever Required; Welding Prefabricated Shoes And Supports ( Including Alignment ) As Per The Drawings Including Preparation Of Small Bore Isometrics Upto 1.5 Inch Nb, Specifications, Codes Etc. And As Per The Instructions Of The Engineer-In-Charge To His Entire Satisfaction Including Supplying Of All Types Of Tools And Tackles, Lifting Arrangements, Equipment, Machineries, All Consumables And Labour Etc. To Complete The Work In All Respects In A Workman Like Manner Including Area Preparation For Hot Jobs, Area Cleaning After Completion Of Work, Flushing Wherever Required, Cleaning Of Pipes Externally Off All Foreign Materials Like Weld Beads, Clamps Fixtures Etc. Used In Fabrication As Directed By The Engineer-In-Charge. Note : Proper Safety Arrangements For Carrying Out The Job Is Under Contractors Scope And The Same Has To Be Complied With As Per The Dire Ctions Of The Engineer- In-Charge. Note: For Piping Beyond 5 Mtr. Elevation Above And Below Ground Piping And Upto 10Mtr. Rates Is To Be Escalated By 20%. For More Than 10 Mtr. But Upto 15 Mtr. Rates Is To Be Escalated By 30%. For More Than 15 Mtr But Upto 20 Mtr. Rates To Be Escalated By 40% Respectively. Requirement Of Scaffolding To Be Envisaged And Decided By Engineer In Charge As Per Site Requirement And Scaffolding Item To Be Paid Separately. Note: For Piping Where Tig Welding Is Used For Root Run Only, The Rates To Be Escalated By 15% And Where Tig Welding Is Used For Entire Joints The Rates To Be Escalated By 20%. 147 15 Mm Nb, Schedule Upto 80 148 20 Mm Nb, Schedule Upto 80 149 25 Mm Nb, Schedule Upto 80 150 40 Mm Nb, Schedule Upto 80 151 50 Mm Nb, Schedule More Than 40 But Upto 80 152 80 Mm Nb, Schedule Upto 40 153 100 Mm Nb, Schedule Upto 40 154 150 Mm Nb, Schedule Upto 40 155 200 Mm Nb, Schedule Above 20 But Upto 40 156 250 Mm Nb, Schedule Above 20 But Upto 40 157 300 Mm Nb, Schedule Above 20 But Upto 40 158 350 Mm Nb, Schedule Above 20 But Upto 40 159 400 Mm Nb, Schedule Above 20 But Upto 40 160 Hydrotesing Of Piping Works Hydrostatic Testing Of Pipelines At The Specified Pressure Including Blinding / Deblinding, Fabrication And Fixing Of Testing Connections, Pressure Gauge Installation. Hose Pipe Connection And Making All Other Arrangements As Required And Dewatering, Flushing And Boxing Up After Fixing Proper Gaskets With Supply Of All Labour, Tools Andtackles, Instruments And Instruction Of The Engineer-In-Charge. The Job Has To Be Carried Out At All Elevations. 161 15 Mm 162 20 Mm 163 25 Mm 164 40 Mm 165 50 Mm 166 80 Mm 167 100 Mm 168 150 Mm 169 200 Mm 170 250 Mm 171 300 Mm 172 350 Mm 173 400 Mm 174 450 Mm 175 500 Mm 176 Wrapping & Coating Of Vessels / Underground Piping Etc. Providing Wrapping And Coating As Per The Specifications Including Supply Of All Materials, Tools And Tackles, Etc. The Detailed Spe Cification For Wrapping And Coating Is As Under: 1. The Surface Preparation Of Pipes Shall Be Done By Grit / Shot Blast Cleaning To Swedish Standard Sa-2. 2. The Grit / Shot Blasting Operation Shall Be Carried Out In The Day Time. Blast Cleaning Operation Shall Not Be Under Taken In Humid Condition. 3. Only Approved Quality Grit / Shot Shall Be Used For Grit / Shot Blasting. The Grit / Shot Used Shall Be Dry And Free Form Any Other Impurities. 4. The Grit / Shot Blasted Surface Shall Have A Shining And Near White Metal Appearances. 5. After Grit / Shot Blast Cleaning, The Surface Shall Be Dry Brushed To Remove Deposits. 6. The Grit / Shot Blasted Surface Should Be Inspected By Quality Control / Inspection Agency Of Owner / Contractor. Coating System Following Steps Shall Be Followed: 1. Application Of One Coat Of Primer. 2. Application Of One Coat Of Coal Tar Enamel. 3. Wrapping Fibre Glass. 4. Application Of 2Nd Coat Of Coal Tar Enamel. 5. Wrapping Of Craft Paper / Coal Tar Impregnated Outer Wrap. Priming 1. Single Coat Of Coal Tar Primer Shall Be Applied Manually With Good Quality Brushes. Following Precautions Shall Be Taken During Application Of Primer. 2. Primer Drum Shall Be Inspected For Manufacturing Date Batch No. Etc. 3. Primer Drum Shall Be Rotated Before Opening For Proper Mixing. 4. Primer Shall Be Applied Within 12 Hrs. Of Completion Of Sand Blasting. 5. Primer Shall Be Applied Evenly All Along The Pipe Surface. 6. Any Holiday Or Bare Pipe Left Over During Priming Shall Be Primed Again. 7. Primer Will Not Be Applied During Rainy / Moist Weather. 8. After Application Of Primer And Before Drying, Adequate Precaution Shall Be Taken To Avoid Contact Of Dust / Sand Etc. With Primed Surface. 9. Normal Primer Requires 1 Hr. Time For Proper Drying And Becomes Dead After 24 Hrs. Of Its Application. 10. Coating Shall Be Completed Within These Limits Failing Which Dead Primer Shall Be Cleaned And Fresh Primer Shall Be Applied Again. Coating And Wrapping I ) When The Priming Coat Has Dried And The Surface Of The Primed Pipe Has Been Cleaned Preferably By Clean White Rags To Remove The Settled Dust Just Preceding Of The Coating Operation. The Pipe Shall Be Coated With Hot Application Of One Coat Of Coal Tar Enamel To Give A Minimum Thickness Of 2.5 Mm And To Be Securely Bonded To The Primer. Ii ) The Coal Tar Enamel Shall Be Cut Into Lumps Preferably At The Storage Place Upon A Clean Platform With Side Boards And Due Care Must Always Be Exercised By The Contractor To Keep The Broken Enamel Absolutely Free Form Dirt, Grass, Water Or Any Other Foreign Material Up To The Time When Enamel Is Charged Into The Melting Kettle. Iii ) The Coal Tar Enamel Shall Be Slowly Heated On Reduced Fire And Maintained To The Even Temperature Recommended For Application I.E. 220 Deg. C To 240 Deg. C. Iv ) Constant Stirring Shall Be Necessary In Continuously Operating Melting Kettles. V ) Melting Kettle Should Have Proper Insulation. Vi ) The Melting Kettle Should Be Of Movable Type I.E. Wheel Mounted And Have Towing Arrangement. Vii ) The Melting Kettle Should Be Kept Near The Work Site. However, In No Case The Molten Enamel Shall Be Carried In Bucket For More Than 50 Meter Distance. Viii ) During Pouring Of Molten Enamel, Fine Wire Mesh Filter Shall Be Used To Avoid The Flow Of Impurity / Dirt / Sand. Ix ) During Temporary Interruption Of The Work The Temperature In The Kettle Not Shall Be Reduced By At Least 50 Deg. C Below The Normal Specified Temperature. X ) Any Enamel Heated To Temperature In Excess Of The Maximum Allowable Temperature Shall Be Rejected And Suitably Disposed Off By The Contractor. Xi ) Melting Kettles / Pots Shall Always Be Maintained Clean And In Good Working Order And Must Be Cleaned Whenever Deposits Form On The Heating Surface. Xii ) A Uniform Thickness Of 2.5 Mm Of Enamel Shall Be Applied To The Surface Of The Primed Pipe. Xiii ) A Uniform Thickness Of 2.5 Mm Of Enamel Shall Be Applied To The Surface Of The Primed Pipe. Xiv ) The Enamel Shall Be Then Reinforced By A Spirally Wrapped Fibre Glass Wrap, Pulled And Embedded Into The Hot Coating With An Over Lapping Of Edges Of The Wrap Not Less Than 1 / 2 And Not More Than 1 Xv ) This Will Be Followed By Another Coat Of Hot Coal Tar Enamel Application With A Uniform Thickness Of 1.5 Mm Followed By Craft Paper / Coal Tar Impregnated Fibre Glass Covering. Xvi The Coating And Wrapping Must Be Absolutely Free Of Wrinkles In The Wrappers, Pinholes, Bubbles, Holidays Voids Thin Spots Or Foreign Matter. Xvii Rolls Of Wrapping Material Shall Not Be Kept Along The Right Of Way And Shall Be Stored Properly And Brought To Site. Xviii ) Wrapping Material Shall Be So Hauled And Handled As To Prevent Injury To The Packages. Xix ) No Packages Shall Be Handled With Hooks Or Thrown Form Trucks. Xx ) Any Such Material Which Shows Evidence Of Deterioration Due To Weather Or Any Other Cause, Shall Be Rejected. Coating Thickness Minimum Thickness Of First Should Be 2.5 Mm Whereas Total Thickness Should Be Approx. 4.5 Mm. Testing Following Testing Shall Be Undertaken: I ) Physical Inspection: All The Coated Surface Shall Be Visually Inspected And All The Wrinkles, Bubbles, Lack Of Overlap Etc. Shall Be Marked For Repair. Ii ) Sound Test: The Coating Adhesion Can Be Checked Easily With Small Wooden Hammer By Soft Striking On Coated Surface. Change In Sound Indicates Coating Defects And Same Can Be Checked There By Peel Test. Iii ) Peel Test: The Field Bond Test For Coal Tar Enamel Adhesion Shall Be Preformed At 50-80F Normal Operating Temperature Of Steel Piping. If The Coating Temperature Is Above 80 °F Or Below 50 Deg. F, Pour Cold Or Hot Water Over The Test Area To Adjust The Enamel Temperature Within This Range. Using A Knife, Heated If Necessary Make Two Parallel Cuts Through The Coating About 4 Inch In Length And 3 / 4 Inch Apart. With The Edge Of Knife Blade Cut Under The Enamel Strip At One End And Loosen The Enamel Form The Pipe The Full Width Of The Strip For About A 1 / 2 Place The Knife Blade Under The Loosened End And Apply A Slow, Steady Pull Upward On Enamel Strip. Iv ) If The Peel Length Exceeds 1 / 8 The Test Is A Failure And Two Additional Tests Shall Be Made At Two Different Locations On The Same Section. If The Additional Tests Are Satisfactory Then The Section Shall Be Approved. If The Either Additional Test Fails, The Pipe Section Shall Be Rejected. Specification Of Coal Tar Primer The Primer Consists Of Processed Coal Tar Pitch And Refined Coal Tar Oil Suitably Blended With A Solvent Without Pigment Or Inert Filler Or Other Substances ( To Be Applied Cold ) For Brushing Or Spraying As Liquid Coat To The Clean Surface Piping As Provided For In Awwa Specification C-203-73. The Primer Should Have No Tendency To Settle Down In The Container And When Applied Without Producing Bubbles, Becomes Dry And Hard To Touch Within Specified Time Ensuring And Effective Bond Between The Metal Pipe Surface And The Enamel Coating. The Main Characteristics Of The Coal Tap Primer Should Be As Follows: 1. Drying Time To Touch Dry, At Normal Humidity At 32 Deg. C Is Less Than 1 Hr. 2. Max Boiling Point Of Solvent 25 Deg. C. 3. Penetration Of Residue At 25 Deg. C. 4. Softening Point Of Residue ( Astm-D-36 ) 104 Deg. C. 5. Flash Point Of ( Astm 1310 ) 37 Deg. C. 6. Pigment 7. Solvent Benzol Solvent Or Highly Toxic Volatile Solvents Excluded. Reputed Indian Supplier ( For Coal Tar Enamel And Coal Tar Primer ) . I ) M / S Shalimar Tar Products, Calcutta. Ii ) M / S Lloyd Insulation ( India ) Ltd., New Delhi. 2. Specification For Coal Tar Enamel The Enamel Shall Be A Wwa Coal Enamel Type-I Conforming To Awwa Standard, Awwa C-203-86. The Enamel Be Composed Of A Specially Processed Coal Tar Type Blended With An Inert Mineral Filter, Properly Graded, Cleaned, Dust Free And Without Asphalt Of Either Petroleum Or Nature Base, To Be Applied To A Recommended Temperature. The Main Characteristics Of The Enamel Shall Be As Follows: S. No. Test Enamel Type - 1 Min Max. 1. Softening Point, Astm-D-36 140 Deg.C 116 Deg. C 2. Filter ( Ash ) Astmd-71 25% 35% 3. Fineness Fillet Through 90% Through 200 Mesh. Astm-D-54G 3. Specification Of Fibre Glass Inner Wrap The Fibre Glass Inner Wrap Of High Tensile Long Monofilament, Chemically Inert Glass Fibre In Jack Straces Patterns Mat Reinforced By Longitudinal Continuous Stands Of Glass Fibre Yarn Blended With Insoluble Inert Resinous Binder Compatible With Hot Coal Tar Enamel And Should Conform To The Following Specifications: Tensile Strength ( Transverse ) Kg / Cm 0.50 + 0.10 Weight 41Gm / Sq.M Reputed Indian Supplier For Fibre Glass Paper And Kraft Paper: I ) M / S United Paper Product, Saharanpur, U.P. Ii ) M / S Fgp Limited New Delhi. Iii ) Specification Of Craft Paper. The Craft Paper Shall Be Smooth Bituminised To Be Supplied In Rolls. The Average Weight Of A Composite Bituminised Craft Paper Shall Be A Minimum Of 120 Gms / Sq. Meter. A Negative Weight Tolerance Upto 5% Of The Composite Weight May Be Permitted At The Discretion To The Owner, ( Bituminised Craft Paper With Average Weight Less Than 120 Gms / Sq. Meter In Not Acceptable ) . The Bituminised Craft Paper Shall Be Composed Of Two Layers Of Craft Paper Shall Be Composed Of Two Layers Of Craft Paper And Each Weighing Not Less Than 45 Gm / Sq. Meter And Laminated With A Layer Of Bitumen Approachments Weight 50 Gms / Sq. M To Have A Proper Bond Between The Two Layer Of Paper. He Bituminised Craft Paper For Field Application Shall Be Able To Resist Penetration. Specific Gravity At 25 Deg. C Astm D-71 1.4 1.6 Penetration, Astm-D-5 10 A ) At 25 Deg. C 100 Gms. Weight 5 Secs. High Temperature Test At 71 Deg.C 1 / 32 ( Sag O Awwa C-203. Sec. 2.8.9 Low Temperature Test At 23 Deg. C ( Cracking ) , Awwac-203 Sec. 2.8.10 Peel Test, Awwac-203 Sec. 2.8.11 No Peeling Electrical Resistance Test At 17000 Volts And Low Amperage ( 1.5 Mm Thickness ) Other Requirements ( For Wrapping And Coating ) 1. Third Party Inspection Certificate For All Materials By Eil / Dnv / Lris / Mecon Or Providing Iocl Approved Manufacturers Test Certificate Shall Be In Contractors Scope. 2. Holiday Testing Machine Shall Be Arranged And Provided By Contractor. 3. Vendor To Submit Transportation And Handling Procedure T Avoid Wrapping And Coating Of Pipes. 4. Vendor To Submit And Get Quality Assurance Plan ( Qap ) For Wrapping And Coating Approved By Owner / Inspector. 5. The Wrapping And Coating Surface Must Have Machine Finish In Workmanship. Note: Additional Payment For Earth Excavation And Wrapping Coating Will Be Made Extra For Underground Piping. 177 50 Mm Nb 178 80 Mm Nb 179 100 Mm Nb 180 150 Mm Nb 181 200 Mm Nb 182 250 Mm Nb 183 300 Mm Nb 184 400 Mm Nb 185 450 Mm Nb 186 500 Mm Nb 187 600 Mm Nb 188 Dye Penetration Test For Piping Works Performance Of Dye Penetration Test Including Supply Of All Necessary Materials, Penetrant, Developer Etc. Along With All Equipment#S, Labour, For Carrying Out The Work As Per Specification & Direction Of Engineer -In-Charge At All Elevations. Test Has To Be Carried Out In All Metallurgy The Test Has To Carry Out On All Schedules Of Pipes. Note: Since Inch Dia Unit Is Not Available In Sap, Hence For Estimate Unit Is To Be Taken As Dia. 189 For Pipes ( Per Inch Dia ) 190 For Vessels / Tanks ( Per Inch ) 191 Radiography Of Piping Works Performance Of Radiographic Inspection On All Type & Sizing Of Piping / Pipe Fittings In Position At All Heights Inclusive Of Providing Sources, Film, Chemicals, & All Necessary Equipment#S, Consumables Etc. Complete In All Respect As Per Specification & Instruction Of The Engineer-In-Charge. Note: Since Inch Dia Unit Is Not Available In Sap, Hence For Estimate Unit Is To Be Taken As Dia. 192 For Pipes ( Per Inch Dia ) 193 For Vessel / Tanks Etc. ( Per Inch ) 194 Heat Treatment Heat Treatment Of Shop Fabricated For Already Installed Piping / Static Equipment Etc. For Joints Or Other Operations Wherever Required. Heating To Be Carried Out In A Furnace Or By Using An Electric Resistance Or Induction Heating Equipment Ensuring Uniform Temperature Attainment At All Points Of The Portion Being Heat-Treated. The Portion Under Heat Treatment Shall Be Wrapped Suitably Under Insulation To Avoid Any Harmful Temperature Gradient. The Temperature Thus Attainted In The Portion Under Heat Treatment Shall Be Recorded By Means Of Thermocouples, Pyrometer And An Automatic Temperature Recorders Suitably Calibrated Should Be Employed. The Calibration Chart Of Each Recorder Along With Hardness Test Results Shall Be Submitted To The Engineer-In-Charge For Approval. The Details Of Heat Treatment Such As Heating Rate, Soaking Temperature Pause Period And Cooling Rate Etc. To Be Carried Out As Per Relevant Standards / Code As Instructed By The Engineer-In-Charge. Note: Since Inch Dia Unit Is Not Available In Sap, Hence For Estimate Unit Is To Be Taken As Dia. 195 For Pipes ( Per Inch Dia ) 196 Welding Of Cs Plates Transportation Of All Items Including Plates Etc. From Owners Storage Point To Work Site And / Or Prefabrication Yard And Welding Of Cs Plates Including Cutting / Grinding / Edge Preparing And Required Testing To Prove Soundness Of Weld Joint With Supply Of All Consumables, Manpower, Tools As Per Technical Specification And Direction Of The Engineer-In-Charge. 197 Upto 3Mm Thick 198 Above 3Mm & Upto 5Mm Thick. 199 Above 5Mm & Upto 6Mm Thick 200 Above 6Mm & Upto 7Mm Thick 201 Above 7Mm & Upto 9Mm Thick. 202 Above 9Mm & Upto 11Mm Thick 203 Welding Of Ss / As Plates Transportation Of All Items Including Plates Etc. From Owners Storage Point To Work Site And / Or Prefabrication Yard And Welding Of Ss / As Plates / Structural Etc. Including Cutting / Grinding / Edge Preparing And Required Testing To Prove Soundness Of Weld Joint With Supply Of All Consumables, Manpower, Tools As Per Technical Specification And Direction Of The Engineer-In-Charge ( Heat Treatment And Other Ndt Charges Shall Be Paid Extra ) . 204 Upto 3Mm Thick Alloy Steel ( P22 ) 205 Above 5Mm & Upto 6Mm Thick Alloy Steel ( P22 ) 206 Above 6Mm & Upto 7Mm Thick Alloy Ateel ( P22 ) 207 Upto 3 Mm Thick Alloy Steel ( P5 ) 208 Above 5 Mm & Upto 6 Mm Thick Alloy Steel ( P5 ) 209 Above 6 Mm & Upto 7 Mm Thick Alloy Steel ( P5 ) 210 Above 7 Mm & Upto 9 Mm Thick Alloy Steel ( P5 ) 211 Above 9 Mm & Upto 11 Mm Thick Alloy Steel ( P5 ) 212 Above 15 Mm & Upto 16 Mm Thick Alloy Steel ( P5 ) 213 Above 18 Mm & Upto 20 Mm Thick Alloy Steel ( P5 ) 214 Cs / As Plate Cutting Cutting Of Cs / As Plate By Gas / Grinding Or Any Other Means As Per Direction Of The Engineer-In-Charge According To Suitability Including Transportation From Stores To Site With Supply Of All Tools, Tackles, Consumables, Equipment, Labour Etc. 215 3Mm Thick 216 5Mm Thick 217 6Mm Thick 218 8Mm Thick 219 10Mm Thick 220 12Mm Thick 221 Ss Plate Cutting Cutting Of Ss Plate By Electric / Grinding Or Any Other Means Including Preheating Wherever Required As Per Direction Of The Engineer-In-Charge According To Suitability Including Transportation From Stores To Site With Supply Of All Tools, Tackles, Consumables, Equipment, Labour Etc. 222 3Mm Thick 223 5Mm Thick 224 6Mm Thick 225 8Mm Thick 226 10Mm Thick 227 12Mm Thick 228 Alloy Steel Piping ( Astm A335 Gr. P5 ) Joints Transportation Of All Piping Items From Owners Storage Points To Work Site And / Or Pre-Fabrication Yard And To Site After Pre-Fabrication; Cutting, Grinding, Edge Preparation Of Pipes And Fittings, Like Flanges, Elbows, Tees, Reducers Etc. To Match The Mating Edges Of Different Thickness; Fit-Up, Bending, Welding Using Approved Welding Electrodes As Per Owners Quality Requirements Etc. As Per Codes / Specifications, Drawings Etc. ( Alloy Steel Joints Shall Be Welded By Doing Root Run Using Tig Welding Followed By Filler Passes By Manual / Semi-Automatic Arc Welding. The Job Is To Be Pre-Heated Prior To Welding And All Joints To Be Stress Relieved And Fully Radiographed, However, Charges For Stress Relieving And Radiography Shall Be Paid Separately ) , Threading, Laying, Erection And Alignment Of Pipes At Ground Level I.E. Upto A Height Of 5 Meters On Sleepers, Pipe Racks Etc. Or Upto 5 Meters Depth In Trenches, Anchoring Wherever Required, Connecting With Equipment, Nozzles, Steam Traps, Strainers, Orifice Assemblies ( Including Tapping Upto First Block Valve ) , Spray Nozzles Rotameters; Tapping For Instrument Connections Like Pressure Gauges, Thermowells, Sample Connections, Vents, Drains Etc. Including Fixing Of All Types Of Sw Valves, Gaskets, Nuts And Bolts, All Inline Instruments, Elbows, Tees, Flanges, Reducers, Full Coupling Or Half Coupling, Earthing Strip Wherever Required; Welding Prefabricated Shoes And Supports ( Including Alignment ) As Per The Drawings Including Preparation Of Small Bore Isometric Upto 1.5 Inch Nb, Specifications, Codes Etc. And As Per The Instructions Of The Engineer-In-Charge To His Entire Satisfaction Including Supplying Of All Types Of Tools And Tackles, Lifting Arrangements, Equipment, Machineries, All Consumables And Labour Etc. To Complete The Work In All Respects In A Workman Like Manner Including Area Preparation For Hot Jobs, Area Cleaning After Completion Of Work, Flushing Wherever Required, Cleaning Of Pipes Externally Off All Foreign Materials Like Weld Beads, Clamps Fixtures Etc. Used In Fabrication As Directed By The Engineer-In-Charge. Note: Proper Safety Arrangements For Carrying Out The Job Is Under Contractors Scope And The Same Has To Be Complied With As Per The Dire Ctions Of The Engineer-In-Charge. Note: For Piping Beyond 5 Mtr. Elevation Above And Below Ground Piping And Upto 10Mtr. Rates Is To Be Escalated By 20%. For More Than 10 Mtr. But Upto 15 Mtr. Rates Is To Be Escalated By 30%. For More Than 15 Mtr But Upto 20 Mtr. Rates To Be Escalated By 40% Respectively. Requirement Of Scaffolding To Be Envisaged And Decided By Engineer In Charge As Per Site Requirement And Scaffolding Item To Be Paid Separately. Note: For Piping Where Tig Welding Is Used For Root Run Only, The Rates To Be Escalated By 15% And Where Tig Welding Is Used For Entire Joints The Rates To Be Escalated By 20%. Note: Payment Of Tapping Points Will Also Be Made Extra On Joint Basis, As The Measurement Is On Joint Basis. 229 15 Mm Nb, Schedule Upto 80 230 15 Mm Nb, Schedule Above 80 231 20 Mm Nb, Schedule Upto 80 232 20 Mm Nb, Schedule Above 80 233 25 Mm Nb, Schedule Upto 80 234 25 Mm Nb, Schedule Above 80 235 40Mm Nb, Schedule Above 40 But Upto 80 236 50Mm Nb, Schedule Above 40 But Upto 80 237 80 Mm Nb, Schedule Upto 40 238 80Mm Nb, Schedule Above 40 But Upto 80 239 100Mm Nb, Schedule Upto 40 240 150 Mm Nb, Schedule Upto 40 241 200 Mm Nb, Schedule Above 20 But Upto 40 242 250 Mm Nb, Schedule Above 20 But Upto 40 243 Fabrication And Erection Of Pipe Support / Platforms / Devits / Stair Case Etc. The Job Includes Getting The Materials Issued, Transportation To Work Site And Handling At Site, Fabrication At The Required Size And Shape Using Steel Pipes, Ms Structural / Plates Etc. By Cutting, Bevelling And Welding Including Fixing Of Ms Gratings / Chequered Plates On Platform At All Elevation By Welding, Bolting Or Otherwise To Existing Members Or Equipment. This Also Includes Fabrication And Fixing Of Pipe Clamps, Non-Standard Bolts Etc. Inclusive Of Labour, Consumables, Tools And Tackles And Materials Required For U-Clamps, J-Bolts Etc. And Applying One Coat Of Primer And Two Coats Of High Built Black Bituminous Paint And Complete In All Respect As Per Drawings, Specifications And Instructions Of The Engineer-In-Charge. ( Excluding Cost Of Structural Steel ) . 244 Dismantling Of Structurals Like Pipe Support / Stairway / Devit Etc. Removal Of Existing Platforms / Pipe Supports / Davits / Stairways Etc. Along With Adjacent Fittings / Members By Cutting / Debolting Or By Any Other Means Without Damaging The Remaining Unit And Lowering Down To The Ground Including Erection Of Scaffolding, Retrieving Of All The Usable Materials And Transportation To The Storage Point As Directed By The Engineer-In-Charge. 245 Fabrication Of Carbon Steel Reducers With Welding Electrode E-6013 Preparing Drawings And Fabrication Of The Following Specials Including Transportation Of Materials From Owners Storage Points To Work Site And / Shop, Cutting, Edge Preparing, Welding, As Per Owners Quality Requirements, Including Supply Of All Necessary Equipment, Consumables, Labour, Tools, Tackles, And Supervision, Work Shall Be Carried Out As Per The Specifications Drawings, Codes, And Instructions To The Full Satisfaction Of The Engineer-In-Charge. 246 200 Mm Nb To Below Reducer, Schedule Upto 40 247 250 Mm Nb To Below Reducer, Schedule Upto 40 248 300 Mm Nb To Below Reducer, Schedule Above 20 But Upto 40 249 350 Mm Nb To Below Reducer, Schedule Upto 20 250 400 Mm Nb To Below Reducer, Schedule Upto 20 251 450Mm Nb To Below Reducer, Schedule Upto 20 252 Stainless Steel Piping ( Gr. Ss 300 ) Joints Transportation Of All Piping Items From Owners Storage Points To Work Site And / Or Pre-Fabrication Yard And To Site After Pre-Fabrication; Cutting, Grinding, Edge Preparation Of Pipes And Fittings, Like Flanges, Elbows, Tees, Reducers Etc. To Match The Mating Edges Of Different Thickness; Fit-Up, Bending, Welding Using Approved Welding Electrodes As Per Owners Quality Requirements Etc. As Per Codes / Specifications, Drawing Etc., Threading, Laying, Erection And Alignment Of Pipes At Ground Level I.E. Upto A Height Of 5 Meters On Sleepers, Pipe Racks Etc. Or Upto 5 Meters Depth In Trenches; Anchoring Wherever Required, Connecting With Equipment, Nozzles, Steam Traps, Strainers, Orifice Assemblies ( Including Tapping Upto First Block Valve ) , Spray Nozzles Rotameters; Tapping For Instrument Connections Like Pressure Gauges, Thermowells, Sample Connections, Vents, Drains Etc. Including Fixing Of All Types Of Sw Valves, Gaskets, Nuts And Bolts, All Inline Instruments, Elbows, Tees, Flanges, Reducers, Full Coupling Or Half Coupling, Earthing Strip Wherever Required; Welding Prefabricated Shoes And Supports ( Including Alignment ) As Per The Drawings, Including Preparation Of Small Bore Isometric Upto 1.5 Inch Nb, Specifications, Codes Etc. And As Per The Instructions Of The Engineer-In-Charge To His Entire Satisfaction Including Supplying Of All Types Of Tools And Tackles, Lifting Arrangements, Equipment, Machineries, All Consumables A Nd Labour Etc. To Complete The Work In All Respects In A Workman Like Manner Including Area Preparation For Hot Jobs, Area Cleaning After Completion Of Work, Flushing Wherever Required, Cleaning Of Pipes Externally Off All Foreign Materials Like Weld Beads, Clamps Fixtures Etc. Used In Fabrication As Directed By The Engineer-In-Charge. Note : Proper Safety Arrangements For Carrying Out The Job Is Under Contractors Scope And The Same Has To Be Complied With As Per The Dire Ctions Of The Engineer- In-Charge. Note: For Piping Beyond 5 Mtr. Elevation Above And Below Ground Piping And Upto 10Mtr. Rates Is To Be Escalated By 20%. For More Than 10 Mtr. But Upto 15 Mtr. Rates Is To Be Escalated By 30%. For More Than 15 Mtr But Upto 20 Mtr. Rates To Be Escalated By 40% Respectively. Requirement Of Scaffolding To Be Envisaged And Decided By Engineer In Charge As Per Site Requirement And Scaffolding Item To Be Paid Separately. Note: For Piping Where Tig Welding Is Used For Root Run Only, The Rates To Be Escalated By 15% And Where Tig Welding Is Used For Entire Joints The Rates To Be Escalated By 20%. Note: Payment Of Tapping Points Will Also Be Made Extra On Joint Basis, As The Measurement Is On Joint Basis. 253 15 Mm Nb, Schedule Upto 40 254 15 Mm Nb, Schedule More Than 40 But Upto 80 255 15 Mm Nb, Schedule Above 80 But Upto 120 256 20 Mm Nb, Schedule Upto 40 257 20 Mm Nb, Schedule More Than 40 But Upto 80 258 25 Mm Nb, Schedule Upto 40 259 25 Mm Nb, Schedule More Than 40 But Upto 80 260 40 Mm Nb, Schedule Upto 40 261 40 Mm Nb, Schedule More Than 40 But Upto 80 262 50 Mm Nb, Schedule Upto 40 263 50 Mm Nb, Schedule More Than 40 But Upto 80 264 80 Mm Nb, Schedule Upto 40 265 80 Mm Nb, Schedule More Than 40 But Upto 80 266 100 Mm Nb, Schedule Upto 40 267 100 Mm Nb, Schedule More Than 40 But Upto 80 268 150 Mm Nb, Schedule Upto 40 269 150 Mm Nb, Schedule More Than 40 But Upto 80 270 150 Mm Nb, Schedule Above 80 But Upto 120 271 200 Mm Nb, Schedule Upto 40 272 200 Mm Nb, Schedule More Than 40 But Upto 80 273 200 Mm Nb, Schedule Above 80 But Upto 120 274 250 Mm Nb, Schedule Upto 40 275 250 Mm Nb, Schedule More Than 40 But Upto 80 276 250 Mm Nb, Schedule Above 80 But Upto 120 277 300 Mm Nb, Schedule Upto 40 278 300 Mm Nb, Schedule More Than 40 But Upto 80 279 300 Mm Nb, Schedule Above 80 But Upto 120 280 350 Mm Nb, Schedule Upto 40 281 350 Mm Nb, Schedule More Than 40 But Upto 80 282 350 Mm Nb, Schedule Above 80 But Upto 120 283 400 Mm Nb, Schedule Upto 40 284 400 Mm Nb, Schedule More Than 40 But Upto 80 285 450 Mm Nb, Schedule Upto 40 286 450 Mm Nb, Schedule More Than 40 But Upto 80 287 500 Mm Nb, Schedule Upto 40 288 500 Mm Nb, Schedule More Than 40 But Upto 80 289 600 Mm Nb, Schedule Upto 40 290 Bending Of Pipes Bending Of Pipes: The Job Includes Bending Of Pipes In The Required Curvature And Supply Of All Tools, Tackles, Labour And The Supervision To Complete The Job As Per And To The Full Satisfaction Of The Engineer-In-Charge. 291 15 Mm Nb 292 20 Mm Nb 293 25 Mm Nb 294 40 Mm Nb 295 50 Mm Nb 296 80 Mm Nb 297 100 Mm Nb 298 150 Mm Nb 299 200 Mm Nb 300 Fixing Of Lugs Fabrication Of Cs / Ss Lugs By Cutting, Bending Etc. From Cs / Ss Annealed Wire Etc. ( Supplied By Owner Free Of Cost ) And Fixing The Same By Welding On The Fabricated Panel Segments For Holding The Castable Refractories Including Supply Of Labour, Tools, Tackles As Per Direction Of The Engineer-In-Charge. 301 Cs Lugs 302 Ss Lugs 303 Buffing Of Weld Joints Job Involves Buffing And Cleaning Of Total Weld Area Of The Vessel / Column Etc. Using Power Brush. The Job Has To Be Completed In All Respect To The Entire Satisfaction Of The Engineer-In-Charge ( Each Length Of Buffing Will Be Up To Width Of 150 Mm ) . 304 Extra For Fixing / Removal Of Rtj Flanges / Blind Flanges Extra For Opening / Fixing Etc. Of Rtj Flanges / Blind Flanges / Spool Pieces For Lapping Etc. 305 50 Mm 306 80 Mm 307 100 Mm 308 150 Mm 309 200 Mm 310 250 Mm 311 300 Mm 312 600 Mm 313 Dechoking Of Cw Line / Product Line Dechoking Of Cw Line / Product Line By Poking Rod Inside Or Any Other Mech. Means. This Include Opening / Removal Of Spool Piece Of Piping To Be Dechoked, Removal Of Sludge / Hard Deposits Etc. By Poking Rod / Dechoking By Steam Or Any Other Mechanical Means And Fixing / Erecting The Line In Position After Dechoking, Including Cutting And Fixing Suitable Size. 314 Dia ½ To 1 315 Dia 1½ 316 Dia 2 317 Dia 4 318 Dia 6 319 Dia 8 320 Hose Connection & Disconnection Job Hose Connection And Disconnection Job Involves Transportation Of Hoses From The Owners Storage To Worksite, Opening The Roll And Laying The Hose, Cutting If Required, Joining Them Properly, Connection Of Ends To Specified Locations / Equipment / Supply Points As Per Production Requirement, Tying The Hose Wherever Required, Opening Of End Connections And Removal Of Hose After Job Completion, Rolling The Same And Shifting To Scrap Yard / Storage Point As Per Direction Of Eic. The Job Also Covers Lowering, Lifting, Handling Of Hoses, Erection / Removal Of Steel Scaffolding, Area Preparation, Area Cleaning And Compliance To All Safety Norms And Work Permit Systems. Note: The Rates Shall Be Applicable For Working And Connection At All Elevation. The Hoses, Clamps And Bolts Shall Be Supplied By Iocl Free Of Charge. This Item Shall Be Operative Only If Hose Connection / Disconnection Is Required By Production / Maintenance And Is Not Related To Execution Of Any Of The Item. Only Hose Connection Or Dis-Connection Shall Be Treated As Half Activity. 321 Preparatory Jobs For Hot Work The Job Includes Opening Of Flanges, Blinding / Deblinding By Bolting / Debolting Etc. Fabrication Of Tail Blinds, Cover Plate Connections Fittings Etc., Elbow Reversing, Opening And Fixing Of Plugs From The Furnace Tube Etc., Making Hose Connections And All Other Arrangements As Required For Flushing The Lines Including Wedge Opening, Dewatering After Flushing, Decoking, Isolation Etc., Boxing Up The Lines With New Gaskets And Hot Bolting Of All The Joints During Hot Circulation And Complete The Job With Supply Of Tools, Tackles, Labours And Consumables Etc. As Per Direction Of The Engineer-In-Charge. 322 15 Mm 323 20 Mm 324 25 Mm 325 40 Mm 326 50 Mm 327 80 Mm 328 100 Mm 329 150 Mm 330 200 Mm 331 250 Mm 332 600 Mm 333 Stainless Steel Piping ( Gr. Ss 400 ) Joints Transportation Of All Piping Items From Owners Storage Points To Work Site And / Or Pre-Fabrication Yard And To Site After Pre-Fabrication; Cutting, Grinding, Edge Preparation Of Pipes And Fittings, Like Flanges, Elbows, Tees, Reducers Etc. To Match The Mating Edges Of Different Thickness; Fit-Up, Bending, Welding Using Approved Welding Electrodes As Per Owners Quality Requirements Etc. As Per Codes / Specifications, Drawing Etc., Threading, Laying, Erection And Alignment Of Pipes At Ground Level I.E. Upto A Height Of 5 Meters On Sleepers, Pipe Racks Etc. Or Upto 5 Meters Depth In Trenches; Anchoring Wherever Required, Connecting With Equipment, Nozzles, Steam Traps, Strainers, Orifice Assemblies ( Including Tapping Upto First Block Valve ) , Spray Nozzles Rotameters; Tapping For Instrument Connections Like Pressure Gauges, Thermowells, Sample Connections, Vents, Drains Etc. Including Fixing Of All Types Of Sw Valves, Gaskets, Nuts And Bolts, All Inline Instruments, Elbows, Tees, Flanges, Reducers, Full Coupling Or Half Coupling, Earthing Strip Wherever Required; Welding Prefabricated Shoes And Supports ( Including Alignment ) As Per The Drawings, Including Preparation Of Small Bore Isometric Upto 1.5 Inch Nb, Specifications, Codes Etc. And As Per The Instructions Of The Engineer-In-Charge To His Entire Satisfaction Including Supplying Of All Types Of Tools And Tackles, Lifting Arrangements, Equipment, Machineries, All Consumables A Nd Labour Etc. To Complete The Work In All Respects In A Workman Like Manner Including Area Preparation For Hot Jobs, Area Cleaning After Completion Of Work, Flushing Wherever Required, Cleaning Of Pipes Externally Off All Foreign Materials Like Weld Beads, Clamps Fixtures Etc. Used In Fabrication As Directed By The Engineer-In-Charge. Note : Proper Safety Arrangements For Carrying Out The Job Is Under Contractors Scope And The Same Has To Be Complied With As Per The Dire Ctions Of The Engineer- In-Charge. Note: For Piping Beyond 5 Mtr. Elevation Above And Below Ground Piping And Upto 10Mtr. Rates Is To Be Escalated By 20%. For More Than 10 Mtr. But Upto 15 Mtr. Rates Is To Be Escalated By 30%. For More Than 15 Mtr But Upto 20 Mtr. Rates To Be Escalated By 40% Respectively. Requirement Of Scaffolding To Be Envisaged And Decided By Engineer In Charge As Per Site Requirement And Scaffolding Item To Be Paid Separately. Note: For Piping Where Tig Welding Is Used For Root Run Only, The Rates To Be Escalated By 15% And Where Tig Welding Is Used For Entire Joints The Rates To Be Escalated By 20%. Note: Payment Of Tapping Points Will Also Be Made Extra On Joint Basis, As The Measurement Is On Joint Basis. 334 15 Mm Nb, Schedule More Than 40 But Upto 80 335 20 Mm Nb, Schedule More Than 40 But Upto 80 336 25 Mm Nb, Schedule More Than 40 But Upto 80 337 40 Mm Nb, Schedule More Than 40 But Upto 80 338 50 Mm Nb, Schedule More Than 40 But Upto 80 339 80 Mm Nb, Schedule More Than 40 But Upto 80 340 100 Mm Nb, Schedule Upto 40 341 150 Mm Nb, Schedule Upto 40 342 200 Mm Nb, Schedule Upto 40 343 Scrap Removal Collection Of Metallic Scrap / Unwanted Materials Such As Valves, Pipes, Bends, Plates, Structural, Gasket Sheets, Hoses, Fasteners Etc., From Different Location And Elevations And Transporting Them To Scrap Yard Or Any Other Place As Per Instruction Of Engineer-In-Charge. Job Includes Supplying Of All Types Of Tools And Tackles, Lifting Arrangements, Hydra / Crane, Tractor Trolley And Equipment, Machineries All Consumables And Labour. All Jobs Are To Be Carried Out As Per The Instruction And To The Full Satisfaction Of The Engineer-In-Charge. Note: If Cutting Is Required As Per Site Requirement The Same Shall Be Paid Separately. 344 Material Handling Within Refinery Handling, Shifting, Stacking Etc. Of Piping And Structural Material As Per Job Requirement At Elevation And As Per Instruction Of En Gineer-In-Charge. This Item To Be Operated In Case Of Lifting And Lowering Of Piping / Plates / Structural For Repair Job To Safe Working Site Where Fire Permit Can Be Given, Redundant Material Removal From Position And Transporting To Store / Scrap Yard Etc. Supply Of Labour, Tools And Tackles, Lifting Arrangements, Hydra / Crane, Tractor Trolley, Equipment, Consumables Etc. Will Be In Contractors Scope. All Jobs Are To Be Carried Out As Per The Instruction And To The Full Satisfaction Of The Engineer-In-Charge. ( Item Should Not Be Operated For Area Scrap Removal ) . 345 Installation / Removal Of Level Troll, Fire Hydrant, Monitors, Safety Valves Etc. The Job Involves Opening Of Flanged And Removal Of All Types Of Level Troll, Fire Hydrant And Monitor By Debolting / Cold / Hot Cutting Of Fasteners Wherever Required, Cleaning, Or Flange Facing, Lapping Of Rtj Rings, Level Troll, Fire Hydrant, Monitor, In Position With Correct Direction And Providing New Gasket ( Iocl Supplied ) Including Cutting Of Gaskets If Required And Finally Tightening Of The Gland To Ensure Zero Leak Including Hot Bolting Wherever Applicable. 346 Installation ( Same As 7.1 ) 347 Removal ( Same As 7.2 ) 348 Handling / Erection Of Fabricated Pipes / Coil Assemblies The Job Includes Getting The Materials Issued, Transportation To Work-Site, Handling And Care At Work-Site, Erecting The Fabricated Item At Position And Fixing, Aligning And Making Connections To The Companion Pipe Etc. And Complete In All Respect With All Labour, Tools, Tackles And Supervision Etc. As Per The Direction Of The Engineer-In-Charge. 349 Transportation From Owners Storage Points To Work Site And / Or Pre-Fabrication Yard And To Site After Pre-Fabrication; Cutting, Gr Inding, Edge Preparation As Per The Instructions Of The Engineer-In-Charge To His Entire Satisfaction Including Supplying Of All Types Of Tools And Tackles, Lifting Arrangements, Equipment, Machineries, All Consumables And Labour Etc. To Complete The Work In All Respects In A Workman Like Manner Including Area Preparation For Hot Jobs, Area Cleaning After Completion Of Work, Pneumatic Testing, Cleaning Of Pipes Externally Off All Foreign Materials Like Weld Beads, Clamps Fixtures Etc. Used In Fabrication As Directed By The Engineer-In-Charge. Note : Proper Safety Arrangements For Carrying Out The Job Is Under Contractors Scope And The Same Has To Be Complied With As Per The Dire Ctions Of The Engineer- In-Charge. 350 Branch Size 2 Inch 351 Branch Size 3 Inch 352 Branch Size 4 Inch 353 Branch Size 6 Inch 354 Branch Size 8 Inch 355 Branch Size 10 Inch 356 Branch Size 12 Inch 357 Branch Size 14 Inch 358 Branch Size 16 Inch 359 Branch Size 18 Inch 360 Alloy Steel Piping ( Astm A335 Gr. P1, P2, P11 & P12 ) Joints Transportation Of All Piping Items From Owners Storage Points To Work Site And / Or Pre-Fabrication Yard And To Site After Pre-Fabrication; Cutting, Grinding, Edge Preparation Of Pipes And Fittings, Like Flanges, Elbows, Tees, Reducers Etc. To Match The Mating Edges Of Different Thickness; Fit-Up, Bending, Welding Using Approved Welding Electrodes As Per Owners Quality Requirements Etc. As Per Codes / Specifications, Drawings Etc. ( Alloy Steel Joints Shall Be Welded By Doing Root Run Using Tig Welding Followed By Filler Passes By Manual / Semi-Automatic Arc Welding. The Job Is To Be Pre-Heated Prior To Welding And All Joints To Be Stress Relieved And Fully Radiographed, However, Charges For Stress Relieving And Radiography Shall Be Paid Separately ) , Threading, Laying, Erection And Alignment Of Pipes At Ground Level I.E. Upto A Height Of 5 Meters On Sleepers, Pipe Racks Etc. Or Upto 5 Meters Depth In Trenches, Anchoring Wherever Required, Connecting With Equipment, Nozzles, Steam Traps, Strainers, Orifice Assemblies ( Including Tapping Upto First Block Valve ) , Spray Nozzles Rotameters; Tapping For Instrument Connections Like Pressure Gauges, Thermowells, Sample Connections, Vents, Drains Etc. Including Fixing Of All Types Of Sw Valves, Gaskets, Nuts And Bolts, All Inline Instruments, Elbows, Tees, Flanges, Reducers, Full Coupling Or Half Coupling, Earthing Strip Wherever Required; Welding Prefabricated Shoes And Supports ( Including Alignment ) As Per The Drawings Including Preparation Of Small Bore Isometric Upto 1.5 Inch Nb, Specifications, Codes Etc. And As Per The Instructions Of The Engineer-In-Charge To His Entire Satisfaction Including Supplying Of All Types Of Tools And Tackles, Lifting Arrangements, Equipment, Machineries, All Consumables And Labour Etc. To Complete The Work In All Respects In A Workman Like Manner Including Area Preparation For Hot Jobs, Area Cleaning After Completion Of Work, Flushing Wherever Required, Cleaning Of Pipes Externally Off All Foreign Materials Like Weld Beads, Clamps Fixtures Etc. Used In Fabrication As Directed By The Engineer-In-Charge. Note : Proper Safety Arrangements For Carrying Out The Job Is Under Contractors Scope And The Same Has To Be Complied With As Per The Dire Ctions Of The Engineer- In-Charge. Note: For Piping Beyond 5 Mtr. Elevation Above And Below Ground Piping And Upto 10Mtr. Rates Is To Be Escalated By 20%. For More Than 10 Mtr. But Upto 15 Mtr. Rates Is To Be Escalated By 30%. For More Than 15 Mtr But Upto 20 Mtr. Rates To Be Escalated By 40% Respectively. Requirement Of Scaffolding To Be Envisaged And Decided By Engineer In Charge As Per Site Requirement And Scaffolding Item To Be Paid Separately. Note: For Piping Where Tig Welding Is Used For Root Run Only, The Rates To Be Escalated By 15% And Where Tig Welding Is Used For Entire Joints The Rates To Be Escalated By 20%. Note: Payment Of Tapping Points Will Also Be Made Extra On Joint Basis, As The Measurement Is On Joint Basis. 361 15 Mm Nb, Schedule Upto 80 362 15 Mm Nb, Schedule Above 80 363 20 Mm Nb, Schedule Upto 80 364 20 Mm Nb, Schedule Above 80 365 25 Mm Nb, Schedule Upto 80 366 25 Mm Nb, Schedule Above 80 367 40 Mm Nb, Schedule Upto 40 368 40Mm Nb, Schedule Above 40 But Upto 80 369 40 Mm Nb, Schedule Above 120 370 50 Mm Nb, Schedule Upto 40 371 50Mm Nb, Schedule Above 40 But Upto 80 372 50 Mm Nb, Schedule Above 120 373 80 Mm Nb, Schedule Upto 40 374 80Mm Nb, Schedule Above 40 But Upto 80 375 80 Mm Nb, Schedule Above 120 376 100Mm Nb, Schedule Upto 40 377 100Mm Nb, Schedule Above 40 But Upto 80 378 100Mm Nb, Schedule Above 120 379 150 Mm Nb, Schedule Upto 40 380 150 Mm Nb, Schedule More Than 40 But Upto 80 381 150 Mm Nb, Schedule Above 120 382 200 Mm Nb, Schedule Upto 20 383 200 Mm Nb, Schedule Above 20 But Upto 40 384 200 Mm Nb, Schedule More Than 40 But Upto 80 385 200 Mm Nb, Schedule Above 120 386 250 Mm Nb, Schedule Upto 20 387 250 Mm Nb, Schedule Above 20 But Upto 40 388 250 Mm Nb, Schedule More Than 40 But Upto 80 389 250 Mm Nb, Schedule Above 120 390 300 Mm Nb, Schedule Upto 20 391 300 Mm Nb, Schedule Above 20 But Upto 40 392 300 Mm Nb, Schedule More Than 40 But Upto 80 393 300 Mm Nb, Schedule Above 120 394 350 Mm Nb, Schedule Upto 20 395 350 Mm Nb, Schedule Above 20 But Upto 40 396 350 Mm Nb, Schedule More Than 40 But Upto 80 397 350 Mm Nb, Schedule Above 120 398 Provision Of Reinforcement Pad For P-1, P-2, P-11 And P-12 Transportation From Owners Storage Points To Work Site And / Or Pre-Fabrication Yard And To Site After Pre-Fabrication; Cutting, Gri Nding, Edge Preparation As Per The Instructions Of The Engineer-In-Charge To His Entire Satisfaction Including Supplying Of All Types Of Tools And Tackles, Lifting Arrangements, Equipment, Machineries, All Consumables And Labour Etc. To Complete The Work In All Respects In A Workman Like Manner Including Area Preparation For Hot Jobs, Area Cleaning After Completion Of Work, Pneumatic Testing, Cleaning Of Pipes Externally Off All Foreign Materials Like Weld Beads, Clamps Fixtures Etc. Used In Fabrication As Directed By The Engineer-In-Charge. Note : Proper Safety Arrangements For Carrying Out The Job Is Under Contractors Scope And The Same Has To Be Complied With As Per The Dire Ctions Of The Engineer- In-Charge. 399 Branch Size 2 Inch 400 Branch Size 3 Inch 401 Branch Size 4 Inch 402 Branch Size 6 Inch 403 Branch Size 8 Inch 404 Branch Size 10 Inch 405 Branch Size 12 Inch 406 Branch Size 14 Inch 407 Extra For Ibr Grade Alloy Steel Piping ( Astm A335 Gr.P1, P2, P11 & 12 ) Joints Extra For Ibr Grade Alloy Steel Piping ( Astm A335 Gr. P1, P2, P11 And 12 ) Joints. For Ibr Piping Jobs, The Scope Of Contractor Shall Be Liasoning With Ibr Authorities Including Approval Of Drawings / Documents From Ibr Authorities And Also Getting The Final Approval Of The Job From Ibr Authorities Including Payment Of Any Fee Or Charges To Ibr Authorities For This Purpose. 408 15 Mm Nb, Schedule Upto 80 409 15 Mm Nb, Schedule Above 80 410 20 Mm Nb, Schedule Upto 80 411 20 Mm Nb, Schedule Above 80 412 25 Mm Nb, Schedule Upto 80 413 25 Mm Nb, Schedule Above 80 414 40 Mm Nb, Schedule Upto 40 415 40Mm Nb, Schedule Above 40 But Upto 80 416 40 Mm Nb, Schedule Above 120 417 50 Mm Nb, Schedule Upto 40 418 50Mm Nb, Schedule Above 40 But Upto 80 419 50 Mm Nb, Schedule Above 120 420 80 Mm Nb, Schedule Upto 40 421 80Mm Nb, Schedule Above 40 But Upto 80 422 80 Mm Nb, Schedule Above 120 423 100Mm Nb, Schedule Upto 40 424 100Mm Nb, Schedule Above 40 But Upto 80 425 100Mm Nb, Schedule Above 120 426 150 Mm Nb, Schedule Upto 40 427 150 Mm Nb, Schedule More Than 40 But Upto 80 428 150 Mm Nb, Schedule Above 120 429 200 Mm Nb, Schedule Upto 20 430 200 Mm Nb, Schedule Above 20 But Upto 40 431 200 Mm Nb, Schedule More Than 40 But Upto 80 432 200 Mm Nb, Schedule Above 120 433 250 Mm Nb, Schedule Upto 20 434 250 Mm Nb, Schedule Above 20 But Upto 40 435 250 Mm Nb, Schedule More Than 40 But Upto 80 436 250 Mm Nb, Schedule Above 120 437 300 Mm Nb, Schedule Upto 20 438 300 Mm Nb, Schedule Above 20 But Upto 40 439 300 Mm Nb, Schedule More Than 40 But Upto 80 440 300 Mm Nb, Schedule Above 120 441 350 Mm Nb, Schedule Upto 20 442 350 Mm Nb, Schedule Above 20 But Upto 40 443 350 Mm Nb, Schedule More Than 40 But Upto 80 444 350 Mm Nb, Schedule Above 120 445 Alloy Steel Piping ( Astm A335 Gr. P22 ) Transportation Of All Piping Items From Owners Storage Points To Work Site And / Or Pre-Fabrication Yard And To Site After Pre-Fabrication; Cutting, Grinding, Edge Preparation Of Pipes And Fittings, Like Flanges, Elbows, Tees, Reducers Etc. To Match The Mating Edges Of Different Thickness; Fit-Up, Bending, Welding Using Approved Welding Electrodes As Per Owners Quality Requirements Etc. As Per Codes / Specifications, Drawings Etc. ( Alloy Steel Joints Shall Be Welded By Doing Root Run Using Tig Welding Followed By Filler Passes By Manual / Semi-Automatic Arc Welding. The Job Is To Be Pre-Heated Prior To Welding And All Joints To Be Stress Relieved And Fully Radiographed, However, Charges For Stress Relieving And Radiography Shall Be Paid Separately ) , Threading, Laying, Erection And Alignment Of Pipes At Ground Level I.E. Upto A Height Of 5 Meters On Sleepers, Pipe Racks Etc. Or Upto 5 Meters Depth In Trenches, Anchoring Wherever Required, Connecting With Equipment, Nozzles, Steam Traps, Strainers, Orifice Assemblies ( Including Tapping Upto First Block Valve ) , Spray Nozzles Rotameters; Tapping For Instrument Connections Like Pressure Gauges, Thermowells, Sample Connections, Vents, Drains Etc. Including Fixing Of All Types Of Sw Valves, Gaskets, Nuts And Bolts, All Inline Instruments, Elbows, Tees, Flanges, Reducers, Full Coupling Or Half Coupling, Reinforcement Pads, Earthing Strip Wherever Required; Welding Prefabricated Shoes And Supports ( Including Alignment ) As Per The Drawings Including Preparation Of Small Bore Isometric Upto 1.5 Inch Nb, Specifications, Codes Etc. And As Per The Instructions Of The Engineer-In-Charge To His Entire Satisfaction Including Supplying Of All Types Of Tools And Tackles, Lifting Arrangements, Equipment, Machineries, All Consumables And Labour Etc. To Complete The Work In All Respects In A Workman Like Manner Including Area Preparation For Hot Jobs, Area Cleaning After Completion Of Work, Flushing Wherever Required, Cleaning Of Pipes Externally Off All Foreign Materials Like Weld Beads, Clamps Fixtures Etc. Used In Fabrication As Directed By The Engineer-In-Charge. Note : Proper Safety Arrangements For Carrying Out The Job Is Under Contractors Scope And The Same Has To Be Complied With As Per The Dire Ctions Of The Engineer- In-Charge. Note: For Piping Beyond 5 Mtr. Elevation Above And Below Ground Piping And Upto 10Mtr. Rates Is To Be Escalated By 20%. For More Than 10 Mtr. But Upto 15 Mtr. Rates Is To Be Escalated By 30%. For More Than 15 Mtr But Upto 20 Mtr. Rates To Be Escalated By 40% Respectively. Requirement Of Scaffolding To Be Envisaged And Decided By Engineer In Charge As Per Site Requirement And Scaffolding Item To Be Paid Separately. Note: For Piping Where Tig Welding Is Used For Root Run Only, The Rates To Be Escalated By 15% And Where Tig Welding Is Used For Entire Joints The Rates To Be Escalated By 20%. 446 15 Mm Nb, Schedule Upto 80 447 15 Mm Nb, Schedule Above 80 448 20 Mm Nb, Schedule Upto 80 449 20 Mm Nb, Schedule Above 80 450 25 Mm Nb, Schedule Upto 80 451 25 Mm Nb, Schedule Above 80 452 40 Mm Nb, Schedule Upto 40 453 40Mm Nb, Schedule Above 40 But Upto 80 454 40 Mm Nb, Schedule Above 120 455 50 Mm Nb, Schedule Upto 40 456 50Mm Nb, Schedule Above 40 But Upto 80 457 50 Mm Nb, Schedule Above 120 458 80 Mm Nb, Schedule Upto 40 459 80Mm Nb, Schedule Above 40 But Upto 80 460 80 Mm Nb, Schedule Above 120 461 100Mm Nb, Schedule Upto 40 462 100Mm Nb, Schedule Above 40 But Upto 80 463 100Mm Nb, Schedule Above 120 464 150 Mm Nb, Schedule Upto 40 465 150 Mm Nb, Schedule More Than 40 But Upto 80 466 150 Mm Nb, Schedule Above 120 467 200 Mm Nb, Schedule Upto 20 468 200 Mm Nb, Schedule Above 20 But Upto 40 469 200 Mm Nb, Schedule More Than 40 But Upto 80 470 200 Mm Nb, Schedule Above 120 471 250 Mm Nb, Schedule Upto 20 472 250 Mm Nb, Schedule Above 20 But Upto 40 473 250 Mm Nb, Schedule More Than 40 But Upto 80 474 250 Mm Nb, Schedule Above 120 475 300 Mm Nb, Schedule Upto 20 476 300 Mm Nb, Schedule Above 20 But Upto 40 477 300 Mm Nb, Schedule More Than 40 But Upto 80 478 300 Mm Nb, Schedule Above 120 479 350 Mm Nb, Schedule Upto 20 480 350 Mm Nb, Schedule Above 20 But Upto 40 481 350 Mm Nb, Schedule More Than 40 But Upto 80 482 350 Mm Nb, Schedule Above 120 483 Fabrication & Fixing Of Fabric Bellow The Job Involves Removal Of Old Fabric Bellow From The Expansion Joint, Cleaning Of The Bellow And Fixing Of New Fabric Bellow With Bellow As Per Instruction Of Engineer-In-Charge Including Tools And Tackles And All Manpower. Dismantling / Erection Of Bellow Assembly And Supply Of New Fabric Bellow Shall Be In The Scope Of Iocl. 484 Cutting Various Sizes Of Gaskets Job Involves Collection Of Gasket Sheets From Materials Dept, Bringing Them To Drum Plant Or Wherever The Gasket Machine Is Available, Install The Die Required, Cut The Reqd Quantities Of Gaskets, As Advised By The Engineer-In-Charge. 485 25 Mm 486 40 Mm 487 50 Mm 488 80 Mm 489 100 Mm 490 150 Mm 491 200 Mm 492 250 Mm 493 300 Mm 494 350 Mm 495 400 Mm 496 450 Mm 497 500 Mm 498 600 Mm 499 700 Mm 500 750 Mm 501 Flame Heating Brg, Hub And Furnace Plug Etc. Heating Of Bearings, Hubs, Furnace Header Etc. By Gas At Different Elevations As Per Requirement And Instruction Of The Engineer-In-Charge. Including Supply Of All Tools, Tackles, Equipment#S, Labour, Consumables Etc. 502 B Dismatnling / Installation Of Valves 503 Removal Of Flanged / Rtj Valves Dismantling And Removal Of All Types Of Flanged Including Rtj Valves From Pipelines At Ground Level I.E. Up To A Height Of 5 Meters On Sleepers, Pipe Racks Etc. Or Up To 5 Meters Depth In Trenches Including Removal Of Gaskets, Nut Bolts Etc. And Transportation Either To Owners Storage Point / Workshop And / Or Scrapyard Including Loosening Of Studs, Disconnecting Earthing Protection All Complete As Per Direction Of The Engineer-In-Charge Including All Labour, Tools, Tackles, Consumables And Supervision Etc. 504 Installation Of Flanged / Rtj Valves Transportation Of All Types Of Flanged / Rtj Valves, Gaskets, Nut Bolts Etc. Either From Owners Storage Point To Workshop And / Or Worksite And Installation Of Valves At Ground Level I.E. Up To A Height Of 5 Meters On Sleepers, Pipe Racks Etc. Or Up To 5 Meters Depth In Trenches Including Assembly Of Valve Accessories, Cleaning Of Flanged Faces, Lapping Of Rtj Rings, Cutting The Gaskets To Proper Size, Placing The Gaskets / Rtj Ring Properly, Tightening Of Studs, Providing Earthing Protection By Way Of Fixing Strips, All Complete As Per Drawings And Direction Of The Engineer-In-Charge Including All Labour, Tools, Tackles, Consumables And Supervision Etc. 505 For Valves ( Other Than Rtj ) 506 For Rtj Valves 507 Extra For Over Head Installation / Removal Of Flanged / Rtj Valves At Additional Heights Extra For Overhead Installation / Removal Of Flanged Valves Of All Metallurgies For Every Additional Height Of Ten Metres Or Part Thereof. Note: Since Lift-Kg Unit Is Not Available In Sap, Hence For Estimate Unit Is To Be Taken As Kg. 508 Installation 509 Removal 510 C Steel Scaffolding Jobs 511 <H><U>Scaffolding Jobs To Be Done As Follows:-< / >< / > <H>1 ) For Normal Jobs, ( 100% ) Cup-Lok Type Of Scaffolding To Be Erected At Site.< / > <H>2 ) Only In Exceptional Cases, Where Erection Of Cup-Lok Type Of Scaffolding Is Not Possible At Site Due To In Accessibility Or Any Other Reason, Normal Scaffolding Pipes With Clamp Arrangement May Be Allowed After Clearance From Eic As Described< / >. 512 Steel Scaffloding Materials In Contractors Scope The Job Includes Transportation Of Scaffolding Materials In Contractors Scope Of Supply, Erection Of Scaffolding At Site Covering The Areas Specified Including Providing Vertical Posts Of Pipes At Inter Distance Of 1.5 M And Horizontal Numbers At A Inter Distance Of 0.5 To 0.75 M, Providing Tie Rods At Corners To Give Sufficient Strength To The Structure, Placing The Wooden / Steel Planks / Frp Gratings On Top For Making Sufficient Area. Dismantling Scaffolding After Completion Of Job And Returning The Scaffolding Material To Specified Place Including All Tools, Tackles, Consumables, Labours And Contractors Supervision As Directed By The Engineer-In-Charge 1. For Measurement In Sqm: 2 ( Length + Width ) X Height Area Covered By The Scaffolding Is To Be Taken. 2. Scaffolding Measurement To Be Done By Breaking The Height Into Parts As Per Height Slab Mentioned Below And Adopting Respective Rates Against Mentioned Height Slabs. 513 Upto 6 M 514 Above 6 M Upto 10 M 515 Above 10 M Upto 20 M 516 Above 20 M Upto 30 M 517 Above 30 M Upto 40 M 518 Above 40 M Upto 50 M 519 Intermediate Plate Form 520 D Dismanlting Of Structure 521 Dismantling Of Structurals Like Pipe Support / Stairway / Devit Etc. Removal Of Existing Platforms / Pipe Supports / Davits / Stairways Etc. Along With Adjacent Fittings / Members By Cutting / Debolting Or By Any Other Means Without Damaging The Remaining Unit And Lowering Down To The Ground Including Erection Of Scaffolding, Retrieving Of All The Usable Materials And Transportation To The Storage Point As Directed By The Engineer-In-Charge. 522 Fabrication And Erection Of Pipe Support / Platforms / Devits / Stair Case Etc. The Job Includes Getting The Materials Issued, Transportation To Work Site And Handling At Site, Fabrication At The Required Size And Shape Using Steel Pipes, Ms Structural / Plates Etc. By Cutting, Bevelling And Welding Including Fixing Of Ms Gratings / Chequered Plates On Platform At All Elevation By Welding, Bolting Or Otherwise To Existing Members Or Equipment. This Also Includes Fabrication And Fixing Of Pipe Clamps, Non-Standard Bolts Etc. Inclusive Of Labour, Consumables, Tools And Tackles And Materials Required For U-Clamps, J-Bolts Etc. And Applying One Coat Of Primer And Two Coats Of High Built Black Bituminous Paint And Complete In All Respect As Per Drawings, Specifications And Instructions Of The Engineer-In-Charge. ( Excluding Cost Of Structural Steel ) . 523 Installation Of Vessels / Columns / Drums / Filters Upto 5 Mt Transportation Of Vessel / Columns / Filters / Drums Etc. From Owners Storage Point To Worksite, Assembly Of Parts, Sub-Assemblies ( Including Internals ) , Erection At All Elevations, Aligning, Tightening Of Bolts, Grouting, Cleaning, Hydrotesting And Flushing By Water, Draining, Drying By Compressed Air And Installation Of All Mountings And Completing The Works In All Respects Including Earthing Protection By Way Of Fixing Strips And Electrodes As Per Drawings And Specifications. Job Also Includes Supplying Of All Types Of Tools, Tackles, Lifting Arrangements, Cranes, Tractor Trolley And Equipment, Machineries All Consumables And Labour To Complete The Job In A Workman Like Manner, Erection And Removal Of Steel Scaffolding Wherever Required, Area Preparation For Hot Job And Area Cleaning After Completion Of Work Including Blinding, Deblinding, Removal Of Insulation, Gas Cutting Of Bolts, Chipping Of Foundation, Flushing Wherever Required. All Jobs Are To Be Carried Out As Per The Instruction And To The Full Satisfaction Of The Engineer-In-Charge. 524 Installation Of Vessels / Columns / Drums / Filters More Than 5 Mt And Upto 10 Mt Transportation Of Vessel / Columns / Filters / Drums Etc. From Owners Storage Point To Worksite, Assembly Of Parts, Sub-Assemblies ( Including Internals ) , Erection At All Elevations, Aligning, Tightening Of Bolts, Grouting, Cleaning, Hydrotesting And Flushing By Water, Draining, Drying By Compressed Air And Installation Of All Mountings And Completing The Works In All Respects Including Earthing Protection By Way Of Fixing Strips And Electrodes As Per Drawings And Specifications. Job Also Includes Supplying Of All Types Of Tools, Tackles, Lifting Arrangements, Cranes, Tractor Trolley And Equipment, Machineries All Consumables And Labour To Complete The Job In A Workman Like Manner, Erection And Removal Of Steel Scaffolding Wherever Required, Area Preparation For Hot Job And Area Cleaning After Completion Of Work Including Blinding, Deblinding, Removal Of Insulation, Gas Cutting Of Bolts, Chipping Of Foundation, Flushing Wherever Required. All Jobs Are To Be Carried Out As Per The Instruction And To The Full Satisfaction Of The Engineer-In-Charge. 525 E Shutdown Factor 526 Shutdown Factor-25%

BOQ

Name of Work: MECH JOBS FOR HGU/DHDT/SRU SHUTDOWN AT BGR, IOCL
Sl.No.Item DescriptionItem Code / MakeQuantityUnits
110Mech jobs for HGU/DHDT/SRUItem 00010
210Mech jobs for HGU/DHDT/SRUItem 10.10
310.02A MISC PIPING & OTHER JOBSItem 10.A
410.02DISMANTLING OF CARBON STEEL/ ALLOY STEEL PIPING BY HOT WORK (INSULATED/ UNINSULATED) Dismantling and removal of above ground, overhead under ground (upto depth of 5m) redundant, steam traced pipelines, insulated and u ninsulated, of carbon steel / alloy steel by gas cutting or by grinder from various locations such as pipe racks, columns, pump house, vessels, heaters, heat exchangers, desalter etc. upto a height of 5 meters including, removal of insulation material, all on line instruments, fittings, flanges, valves, vents, drains, branching etc.; lowering down the same to ground level with due care so that no other piping, equipment#s, machinery#s etc. is damaged; cutting into pieces if required; segregating for reclaiming useful fittings such as bends, flanges, valves, instruments etc. by unbolting, gas cutting, cold cutting etc.; transporting and stacking the salvageable useful materials to workshop / instrument workshop/ store or as per the direction of the Engineer-in-Charge and shifting the scrap pipes etc. to scrap yard or any other location within refinery premises and completing the job as per the instructions of Engineer-in-Charge. Job also includes supplying of all types of tools and tackles, lifting arrangements, equipment, machineries, all consumables and labour etc. to complete the work in all respects in a workman like manner including area preparation, taking clearance for hot jobs, blinding and de-blinding, area cleaning after completion of work, flushing wherever required as directed by the Engineer-in-Charge. NOTE : 1. Proper safety arrangements for carrying out the job is under contractor's scope and the same has to be complied with as per the d irections of the Engineer- in-Charge. 2. Salvaging of useful fitting from redundant pipe, if done, will be paid under separate item. 3. Civil works (excavation and back filling) for underground dismantling shall be paid under separate item from Civil SOR. Note: For piping beyond 5 Mtr. elevation above and below ground piping and upto 10Mtr. rates is to be escalated by 20%. For more than 10 Mtr. but upto 15 Mtr. rates is to be escalated by 30%. For more than 15 Mtr but upto 20 Mtr. rates to be escalated by 40% respectively. Requirement of scaffolding to be envisaged and decided by Engineer in Charge as per site requirement and scaffolding item to be paid separately.Item 10.A.10
510.0215 mm NBItem 10.A.2010M
610.0220 mm NBItem 10.A.3010M
710.0225 mm NBItem 10.A.4010M
810.0240 mm NBItem 10.A.5010M
910.020150 mm NBItem 10.A.6010M
1010.020180 mm NBItem 10.A.705M
1110.0201100 mm NBItem 10.A.805M
1210.0201150 mm NBItem 10.A.905M
1310.0201200 mm NBItem 10.A.1005M
1410.0201250 mm NBItem 10.A.1105M
1510.0201300 mm NBItem 10.A.1205M
1610.0201350 mm NBItem 10.A.1305M
1710.0201400 mm NBItem 10.A.1405M
1810.0201450 mm NBItem 10.A.1505M
1910.0202500 mm NBItem 10.A.1605M
2010.0202600 mm NBItem 10.A.1705M
2110.0202COLD CUTTING OF CARBON / ALLOY STEEL PIPE LINES (INSULATED / UNINSULATED) Cold cutting and removal of above ground/overhead/underground in tranches (upto 5 meters depth) insulated or uninsulated pipelines of carbon steel/ alloy steel/ and/or any other type from various location such as pipe racks, columns, pump house, vessels, heaters, heat exchangers, desalters etc. upto a height of 5 meters including removal of insulation materials, all on line instruments, fittings, flanges, valves, vents, drains, branching etc.; lowering down / lifting the same to ground level with due care so that no other piping, equipment#s, machinery#s etc. is damaged; cutting into pieces if required; segregating for reclaiming useful fittings such as bends, flanges, valves, instruments etc. by unbolting, gas cutting, cold cutting etc. transporting and stacking the salvageable useful materials to workshop / instrument workshop/ store or as per the direction of the Engineer-in-Charge and shifting the scrap pipes etc. to scrap yard or any other location within refinery premises all complete as per the instructions of Engineer-in-Charge.°° Job also includes supplying of all types of tools and tackles, lifting arrangements, equipment, machineries, all consumables and labour etc. to complete the work in all respects in a workman like manner including area preparation, taking clearance for hot jobs, blinding and deblinding area cleaning after completion of work, flushing wherever required as directed by the Engineer-in-Charge. NOTE : 1. Proper safety arrangements for carrying out the job is under contractor's scope and the same has to be complied with as per the d irections of the Engineer- in-Charge. 2. Salvaging of useful fitting from redundant pipe, if done, will be paid under separate item. 3. Civil works (excavation and back filling) for underground dismantling shall be paid under separate item from Civil SOR. Note: For piping beyond 5 Mtr. elevation above and below ground piping and upto 10Mtr. rates is to be escalated by 20%. For more than 10 Mtr. but upto 15 Mtr. rates is to be escalated by 30%. For more than 15 Mtr but upto 20 Mtr. rates to be escalated by 40% respectively. Requirement of scaffolding to be envisaged and decided by Engineer in Charge as per site requirement and scaffolding item to be paid separately.Item 10.A.180
2210.020215 MM NBItem 10.A.19025EA
2310.020220 MM NBItem 10.A.20025EA
2410.020225 MM NBItem 10.A.21025EA
2510.020240 MM NBItem 10.A.22015EA
2610.020250 MM NBItem 10.A.23015EA
2710.020280 MM NBItem 10.A.24015EA
2810.0203100 MM NBItem 10.A.2505EA
2910.0203150 MM NBItem 10.A.2605EA
3010.0203200 MM NBItem 10.A.2705EA
3110.0203250 MM NBItem 10.A.2805EA
3210.0203300 MM NBItem 10.A.2905EA
3310.0203350 MM NBItem 10.A.3005EA
3410.0203400 MM NBItem 10.A.3105EA
3510.0203450 MM NBItem 10.A.3205EA
3610.0203500 MM NBItem 10.A.3305EA
3710.0203FIXING / REMOVAL OF FLANGES / BLIND FLANGES OF RATING UPTO 300# Opening / fixing etc. of flanges / blind flanges / spool pieces at the two flange joint (rating upto 300#) as and when required for elbow reversing, wedge opening etc. or any other job including handling of flanges and preparation of gaskets from the sheet including tools and tackles, consumables, supervision etc. and as per direction of the Engineer-in-Charge.Item 10.A.340
3810.020415 mmItem 10.A.35050EA
3910.020420 mmItem 10.A.36050EA
4010.020425 mmItem 10.A.37050EA
4110.020440 mmItem 10.A.38050EA
4210.020450 mmItem 10.A.39050EA
4310.020480 mmItem 10.A.40050EA
4410.0204100 mmItem 10.A.41050EA
4510.0204150 mmItem 10.A.42050EA
4610.0204200 mmItem 10.A.43050EA
4710.0204250 mmItem 10.A.44050EA
4810.0205300 mmItem 10.A.45050EA
4910.0205350 mmItem 10.A.46025EA
5010.0205400 mmItem 10.A.47025EA
5110.0205450 mmItem 10.A.48025EA
5210.0205500 mmItem 10.A.49025EA
5310.0205600 mmItem 10.A.50025EA
5410.0205FIXING / REMOVAL OF FLANGES / BLIND FLANGES OF RATING MORE THAN 300# AND UPTO 600# Opening / fixing etc. of flanges / blind flanges / spool pieces at the two flange joint (rating more than 300# and upto 600#) as and when required for elbow reversing, wedge opening etc. or any other job including handling of flanges and preparation of gaskets from the sheet including tools and tackles, consumables, supervision etc. and as per direction of the Engineer-in-Charge.Item 10.A.510
5510.020515 mmItem 10.A.52050EA
5610.020520 mmItem 10.A.53050EA
5710.020525 mmItem 10.A.54050EA
5810.020640 mmItem 10.A.55050EA
5910.020650 mmItem 10.A.56050EA
6010.020680 mmItem 10.A.57050EA
6110.0206100 mmItem 10.A.58050EA
6210.0206150 mmItem 10.A.59050EA
6310.0206200 mmItem 10.A.60050EA
6410.0206250 mmItem 10.A.61050EA
6510.0206300 mmItem 10.A.62050EA
6610.0206350 mmItem 10.A.63050EA
6710.0206DISMANTLING OF STAINLESS STEEL PIPING BY HOT WORK (INSULATED / UNINSULATED) Dismantling and removal of above ground / overhead / underground in trenches (upto 5 m) redundant, steam traced pipelines, insulated and uninsulated of stainless steel by grinding / gouging / plasma cutting from various locations such as pipe racks, columns, pump house, vessels, heaters, heat exchangers, desalter etc. upto a height of 5 meters including removal of insulation materials all on line instruments, fittings, flanges, valves, vents, drains, branching etc.; lowering down the same to ground level with due care so that no other piping, equipment#s, machinery#s etc. is damaged; cutting into pieces if required; segregating for reclaiming useful fittings such as bends, flanges, valves, instruments etc. by unbolting, gas cutting, cold cutting etc.; transporting and stacking the salvageable useful materials to workshop / instrument workshop / store or as per the direction of the Engineer-in-Charge and shifting the scrap pipes etc. to scrap yard or any other location within refinery premises all complete as per the instructions of engineer in-charge. Job also includes supplying of all types of tools and tackles, lifting arrangements, equipment, machineries, all consumables and labour etc. to complete the work in all respects in a workman like manner including area preparation, taking clearance for hot jobs, blinding and deblinding area cleaning after completion of work, flushing wherever required as directed by the Engineer-in-Charge. NOTE : 1. Proper safety arrangements for carrying out the job is under contractor's scope and the same has to be complied with as per the d irections of the Engineer- in-Charge. 2. Salvaging of useful fitting from redundant pipe, if done, will be paid under separate item. 3. Civil works (excavation and back filling) for underground dismantling shall be paid under separate item from Civil SOR. Note: For piping beyond 5 Mtr. elevation above and below ground piping and upto 10Mtr. rates is to be escalated by 20%. For more than 10 Mtr. but upto 15 Mtr. rates is to be escalated by 30%. For more than 15 Mtr but upto 20 Mtr. rates to be escalated by 40% respectively. Requirement of scaffolding to be envisaged and decided by Engineer in Charge as per site requirement and scaffolding item to be paid separately.Item 10.A.640
6810.020620 mm NBItem 10.A.65010M
6910.020725 mm NBItem 10.A.66010M
7010.020740 mm NBItem 10.A.67010M
7110.020750 mm NBItem 10.A.68010M
7210.020780 mm NBItem 10.A.69010M
7310.0207100 mm NBItem 10.A.70010M
7410.0207150 mm NBItem 10.A.71010M
7510.0207200 mm NBItem 10.A.72010M
7610.0207250 mm NBItem 10.A.73010M
7710.0207CARBON STEEL PIPING JOINTS FOR HYDROCARBON SERVICE (WITH WELDING ELECTRODE E-6010 / E-7018) Transportation of all piping items from owner's storage points to work site and/ or pre-fabrication yard and to site after pre-fabrication; cutting, grinding, edge preparation of pipes and fittings, like flanges, elbows, tees, reducers etc. to match the mating edges of different thickness; fit-up, bending, welding using approved welding electrodes as per owners quality requirements etc. as per codes/specifications, drawing etc., threading, laying, erection and alignment of pipes at ground level i.e. upto a height of 5 meters on sleepers, pipe racks etc. or upto 5 meters depth in trenches; connecting with equipment, nozzles, steam traps, strainers, orifice assemblies (including tapping upto first block valve), spray nozzles rotameters; tapping for instrument connections like pressure gauges, thermowells, sample connections, vents, drains etc. including fixing of all types of SW valves, gaskets, nuts and bolts, all inline instruments, elbows, tees, flanges, reducers, full coupling or half coupling, earthing strip wherever required; welding prefabricated shoes and supports (including alignment) as per the drawings, including preparation small bore isometric upto 1.5 inch NB, specifications, codes etc. and as per the instructions of the Engineer-in-Charge to his entire satisfaction including supplying of all types of tools and tackles, lifting arrangements, equipment, machineries, all consumables and labour etc. to complete the work in all respects in a workman like manner including area preparation for hot jobs, area cleaning after completion of work, flushing wherever required, cleaning of pipes externally off all foreign materials like weld beads, clamps fixtures etc. used in fabrication as directed by the Engineer-in-Charge. NOTE : Proper safety arrangements for carrying out the job is under contractor's scope and the same has to be complied with as per the dire ctions of the Engineer- in-Charge. NOTE: For piping beyond 5 Mtr. elevation above and below ground piping and upto 10Mtr. rates is to be escalated by 20%. For more than 10 Mtr. but upto 15 Mtr. rates is to be escalated by 30%. For more than 15 Mtr but upto 20 Mtr. rates to be escalated by 40% respectively. Requirement of scaffolding to be envisaged and decided by Engineer in Charge as per site requirement and scaffolding item to be paid separately. NOTE: For piping where TIG welding is used for root run only, the rates to be escalated by 15% and where TIG welding is used for entire joints the rates to be escalated by 20%. NOTE: Payment of tapping points will also be made extra on joint basis, as the measurement is on joint basis.Item 10.A.740
7810.020715 mm NB, Schedule upto 80Item 10.A.750150EA
7910.020815 mm NB, Schedule above 80 but upto 160Item 10.A.76050EA
8010.020820 mm NB, Schedule upto 80Item 10.A.770150EA
8110.020820 mm NB, Schedule above 80 but upto 160Item 10.A.78050EA
8210.020825 mm NB, Schedule upto 80Item 10.A.790150EA
8310.020825 mm NB, Schedule above 80 but upto 160Item 10.A.80050EA
8410.020840 mm NB, Schedule upto 80Item 10.A.810150EA
8510.020840 mm NB, Schedule above 80 but upto 160Item 10.A.82050EA
8610.020850 mm NB, Schedule more than 40 but upto 80Item 10.A.830150EA
8710.020850 mm NB, Schedule above 80 but upto 160Item 10.A.84050EA
8810.020880 mm NB, Schedule upto 40Item 10.A.85050EA
8910.020980 mm NB, Schedule more than 40 but upto 80Item 10.A.86050EA
9010.020980 mm NB, Schedule above 80 but upto 160Item 10.A.87050EA
9110.0209100 mm NB, Schedule upto 40Item 10.A.88050EA
9210.0209100 mm NB, Schedule more than 40 but upto 80Item 10.A.89050EA
9310.0209100 mm NB, Schedule above 80 but upto 160Item 10.A.90050EA
9410.0209150 mm NB, Schedule upto 40Item 10.A.91050EA
9510.0209150 mm NB, Schedule more than 40 but upto 80Item 10.A.92050EA
9610.0209150 mm NB, Schedule above 80 but upto 120Item 10.A.93050EA
9710.0209200 mm NB, Schedule above 20 but upto 40Item 10.A.94050EA
9810.0209200 mm NB, Schedule more than 40 but upto 80Item 10.A.95050EA
9910.021200 mm NB, Schedule above 80 but upto 120Item 10.A.96050EA
10010.021250 mm NB, Schedule above 20 but upto 40Item 10.A.97050EA
10110.021250 mm NB, Schedule more than 40 but upto 80Item 10.A.98050EA
10210.021250 mm NB, Schedule above 80 but upto 120Item 10.A.99050EA
10310.021300 mm NB, Schedule upto 20Item 10.A.10001EA
10410.021300 mm NB, Schedule above 20 but upto 40Item 10.A.10101EA
10510.021300 mm NB, Schedule more than 40 but upto 80Item 10.A.10201EA
10610.021350 mm NB, Schedule upto 20Item 10.A.10301EA
10710.021350 mm NB, Schedule above 20 but upto 40Item 10.A.10401EA
10810.0211350 mm NB, Schedule more than 40 but upto 80Item 10.A.10501EA
10910.0211400 mm NB, Schedule upto 20Item 10.A.10601EA
11010.0211400 mm NB, Schedule above 20 but upto 40Item 10.A.10701EA
11110.0211450 mm NB, Schedule upto 20Item 10.A.10801EA
11210.0211450 mm NB, Schedule above 20 but upto 40Item 10.A.10901EA
11310.0211500 mm NB, Schedule upto 20Item 10.A.11001EA
11410.0211500 mm NB, Schedule above 20 but upto 40Item 10.A.11101EA
11510.0211600 mm NB, Schedule upto 20Item 10.A.11201EA
11610.0211600 mm NB, Schedule above 20 but upto 40Item 10.A.11301EA
11710.0211CS PPG JOINTS NHC ELECTD E-6013 Transportation of all piping items from owner's storage points to work site and/ or pre-fabrication yard and to site after pre-fabrication; cutting, grinding, edge preparation of pipes and fittings, like flanges, elbows, tees, reducers etc. to match the mating edges of different thickness; fit-up, bending, welding using approved welding electrodes as per owners quality requirements etc. as per codes/specifications, drawing etc., threading, laying, erection and alignment of pipes at ground level i.e. upto a height of 5 meters on sleepers, pipe racks etc. or upto 5 meters depth in trenches; connecting with equipment, nozzles, steam traps, strainers, orifice assemblies (including tapping upto first block valve), spray nozzles rotameters; tapping for instrument connections like pressure gauges, thermowells, sample connections, vents, drains etc. including fixing of all types of SW valves, gaskets, nuts and bolts, all inline instruments, elbows, tees, flanges, reducers, full coupling or half coupling, earthing strip wherever required; welding prefabricated shoes and supports (including alignment) as per the drawings, including preparation small bore isometric upto 1.5 inch NB, specifications, codes etc. and as per the instructions of the Engineer-in-Charge to his entire satisfaction including supplying of all types of tools and tackles, lifting arrangements, equipment, machineries, all consumables and labour etc. to complete the work in all respects in a workman like manner including area preparation for hot jobs, area cleaning after completion of work, flushing wherever required, cleaning of pipes externally off all foreign materials like weld beads, clamps fixtures etc. used in fabrication as directed by the Engineer-in-Charge. NOTE : Proper safety arrangements for carrying out the job is under contractor's scope and the same has to be complied with as per the dire ctions of the Engineer- in-Charge. NOTE: For piping beyond 5 Mtr. elevation above and below ground piping and upto 10Mtr. rates is to be escalated by 20%. For more than 10 Mtr. but upto 15 Mtr. rates is to be escalated by 30%. For more than 15 Mtr but upto 20 Mtr. rates to be escalated by 40% respectively. Requirement of scaffolding to be envisaged and decided by Engineer in Charge as per site requirement and scaffolding item to be paid separately. NOTE: For piping where TIG welding is used for root run only, the rates to be escalated by 15% and where TIG welding is used for entire joints the rates to be escalated by 20%. NOTE: Payment of tapping points will also be made extra on joint basis, as the measurement is on joint basis.Item 10.A.1140
11810.021215 mm NB, Schedule upto 80Item 10.A.115050EA
11910.021215 mm NB, Schedule above 80 but upto 160Item 10.A.116050EA
12010.021220 mm NB, Schedule upto 80Item 10.A.117050EA
12110.021220 mm NB, Schedule above 80 but upto 160Item 10.A.118050EA
12210.021225 mm NB, Schedule upto 80Item 10.A.119050EA
12310.021225 mm NB, Schedule above 80 but upto 160Item 10.A.120050EA
12410.021240 mm NB, Schedule upto 80Item 10.A.121050EA
12510.021240 mm NB, Schedule above 80 but upto 160Item 10.A.122050EA
12610.021250 mm NB, Schedule more than 40 but upto 80Item 10.A.123050EA
12710.021250 mm NB, Schedule above 80 but upto 160Item 10.A.124050EA
12810.021380 mm NB, Schedule more than 40 but upto 80Item 10.A.125050EA
12910.021380 mm NB, Schedule above 80 but upto 160Item 10.A.126010EA
13010.0213100 mm NB, Schedule upto 40Item 10.A.127050EA
13110.0213100 mm NB, Schedule more than 40 but upto 80Item 10.A.128050EA
13210.0213150 mm NB, Schedule upto 40Item 10.A.129050EA
13310.0213150 mm NB, Schedule more than 40 but upto 80Item 10.A.130050EA
13410.0213200 mm NB, Schedule above 20 but upto 40Item 10.A.131050EA
13510.0213200 mm NB, Schedule more than 40 but upto 80Item 10.A.132050EA
13610.0213250 mm NB, Schedule above 20 but upto 40Item 10.A.133050EA
13710.0213250 mm NB, Schedule more than 40 but upto 80Item 10.A.134050EA
13810.0213300 mm NB, Schedule above 20 but upto 40Item 10.A.13505EA
13910.0214300 mm NB, Schedule more than 40 but upto 80Item 10.A.13605EA
14010.0214400 mm NB, Schedule above 20 but upto 40Item 10.A.13701EA
14110.0214400 mm NB, Schedule more than 40 but upto 80Item 10.A.13801EA
14210.0214450 mm NB, Schedule above 20 but upto 40Item 10.A.13901EA
14310.0214450 mm NB, Schedule above 40 but upto 80Item 10.A.14001EA
14410.0214500 mm NB, Schedule above 20 but upto 40Item 10.A.14101EA
14510.0214500 mm NB, Schedule above 40 but upto 80Item 10.A.14201EA
14610.0214CARBON STEEL PIPING FOR NON-HYDROCARBON SERVICE (WITH WELDING ELECTRODE E-6013) Transportation of all piping items from owner's storage points to work site and / or pre-fabrication yard and to site after pre-fabrication; cutting, grinding, edge preparation of pipes and fittings, like flanges, elbows, tees, reducers etc. to match the mating edges of different thickness; fit-up, bending, welding using approved welding electrodes as per owners quality requirements etc. as per codes/specifications, drawing etc., threading, laying, erection and alignment of pipes at ground level i.e. upto a height of 5 meters on sleepers, pipe racks etc. or upto 5 meters depth in trenches; anchoring wherever required, connecting with equipment, nozzles, steam traps, strainers, orifice assemblies (including tapping upto first block valve), spray nozzles rotameters; tapping for instrument connections like pressure gauges, thermowells, sample connections, vents, drains etc. including fixing of all types of SW valves, gaskets, nuts and bolts, all inline instruments, elbows, tees, flanges, reducers, full coupling or half coupling, reinforcement pads, earthing strip wherever required; welding prefabricated shoes and supports (including alignment) as per the drawings including preparation of small bore isometrics upto 1.5 inch NB, specifications, codes etc. and as per the instructions of the Engineer-in-Charge to his entire satisfaction including supplying of all types of tools and tackles, lifting arrangements, equipment, machineries, all consumables and labour etc. to complete the work in all respects in a workman like manner including area preparation for hot jobs, area cleaning after completion of work, flushing wherever required, cleaning of pipes externally off all foreign materials like weld beads, clamps fixtures etc. used in fabrication as directed by the Engineer-in-Charge. NOTE : Proper safety arrangements for carrying out the job is under contractor's scope and the same has to be complied with as per the dire ctions of the Engineer- in-Charge. NOTE: For piping beyond 5 Mtr. elevation above and below ground piping and upto 10Mtr. rates is to be escalated by 20%. For more than 10 Mtr. but upto 15 Mtr. rates is to be escalated by 30%. For more than 15 Mtr but upto 20 Mtr. rates to be escalated by 40% respectively. Requirement of scaffolding to be envisaged and decided by Engineer in Charge as per site requirement and scaffolding item to be paid separately. NOTE: For piping where TIG welding is used for root run only, the rates to be escalated by 15% and where TIG welding is used for entire joints the rates to be escalated by 20%.Item 10.A.1430
14710.021415 mm NB, Schedule upto 80Item 10.A.144025M
14810.021420 mm NB, Schedule upto 80Item 10.A.145025M
14910.021525 mm NB, Schedule upto 80Item 10.A.146025M
15010.021540 mm NB, Schedule upto 80Item 10.A.147025M
15110.021550 mm NB, Schedule more than 40 but upto 80Item 10.A.148025M
15210.021580 mm NB, Schedule upto 40Item 10.A.149025M
15310.0215100 mm NB, Schedule upto 40Item 10.A.150025M
15410.0215150 mm NB, Schedule upto 40Item 10.A.151025M
15510.0215200 mm NB, Schedule above 20 but upto 40Item 10.A.152025M
15610.0215250 mm NB, Schedule above 20 but upto 40Item 10.A.153025M
15710.0215300 mm NB, Schedule above 20 but upto 40Item 10.A.154025M
15810.0215350 mm NB, Schedule above 20 but upto 40Item 10.A.155025M
15910.0216400 mm NB, Schedule above 20 but upto 40Item 10.A.156025M
16010.0216HYDROTESING OF PIPING WORKS Hydrostatic testing of pipelines at the specified pressure including blinding/deblinding, fabrication and fixing of testing connections, pressure gauge installation. Hose pipe connection and making all other arrangements as required and dewatering, flushing and boxing up after fixing proper gaskets with supply of all labour, tools andtackles, instruments and instruction of the Engineer-in-Charge. The job has to be carried out at all elevations.Item 10.A.1570
16110.021615 mmItem 10.A.158050M
16210.021620 mmItem 10.A.159050M
16310.021625 mmItem 10.A.160050M
16410.021640 mmItem 10.A.161050M
16510.021650 mmItem 10.A.162050M
16610.021680 mmItem 10.A.163050M
16710.0216100 mmItem 10.A.164050M
16810.0216150 mmItem 10.A.165050M
16910.0217200 mmItem 10.A.166050M
17010.0217250 mmItem 10.A.167050M
17110.0217300 mmItem 10.A.168050M
17210.0217350 mmItem 10.A.169050M
17310.0217400 mmItem 10.A.170050M
17410.0217450 mmItem 10.A.171050M
17510.0217500 mmItem 10.A.172050M
17610.0217WRAPPING & COATING OF VESSELS/ UNDERGROUND PIPING ETC. Providing wrapping and coating as per the specifications including supply of all materials, tools and tackles, etc. The detailed spe cification for wrapping and coating is as under: 1. The surface preparation of pipes shall be done by grit/ shot blast cleaning to Swedish standard SA-2. 2. The grit/ shot blasting operation shall be carried out in the day time. Blast cleaning operation shall not be under taken in humid condition. 3. Only approved quality grit/ shot shall be used for grit/ shot blasting. The grit/ shot used shall be dry and free form any other impurities. 4. The grit/ shot blasted surface shall have a shining and near white metal appearances. 5. After grit/ shot blast cleaning, the surface shall be dry brushed to remove deposits. 6. The grit/ shot blasted surface should be inspected by quality control/ Inspection agency of owner/ contractor. COATING SYSTEM Following steps shall be followed: 1. Application of one coat of primer. 2. Application of one coat of coal tar enamel. 3. Wrapping fibre glass. 4. Application of 2nd coat of coal tar enamel. 5. Wrapping of craft paper/ coal tar impregnated outer wrap. PRIMING 1. Single coat of coal tar primer shall be applied manually with good quality brushes. Following precautions shall be taken during application of primer. 2. Primer drum shall be inspected for manufacturing date batch No. etc. 3. Primer drum shall be rotated before opening for proper mixing. 4. Primer shall be applied within 12 hrs. of completion of sand blasting. 5. Primer shall be applied evenly all along the pipe surface. 6. Any holiday or bare pipe left over during priming shall be primed again. 7. Primer will not be applied during rainy/ moist weather. 8. After application of primer and before drying, adequate precaution shall be taken to avoid contact of dust/ sand etc. with primed surface. 9. Normal primer requires 1 hr. time for proper drying and becomes dead after 24 hrs. of its application. 10. Coating shall be completed within these limits failing which dead primer shall be cleaned and fresh primer shall be applied again. COATING AND WRAPPING i) When the priming coat has dried and the surface of the primed pipe has been cleaned preferably by clean white rags to remove the settled dust just preceding of the coating operation. The pipe shall be coated with hot application of one coat of coal tar enamel to give a minimum thickness of 2.5 mm and to be securely bonded to the primer. ii) The coal tar enamel shall be cut into lumps preferably at the storage place upon a clean platform with side boards and due care must always be exercised by the contractor to keep the broken enamel absolutely free form dirt, grass, water or any other foreign material up to the time when enamel is charged into the melting kettle. iii) The coal tar enamel shall be slowly heated on reduced fire and maintained to the even temperature recommended for application i.e. 220 deg. C to 240 deg. C. iv) Constant stirring shall be necessary in continuously operating melting kettles. v) Melting kettle should have proper insulation. vi) The melting kettle should be of movable type i.e. wheel mounted and have towing arrangement. vii) The melting kettle should be kept near the work site. However, in no case the molten enamel shall be carried in bucket for more than 50 meter distance. Viii) During pouring of molten enamel, fine wire mesh filter shall be used to avoid the flow of impurity/ dirt/ sand. ix) During temporary interruption of the work the temperature in the kettle not shall be reduced by at least 50 deg. C below the normal specified temperature. x) Any enamel heated to temperature in excess of the maximum allowable temperature shall be rejected and suitably disposed off by the contractor. xi) Melting kettles/ pots shall always be maintained clean and in good working order and must be cleaned whenever deposits form on the heating surface. xii) A uniform thickness of 2.5 mm of enamel shall be applied to the surface of the primed pipe. xiii) A uniform thickness of 2.5 mm of enamel shall be applied to the surface of the primed pipe. xiv) The enamel shall be then reinforced by a spirally wrapped fibre glass wrap, pulled and embedded into the hot coating with an over lapping of edges of the wrap not less than 1/2\" and not more than 1\" xv) This will be followed by another coat of hot coal tar enamel application with a uniform thickness of 1.5 mm followed by craft paper/ coal tar impregnated fibre glass covering. xvi The coating and wrapping must be absolutely free of wrinkles in the wrappers, pinholes, bubbles, holidays voids thin spots or foreign matter. xvii Rolls of wrapping material shall not be kept along the right of way and shall be stored properly and brought to site. xviii) Wrapping material shall be so hauled and handled as to prevent injury to the packages. xix) No packages shall be handled with hooks or thrown form trucks. xx) Any such material which shows evidence of deterioration due to weather or any other cause, shall be rejected. COATING THICKNESS Minimum thickness of first should be 2.5 mm whereas total thickness should be approx. 4.5 mm. TESTING Following testing shall be undertaken: I) Physical Inspection: All the coated surface shall be visually inspected and all the wrinkles, bubbles, lack of overlap etc. shall be marked for repair. Ii) Sound Test: The coating adhesion can be checked easily with small wooden hammer by soft striking on coated surface. Change in sound indicates coating defects and same can be checked there by peel test. iii) Peel Test: The field bond test for coal tar enamel adhesion shall be preformed at 50-80F normal operating temperature of steel piping. If the coating temperature is above 80 °F or below 50 deg. F, pour cold or hot water over the test area to adjust the enamel temperature within this range. Using a knife, heated if necessary make two parallel cuts through the coating about 4 inch in length and 3/4 inch apart. With the edge of knife blade cut under the enamel strip at one end and loosen the enamel form the pipe the full width of the strip for about a 1/2\" place the knife blade under the loosened end and apply a slow, steady pull upward on enamel strip. iv) If the peel length exceeds 1/8\" the test is a failure and two additional tests shall be made at two different locations on the same section. If the additional tests are satisfactory then the section shall be approved. If the either additional test fails, the pipe section shall be rejected. SPECIFICATION OF COAL TAR PRIMER The primer consists of processed coal tar pitch and refined coal tar oil suitably blended with a solvent without pigment or inert filler or other substances (to be applied cold) for brushing or spraying as liquid coat to the clean surface piping as provided for in AWWA specification C-203-73. The primer should have no tendency to settle down in the container and when applied without producing bubbles, becomes dry and hard to touch within specified time ensuring and effective bond between the metal pipe surface and the enamel coating. The main characteristics of the coal tap primer should be as follows: 1. Drying time to touch dry, at normal humidity at 32 deg. C is less than 1 hr. 2. Max Boiling point of solvent 25 deg. C. 3. Penetration of residue at 25 deg. C. 4. Softening point of residue (ASTM-D-36) 104 deg. C. 5. Flash point of (ASTM 1310) 37 deg. C. 6. Pigment 7. Solvent Benzol solvent or highly toxic volatile solvents excluded. Reputed Indian Supplier (for Coal Tar Enamel and Coal Tar Primer). i) M/s Shalimar Tar Products, Calcutta. ii) M/s Lloyd Insulation (India) Ltd., New Delhi. 2. SPECIFICATION FOR COAL TAR ENAMEL The enamel shall be a WWA coal enamel type-I conforming to AWWA standard, AWWA C-203-86. The enamel be composed of a specially processed coal tar type blended with an inert mineral filter, properly graded, cleaned, dust free and without asphalt of either petroleum or nature base, to be applied to a recommended temperature. The main characteristics of the enamel shall be as follows: S. No. Test Enamel Type - 1 Min Max. 1. Softening Point, ASTM-D-36 140 deg.C 116 deg. C 2. Filter(ash) ASTMD-71 25% 35% 3. Fineness fillet through 90% Through 200 mesh. ASTM-D-54G 3. SPECIFICATION OF FIBRE GLASS INNER WRAP The fibre glass inner wrap of high tensile long monofilament, chemically inert glass fibre in jack straces patterns mat reinforced by longitudinal continuous stands of glass fibre yarn blended with insoluble inert resinous binder compatible with hot coal tar enamel and should conform to the following specifications: Tensile Strength (transverse) Kg/cm 0.50 + 0.10 Weight 41gm/sq.m Reputed Indian Supplier for Fibre Glass paper and Kraft Paper: i) M/s united paper product, Saharanpur, U.P. ii) M/s FGP limited New Delhi. iii) Specification of craft paper. The craft paper shall be smooth bituminised to be supplied in rolls. The average weight of a composite bituminised craft paper shall be a minimum of 120 gms/sq. Meter. A negative weight tolerance upto 5% of the composite weight may be permitted at the discretion to the owner, (bituminised craft paper with average weight less than 120 gms/sq. Meter in not acceptable). The bituminised craft paper shall be composed of two layers of craft paper shall be composed of two layers of craft paper and each weighing not less than 45 gm/sq. Meter and laminated with a layer of bitumen approachments weight 50 gms/sq. M to have a proper bond between the two layer of paper. He bituminised craft paper for field application shall be able to resist penetration. Specific Gravity at 25 deg. C ASTM D-71 1.4 1.6 Penetration, ASTM-D-5 10 a) At 25 deg. C 100 gms. Weight 5 secs. High temperature test at 71 deg.C 1/32 (Sag O AWWA C-203. Sec. 2.8.9 Low temperature test at 23 deg. C (Cracking), AWWAC-203 sec. 2.8.10 Peel Test, AWWAC-203 sec. 2.8.11 No peeling Electrical Resistance test at 17000 Volts and low amperage (1.5 mm thickness) Other Requirements (For wrapping and coating) 1. Third party Inspection certificate for all materials by EIL/ DNV/ LRIS/ MECON or providing IOCL approved manufacturers test certificate shall be in contractors scope. 2. Holiday testing machine shall be arranged and provided by contractor. 3. Vendor to submit transportation and Handling procedure T avoid wrapping and coating of pipes. 4. Vendor to submit and Get quality assurance plan (QAP) for wrapping and coating approved by owner/ Inspector. 5. The wrapping and coating surface must have machine finish in workmanship. Note: Additional payment for earth excavation and wrapping coating will be made extra for underground piping.Item 10.A.1730
17710.021750 mm NBItem 10.A.17405M
17810.021880 mm NBItem 10.A.17505M
17910.0218100 mm NBItem 10.A.17605M
18010.0218150 mm NBItem 10.A.17701M
18110.0218200 mm NBItem 10.A.17801M
18210.0218250 mm NBItem 10.A.17901M
18310.0218300 mm NBItem 10.A.18001M
18410.0218400 mm NBItem 10.A.18101M
18510.0218450 mm NBItem 10.A.18201M
18610.0218500 mm NBItem 10.A.18301M
18710.0218600 mm NBItem 10.A.18401M
18810.0219DYE PENETRATION TEST FOR PIPING WORKS Performance of dye penetration test including supply of all necessary materials, penetrant, developer etc. along with all equipment#s, labour, for carrying out the work as per specification & direction of engineer -in-charge at all elevations. Test has to be carried out in all metallurgy the test has to carry out on all schedules of pipes. NOTE: Since inch dia unit is not available in SAP, hence for estimate unit is to be taken as \" dia.Item 10.A.1850
18910.0219For Pipes (Per Inch Dia)Item 10.A.18602000\"
19010.0219For Vessels / Tanks (Per Inch)Item 10.A.1870250\"
19110.0219RADIOGRAPHY OF PIPING WORKS Performance of radiographic inspection on all type & sizing of piping/ pipe fittings in position at all heights inclusive of providing sources, film, chemicals, & all necessary equipment#s, consumables etc. complete in all respect as per specification & instruction of the Engineer-in-Charge. NOTE: Since inch dia unit is not available in SAP, hence for estimate unit is to be taken as \" dia.Item 10.A.1880
19210.0219For Pipes (Per Inch Dia)Item 10.A.18902000\"
19310.0219For Vessel/ tanks etc. (Per Inch)Item 10.A.1900250\"
19410.0219HEAT TREATMENT Heat treatment of shop fabricated for already installed piping / static equipment etc. for joints or other operations wherever required. Heating to be carried out in a furnace or by using an electric resistance or induction heating equipment ensuring uniform temperature attainment at all points of the portion being heat-treated. The portion under heat treatment shall be wrapped suitably under insulation to avoid any harmful temperature gradient. The temperature thus attainted in the portion under heat treatment shall be recorded by means of thermocouples, pyrometer and an automatic temperature recorders suitably calibrated should be employed. The calibration chart of each recorder along with hardness test results shall be submitted to the Engineer-in-Charge for approval. The details of heat treatment such as heating rate, soaking temperature pause period and cooling rate etc. to be carried out as per relevant standards / code as instructed by the Engineer-in-Charge. NOTE: Since inch dia unit is not available in SAP, hence for estimate unit is to be taken as \" dia.Item 10.A.1910
19510.0219For Pipes (Per Inch Dia)Item 10.A.19201000\"
19610.0219WELDING OF CS PLATES Transportation of all items including plates etc. from owner's storage point to work site and / or prefabrication yard and welding of CS plates including cutting / grinding / edge preparing and required testing to prove soundness of weld joint with supply of all consumables, manpower, tools as per technical specification and direction of the Engineer-in-Charge.Item 10.A.1930
19710.0219Upto 3mm thickItem 10.A.194050M
19810.022Above 3mm & upto 5mm thick.Item 10.A.195050M
19910.022Above 5mm & upto 6mm thickItem 10.A.196050M
20010.022Above 6mm & upto 7mm thickItem 10.A.197050M
20110.022Above 7mm & upto 9mm thick.Item 10.A.198050M
20210.022Above 9mm & upto 11mm thickItem 10.A.199050M
20310.022WELDING OF SS / AS PLATES Transportation of all items including plates etc. from owner's storage point to work site and / or prefabrication yard and welding of SS / AS plates / structural etc. including cutting / grinding / edge preparing and required testing to prove soundness of weld joint with supply of all consumables, manpower, tools as per technical specification and direction of the Engineer-in-Charge (Heat treatment and other NDT charges shall be paid extra).Item 10.A.2000
20410.022Upto 3mm thick Alloy Steel (P22)Item 10.A.201020M
20510.022Above 5mm & upto 6mm thick Alloy Steel (P22)Item 10.A.202020M
20610.022Above 6mm & upto 7mm thick Alloy Ateel (P22)Item 10.A.203020M
20710.022Upto 3 mm thick alloy steel (P5)Item 10.A.204020M
20810.0221Above 5 mm & upto 6 mm thick alloy steel (P5)Item 10.A.205020M
20910.0221Above 6 mm & upto 7 mm thick alloy steel (P5)Item 10.A.206020M
21010.0221Above 7 mm & upto 9 mm thick alloy steel (P5)Item 10.A.207020M
21110.0221Above 9 mm & upto 11 mm thick alloy steel (P5)Item 10.A.208020M
21210.0221Above 15 mm & upto 16 mm thick alloy steel (P5)Item 10.A.209020M
21310.0221Above 18 mm & upto 20 mm thick alloy steel (P5)Item 10.A.210020M
21410.0221CS / AS PLATE CUTTING Cutting of CS / AS plate by gas/ grinding or any other means as per direction of the Engineer-in-Charge according to suitability including transportation from stores to site with supply of all tools, tackles, consumables, equipment, labour etc.Item 10.A.2110
21510.02213mm thickItem 10.A.212010M
21610.02215mm thickItem 10.A.213010M
21710.02216mm thickItem 10.A.21405M
21810.02218mm thickItem 10.A.21502M
21910.022210mm thickItem 10.A.21602M
22010.022212mm thickItem 10.A.21702M
22110.0222SS PLATE CUTTING Cutting of SS plate by electric/ grinding or any other means including preheating wherever required as per direction of the Engineer-in-Charge according to suitability including transportation from stores to site with supply of all tools, tackles, consumables, equipment, labour etc.Item 10.A.2180
22210.02223mm thickItem 10.A.219010M
22310.02225mm thickItem 10.A.220010M
22410.02226mm thickItem 10.A.221010M
22510.02228mm thickItem 10.A.22205M
22610.022210mm thickItem 10.A.22305M
22710.022212mm thickItem 10.A.22405M
22810.0222ALLOY STEEL PIPING (ASTM A335 GR. P5) JOINTS Transportation of all piping items from owner's storage points to work site and/ or pre-fabrication yard and to site after pre-fabrication; cutting, grinding, edge preparation of pipes and fittings, like flanges, elbows, tees, reducers etc. to match the mating edges of different thickness; fit-up, bending, welding using approved welding electrodes as per owners quality requirements etc. as per codes/specifications, drawings etc. (alloy steel joints shall be welded by doing root run using TIG welding followed by filler passes by manual / semi-automatic arc welding. The job is to be pre-heated prior to welding and all joints to be stress relieved and fully radiographed, however, charges for stress relieving and radiography shall be paid separately), threading, laying, erection and alignment of pipes at ground level i.e. upto a height of 5 meters on sleepers, pipe racks etc. or upto 5 meters depth in trenches, anchoring wherever required, connecting with equipment, nozzles, steam traps, strainers, orifice assemblies (including tapping upto first block valve), spray nozzles rotameters; tapping for instrument connections like pressure gauges, thermowells, sample connections, vents, drains etc. including fixing of all types of SW valves, gaskets, nuts and bolts, all inline instruments, elbows, tees, flanges, reducers, full coupling or half coupling, earthing strip wherever required; welding prefabricated shoes and supports (including alignment) as per the drawings including preparation of small bore isometric upto 1.5 inch NB, specifications, codes etc. and as per the instructions of the Engineer-in-Charge to his entire satisfaction including supplying of all types of tools and tackles, lifting arrangements, equipment, machineries, all consumables and labour etc. to complete the work in all respects in a workman like manner including area preparation for hot jobs, area cleaning after completion of work, flushing wherever required, cleaning of pipes externally off all foreign materials like weld beads, clamps fixtures etc. used in fabrication as directed by the Engineer-in-Charge. NOTE: Proper safety arrangements for carrying out the job is under contractor's scope and the same has to be complied with as per the dire ctions of the Engineer-in-charge. NOTE: For piping beyond 5 Mtr. elevation above and below ground piping and upto 10Mtr. rates is to be escalated by 20%. For more than 10 Mtr. but upto 15 Mtr. rates is to be escalated by 30%. For more than 15 Mtr but upto 20 Mtr. rates to be escalated by 40% respectively. Requirement of scaffolding to be envisaged and decided by Engineer in Charge as per site requirement and scaffolding item to be paid separately. NOTE: For piping where TIG welding is used for root run only, the rates to be escalated by 15% and where TIG welding is used for entire joints the rates to be escalated by 20%. NOTE: Payment of tapping points will also be made extra on joint basis, as the measurement is on joint basis.Item 10.A.2250
22910.0223\"15 mm NB, Schedule upto 80 \"Item 10.A.226025EA
23010.0223\"15 mm NB, Schedule above 80 \"Item 10.A.227025EA
23110.0223\"20 mm NB, Schedule upto 80 \"Item 10.A.228025EA
23210.0223\"20 mm NB, Schedule above 80 \"Item 10.A.229025EA
23310.0223\"25 mm NB, Schedule upto 80 \"Item 10.A.230025EA
23410.0223\"25 mm NB, Schedule above 80 \"Item 10.A.231025EA
23510.0223\"40mm NB, Schedule above 40 but upto 80 \"Item 10.A.232025EA
23610.0223\"50mm NB, Schedule above 40 but upto 80 \"Item 10.A.233025EA
23710.0223\"80 mm NB, Schedule upto 40 \"Item 10.A.234025EA
23810.0223\"80mm NB, Schedule above 40 but upto 80 \"Item 10.A.235025EA
23910.0224\"100mm NB, Schedule upto 40 \"Item 10.A.236025EA
24010.0224\"150 mm NB, Schedule upto 40 \"Item 10.A.237025EA
24110.0224\"200 mm NB, Schedule above 20 but upto 40 \"Item 10.A.238025EA
24210.0224\"250 mm NB, Schedule above 20 but upto 40 \"Item 10.A.239025EA
24310.0224FABRICATION AND ERECTION OF PIPE SUPPORT / PLATFORMS / DEVITS / STAIR CASE ETC. The job includes getting the materials issued, transportation to work site and handling at site, fabrication at the required size and shape using steel pipes, MS structural / plates etc. by cutting, bevelling and welding including fixing of MS gratings / chequered plates on platform at all elevation by welding, bolting or otherwise to existing members or equipment. This also includes fabrication and fixing of pipe clamps, non-standard bolts etc. inclusive of labour, consumables, tools and tackles and materials required for U-clamps, J-bolts etc. and applying one coat of primer and two coats of high built black bituminous paint and complete in all respect as per drawings, specifications and instructions of the Engineer-in-Charge. (Excluding cost of structural steel).Item 10.A.24005TO
24410.0224DISMANTLING OF STRUCTURALS LIKE PIPE SUPPORT / STAIRWAY / DEVIT ETC. Removal of existing platforms / pipe supports / davits / stairways etc. along with adjacent fittings / members by cutting / debolting or by any other means without damaging the remaining unit and lowering down to the ground including erection of scaffolding, retrieving of all the usable materials and transportation to the storage point as directed by the Engineer-in-Charge.Item 10.A.24105TO
24510.0224FABRICATION OF CARBON STEEL REDUCERS WITH WELDING ELECTRODE E-6013 Preparing drawings and fabrication of the following specials including transportation of materials from owner's storage points to work site and / shop, cutting, edge preparing, welding, as per owner's quality requirements, including supply of all necessary equipment, consumables, labour, tools, tackles, and supervision, work shall be carried out as per the specifications drawings, codes, and instructions to the full satisfaction of the Engineer-in-charge.Item 10.A.2420
24610.0224200 mm NB to below reducer, Schedule upto 40Item 10.A.24301EA
24710.0224250 mm NB to below reducer, Schedule upto 40Item 10.A.24401EA
24810.0224300 mm NB to below reducer, Schedule above 20 but upto 40Item 10.A.24501EA
24910.0225350 mm NB to below reducer, Schedule upto 20Item 10.A.24601EA
25010.0225400 mm NB to below reducer, Schedule upto 20Item 10.A.24701EA
25110.0225450mm NB to below reducer, Schedule upto 20Item 10.A.24801EA
25210.0225STAINLESS STEEL PIPING (GR. SS 300) JOINTS Transportation of all piping items from owner's storage points to work site and/ or pre-fabrication yard and to site after pre-fabrication; cutting, grinding, edge preparation of pipes and fittings, like flanges, elbows, tees, reducers etc. to match the mating edges of different thickness; fit-up, bending, welding using approved welding electrodes as per owners quality requirements etc. as per codes/specifications, drawing etc., threading, laying, erection and alignment of pipes at ground level i.e. upto a height of 5 meters on sleepers, pipe racks etc. or upto 5 meters depth in trenches; anchoring wherever required, connecting with equipment, nozzles, steam traps, strainers, orifice assemblies (including tapping upto first block valve), spray nozzles rotameters; tapping for instrument connections like pressure gauges, thermowells, sample connections, vents, drains etc. including fixing of all types of SW valves, gaskets, nuts and bolts, all inline instruments, elbows, tees, flanges, reducers, full coupling or half coupling, earthing strip wherever required; welding prefabricated shoes and supports (including alignment) as per the drawings, including preparation of small bore isometric upto 1.5 inch NB, specifications, codes etc. and as per the instructions of the Engineer-in-Charge to his entire satisfaction including supplying of all types of tools and tackles, lifting arrangements, equipment, machineries, all consumables a nd labour etc. to complete the work in all respects in a workman like manner including area preparation for hot jobs, area cleaning after completion of work, flushing wherever required, cleaning of pipes externally off all foreign materials like weld beads, clamps fixtures etc. used in fabrication as directed by the Engineer-in-Charge. NOTE : Proper safety arrangements for carrying out the job is under contractor's scope and the same has to be complied with as per the dire ctions of the Engineer- in-Charge. NOTE: For piping beyond 5 Mtr. elevation above and below ground piping and upto 10Mtr. rates is to be escalated by 20%. For more than 10 Mtr. but upto 15 Mtr. rates is to be escalated by 30%. For more than 15 Mtr but upto 20 Mtr. rates to be escalated by 40% respectively. Requirement of scaffolding to be envisaged and decided by Engineer in Charge as per site requirement and scaffolding item to be paid separately. NOTE: For piping where TIG welding is used for root run only, the rates to be escalated by 15% and where TIG welding is used for entire joints the rates to be escalated by 20%. NOTE: Payment of tapping points will also be made extra on joint basis, as the measurement is on joint basis.Item 10.A.2490
25310.0225\"15 mm NB, Schedule upto 40 \"Item 10.A.250050EA
25410.0225\"15 mm NB, Schedule more than 40 but upto 80\"Item 10.A.251050EA
25510.0225\"15 mm NB, Schedule above 80 but upto 120\"Item 10.A.252050EA
25610.0225\"20 mm NB, Schedule upto 40 \"Item 10.A.253050EA
25710.0225\"20 mm NB, Schedule more than 40 but upto 80\"Item 10.A.254050EA
25810.0226\"25 mm NB, Schedule upto 40 \"Item 10.A.255050EA
25910.0226\"25 mm NB, Schedule more than 40 but upto 80\"Item 10.A.256050EA
26010.0226\"40 mm NB, Schedule upto 40 \"Item 10.A.257050EA
26110.0226\"40 mm NB, Schedule more than 40 but upto 80\"Item 10.A.258050EA
26210.0226\"50 mm NB, Schedule upto 40 \"Item 10.A.259050EA
26310.0226\"50 mm NB, Schedule more than 40 but upto 80\"Item 10.A.260050EA
26410.0226\"80 mm NB, Schedule upto 40 \"Item 10.A.261050EA
26510.0226\"80 mm NB, Schedule more than 40 but upto 80\"Item 10.A.262050EA
26610.0226\"100 mm NB, Schedule upto 40 \"Item 10.A.263050EA
26710.0226\"100 mm NB, Schedule more than 40 but upto 80\"Item 10.A.264050EA
26810.0227\"150 mm NB, Schedule upto 40 \"Item 10.A.265050EA
26910.0227\"150 mm NB, Schedule more than 40 but upto 80\"Item 10.A.266050EA
27010.0227\"150 mm NB, Schedule above 80 but upto 120\"Item 10.A.267050EA
27110.0227\"200 mm NB, Schedule upto 40 \"Item 10.A.26805EA
27210.0227\"200 mm NB, Schedule more than 40 but upto 80\"Item 10.A.26905EA
27310.0227\"200 mm NB, Schedule above 80 but upto 120\"Item 10.A.27005EA
27410.0227\"250 mm NB, Schedule upto 40 \"Item 10.A.27105EA
27510.0227\"250 mm NB, Schedule more than 40 but upto 80\"Item 10.A.27205EA
27610.0227\"250 mm NB, Schedule above 80 but upto 120\"Item 10.A.27305EA
27710.0227\"300 mm NB, Schedule upto 40 \"Item 10.A.27405EA
27810.0228\"300 mm NB, Schedule more than 40 but upto 80\"Item 10.A.27505EA
27910.0228\"300 mm NB, Schedule above 80 but upto 120\"Item 10.A.27605EA
28010.0228\"350 mm NB, Schedule upto 40 \"Item 10.A.27705EA
28110.0228\"350 mm NB, Schedule more than 40 but upto 80\"Item 10.A.27805EA
28210.0228\"350 mm NB, Schedule above 80 but upto 120\"Item 10.A.27905EA
28310.0228\"400 mm NB, Schedule upto 40 \"Item 10.A.28005EA
28410.0228\"400 mm NB, Schedule more than 40 but upto 80\"Item 10.A.28105EA
28510.0228\"450 mm NB, Schedule upto 40 \"Item 10.A.28205EA
28610.0228\"450 mm NB, Schedule more than 40 but upto 80\"Item 10.A.28305EA
28710.0228\"500 mm NB, Schedule upto 40 \"Item 10.A.28405EA
28810.0229\"500 mm NB, Schedule more than 40 but upto 80 \"Item 10.A.28505EA
28910.0229\"600 mm NB, Schedule upto 40 \"Item 10.A.28605EA
29010.0229BENDING OF PIPES Bending of pipes: the job includes bending of pipes in the required curvature and supply of all tools, tackles, labour and the supervision to complete the job as per and to the full satisfaction of the Engineer-in-Charge.Item 10.A.2870
29110.022915 mm NBItem 10.A.288010EA
29210.022920 mm NBItem 10.A.289010EA
29310.022925 mm NBItem 10.A.290010EA
29410.022940 mm NBItem 10.A.291010EA
29510.022950 mm NBItem 10.A.292010EA
29610.022980 mm NBItem 10.A.293010EA
29710.0229100 mm NBItem 10.A.29405EA
29810.0229150 mm NBItem 10.A.29505EA
29910.023200 mm NBItem 10.A.29605EA
30010.023FIXING OF LUGS Fabrication of CS / SS lugs by cutting, bending etc. from CS / SS annealed wire etc. (supplied by owner free of cost) and fixing the same by welding on the fabricated panel segments for holding the castable refractories including supply of labour, tools, tackles as per direction of the Engineer-in-Charge.Item 10.A.2970
30110.023CS LugsItem 10.A.298075EA
30210.023SS LugsItem 10.A.299075EA
30310.023BUFFING OF WELD JOINTS Job involves buffing and cleaning of total weld area of the vessel / column etc. using power brush. The job has to be completed in all respect to the entire satisfaction of the Engineer-in-Charge (each length of buffing will be up to width of 150 mm).Item 10.A.300050M
30410.023EXTRA FOR FIXING / REMOVAL OF RTJ FLANGES / BLIND FLANGES Extra for opening / fixing etc. of RTJ flanges / blind flanges / spool pieces for lapping etc.Item 10.A.3010
30510.02350 mmItem 10.A.302010EA
30610.02380 mmItem 10.A.303010EA
30710.023100 mmItem 10.A.304010EA
30810.023150 mmItem 10.A.305030EA
30910.0231200 mmItem 10.A.306050EA
31010.0231250 mmItem 10.A.30702EA
31110.0231300 mmItem 10.A.30802EA
31210.0231600 mmItem 10.A.30902EA
31310.0231DECHOKING OF CW LINE / PRODUCT LINE Dechoking of CW line/product line by poking rod inside or any other Mech. means. This include opening/ removal of spool piece of piping to be dechoked, removal of sludge/ hard deposits etc. by poking rod/ dechoking by steam or any other mechanical means and fixing / erecting the line in position after dechoking, including cutting and fixing suitable size.Item 10.A.3100
31410.0231Dia ½\" to 1\"Item 10.A.311010M
31510.0231Dia 1½\"Item 10.A.312010M
31610.0231Dia 2\"Item 10.A.313010M
31710.0231Dia 4\"Item 10.A.31405M
31810.0231Dia 6\"Item 10.A.31505M
31910.0232Dia 8\"Item 10.A.31605M
32010.0232HOSE CONNECTION & DISCONNECTION JOB Hose connection and disconnection job involves transportation of hoses from the owner's storage to worksite, opening the roll and laying the hose, cutting if required, joining them properly, connection of ends to specified locations/ equipment/ supply points as per production requirement, tying the hose wherever required, opening of end connections and removal of hose after job completion, rolling the same and shifting to scrap yard/ storage point as per direction of EIC. The job also covers lowering, lifting, handling of hoses, erection/ removal of steel scaffolding, area preparation, area cleaning and compliance to all safety norms and work permit systems. Note: The rates shall be applicable for working and connection at all elevation. The hoses, clamps and bolts shall be supplied by IOCL free of charge. This item shall be operative only if hose connection/ disconnection is required by production/ maintenance and is not related to execution of any of the item. Only hose connection or dis-connection shall be treated as half activity.Item 10.A.317075EA
32110.0232PREPARATORY JOBS FOR HOT WORK The job includes opening of flanges, blinding / deblinding by bolting / debolting etc. fabrication of tail blinds, cover plate connections fittings etc., elbow reversing, opening and fixing of plugs from the furnace tube etc., making hose connections and all other arrangements as required for flushing the lines including wedge opening, dewatering after flushing, decoking, isolation etc., boxing up the lines with new gaskets and hot bolting of all the joints during hot circulation and complete the job with supply of tools, tackles, labours and consumables etc. as per direction of the Engineer-in-Charge.Item 10.A.3180
32210.023215 mmItem 10.A.319010EA
32310.023220 mmItem 10.A.320010EA
32410.023225 mmItem 10.A.321010EA
32510.023240 mmItem 10.A.322010EA
32610.023250 mmItem 10.A.323010EA
32710.023280 mmItem 10.A.324010EA
32810.0233100 mmItem 10.A.32502EA
32910.0233150 mmItem 10.A.32602EA
33010.0233200 mmItem 10.A.32702EA
33110.0233250 mmItem 10.A.32802EA
33210.0233600 mmItem 10.A.32902EA
33310.0233STAINLESS STEEL PIPING (GR. SS 400) JOINTS Transportation of all piping items from owner's storage points to work site and/ or pre-fabrication yard and to site after pre-fabrication; cutting, grinding, edge preparation of pipes and fittings, like flanges, elbows, tees, reducers etc. to match the mating edges of different thickness; fit-up, bending, welding using approved welding electrodes as per owners quality requirements etc. as per codes/specifications, drawing etc., threading, laying, erection and alignment of pipes at ground level i.e. upto a height of 5 meters on sleepers, pipe racks etc. or upto 5 meters depth in trenches; anchoring wherever required, connecting with equipment, nozzles, steam traps, strainers, orifice assemblies (including tapping upto first block valve), spray nozzles rotameters; tapping for instrument connections like pressure gauges, thermowells, sample connections, vents, drains etc. including fixing of all types of SW valves, gaskets, nuts and bolts, all inline instruments, elbows, tees, flanges, reducers, full coupling or half coupling, earthing strip wherever required; welding prefabricated shoes and supports (including alignment) as per the drawings, including preparation of small bore isometric upto 1.5 inch NB, specifications, codes etc. and as per the instructions of the Engineer-in-Charge to his entire satisfaction including supplying of all types of tools and tackles, lifting arrangements, equipment, machineries, all consumables a nd labour etc. to complete the work in all respects in a workman like manner including area preparation for hot jobs, area cleaning after completion of work, flushing wherever required, cleaning of pipes externally off all foreign materials like weld beads, clamps fixtures etc. used in fabrication as directed by the Engineer-in-Charge. NOTE : Proper safety arrangements for carrying out the job is under contractor's scope and the same has to be complied with as per the dire ctions of the Engineer- in-Charge. NOTE: For piping beyond 5 Mtr. elevation above and below ground piping and upto 10Mtr. rates is to be escalated by 20%. For more than 10 Mtr. but upto 15 Mtr. rates is to be escalated by 30%. For more than 15 Mtr but upto 20 Mtr. rates to be escalated by 40% respectively. Requirement of scaffolding to be envisaged and decided by Engineer in Charge as per site requirement and scaffolding item to be paid separately. NOTE: For piping where TIG welding is used for root run only, the rates to be escalated by 15% and where TIG welding is used for entire joints the rates to be escalated by 20%. NOTE: Payment of tapping points will also be made extra on joint basis, as the measurement is on joint basis.Item 10.A.3300
33410.0233\"15 mm NB, Schedule more than 40 but upto 80\"Item 10.A.33105EA
33510.0233\"20 mm NB, Schedule more than 40 but upto 80\"Item 10.A.33205EA
33610.0233\"25 mm NB, Schedule more than 40 but upto 80\"Item 10.A.33305EA
33710.0233\"40 mm NB, Schedule more than 40 but upto 80\"Item 10.A.33405EA
33810.0234\"50 mm NB, Schedule more than 40 but upto 80\"Item 10.A.33502EA
33910.0234\"80 mm NB, Schedule more than 40 but upto 80\"Item 10.A.33602EA
34010.0234\"100 mm NB, Schedule upto 40 \"Item 10.A.33702EA
34110.0234\"150 mm NB, Schedule upto 40 \"Item 10.A.33802EA
34210.0234\"200 mm NB, Schedule upto 40 \"Item 10.A.33902EA
34310.0234SCRAP REMOVAL Collection of metallic scrap / unwanted materials such as valves, pipes, bends, plates, structural, gasket sheets, hoses, fasteners etc., from different location and elevations and transporting them to scrap yard or any other place as per instruction of Engineer-in-Charge. Job includes supplying of all types of tools and tackles, lifting arrangements, hydra/ crane, tractor trolley and equipment, machineries all consumables and labour. All jobs are to be carried out as per the instruction and to the full satisfaction of the Engineer-in-Charge. Note: If cutting is required as per site requirement the same shall be paid separately.Item 10.A.34005TO
34410.0234MATERIAL HANDLING WITHIN REFINERY Handling, shifting, stacking etc. of piping and structural material as per job requirement at elevation and as per instruction of En gineer-in-Charge. This item to be operated in case of lifting and lowering of piping/ plates/ structural for repair job to safe working site where fire permit can be given, redundant material removal from position and transporting to store/scrap yard etc. Supply of labour, tools and tackles, lifting arrangements, hydra/ crane, tractor trolley, equipment, consumables etc. will be in contractor's scope. All jobs are to be carried out as per the instruction and to the full satisfaction of the Engineer-in-Charge. (Item should not be operated for area scrap removal).Item 10.A.34105TO
34510.0234INSTALLATION/ REMOVAL OF LEVEL TROLL, FIRE HYDRANT, MONITORS, SAFETY VALVES ETC. The job involves opening of flanged and removal of all types of level troll, fire hydrant and monitor by debolting/ cold/ hot cutting of fasteners wherever required, cleaning, or flange facing, lapping of RTJ rings, level troll, fire Hydrant, monitor, in position with correct direction and providing new gasket (IOCL supplied) including cutting of gaskets if required and finally tightening of the gland to ensure zero leak including hot bolting wherever applicable.Item 10.A.3420
34610.0234Installation (same as 7.1)Item 10.A.3430500KG
34710.0234Removal (same as 7.2)Item 10.A.3440500KG
34810.0235HANDLING / ERECTION OF FABRICATED PIPES / COIL ASSEMBLIES The job includes getting the materials issued, transportation to work-site, handling and care at work-site, erecting the fabricated item at position and fixing, aligning and making connections to the companion pipe etc. And complete in all respect with all labour, tools, tackles and supervision etc. as per the direction of the Engineer-in-Charge.Item 10.A.34502TO
34910.0235Transportation from owner's storage points to work site and/ or pre-fabrication yard and to site after pre-fabrication; cutting, gr inding, edge preparation as per the instructions of the Engineer-in-Charge to his entire satisfaction including supplying of all types of tools and tackles, lifting arrangements, equipment, machineries, all consumables and labour etc. to complete the work in all respects in a workman like manner including area preparation for hot jobs, area cleaning after completion of work, pneumatic testing, cleaning of pipes externally off all foreign materials like weld beads, clamps fixtures etc. used in fabrication as directed by the Engineer-in-Charge. NOTE : Proper safety arrangements for carrying out the job is under contractor's scope and the same has to be complied with as per the dire ctions of the Engineer- in-Charge.Item 10.A.3460
35010.0235Branch size 2 inchItem 10.A.34701EA
35110.0235Branch size 3 inchItem 10.A.34801EA
35210.0235Branch size 4 inchItem 10.A.34901EA
35310.0235Branch size 6 inchItem 10.A.35001EA
35410.0235Branch size 8 inchItem 10.A.35101EA
35510.0235Branch size 10 inchItem 10.A.35201EA
35610.0235Branch size 12 inchItem 10.A.35301EA
35710.0235Branch size 14 inchItem 10.A.35401EA
35810.0236Branch size 16 inchItem 10.A.35501EA
35910.0236Branch size 18 inchItem 10.A.35601EA
36010.0236ALLOY STEEL PIPING (ASTM A335 GR. P1, P2, P11 & P12) JOINTS Transportation of all piping items from owner's storage points to work site and/ or pre-fabrication yard and to site after pre-fabrication; cutting, grinding, edge preparation of pipes and fittings, like flanges, elbows, tees, reducers etc. to match the mating edges of different thickness; fit-up, bending, welding using approved welding electrodes as per owners quality requirements etc. as per codes/specifications, drawings etc. (alloy steel joints shall be welded by doing root run using TIG welding followed by filler passes by manual / semi-automatic arc welding. The job is to be pre-heated prior to welding and all joints to be stress relieved and fully radiographed, however, charges for stress relieving and radiography shall be paid separately), threading, laying, erection and alignment of pipes at ground level i.e. upto a height of 5 meters on sleepers, pipe racks etc. or upto 5 meters depth in trenches, anchoring wherever required, connecting with equipment, nozzles, steam traps, strainers, orifice assemblies (including tapping upto first block valve), spray nozzles rotameters; tapping for instrument connections like pressure gauges, thermowells, sample connections, vents, drains etc. including fixing of all types of SW valves, gaskets, nuts and bolts, all inline instruments, elbows, tees, flanges, reducers, full coupling or half coupling, earthing strip wherever required; welding prefabricated shoes and supports (including alignment) as per the drawings including preparation of small bore isometric upto 1.5 inch NB, specifications, codes etc. and as per the instructions of the Engineer-in-Charge to his entire satisfaction including supplying of all types of tools and tackles, lifting arrangements, equipment, machineries, all consumables and labour etc. to complete the work in all respects in a workman like manner including area preparation for hot jobs, area cleaning after completion of work, flushing wherever required, cleaning of pipes externally off all foreign materials like weld beads, clamps fixtures etc. used in fabrication as directed by the Engineer-in-Charge. NOTE : Proper safety arrangements for carrying out the job is under contractor's scope and the same has to be complied with as per the dire ctions of the Engineer- in-Charge. NOTE: For piping beyond 5 Mtr. elevation above and below ground piping and upto 10Mtr. rates is to be escalated by 20%. For more than 10 Mtr. but upto 15 Mtr. rates is to be escalated by 30%. For more than 15 Mtr but upto 20 Mtr. rates to be escalated by 40% respectively. Requirement of scaffolding to be envisaged and decided by Engineer in Charge as per site requirement and scaffolding item to be paid separately. NOTE: For piping where TIG welding is used for root run only, the rates to be escalated by 15% and where TIG welding is used for entire joints the rates to be escalated by 20%. NOTE: Payment of tapping points will also be made extra on joint basis, as the measurement is on joint basis.Item 10.A.3570
36110.0236\"15 mm NB, Schedule upto 80 \"Item 10.A.35801EA
36210.0236\"15 mm NB, Schedule above 80 \"Item 10.A.35901EA
36310.0236\"20 mm NB, Schedule upto 80 \"Item 10.A.36001EA
36410.0236\"20 mm NB, Schedule above 80 \"Item 10.A.36101EA
36510.0236\"25 mm NB, Schedule upto 80 \"Item 10.A.36201EA
36610.0236\"25 mm NB, Schedule above 80 \"Item 10.A.36301EA
36710.0236\"40 mm NB, Schedule upto 40 \"Item 10.A.36401EA
36810.0236\"40mm NB, Schedule above 40 but upto 80 \"Item 10.A.36501EA
36910.0237\"40 mm NB, Schedule above 120 \"Item 10.A.36601EA
37010.0237\"50 mm NB, Schedule upto 40 \"Item 10.A.36701EA
37110.0237\"50mm NB, Schedule above 40 but upto 80 \"Item 10.A.36801EA
37210.0237\"50 mm NB, Schedule above 120 \"Item 10.A.36901EA
37310.0237\"80 mm NB, Schedule upto 40 \"Item 10.A.37001EA
37410.0237\"80mm NB, Schedule above 40 but upto 80 \"Item 10.A.37101EA
37510.0237\"80 mm NB, Schedule above 120 \"Item 10.A.37201EA
37610.0237\"100mm NB, Schedule upto 40 \"Item 10.A.37301EA
37710.0237\"100mm NB, Schedule above 40 but upto 80 \"Item 10.A.37401EA
37810.0237\"100mm NB, Schedule above 120 \"Item 10.A.37501EA
37910.0238\"150 mm NB, Schedule upto 40 \"Item 10.A.37601EA
38010.0238\"150 mm NB, Schedule more than 40 but upto 80\"Item 10.A.37701EA
38110.0238\"150 mm NB, Schedule above 120\"Item 10.A.37801EA
38210.0238\"200 mm NB, Schedule upto 20 \"Item 10.A.37901EA
38310.0238\"200 mm NB, Schedule above 20 but upto 40 \"Item 10.A.38001EA
38410.0238\"200 mm NB, Schedule more than 40 but upto 80\"Item 10.A.38101EA
38510.0238\"200 mm NB, Schedule above 120\"Item 10.A.38201EA
38610.0238\"250 mm NB, Schedule upto 20 \"Item 10.A.38301EA
38710.0238\"250 mm NB, Schedule above 20 but upto 40 \"Item 10.A.38401EA
38810.0238\"250 mm NB, Schedule more than 40 but upto 80\"Item 10.A.38501EA
38910.0239\"250 mm NB, Schedule above 120\"Item 10.A.38601EA
39010.0239\"300 mm NB, Schedule upto 20 \"Item 10.A.38701EA
39110.0239\"300 mm NB, Schedule above 20 but upto 40 \"Item 10.A.38801EA
39210.0239\"300 mm NB, Schedule more than 40 but upto 80\"Item 10.A.38901EA
39310.0239\"300 mm NB, Schedule above 120\"Item 10.A.39001EA
39410.0239\"350 mm NB, Schedule upto 20 \"Item 10.A.39101EA
39510.0239\"350 mm NB, Schedule above 20 but upto 40 \"Item 10.A.39201EA
39610.0239\"350 mm NB, Schedule more than 40 but upto 80\"Item 10.A.39301EA
39710.0239\"350 mm NB, Schedule above 120\"Item 10.A.39401EA
39810.0239PROVISION OF REINFORCEMENT PAD FOR P-1, P-2, P-11 and P-12 Transportation from owner's storage points to work site and/ or pre-fabrication yard and to site after pre-fabrication; cutting, gri nding, edge preparation as per the instructions of the Engineer-in-Charge to his entire satisfaction including supplying of all types of tools and tackles, lifting arrangements, equipment, machineries, all consumables and labour etc. to complete the work in all respects in a workman like manner including area preparation for hot jobs, area cleaning after completion of work, pneumatic testing, cleaning of pipes externally off all foreign materials like weld beads, clamps fixtures etc. used in fabrication as directed by the Engineer-in-Charge. NOTE : Proper safety arrangements for carrying out the job is under contractor's scope and the same has to be complied with as per the dire ctions of the Engineer- in-Charge.Item 10.A.3950
39910.024Branch size 2 inchItem 10.A.39601EA
40010.024Branch size 3 inchItem 10.A.39701EA
40110.024Branch size 4 inchItem 10.A.39801EA
40210.024Branch size 6 inchItem 10.A.39901EA
40310.024Branch size 8 inchItem 10.A.40001EA
40410.024Branch size 10 inchItem 10.A.40101EA
40510.024Branch size 12 inchItem 10.A.40201EA
40610.024Branch size 14 inchItem 10.A.40301EA
40710.024EXTRA FOR IBR GRADE ALLOY STEEL PIPING (ASTM A335 GR.\"P1, P2, P11 & 12) JOINTS Extra for IBR grade alloy steel piping (ASTM A335 GR. P1, P2, P11 and 12) joints. For IBR piping jobs, the scope of contractor shall be liasoning with IBR authorities including approval of drawings / documents from IBR authorities and also getting the final approval of the job from IBR authorities including payment of any fee or charges to IBR authorities for this purpose.Item 10.A.4040
40810.0241\"15 mm NB, Schedule upto 80 \"Item 10.A.40501EA
40910.0241\"15 mm NB, Schedule above 80 \"Item 10.A.40601EA
41010.0241\"20 mm NB, Schedule upto 80 \"Item 10.A.40701EA
41110.0241\"20 mm NB, Schedule above 80 \"Item 10.A.40801EA
41210.0241\"25 mm NB, Schedule upto 80 \"Item 10.A.40901EA
41310.0241\"25 mm NB, Schedule above 80 \"Item 10.A.41001EA
41410.0241\"40 mm NB, Schedule upto 40 \"Item 10.A.41101EA
41510.0241\"40mm NB, Schedule above 40 but upto 80 \"Item 10.A.41201EA
41610.0241\"40 mm NB, Schedule above 120 \"Item 10.A.41301EA
41710.0241\"50 mm NB, Schedule upto 40 \"Item 10.A.41401EA
41810.0242\"50mm NB, Schedule above 40 but upto 80 \"Item 10.A.41501EA
41910.0242\"50 mm NB, Schedule above 120 \"Item 10.A.41601EA
42010.0242\"80 mm NB, Schedule upto 40 \"Item 10.A.41701EA
42110.0242\"80mm NB, Schedule above 40 but upto 80 \"Item 10.A.41801EA
42210.0242\"80 mm NB, Schedule above 120 \"Item 10.A.41901EA
42310.0242\"100mm NB, Schedule upto 40 \"Item 10.A.42001EA
42410.0242\"100mm NB, Schedule above 40 but upto 80 \"Item 10.A.42101EA
42510.0242\"100mm NB, Schedule above 120 \"Item 10.A.42201EA
42610.0242\"150 mm NB, Schedule upto 40 \"Item 10.A.42301EA
42710.0242\"150 mm NB, Schedule more than 40 but upto 80\"Item 10.A.42401EA
42810.0243\"150 mm NB, Schedule above 120\"Item 10.A.42501EA
42910.0243\"200 mm NB, Schedule upto 20 \"Item 10.A.42601EA
43010.0243\"200 mm NB, Schedule above 20 but upto 40 \"Item 10.A.42701EA
43110.0243\"200 mm NB, Schedule more than 40 but upto 80\"Item 10.A.42801EA
43210.0243\"200 mm NB, Schedule above 120\"Item 10.A.42901EA
43310.0243\"250 mm NB, Schedule upto 20 \"Item 10.A.43001EA
43410.0243\"250 mm NB, Schedule above 20 but upto 40 \"Item 10.A.43101EA
43510.0243\"250 mm NB, Schedule more than 40 but upto 80\"Item 10.A.43201EA
43610.0243\"250 mm NB, Schedule above 120\"Item 10.A.43301EA
43710.0243\"300 mm NB, Schedule upto 20 \"Item 10.A.43401EA
43810.0244\"300 mm NB, Schedule above 20 but upto 40 \"Item 10.A.43501EA
43910.0244\"300 mm NB, Schedule more than 40 but upto 80\"Item 10.A.43601EA
44010.0244\"300 mm NB, Schedule above 120\"Item 10.A.43701EA
44110.0244\"350 mm NB, Schedule upto 20 \"Item 10.A.43801EA
44210.0244\"350 mm NB, Schedule above 20 but upto 40 \"Item 10.A.43901EA
44310.0244\"350 mm NB, Schedule more than 40 but upto 80\"Item 10.A.44001EA
44410.0244\"350 mm NB, Schedule above 120\"Item 10.A.44101EA
44510.0244ALLOY STEEL PIPING (ASTM A335 GR. P22) Transportation of all piping items from owner's storage points to work site and/ or pre-fabrication yard and to site after pre-fabrication; cutting, grinding, edge preparation of pipes and fittings, like flanges, elbows, tees, reducers etc. to match the mating edges of different thickness; fit-up, bending, welding using approved welding electrodes as per owners quality requirements etc. as per codes/specifications, drawings etc. (alloy steel joints shall be welded by doing root run using TIG welding followed by filler passes by manual / semi-automatic arc welding. The job is to be pre-heated prior to welding and all joints to be stress relieved and fully radiographed, however, charges for stress relieving and radiography shall be paid separately), threading, laying, erection and alignment of pipes at ground level i.e. upto a height of 5 meters on sleepers, pipe racks etc. or upto 5 meters depth in trenches, anchoring wherever required, connecting with equipment, nozzles, steam traps, strainers, orifice assemblies (including tapping upto first block valve), spray nozzles rotameters; tapping for instrument connections like pressure gauges, thermowells, sample connections, vents, drains etc. including fixing of all types of SW valves, gaskets, nuts and bolts, all inline instruments, elbows, tees, flanges, reducers, full coupling or half coupling, reinforcement pads, earthing strip wherever required; welding prefabricated shoes and supports (including alignment) as per the drawings including preparation of small bore isometric upto 1.5 inch NB, specifications, codes etc. and as per the instructions of the Engineer-in-Charge to his entire satisfaction including supplying of all types of tools and tackles, lifting arrangements, equipment, machineries, all consumables and labour etc. to complete the work in all respects in a workman like manner including area preparation for hot jobs, area cleaning after completion of work, flushing wherever required, cleaning of pipes externally off all foreign materials like weld beads, clamps fixtures etc. used in fabrication as directed by the Engineer-in-Charge. NOTE : Proper safety arrangements for carrying out the job is under contractor's scope and the same has to be complied with as per the dire ctions of the Engineer- in-Charge. NOTE: For piping beyond 5 Mtr. elevation above and below ground piping and upto 10Mtr. rates is to be escalated by 20%. For more than 10 Mtr. but upto 15 Mtr. rates is to be escalated by 30%. For more than 15 Mtr but upto 20 Mtr. rates to be escalated by 40% respectively. Requirement of scaffolding to be envisaged and decided by Engineer in Charge as per site requirement and scaffolding item to be paid separately. NOTE: For piping where TIG welding is used for root run only, the rates to be escalated by 15% and where TIG welding is used for entire joints the rates to be escalated by 20%.Item 10.A.4420
44610.0244\"15 mm NB, Schedule upto 80 \"Item 10.A.44301M
44710.0244\"15 mm NB, Schedule above 80 \"Item 10.A.44401M
44810.0244\"20 mm NB, Schedule upto 80 \"Item 10.A.44501M
44910.0245\"20 mm NB, Schedule above 80 \"Item 10.A.44601M
45010.0245\"25 mm NB, Schedule upto 80 \"Item 10.A.44701M
45110.0245\"25 mm NB, Schedule above 80 \"Item 10.A.44801M
45210.0245\"40 mm NB, Schedule upto 40 \"Item 10.A.44901M
45310.0245\"40mm NB, Schedule above 40 but upto 80 \"Item 10.A.45001M
45410.0245\"40 mm NB, Schedule above 120 \"Item 10.A.45101M
45510.0245\"50 mm NB, Schedule upto 40 \"Item 10.A.45201M
45610.0245\"50mm NB, Schedule above 40 but upto 80 \"Item 10.A.45301M
45710.0245\"50 mm NB, Schedule above 120 \"Item 10.A.45401M
45810.0245\"80 mm NB, Schedule upto 40 \"Item 10.A.45501M
45910.0246\"80mm NB, Schedule above 40 but upto 80 \"Item 10.A.45601M
46010.0246\"80 mm NB, Schedule above 120 \"Item 10.A.45701M
46110.0246\"100mm NB, Schedule upto 40 \"Item 10.A.45801M
46210.0246\"100mm NB, Schedule above 40 but upto 80 \"Item 10.A.45901M
46310.0246\"100mm NB, Schedule above 120 \"Item 10.A.46001M
46410.0246\"150 mm NB, Schedule upto 40 \"Item 10.A.46101M
46510.0246\"150 mm NB, Schedule more than 40 but upto 80\"Item 10.A.46201M
46610.0246\"150 mm NB, Schedule above 120\"Item 10.A.46301M
46710.0246\"200 mm NB, Schedule upto 20 \"Item 10.A.46401M
46810.0246\"200 mm NB, Schedule above 20 but upto 40 \"Item 10.A.46501M
46910.0247\"200 mm NB, Schedule more than 40 but upto 80\"Item 10.A.46601M
47010.0247\"200 mm NB, Schedule above 120\"Item 10.A.46701M
47110.0247\"250 mm NB, Schedule upto 20 \"Item 10.A.46801M
47210.0247\"250 mm NB, Schedule above 20 but upto 40 \"Item 10.A.46901M
47310.0247\"250 mm NB, Schedule more than 40 but upto 80\"Item 10.A.47001M
47410.0247\"250 mm NB, Schedule above 120\"Item 10.A.47101M
47510.0247\"300 mm NB, Schedule upto 20 \"Item 10.A.47201M
47610.0247\"300 mm NB, Schedule above 20 but upto 40 \"Item 10.A.47301M
47710.0247\"300 mm NB, Schedule more than 40 but upto 80\"Item 10.A.47401M
47810.0247\"300 mm NB, Schedule above 120\"Item 10.A.47501M
47910.0248\"350 mm NB, Schedule upto 20 \"Item 10.A.47601M
48010.0248\"350 mm NB, Schedule above 20 but upto 40 \"Item 10.A.47701M
48110.0248\"350 mm NB, Schedule more than 40 but upto 80\"Item 10.A.47801M
48210.0248\"350 mm NB, Schedule above 120\"Item 10.A.47901M
48310.0248FABRICATION & FIXING OF FABRIC BELLOW The job involves removal of old fabric bellow from the expansion joint, cleaning of the bellow and fixing of new fabric bellow with bellow as per instruction of Engineer-in-charge including tools and tackles and all manpower. Dismantling/ erection of bellow assembly and supply of new fabric bellow shall be in the scope of IOCL.Item 10.A.480050M2
48410.0248CUTTING VARIOUS SIZES OF GASKETS Job involves collection of gasket sheets from materials dept, bringing them to drum plant or wherever the gasket machine is available, install the die required, cut the reqd quantities of gaskets, as advised by the Engineer-in-Charge.Item 10.A.4810
48510.024825 mmItem 10.A.48201EA
48610.024840 mmItem 10.A.48301EA
48710.024850 mmItem 10.A.48401EA
48810.024980 mmItem 10.A.48501EA
48910.0249100 mmItem 10.A.48601EA
49010.0249150 mmItem 10.A.48701EA
49110.0249200 mmItem 10.A.48801EA
49210.0249250 mmItem 10.A.48901EA
49310.0249300 mmItem 10.A.49001EA
49410.0249350 mmItem 10.A.49101EA
49510.0249400 mmItem 10.A.49201EA
49610.0249450 mmItem 10.A.49301EA
49710.0249500 mmItem 10.A.49401EA
49810.025600 mmItem 10.A.49501EA
49910.025700 mmItem 10.A.49601EA
50010.025750 mmItem 10.A.49701EA
50110.025FLAME HEATING BRG, HUB AND FURNACE PLUG ETC. Heating of bearings, hubs, furnace header etc. by gas at different elevations as per requirement and instruction of the Engineer-in-Charge. including supply of all tools, tackles, equipment#s, labour, consumables etc.Item 10.A.498025H
50210.03B DISMATNLING/INSTALLATION OF VALVESItem 10.B
50310.03REMOVAL OF FLANGED / RTJ VALVES Dismantling and removal of all types of flanged including RTJ valves from pipelines at ground level i.e. up to a height of 5 meters on sleepers, pipe racks etc. or up to 5 meters depth in trenches including removal of gaskets, nut bolts etc. and transportation either to owner's storage point / workshop and / or scrapyard including loosening of studs, disconnecting earthing protection all complete as per direction of the Engineer-in-Charge including all labour, tools, tackles, consumables and supervision etc.Item 10.B.101500KG
50410.03INSTALLATION OF FLANGED / RTJ VALVES Transportation of all types of flanged / RTJ valves, gaskets, nut bolts etc. either from owner's storage point to workshop and / or worksite and installation of valves at ground level i.e. up to a height of 5 meters on sleepers, pipe racks etc. or up to 5 meters depth in trenches including assembly of valve accessories, cleaning of flanged faces, lapping of RTJ rings, cutting the gaskets to proper size, placing the gaskets / RTJ ring properly, tightening of studs, providing earthing protection by way of fixing strips, all complete as per drawings and direction of the Engineer-in-Charge including all labour, tools, tackles, consumables and supervision etc.Item 10.B.20
50510.03For Valves (other than RTJ)Item 10.B.301500KG
50610.03For RTJ ValvesItem 10.B.40250KG
50710.03EXTRA FOR OVER HEAD INSTALLATION / REMOVAL OF FLANGED / RTJ VALVES AT ADDITIONAL HEIGHTS Extra for overhead installation / removal of flanged valves of all metallurgies for every additional height of ten metres or part thereof. NOTE: Since \"Lift-KG\" unit is not available in SAP, hence for estimate unit is to be taken as KG.Item 10.B.50
50810.0301InstallationItem 10.B.60250KG
50910.0301RemovalItem 10.B.70250KG
51010.04C STEEL SCAFFOLDING JOBSItem 10.C
51110.04<H><U>Scaffolding Jobs To Be Done As Follows:-</></> <H>1)For Normal Jobs,(100%) Cup-Lok Type of Scaffolding to be erected at site.</> <H>2)Only in Exceptional Cases, Where Erection of Cup-lok Type of Scaffolding is not possible at site due to in accessibility or any other reason,Normal Scaffolding Pipes with Clamp arrangement may be allowed after clearance from EIC as described</>.Item 10.C.10
51210.04STEEL SCAFFLODING MATERIALS IN CONTRACTOR'S SCOPE The job includes transportation of scaffolding materials in contractor's scope of supply, erection of scaffolding at site covering the areas specified including providing vertical posts of pipes at inter distance of 1.5 m and horizontal numbers at a inter distance of 0.5 to 0.75 m, providing tie rods at corners to give sufficient strength to the structure, placing the wooden / steel planks / FRP gratings on top for making sufficient area. Dismantling scaffolding after completion of job and returning the scaffolding material to specified place including all tools, tackles, consumables, labours and contractor's supervision as directed by the Engineer-in-Charge 1. For measurement in SQM: 2 (length + width) X height area covered by the scaffolding is to be taken. 2. Scaffolding measurement to be done by breaking the height into parts as per height slab mentioned below and adopting respective rates against mentioned height slabs.Item 10.C.20
51310.04Upto 6 MItem 10.C.301500M2
51410.04Above 6 m upto 10 mItem 10.C.40500M2
51510.0401Above 10 m upto 20 mItem 10.C.50100M2
51610.0401Above 20 m upto 30 mItem 10.C.6025M2
51710.0401Above 30 m upto 40 mItem 10.C.7025M2
51810.0401Above 40 m upto 50 mItem 10.C.8025M2
51910.0401Intermediate plate formItem 10.C.90100M2
52010.05D DISMANLTING OF STRUCTUREItem 10.D
52110.05DISMANTLING OF STRUCTURALS LIKE PIPE SUPPORT / STAIRWAY / DEVIT ETC. Removal of existing platforms / pipe supports / davits / stairways etc. along with adjacent fittings / members by cutting / debolting or by any other means without damaging the remaining unit and lowering down to the ground including erection of scaffolding, retrieving of all the usable materials and transportation to the storage point as directed by the Engineer-in-Charge.Item 10.D.102TO
52210.05FABRICATION AND ERECTION OF PIPE SUPPORT / PLATFORMS / DEVITS / STAIR CASE ETC. The job includes getting the materials issued, transportation to work site and handling at site, fabrication at the required size and shape using steel pipes, MS structural / plates etc. by cutting, bevelling and welding including fixing of MS gratings / chequered plates on platform at all elevation by welding, bolting or otherwise to existing members or equipment. This also includes fabrication and fixing of pipe clamps, non-standard bolts etc. inclusive of labour, consumables, tools and tackles and materials required for U-clamps, J-bolts etc. and applying one coat of primer and two coats of high built black bituminous paint and complete in all respect as per drawings, specifications and instructions of the Engineer-in-Charge. (Excluding cost of structural steel).Item 10.D.202TO
52310.05INSTALLATION OF VESSELS / COLUMNS / DRUMS / FILTERS UPTO 5 MT Transportation of vessel/ columns/ filters/ drums etc. from owner's storage point to worksite, assembly of parts, sub-assemblies (including internals), erection at all elevations, aligning, tightening of bolts, grouting, cleaning, hydrotesting and flushing by water, draining, drying by compressed air and installation of all mountings and completing the works in all respects including earthing protection by way of fixing strips and electrodes as per drawings and specifications. Job also includes supplying of all types of tools, tackles, lifting arrangements, cranes, tractor trolley and equipment, machineries all consumables and labour to complete the job in a workman like manner, erection and removal of steel scaffolding wherever required, area preparation for hot job and area cleaning after completion of work including blinding, deblinding, removal of insulation, gas cutting of bolts, chipping of foundation, flushing wherever required. All jobs are to be carried out as per the instruction and to the full satisfaction of the Engineer-in-Charge.Item 10.D.302TO
52410.05INSTALLATION OF VESSELS/ COLUMNS/ DRUMS/ FILTERS MORE THAN 5 MT AND UPTO 10 MT Transportation of vessel/ columns/ filters/ drums etc. from owner's storage point to worksite, assembly of parts, sub-assemblies (including internals), erection at all elevations, aligning, tightening of bolts, grouting, cleaning, hydrotesting and flushing by water, draining, drying by compressed air and installation of all mountings and completing the works in all respects including earthing protection by way of fixing strips and electrodes as per drawings and specifications. Job also includes supplying of all types of tools, tackles, lifting arrangements, cranes, tractor trolley and equipment, machineries all consumables and labour to complete the job in a workman like manner, erection and removal of steel scaffolding wherever required, area preparation for hot job and area cleaning after completion of work including blinding, deblinding, removal of insulation, gas cutting of bolts, chipping of foundation, flushing wherever required. All jobs are to be carried out as per the instruction and to the full satisfaction of the Engineer-in-Charge.Item 10.D.402TO
52510.06E SHUTDOWN FACTORItem 10.E
52610.06Shutdown factor-25%Item 10.E.102.56407e+06LS

AI Tender Summary

OUR REF NO 23420375
AUTHORITY Boards / Undertakings / PSU
TENDER VALUE 1.32 Crore
LAST DATE 04-02-2020
Authority
Authority Name Indian Oil Corporation Limited
Work Description Tender For Mech Jobs For Hgu / Dhdt / Sru Shutdown At Bgr, Iocl -2 Mech Jobs For Hgu / Dhdt / Sru 3 A Misc Piping & Other Jobs 4 Dismantling Of Carbon Steel / Alloy Steel Piping By Hot Work ( Insulated / Uninsulated ) Dismantling And Removal Of Above Ground, Overhead Under Ground ( Upto Depth Of 5M ) Redundant, Steam Traced Pipelines, Insulated And U Ninsulated, Of Carbon Steel / Alloy Steel By Gas Cutting Or By Grinder From Various Locations Such As Pipe Racks, Columns, Pump House, Vessels, Heaters, Heat Exchangers, Desalter Etc. Upto A Height Of 5 Meters Including, Removal Of Insulation Material, All On Line Instruments, Fittings, Flanges, Valves, Vents, Drains, Branching Etc.; Lowering Down The Same To Ground Level With Due Care So That No Other Piping, Equipment#S, Machinery#S Etc. Is Damaged; Cutting Into Pieces If Required; Segregating For Reclaiming Useful Fittings Such As Bends, Flanges, Valves, Instruments Etc. By Unbolting, Gas Cutting, Cold Cutting Etc.; Transporting And Stacking The Salvageable Useful Materials To Workshop / Instrument Workshop / Store Or As Per The Direction Of The Engineer-In-Charge And Shifting The Scrap Pipes Etc. To Scrap Yard Or Any Other Location Within Refinery Premises And Completing The Job As Per The Instructions Of Engineer-In-Charge. Job Also Includes Supplying Of All Types Of Tools And Tackles, Lifting Arrangements, Equipment, Machineries, All Consumables And Labour Etc. To Complete The Work In All Respects In A Workman Like Manner Including Area Preparation, Taking Clearance For Hot Jobs, Blinding And De-Blinding, Area Cleaning After Completion Of Work, Flushing Wherever Required As Directed By The Engineer-In-Charge. Note : 1. Proper Safety Arrangements For Carrying Out The Job Is Under Contractors Scope And The Same Has To Be Complied With As Per The D Irections Of The Engineer- In-Charge. 2. Salvaging Of Useful Fitting From Redundant Pipe, If Done, Will Be Paid Under Separate Item. 3. Civil Works ( Excavation And Back Filling ) For Underground Dismantling Shall Be Paid Under Separate Item From Civil Sor. Note: For Piping Beyond 5 Mtr. Elevation Above And Below Ground Piping And Upto 10Mtr. Rates Is To Be Escalated By 20%. For More Than 10 Mtr. But Upto 15 Mtr. Rates Is To Be Escalated By 30%. For More Than 15 Mtr But Upto 20 Mtr. Rates To Be Escalated By 40% Respectively. Requirement Of Scaffolding To Be Envisaged And Decided By Engineer In Charge As Per Site Requirement And Scaffolding Item To Be Paid Separately. 5 15 Mm Nb 6 20 Mm Nb 7 25 Mm Nb 8 40 Mm Nb 9 50 Mm Nb 10 80 Mm Nb 11 100 Mm Nb 12 150 Mm Nb 13 200 Mm Nb 14 250 Mm Nb 15 300 Mm Nb 16 350 Mm Nb 17 400 Mm Nb 18 450 Mm Nb 19 500 Mm Nb 20 600 Mm Nb 21 Cold Cutting Of Carbon / Alloy Steel Pipe Lines ( Insulated / Uninsulated ) Cold Cutting And Removal Of Above Ground / Overhead / Underground In Tranches ( Upto 5 Meters Depth ) Insulated Or Uninsulated Pipelines Of Carbon Steel / Alloy Steel / And / Or Any Other Type From Various Location Such As Pipe Racks, Columns, Pump House, Vessels, Heaters, Heat Exchangers, Desalters Etc. Upto A Height Of 5 Meters Including Removal Of Insulation Materials, All On Line Instruments, Fittings, Flanges, Valves, Vents, Drains, Branching Etc.; Lowering Down / Lifting The Same To Ground Level With Due Care So That No Other Piping, Equipment#S, Machinery#S Etc. Is Damaged; Cutting Into Pieces If Required; Segregating For Reclaiming Useful Fittings Such As Bends, Flanges, Valves, Instruments Etc. By Unbolting, Gas Cutting, Cold Cutting Etc. Transporting And Stacking The Salvageable Useful Materials To Workshop / Instrument Workshop / Store Or As Per The Direction Of The Engineer-In-Charge And Shifting The Scrap Pipes Etc. To Scrap Yard Or Any Other Location Within Refinery Premises All Complete As Per The Instructions Of Engineer-In-Charge.°° Job Also Includes Supplying Of All Types Of Tools And Tackles, Lifting Arrangements, Equipment, Machineries, All Consumables And Labour Etc. To Complete The Work In All Respects In A Workman Like Manner Including Area Preparation, Taking Clearance For Hot Jobs, Blinding And Deblinding Area Cleaning After Completion Of Work, Flushing Wherever Required As Directed By The Engineer-In-Charge. Note : 1. Proper Safety Arrangements For Carrying Out The Job Is Under Contractors Scope And The Same Has To Be Complied With As Per The D Irections Of The Engineer- In-Charge. 2. Salvaging Of Useful Fitting From Redundant Pipe, If Done, Will Be Paid Under Separate Item. 3. Civil Works ( Excavation And Back Filling ) For Underground Dismantling Shall Be Paid Under Separate Item From Civil Sor. Note: For Piping Beyond 5 Mtr. Elevation Above And Below Ground Piping And Upto 10Mtr. Rates Is To Be Escalated By 20%. For More Than 10 Mtr. But Upto 15 Mtr. Rates Is To Be Escalated By 30%. For More Than 15 Mtr But Upto 20 Mtr. Rates To Be Escalated By 40% Respectively. Requirement Of Scaffolding To Be Envisaged And Decided By Engineer In Charge As Per Site Requirement And Scaffolding Item To Be Paid Separately. 22 15 Mm Nb 23 20 Mm Nb 24 25 Mm Nb 25 40 Mm Nb 26 50 Mm Nb 27 80 Mm Nb 28 100 Mm Nb 29 150 Mm Nb 30 200 Mm Nb 31 250 Mm Nb 32 300 Mm Nb 33 350 Mm Nb 34 400 Mm Nb 35 450 Mm Nb 36 500 Mm Nb 37 Fixing / Removal Of Flanges / Blind Flanges Of Rating Upto 300# Opening / Fixing Etc. Of Flanges / Blind Flanges / Spool Pieces At The Two Flange Joint ( Rating Upto 300# ) As And When Required For Elbow Reversing, Wedge Opening Etc. Or Any Other Job Including Handling Of Flanges And Preparation Of Gaskets From The Sheet Including Tools And Tackles, Consumables, Supervision Etc. And As Per Direction Of The Engineer-In-Charge. 38 15 Mm 39 20 Mm 40 25 Mm 41 40 Mm 42 50 Mm 43 80 Mm 44 100 Mm 45 150 Mm 46 200 Mm 47 250 Mm 48 300 Mm 49 350 Mm 50 400 Mm 51 450 Mm 52 500 Mm 53 600 Mm 54 Fixing / Removal Of Flanges / Blind Flanges Of Rating More Than 300# And Upto 600# Opening / Fixing Etc. Of Flanges / Blind Flanges / Spool Pieces At The Two Flange Joint ( Rating More Than 300# And Upto 600# ) As And When Required For Elbow Reversing, Wedge Opening Etc. Or Any Other Job Including Handling Of Flanges And Preparation Of Gaskets From The Sheet Including Tools And Tackles, Consumables, Supervision Etc. And As Per Direction Of The Engineer-In-Charge. 55 15 Mm 56 20 Mm 57 25 Mm 58 40 Mm 59 50 Mm 60 80 Mm 61 100 Mm 62 150 Mm 63 200 Mm 64 250 Mm 65 300 Mm 66 350 Mm 67 Dismantling Of Stainless Steel Piping By Hot Work ( Insulated / Uninsulated ) Dismantling And Removal Of Above Ground / Overhead / Underground In Trenches ( Upto 5 M ) Redundant, Steam Traced Pipelines, Insulated And Uninsulated Of Stainless Steel By Grinding / Gouging / Plasma Cutting From Various Locations Such As Pipe Racks, Columns, Pump House, Vessels, Heaters, Heat Exchangers, Desalter Etc. Upto A Height Of 5 Meters Including Removal Of Insulation Materials All On Line Instruments, Fittings, Flanges, Valves, Vents, Drains, Branching Etc.; Lowering Down The Same To Ground Level With Due Care So That No Other Piping, Equipment#S, Machinery#S Etc. Is Damaged; Cutting Into Pieces If Required; Segregating For Reclaiming Useful Fittings Such As Bends, Flanges, Valves, Instruments Etc. By Unbolting, Gas Cutting, Cold Cutting Etc.; Transporting And Stacking The Salvageable Useful Materials To Workshop / Instrument Workshop / Store Or As Per The Direction Of The Engineer-In-Charge And Shifting The Scrap Pipes Etc. To Scrap Yard Or Any Other Location Within Refinery Premises All Complete As Per The Instructions Of Engineer In-Charge. Job Also Includes Supplying Of All Types Of Tools And Tackles, Lifting Arrangements, Equipment, Machineries, All Consumables And Labour Etc. To Complete The Work In All Respects In A Workman Like Manner Including Area Preparation, Taking Clearance For Hot Jobs, Blinding And Deblinding Area Cleaning After Completion Of Work, Flushing Wherever Required As Directed By The Engineer-In-Charge. Note : 1. Proper Safety Arrangements For Carrying Out The Job Is Under Contractors Scope And The Same Has To Be Complied With As Per The D Irections Of The Engineer- In-Charge. 2. Salvaging Of Useful Fitting From Redundant Pipe, If Done, Will Be Paid Under Separate Item. 3. Civil Works ( Excavation And Back Filling ) For Underground Dismantling Shall Be Paid Under Separate Item From Civil Sor. Note: For Piping Beyond 5 Mtr. Elevation Above And Below Ground Piping And Upto 10Mtr. Rates Is To Be Escalated By 20%. For More Than 10 Mtr. But Upto 15 Mtr. Rates Is To Be Escalated By 30%. For More Than 15 Mtr But Upto 20 Mtr. Rates To Be Escalated By 40% Respectively. Requirement Of Scaffolding To Be Envisaged And Decided By Engineer In Charge As Per Site Requirement And Scaffolding Item To Be Paid Separately. 68 20 Mm Nb 69 25 Mm Nb 70 40 Mm Nb 71 50 Mm Nb 72 80 Mm Nb 73 100 Mm Nb 74 150 Mm Nb 75 200 Mm Nb 76 250 Mm Nb 77 Carbon Steel Piping Joints For Hydrocarbon Service ( With Welding Electrode E-6010 / E-7018 ) Transportation Of All Piping Items From Owners Storage Points To Work Site And / Or Pre-Fabrication Yard And To Site After Pre-Fabrication; Cutting, Grinding, Edge Preparation Of Pipes And Fittings, Like Flanges, Elbows, Tees, Reducers Etc. To Match The Mating Edges Of Different Thickness; Fit-Up, Bending, Welding Using Approved Welding Electrodes As Per Owners Quality Requirements Etc. As Per Codes / Specifications, Drawing Etc., Threading, Laying, Erection And Alignment Of Pipes At Ground Level I.E. Upto A Height Of 5 Meters On Sleepers, Pipe Racks Etc. Or Upto 5 Meters Depth In Trenches; Connecting With Equipment, Nozzles, Steam Traps, Strainers, Orifice Assemblies ( Including Tapping Upto First Block Valve ) , Spray Nozzles Rotameters; Tapping For Instrument Connections Like Pressure Gauges, Thermowells, Sample Connections, Vents, Drains Etc. Including Fixing Of All Types Of Sw Valves, Gaskets, Nuts And Bolts, All Inline Instruments, Elbows, Tees, Flanges, Reducers, Full Coupling Or Half Coupling, Earthing Strip Wherever Required; Welding Prefabricated Shoes And Supports ( Including Alignment ) As Per The Drawings, Including Preparation Small Bore Isometric Upto 1.5 Inch Nb, Specifications, Codes Etc. And As Per The Instructions Of The Engineer-In-Charge To His Entire Satisfaction Including Supplying Of All Types Of Tools And Tackles, Lifting Arrangements, Equipment, Machineries, All Consumables And Labour Etc. To Complete The Work In All Respects In A Workman Like Manner Including Area Preparation For Hot Jobs, Area Cleaning After Completion Of Work, Flushing Wherever Required, Cleaning Of Pipes Externally Off All Foreign Materials Like Weld Beads, Clamps Fixtures Etc. Used In Fabrication As Directed By The Engineer-In-Charge. Note : Proper Safety Arrangements For Carrying Out The Job Is Under Contractors Scope And The Same Has To Be Complied With As Per The Dire Ctions Of The Engineer- In-Charge. Note: For Piping Beyond 5 Mtr. Elevation Above And Below Ground Piping And Upto 10Mtr. Rates Is To Be Escalated By 20%. For More Than 10 Mtr. But Upto 15 Mtr. Rates Is To Be Escalated By 30%. For More Than 15 Mtr But Upto 20 Mtr. Rates To Be Escalated By 40% Respectively. Requirement Of Scaffolding To Be Envisaged And Decided By Engineer In Charge As Per Site Requirement And Scaffolding Item To Be Paid Separately. Note: For Piping Where Tig Welding Is Used For Root Run Only, The Rates To Be Escalated By 15% And Where Tig Welding Is Used For Entire Joints The Rates To Be Escalated By 20%. Note: Payment Of Tapping Points Will Also Be Made Extra On Joint Basis, As The Measurement Is On Joint Basis. 78 15 Mm Nb, Schedule Upto 80 79 15 Mm Nb, Schedule Above 80 But Upto 160 80 20 Mm Nb, Schedule Upto 80 81 20 Mm Nb, Schedule Above 80 But Upto 160 82 25 Mm Nb, Schedule Upto 80 83 25 Mm Nb, Schedule Above 80 But Upto 160 84 40 Mm Nb, Schedule Upto 80 85 40 Mm Nb, Schedule Above 80 But Upto 160 86 50 Mm Nb, Schedule More Than 40 But Upto 80 87 50 Mm Nb, Schedule Above 80 But Upto 160 88 80 Mm Nb, Schedule Upto 40 89 80 Mm Nb, Schedule More Than 40 But Upto 80 90 80 Mm Nb, Schedule Above 80 But Upto 160 91 100 Mm Nb, Schedule Upto 40 92 100 Mm Nb, Schedule More Than 40 But Upto 80 93 100 Mm Nb, Schedule Above 80 But Upto 160 94 150 Mm Nb, Schedule Upto 40 95 150 Mm Nb, Schedule More Than 40 But Upto 80 96 150 Mm Nb, Schedule Above 80 But Upto 120 97 200 Mm Nb, Schedule Above 20 But Upto 40 98 200 Mm Nb, Schedule More Than 40 But Upto 80 99 200 Mm Nb, Schedule Above 80 But Upto 120 100 250 Mm Nb, Schedule Above 20 But Upto 40 101 250 Mm Nb, Schedule More Than 40 But Upto 80 102 250 Mm Nb, Schedule Above 80 But Upto 120 103 300 Mm Nb, Schedule Upto 20 104 300 Mm Nb, Schedule Above 20 But Upto 40 105 300 Mm Nb, Schedule More Than 40 But Upto 80 106 350 Mm Nb, Schedule Upto 20 107 350 Mm Nb, Schedule Above 20 But Upto 40 108 350 Mm Nb, Schedule More Than 40 But Upto 80 109 400 Mm Nb, Schedule Upto 20 110 400 Mm Nb, Schedule Above 20 But Upto 40 111 450 Mm Nb, Schedule Upto 20 112 450 Mm Nb, Schedule Above 20 But Upto 40 113 500 Mm Nb, Schedule Upto 20 114 500 Mm Nb, Schedule Above 20 But Upto 40 115 600 Mm Nb, Schedule Upto 20 116 600 Mm Nb, Schedule Above 20 But Upto 40 117 Cs Ppg Joints Nhc Electd E-6013 Transportation Of All Piping Items From Owners Storage Points To Work Site And / Or Pre-Fabrication Yard And To Site After Pre-Fabrication; Cutting, Grinding, Edge Preparation Of Pipes And Fittings, Like Flanges, Elbows, Tees, Reducers Etc. To Match The Mating Edges Of Different Thickness; Fit-Up, Bending, Welding Using Approved Welding Electrodes As Per Owners Quality Requirements Etc. As Per Codes / Specifications, Drawing Etc., Threading, Laying, Erection And Alignment Of Pipes At Ground Level I.E. Upto A Height Of 5 Meters On Sleepers, Pipe Racks Etc. Or Upto 5 Meters Depth In Trenches; Connecting With Equipment, Nozzles, Steam Traps, Strainers, Orifice Assemblies ( Including Tapping Upto First Block Valve ) , Spray Nozzles Rotameters; Tapping For Instrument Connections Like Pressure Gauges, Thermowells, Sample Connections, Vents, Drains Etc. Including Fixing Of All Types Of Sw Valves, Gaskets, Nuts And Bolts, All Inline Instruments, Elbows, Tees, Flanges, Reducers, Full Coupling Or Half Coupling, Earthing Strip Wherever Required; Welding Prefabricated Shoes And Supports ( Including Alignment ) As Per The Drawings, Including Preparation Small Bore Isometric Upto 1.5 Inch Nb, Specifications, Codes Etc. And As Per The Instructions Of The Engineer-In-Charge To His Entire Satisfaction Including Supplying Of All Types Of Tools And Tackles, Lifting Arrangements, Equipment, Machineries, All Consumables And Labour Etc. To Complete The Work In All Respects In A Workman Like Manner Including Area Preparation For Hot Jobs, Area Cleaning After Completion Of Work, Flushing Wherever Required, Cleaning Of Pipes Externally Off All Foreign Materials Like Weld Beads, Clamps Fixtures Etc. Used In Fabrication As Directed By The Engineer-In-Charge. Note : Proper Safety Arrangements For Carrying Out The Job Is Under Contractors Scope And The Same Has To Be Complied With As Per The Dire Ctions Of The Engineer- In-Charge. Note: For Piping Beyond 5 Mtr. Elevation Above And Below Ground Piping And Upto 10Mtr. Rates Is To Be Escalated By 20%. For More Than 10 Mtr. But Upto 15 Mtr. Rates Is To Be Escalated By 30%. For More Than 15 Mtr But Upto 20 Mtr. Rates To Be Escalated By 40% Respectively. Requirement Of Scaffolding To Be Envisaged And Decided By Engineer In Charge As Per Site Requirement And Scaffolding Item To Be Paid Separately. Note: For Piping Where Tig Welding Is Used For Root Run Only, The Rates To Be Escalated By 15% And Where Tig Welding Is Used For Entire Joints The Rates To Be Escalated By 20%. Note: Payment Of Tapping Points Will Also Be Made Extra On Joint Basis, As The Measurement Is On Joint Basis. 118 15 Mm Nb, Schedule Upto 80 119 15 Mm Nb, Schedule Above 80 But Upto 160 120 20 Mm Nb, Schedule Upto 80 121 20 Mm Nb, Schedule Above 80 But Upto 160 122 25 Mm Nb, Schedule Upto 80 123 25 Mm Nb, Schedule Above 80 But Upto 160 124 40 Mm Nb, Schedule Upto 80 125 40 Mm Nb, Schedule Above 80 But Upto 160 126 50 Mm Nb, Schedule More Than 40 But Upto 80 127 50 Mm Nb, Schedule Above 80 But Upto 160 128 80 Mm Nb, Schedule More Than 40 But Upto 80 129 80 Mm Nb, Schedule Above 80 But Upto 160 130 100 Mm Nb, Schedule Upto 40 131 100 Mm Nb, Schedule More Than 40 But Upto 80 132 150 Mm Nb, Schedule Upto 40 133 150 Mm Nb, Schedule More Than 40 But Upto 80 134 200 Mm Nb, Schedule Above 20 But Upto 40 135 200 Mm Nb, Schedule More Than 40 But Upto 80 136 250 Mm Nb, Schedule Above 20 But Upto 40 137 250 Mm Nb, Schedule More Than 40 But Upto 80 138 300 Mm Nb, Schedule Above 20 But Upto 40 139 300 Mm Nb, Schedule More Than 40 But Upto 80 140 400 Mm Nb, Schedule Above 20 But Upto 40 141 400 Mm Nb, Schedule More Than 40 But Upto 80 142 450 Mm Nb, Schedule Above 20 But Upto 40 143 450 Mm Nb, Schedule Above 40 But Upto 80 144 500 Mm Nb, Schedule Above 20 But Upto 40 145 500 Mm Nb, Schedule Above 40 But Upto 80 146 Carbon Steel Piping For Non-Hydrocarbon Service ( With Welding Electrode E-6013 ) Transportation Of All Piping Items From Owners Storage Points To Work Site And / Or Pre-Fabrication Yard And To Site After Pre-Fabrication; Cutting, Grinding, Edge Preparation Of Pipes And Fittings, Like Flanges, Elbows, Tees, Reducers Etc. To Match The Mating Edges Of Different Thickness; Fit-Up, Bending, Welding Using Approved Welding Electrodes As Per Owners Quality Requirements Etc. As Per Codes / Specifications, Drawing Etc., Threading, Laying, Erection And Alignment Of Pipes At Ground Level I.E. Upto A Height Of 5 Meters On Sleepers, Pipe Racks Etc. Or Upto 5 Meters Depth In Trenches; Anchoring Wherever Required, Connecting With Equipment, Nozzles, Steam Traps, Strainers, Orifice Assemblies ( Including Tapping Upto First Block Valve ) , Spray Nozzles Rotameters; Tapping For Instrument Connections Like Pressure Gauges, Thermowells, Sample Connections, Vents, Drains Etc. Including Fixing Of All Types Of Sw Valves, Gaskets, Nuts And Bolts, All Inline Instruments, Elbows, Tees, Flanges, Reducers, Full Coupling Or Half Coupling, Reinforcement Pads, Earthing Strip Wherever Required; Welding Prefabricated Shoes And Supports ( Including Alignment ) As Per The Drawings Including Preparation Of Small Bore Isometrics Upto 1.5 Inch Nb, Specifications, Codes Etc. And As Per The Instructions Of The Engineer-In-Charge To His Entire Satisfaction Including Supplying Of All Types Of Tools And Tackles, Lifting Arrangements, Equipment, Machineries, All Consumables And Labour Etc. To Complete The Work In All Respects In A Workman Like Manner Including Area Preparation For Hot Jobs, Area Cleaning After Completion Of Work, Flushing Wherever Required, Cleaning Of Pipes Externally Off All Foreign Materials Like Weld Beads, Clamps Fixtures Etc. Used In Fabrication As Directed By The Engineer-In-Charge. Note : Proper Safety Arrangements For Carrying Out The Job Is Under Contractors Scope And The Same Has To Be Complied With As Per The Dire Ctions Of The Engineer- In-Charge. Note: For Piping Beyond 5 Mtr. Elevation Above And Below Ground Piping And Upto 10Mtr. Rates Is To Be Escalated By 20%. For More Than 10 Mtr. But Upto 15 Mtr. Rates Is To Be Escalated By 30%. For More Than 15 Mtr But Upto 20 Mtr. Rates To Be Escalated By 40% Respectively. Requirement Of Scaffolding To Be Envisaged And Decided By Engineer In Charge As Per Site Requirement And Scaffolding Item To Be Paid Separately. Note: For Piping Where Tig Welding Is Used For Root Run Only, The Rates To Be Escalated By 15% And Where Tig Welding Is Used For Entire Joints The Rates To Be Escalated By 20%. 147 15 Mm Nb, Schedule Upto 80 148 20 Mm Nb, Schedule Upto 80 149 25 Mm Nb, Schedule Upto 80 150 40 Mm Nb, Schedule Upto 80 151 50 Mm Nb, Schedule More Than 40 But Upto 80 152 80 Mm Nb, Schedule Upto 40 153 100 Mm Nb, Schedule Upto 40 154 150 Mm Nb, Schedule Upto 40 155 200 Mm Nb, Schedule Above 20 But Upto 40 156 250 Mm Nb, Schedule Above 20 But Upto 40 157 300 Mm Nb, Schedule Above 20 But Upto 40 158 350 Mm Nb, Schedule Above 20 But Upto 40 159 400 Mm Nb, Schedule Above 20 But Upto 40 160 Hydrotesing Of Piping Works Hydrostatic Testing Of Pipelines At The Specified Pressure Including Blinding / Deblinding, Fabrication And Fixing Of Testing Connections, Pressure Gauge Installation. Hose Pipe Connection And Making All Other Arrangements As Required And Dewatering, Flushing And Boxing Up After Fixing Proper Gaskets With Supply Of All Labour, Tools Andtackles, Instruments And Instruction Of The Engineer-In-Charge. The Job Has To Be Carried Out At All Elevations. 161 15 Mm 162 20 Mm 163 25 Mm 164 40 Mm 165 50 Mm 166 80 Mm 167 100 Mm 168 150 Mm 169 200 Mm 170 250 Mm 171 300 Mm 172 350 Mm 173 400 Mm 174 450 Mm 175 500 Mm 176 Wrapping & Coating Of Vessels / Underground Piping Etc. Providing Wrapping And Coating As Per The Specifications Including Supply Of All Materials, Tools And Tackles, Etc. The Detailed Spe Cification For Wrapping And Coating Is As Under: 1. The Surface Preparation Of Pipes Shall Be Done By Grit / Shot Blast Cleaning To Swedish Standard Sa-2. 2. The Grit / Shot Blasting Operation Shall Be Carried Out In The Day Time. Blast Cleaning Operation Shall Not Be Under Taken In Humid Condition. 3. Only Approved Quality Grit / Shot Shall Be Used For Grit / Shot Blasting. The Grit / Shot Used Shall Be Dry And Free Form Any Other Impurities. 4. The Grit / Shot Blasted Surface Shall Have A Shining And Near White Metal Appearances. 5. After Grit / Shot Blast Cleaning, The Surface Shall Be Dry Brushed To Remove Deposits. 6. The Grit / Shot Blasted Surface Should Be Inspected By Quality Control / Inspection Agency Of Owner / Contractor. Coating System Following Steps Shall Be Followed: 1. Application Of One Coat Of Primer. 2. Application Of One Coat Of Coal Tar Enamel. 3. Wrapping Fibre Glass. 4. Application Of 2Nd Coat Of Coal Tar Enamel. 5. Wrapping Of Craft Paper / Coal Tar Impregnated Outer Wrap. Priming 1. Single Coat Of Coal Tar Primer Shall Be Applied Manually With Good Quality Brushes. Following Precautions Shall Be Taken During Application Of Primer. 2. Primer Drum Shall Be Inspected For Manufacturing Date Batch No. Etc. 3. Primer Drum Shall Be Rotated Before Opening For Proper Mixing. 4. Primer Shall Be Applied Within 12 Hrs. Of Completion Of Sand Blasting. 5. Primer Shall Be Applied Evenly All Along The Pipe Surface. 6. Any Holiday Or Bare Pipe Left Over During Priming Shall Be Primed Again. 7. Primer Will Not Be Applied During Rainy / Moist Weather. 8. After Application Of Primer And Before Drying, Adequate Precaution Shall Be Taken To Avoid Contact Of Dust / Sand Etc. With Primed Surface. 9. Normal Primer Requires 1 Hr. Time For Proper Drying And Becomes Dead After 24 Hrs. Of Its Application. 10. Coating Shall Be Completed Within These Limits Failing Which Dead Primer Shall Be Cleaned And Fresh Primer Shall Be Applied Again. Coating And Wrapping I ) When The Priming Coat Has Dried And The Surface Of The Primed Pipe Has Been Cleaned Preferably By Clean White Rags To Remove The Settled Dust Just Preceding Of The Coating Operation. The Pipe Shall Be Coated With Hot Application Of One Coat Of Coal Tar Enamel To Give A Minimum Thickness Of 2.5 Mm And To Be Securely Bonded To The Primer. Ii ) The Coal Tar Enamel Shall Be Cut Into Lumps Preferably At The Storage Place Upon A Clean Platform With Side Boards And Due Care Must Always Be Exercised By The Contractor To Keep The Broken Enamel Absolutely Free Form Dirt, Grass, Water Or Any Other Foreign Material Up To The Time When Enamel Is Charged Into The Melting Kettle. Iii ) The Coal Tar Enamel Shall Be Slowly Heated On Reduced Fire And Maintained To The Even Temperature Recommended For Application I.E. 220 Deg. C To 240 Deg. C. Iv ) Constant Stirring Shall Be Necessary In Continuously Operating Melting Kettles. V ) Melting Kettle Should Have Proper Insulation. Vi ) The Melting Kettle Should Be Of Movable Type I.E. Wheel Mounted And Have Towing Arrangement. Vii ) The Melting Kettle Should Be Kept Near The Work Site. However, In No Case The Molten Enamel Shall Be Carried In Bucket For More Than 50 Meter Distance. Viii ) During Pouring Of Molten Enamel, Fine Wire Mesh Filter Shall Be Used To Avoid The Flow Of Impurity / Dirt / Sand. Ix ) During Temporary Interruption Of The Work The Temperature In The Kettle Not Shall Be Reduced By At Least 50 Deg. C Below The Normal Specified Temperature. X ) Any Enamel Heated To Temperature In Excess Of The Maximum Allowable Temperature Shall Be Rejected And Suitably Disposed Off By The Contractor. Xi ) Melting Kettles / Pots Shall Always Be Maintained Clean And In Good Working Order And Must Be Cleaned Whenever Deposits Form On The Heating Surface. Xii ) A Uniform Thickness Of 2.5 Mm Of Enamel Shall Be Applied To The Surface Of The Primed Pipe. Xiii ) A Uniform Thickness Of 2.5 Mm Of Enamel Shall Be Applied To The Surface Of The Primed Pipe. Xiv ) The Enamel Shall Be Then Reinforced By A Spirally Wrapped Fibre Glass Wrap, Pulled And Embedded Into The Hot Coating With An Over Lapping Of Edges Of The Wrap Not Less Than 1 / 2 And Not More Than 1 Xv ) This Will Be Followed By Another Coat Of Hot Coal Tar Enamel Application With A Uniform Thickness Of 1.5 Mm Followed By Craft Paper / Coal Tar Impregnated Fibre Glass Covering. Xvi The Coating And Wrapping Must Be Absolutely Free Of Wrinkles In The Wrappers, Pinholes, Bubbles, Holidays Voids Thin Spots Or Foreign Matter. Xvii Rolls Of Wrapping Material Shall Not Be Kept Along The Right Of Way And Shall Be Stored Properly And Brought To Site. Xviii ) Wrapping Material Shall Be So Hauled And Handled As To Prevent Injury To The Packages. Xix ) No Packages Shall Be Handled With Hooks Or Thrown Form Trucks. Xx ) Any Such Material Which Shows Evidence Of Deterioration Due To Weather Or Any Other Cause, Shall Be Rejected. Coating Thickness Minimum Thickness Of First Should Be 2.5 Mm Whereas Total Thickness Should Be Approx. 4.5 Mm. Testing Following Testing Shall Be Undertaken: I ) Physical Inspection: All The Coated Surface Shall Be Visually Inspected And All The Wrinkles, Bubbles, Lack Of Overlap Etc. Shall Be Marked For Repair. Ii ) Sound Test: The Coating Adhesion Can Be Checked Easily With Small Wooden Hammer By Soft Striking On Coated Surface. Change In Sound Indicates Coating Defects And Same Can Be Checked There By Peel Test. Iii ) Peel Test: The Field Bond Test For Coal Tar Enamel Adhesion Shall Be Preformed At 50-80F Normal Operating Temperature Of Steel Piping. If The Coating Temperature Is Above 80 °F Or Below 50 Deg. F, Pour Cold Or Hot Water Over The Test Area To Adjust The Enamel Temperature Within This Range. Using A Knife, Heated If Necessary Make Two Parallel Cuts Through The Coating About 4 Inch In Length And 3 / 4 Inch Apart. With The Edge Of Knife Blade Cut Under The Enamel Strip At One End And Loosen The Enamel Form The Pipe The Full Width Of The Strip For About A 1 / 2 Place The Knife Blade Under The Loosened End And Apply A Slow, Steady Pull Upward On Enamel Strip. Iv ) If The Peel Length Exceeds 1 / 8 The Test Is A Failure And Two Additional Tests Shall Be Made At Two Different Locations On The Same Section. If The Additional Tests Are Satisfactory Then The Section Shall Be Approved. If The Either Additional Test Fails, The Pipe Section Shall Be Rejected. Specification Of Coal Tar Primer The Primer Consists Of Processed Coal Tar Pitch And Refined Coal Tar Oil Suitably Blended With A Solvent Without Pigment Or Inert Filler Or Other Substances ( To Be Applied Cold ) For Brushing Or Spraying As Liquid Coat To The Clean Surface Piping As Provided For In Awwa Specification C-203-73. The Primer Should Have No Tendency To Settle Down In The Container And When Applied Without Producing Bubbles, Becomes Dry And Hard To Touch Within Specified Time Ensuring And Effective Bond Between The Metal Pipe Surface And The Enamel Coating. The Main Characteristics Of The Coal Tap Primer Should Be As Follows: 1. Drying Time To Touch Dry, At Normal Humidity At 32 Deg. C Is Less Than 1 Hr. 2. Max Boiling Point Of Solvent 25 Deg. C. 3. Penetration Of Residue At 25 Deg. C. 4. Softening Point Of Residue ( Astm-D-36 ) 104 Deg. C. 5. Flash Point Of ( Astm 1310 ) 37 Deg. C. 6. Pigment 7. Solvent Benzol Solvent Or Highly Toxic Volatile Solvents Excluded. Reputed Indian Supplier ( For Coal Tar Enamel And Coal Tar Primer ) . I ) M / S Shalimar Tar Products, Calcutta. Ii ) M / S Lloyd Insulation ( India ) Ltd., New Delhi. 2. Specification For Coal Tar Enamel The Enamel Shall Be A Wwa Coal Enamel Type-I Conforming To Awwa Standard, Awwa C-203-86. The Enamel Be Composed Of A Specially Processed Coal Tar Type Blended With An Inert Mineral Filter, Properly Graded, Cleaned, Dust Free And Without Asphalt Of Either Petroleum Or Nature Base, To Be Applied To A Recommended Temperature. The Main Characteristics Of The Enamel Shall Be As Follows: S. No. Test Enamel Type - 1 Min Max. 1. Softening Point, Astm-D-36 140 Deg.C 116 Deg. C 2. Filter ( Ash ) Astmd-71 25% 35% 3. Fineness Fillet Through 90% Through 200 Mesh. Astm-D-54G 3. Specification Of Fibre Glass Inner Wrap The Fibre Glass Inner Wrap Of High Tensile Long Monofilament, Chemically Inert Glass Fibre In Jack Straces Patterns Mat Reinforced By Longitudinal Continuous Stands Of Glass Fibre Yarn Blended With Insoluble Inert Resinous Binder Compatible With Hot Coal Tar Enamel And Should Conform To The Following Specifications: Tensile Strength ( Transverse ) Kg / Cm 0.50 + 0.10 Weight 41Gm / Sq.M Reputed Indian Supplier For Fibre Glass Paper And Kraft Paper: I ) M / S United Paper Product, Saharanpur, U.P. Ii ) M / S Fgp Limited New Delhi. Iii ) Specification Of Craft Paper. The Craft Paper Shall Be Smooth Bituminised To Be Supplied In Rolls. The Average Weight Of A Composite Bituminised Craft Paper Shall Be A Minimum Of 120 Gms / Sq. Meter. A Negative Weight Tolerance Upto 5% Of The Composite Weight May Be Permitted At The Discretion To The Owner, ( Bituminised Craft Paper With Average Weight Less Than 120 Gms / Sq. Meter In Not Acceptable ) . The Bituminised Craft Paper Shall Be Composed Of Two Layers Of Craft Paper Shall Be Composed Of Two Layers Of Craft Paper And Each Weighing Not Less Than 45 Gm / Sq. Meter And Laminated With A Layer Of Bitumen Approachments Weight 50 Gms / Sq. M To Have A Proper Bond Between The Two Layer Of Paper. He Bituminised Craft Paper For Field Application Shall Be Able To Resist Penetration. Specific Gravity At 25 Deg. C Astm D-71 1.4 1.6 Penetration, Astm-D-5 10 A ) At 25 Deg. C 100 Gms. Weight 5 Secs. High Temperature Test At 71 Deg.C 1 / 32 ( Sag O Awwa C-203. Sec. 2.8.9 Low Temperature Test At 23 Deg. C ( Cracking ) , Awwac-203 Sec. 2.8.10 Peel Test, Awwac-203 Sec. 2.8.11 No Peeling Electrical Resistance Test At 17000 Volts And Low Amperage ( 1.5 Mm Thickness ) Other Requirements ( For Wrapping And Coating ) 1. Third Party Inspection Certificate For All Materials By Eil / Dnv / Lris / Mecon Or Providing Iocl Approved Manufacturers Test Certificate Shall Be In Contractors Scope. 2. Holiday Testing Machine Shall Be Arranged And Provided By Contractor. 3. Vendor To Submit Transportation And Handling Procedure T Avoid Wrapping And Coating Of Pipes. 4. Vendor To Submit And Get Quality Assurance Plan ( Qap ) For Wrapping And Coating Approved By Owner / Inspector. 5. The Wrapping And Coating Surface Must Have Machine Finish In Workmanship. Note: Additional Payment For Earth Excavation And Wrapping Coating Will Be Made Extra For Underground Piping. 177 50 Mm Nb 178 80 Mm Nb 179 100 Mm Nb 180 150 Mm Nb 181 200 Mm Nb 182 250 Mm Nb 183 300 Mm Nb 184 400 Mm Nb 185 450 Mm Nb 186 500 Mm Nb 187 600 Mm Nb 188 Dye Penetration Test For Piping Works Performance Of Dye Penetration Test Including Supply Of All Necessary Materials, Penetrant, Developer Etc. Along With All Equipment#S, Labour, For Carrying Out The Work As Per Specification & Direction Of Engineer -In-Charge At All Elevations. Test Has To Be Carried Out In All Metallurgy The Test Has To Carry Out On All Schedules Of Pipes. Note: Since Inch Dia Unit Is Not Available In Sap, Hence For Estimate Unit Is To Be Taken As Dia. 189 For Pipes ( Per Inch Dia ) 190 For Vessels / Tanks ( Per Inch ) 191 Radiography Of Piping Works Performance Of Radiographic Inspection On All Type & Sizing Of Piping / Pipe Fittings In Position At All Heights Inclusive Of Providing Sources, Film, Chemicals, & All Necessary Equipment#S, Consumables Etc. Complete In All Respect As Per Specification & Instruction Of The Engineer-In-Charge. Note: Since Inch Dia Unit Is Not Available In Sap, Hence For Estimate Unit Is To Be Taken As Dia. 192 For Pipes ( Per Inch Dia ) 193 For Vessel / Tanks Etc. ( Per Inch ) 194 Heat Treatment Heat Treatment Of Shop Fabricated For Already Installed Piping / Static Equipment Etc. For Joints Or Other Operations Wherever Required. Heating To Be Carried Out In A Furnace Or By Using An Electric Resistance Or Induction Heating Equipment Ensuring Uniform Temperature Attainment At All Points Of The Portion Being Heat-Treated. The Portion Under Heat Treatment Shall Be Wrapped Suitably Under Insulation To Avoid Any Harmful Temperature Gradient. The Temperature Thus Attainted In The Portion Under Heat Treatment Shall Be Recorded By Means Of Thermocouples, Pyrometer And An Automatic Temperature Recorders Suitably Calibrated Should Be Employed. The Calibration Chart Of Each Recorder Along With Hardness Test Results Shall Be Submitted To The Engineer-In-Charge For Approval. The Details Of Heat Treatment Such As Heating Rate, Soaking Temperature Pause Period And Cooling Rate Etc. To Be Carried Out As Per Relevant Standards / Code As Instructed By The Engineer-In-Charge. Note: Since Inch Dia Unit Is Not Available In Sap, Hence For Estimate Unit Is To Be Taken As Dia. 195 For Pipes ( Per Inch Dia ) 196 Welding Of Cs Plates Transportation Of All Items Including Plates Etc. From Owners Storage Point To Work Site And / Or Prefabrication Yard And Welding Of Cs Plates Including Cutting / Grinding / Edge Preparing And Required Testing To Prove Soundness Of Weld Joint With Supply Of All Consumables, Manpower, Tools As Per Technical Specification And Direction Of The Engineer-In-Charge. 197 Upto 3Mm Thick 198 Above 3Mm & Upto 5Mm Thick. 199 Above 5Mm & Upto 6Mm Thick 200 Above 6Mm & Upto 7Mm Thick 201 Above 7Mm & Upto 9Mm Thick. 202 Above 9Mm & Upto 11Mm Thick 203 Welding Of Ss / As Plates Transportation Of All Items Including Plates Etc. From Owners Storage Point To Work Site And / Or Prefabrication Yard And Welding Of Ss / As Plates / Structural Etc. Including Cutting / Grinding / Edge Preparing And Required Testing To Prove Soundness Of Weld Joint With Supply Of All Consumables, Manpower, Tools As Per Technical Specification And Direction Of The Engineer-In-Charge ( Heat Treatment And Other Ndt Charges Shall Be Paid Extra ) . 204 Upto 3Mm Thick Alloy Steel ( P22 ) 205 Above 5Mm & Upto 6Mm Thick Alloy Steel ( P22 ) 206 Above 6Mm & Upto 7Mm Thick Alloy Ateel ( P22 ) 207 Upto 3 Mm Thick Alloy Steel ( P5 ) 208 Above 5 Mm & Upto 6 Mm Thick Alloy Steel ( P5 ) 209 Above 6 Mm & Upto 7 Mm Thick Alloy Steel ( P5 ) 210 Above 7 Mm & Upto 9 Mm Thick Alloy Steel ( P5 ) 211 Above 9 Mm & Upto 11 Mm Thick Alloy Steel ( P5 ) 212 Above 15 Mm & Upto 16 Mm Thick Alloy Steel ( P5 ) 213 Above 18 Mm & Upto 20 Mm Thick Alloy Steel ( P5 ) 214 Cs / As Plate Cutting Cutting Of Cs / As Plate By Gas / Grinding Or Any Other Means As Per Direction Of The Engineer-In-Charge According To Suitability Including Transportation From Stores To Site With Supply Of All Tools, Tackles, Consumables, Equipment, Labour Etc. 215 3Mm Thick 216 5Mm Thick 217 6Mm Thick 218 8Mm Thick 219 10Mm Thick 220 12Mm Thick 221 Ss Plate Cutting Cutting Of Ss Plate By Electric / Grinding Or Any Other Means Including Preheating Wherever Required As Per Direction Of The Engineer-In-Charge According To Suitability Including Transportation From Stores To Site With Supply Of All Tools, Tackles, Consumables, Equipment, Labour Etc. 222 3Mm Thick 223 5Mm Thick 224 6Mm Thick 225 8Mm Thick 226 10Mm Thick 227 12Mm Thick 228 Alloy Steel Piping ( Astm A335 Gr. P5 ) Joints Transportation Of All Piping Items From Owners Storage Points To Work Site And / Or Pre-Fabrication Yard And To Site After Pre-Fabrication; Cutting, Grinding, Edge Preparation Of Pipes And Fittings, Like Flanges, Elbows, Tees, Reducers Etc. To Match The Mating Edges Of Different Thickness; Fit-Up, Bending, Welding Using Approved Welding Electrodes As Per Owners Quality Requirements Etc. As Per Codes / Specifications, Drawings Etc. ( Alloy Steel Joints Shall Be Welded By Doing Root Run Using Tig Welding Followed By Filler Passes By Manual / Semi-Automatic Arc Welding. The Job Is To Be Pre-Heated Prior To Welding And All Joints To Be Stress Relieved And Fully Radiographed, However, Charges For Stress Relieving And Radiography Shall Be Paid Separately ) , Threading, Laying, Erection And Alignment Of Pipes At Ground Level I.E. Upto A Height Of 5 Meters On Sleepers, Pipe Racks Etc. Or Upto 5 Meters Depth In Trenches, Anchoring Wherever Required, Connecting With Equipment, Nozzles, Steam Traps, Strainers, Orifice Assemblies ( Including Tapping Upto First Block Valve ) , Spray Nozzles Rotameters; Tapping For Instrument Connections Like Pressure Gauges, Thermowells, Sample Connections, Vents, Drains Etc. Including Fixing Of All Types Of Sw Valves, Gaskets, Nuts And Bolts, All Inline Instruments, Elbows, Tees, Flanges, Reducers, Full Coupling Or Half Coupling, Earthing Strip Wherever Required; Welding Prefabricated Shoes And Supports ( Including Alignment ) As Per The Drawings Including Preparation Of Small Bore Isometric Upto 1.5 Inch Nb, Specifications, Codes Etc. And As Per The Instructions Of The Engineer-In-Charge To His Entire Satisfaction Including Supplying Of All Types Of Tools And Tackles, Lifting Arrangements, Equipment, Machineries, All Consumables And Labour Etc. To Complete The Work In All Respects In A Workman Like Manner Including Area Preparation For Hot Jobs, Area Cleaning After Completion Of Work, Flushing Wherever Required, Cleaning Of Pipes Externally Off All Foreign Materials Like Weld Beads, Clamps Fixtures Etc. Used In Fabrication As Directed By The Engineer-In-Charge. Note: Proper Safety Arrangements For Carrying Out The Job Is Under Contractors Scope And The Same Has To Be Complied With As Per The Dire Ctions Of The Engineer-In-Charge. Note: For Piping Beyond 5 Mtr. Elevation Above And Below Ground Piping And Upto 10Mtr. Rates Is To Be Escalated By 20%. For More Than 10 Mtr. But Upto 15 Mtr. Rates Is To Be Escalated By 30%. For More Than 15 Mtr But Upto 20 Mtr. Rates To Be Escalated By 40% Respectively. Requirement Of Scaffolding To Be Envisaged And Decided By Engineer In Charge As Per Site Requirement And Scaffolding Item To Be Paid Separately. Note: For Piping Where Tig Welding Is Used For Root Run Only, The Rates To Be Escalated By 15% And Where Tig Welding Is Used For Entire Joints The Rates To Be Escalated By 20%. Note: Payment Of Tapping Points Will Also Be Made Extra On Joint Basis, As The Measurement Is On Joint Basis. 229 15 Mm Nb, Schedule Upto 80 230 15 Mm Nb, Schedule Above 80 231 20 Mm Nb, Schedule Upto 80 232 20 Mm Nb, Schedule Above 80 233 25 Mm Nb, Schedule Upto 80 234 25 Mm Nb, Schedule Above 80 235 40Mm Nb, Schedule Above 40 But Upto 80 236 50Mm Nb, Schedule Above 40 But Upto 80 237 80 Mm Nb, Schedule Upto 40 238 80Mm Nb, Schedule Above 40 But Upto 80 239 100Mm Nb, Schedule Upto 40 240 150 Mm Nb, Schedule Upto 40 241 200 Mm Nb, Schedule Above 20 But Upto 40 242 250 Mm Nb, Schedule Above 20 But Upto 40 243 Fabrication And Erection Of Pipe Support / Platforms / Devits / Stair Case Etc. The Job Includes Getting The Materials Issued, Transportation To Work Site And Handling At Site, Fabrication At The Required Size And Shape Using Steel Pipes, Ms Structural / Plates Etc. By Cutting, Bevelling And Welding Including Fixing Of Ms Gratings / Chequered Plates On Platform At All Elevation By Welding, Bolting Or Otherwise To Existing Members Or Equipment. This Also Includes Fabrication And Fixing Of Pipe Clamps, Non-Standard Bolts Etc. Inclusive Of Labour, Consumables, Tools And Tackles And Materials Required For U-Clamps, J-Bolts Etc. And Applying One Coat Of Primer And Two Coats Of High Built Black Bituminous Paint And Complete In All Respect As Per Drawings, Specifications And Instructions Of The Engineer-In-Charge. ( Excluding Cost Of Structural Steel ) . 244 Dismantling Of Structurals Like Pipe Support / Stairway / Devit Etc. Removal Of Existing Platforms / Pipe Supports / Davits / Stairways Etc. Along With Adjacent Fittings / Members By Cutting / Debolting Or By Any Other Means Without Damaging The Remaining Unit And Lowering Down To The Ground Including Erection Of Scaffolding, Retrieving Of All The Usable Materials And Transportation To The Storage Point As Directed By The Engineer-In-Charge. 245 Fabrication Of Carbon Steel Reducers With Welding Electrode E-6013 Preparing Drawings And Fabrication Of The Following Specials Including Transportation Of Materials From Owners Storage Points To Work Site And / Shop, Cutting, Edge Preparing, Welding, As Per Owners Quality Requirements, Including Supply Of All Necessary Equipment, Consumables, Labour, Tools, Tackles, And Supervision, Work Shall Be Carried Out As Per The Specifications Drawings, Codes, And Instructions To The Full Satisfaction Of The Engineer-In-Charge. 246 200 Mm Nb To Below Reducer, Schedule Upto 40 247 250 Mm Nb To Below Reducer, Schedule Upto 40 248 300 Mm Nb To Below Reducer, Schedule Above 20 But Upto 40 249 350 Mm Nb To Below Reducer, Schedule Upto 20 250 400 Mm Nb To Below Reducer, Schedule Upto 20 251 450Mm Nb To Below Reducer, Schedule Upto 20 252 Stainless Steel Piping ( Gr. Ss 300 ) Joints Transportation Of All Piping Items From Owners Storage Points To Work Site And / Or Pre-Fabrication Yard And To Site After Pre-Fabrication; Cutting, Grinding, Edge Preparation Of Pipes And Fittings, Like Flanges, Elbows, Tees, Reducers Etc. To Match The Mating Edges Of Different Thickness; Fit-Up, Bending, Welding Using Approved Welding Electrodes As Per Owners Quality Requirements Etc. As Per Codes / Specifications, Drawing Etc., Threading, Laying, Erection And Alignment Of Pipes At Ground Level I.E. Upto A Height Of 5 Meters On Sleepers, Pipe Racks Etc. Or Upto 5 Meters Depth In Trenches; Anchoring Wherever Required, Connecting With Equipment, Nozzles, Steam Traps, Strainers, Orifice Assemblies ( Including Tapping Upto First Block Valve ) , Spray Nozzles Rotameters; Tapping For Instrument Connections Like Pressure Gauges, Thermowells, Sample Connections, Vents, Drains Etc. Including Fixing Of All Types Of Sw Valves, Gaskets, Nuts And Bolts, All Inline Instruments, Elbows, Tees, Flanges, Reducers, Full Coupling Or Half Coupling, Earthing Strip Wherever Required; Welding Prefabricated Shoes And Supports ( Including Alignment ) As Per The Drawings, Including Preparation Of Small Bore Isometric Upto 1.5 Inch Nb, Specifications, Codes Etc. And As Per The Instructions Of The Engineer-In-Charge To His Entire Satisfaction Including Supplying Of All Types Of Tools And Tackles, Lifting Arrangements, Equipment, Machineries, All Consumables A Nd Labour Etc. To Complete The Work In All Respects In A Workman Like Manner Including Area Preparation For Hot Jobs, Area Cleaning After Completion Of Work, Flushing Wherever Required, Cleaning Of Pipes Externally Off All Foreign Materials Like Weld Beads, Clamps Fixtures Etc. Used In Fabrication As Directed By The Engineer-In-Charge. Note : Proper Safety Arrangements For Carrying Out The Job Is Under Contractors Scope And The Same Has To Be Complied With As Per The Dire Ctions Of The Engineer- In-Charge. Note: For Piping Beyond 5 Mtr. Elevation Above And Below Ground Piping And Upto 10Mtr. Rates Is To Be Escalated By 20%. For More Than 10 Mtr. But Upto 15 Mtr. Rates Is To Be Escalated By 30%. For More Than 15 Mtr But Upto 20 Mtr. Rates To Be Escalated By 40% Respectively. Requirement Of Scaffolding To Be Envisaged And Decided By Engineer In Charge As Per Site Requirement And Scaffolding Item To Be Paid Separately. Note: For Piping Where Tig Welding Is Used For Root Run Only, The Rates To Be Escalated By 15% And Where Tig Welding Is Used For Entire Joints The Rates To Be Escalated By 20%. Note: Payment Of Tapping Points Will Also Be Made Extra On Joint Basis, As The Measurement Is On Joint Basis. 253 15 Mm Nb, Schedule Upto 40 254 15 Mm Nb, Schedule More Than 40 But Upto 80 255 15 Mm Nb, Schedule Above 80 But Upto 120 256 20 Mm Nb, Schedule Upto 40 257 20 Mm Nb, Schedule More Than 40 But Upto 80 258 25 Mm Nb, Schedule Upto 40 259 25 Mm Nb, Schedule More Than 40 But Upto 80 260 40 Mm Nb, Schedule Upto 40 261 40 Mm Nb, Schedule More Than 40 But Upto 80 262 50 Mm Nb, Schedule Upto 40 263 50 Mm Nb, Schedule More Than 40 But Upto 80 264 80 Mm Nb, Schedule Upto 40 265 80 Mm Nb, Schedule More Than 40 But Upto 80 266 100 Mm Nb, Schedule Upto 40 267 100 Mm Nb, Schedule More Than 40 But Upto 80 268 150 Mm Nb, Schedule Upto 40 269 150 Mm Nb, Schedule More Than 40 But Upto 80 270 150 Mm Nb, Schedule Above 80 But Upto 120 271 200 Mm Nb, Schedule Upto 40 272 200 Mm Nb, Schedule More Than 40 But Upto 80 273 200 Mm Nb, Schedule Above 80 But Upto 120 274 250 Mm Nb, Schedule Upto 40 275 250 Mm Nb, Schedule More Than 40 But Upto 80 276 250 Mm Nb, Schedule Above 80 But Upto 120 277 300 Mm Nb, Schedule Upto 40 278 300 Mm Nb, Schedule More Than 40 But Upto 80 279 300 Mm Nb, Schedule Above 80 But Upto 120 280 350 Mm Nb, Schedule Upto 40 281 350 Mm Nb, Schedule More Than 40 But Upto 80 282 350 Mm Nb, Schedule Above 80 But Upto 120 283 400 Mm Nb, Schedule Upto 40 284 400 Mm Nb, Schedule More Than 40 But Upto 80 285 450 Mm Nb, Schedule Upto 40 286 450 Mm Nb, Schedule More Than 40 But Upto 80 287 500 Mm Nb, Schedule Upto 40 288 500 Mm Nb, Schedule More Than 40 But Upto 80 289 600 Mm Nb, Schedule Upto 40 290 Bending Of Pipes Bending Of Pipes: The Job Includes Bending Of Pipes In The Required Curvature And Supply Of All Tools, Tackles, Labour And The Supervision To Complete The Job As Per And To The Full Satisfaction Of The Engineer-In-Charge. 291 15 Mm Nb 292 20 Mm Nb 293 25 Mm Nb 294 40 Mm Nb 295 50 Mm Nb 296 80 Mm Nb 297 100 Mm Nb 298 150 Mm Nb 299 200 Mm Nb 300 Fixing Of Lugs Fabrication Of Cs / Ss Lugs By Cutting, Bending Etc. From Cs / Ss Annealed Wire Etc. ( Supplied By Owner Free Of Cost ) And Fixing The Same By Welding On The Fabricated Panel Segments For Holding The Castable Refractories Including Supply Of Labour, Tools, Tackles As Per Direction Of The Engineer-In-Charge. 301 Cs Lugs 302 Ss Lugs 303 Buffing Of Weld Joints Job Involves Buffing And Cleaning Of Total Weld Area Of The Vessel / Column Etc. Using Power Brush. The Job Has To Be Completed In All Respect To The Entire Satisfaction Of The Engineer-In-Charge ( Each Length Of Buffing Will Be Up To Width Of 150 Mm ) . 304 Extra For Fixing / Removal Of Rtj Flanges / Blind Flanges Extra For Opening / Fixing Etc. Of Rtj Flanges / Blind Flanges / Spool Pieces For Lapping Etc. 305 50 Mm 306 80 Mm 307 100 Mm 308 150 Mm 309 200 Mm 310 250 Mm 311 300 Mm 312 600 Mm 313 Dechoking Of Cw Line / Product Line Dechoking Of Cw Line / Product Line By Poking Rod Inside Or Any Other Mech. Means. This Include Opening / Removal Of Spool Piece Of Piping To Be Dechoked, Removal Of Sludge / Hard Deposits Etc. By Poking Rod / Dechoking By Steam Or Any Other Mechanical Means And Fixing / Erecting The Line In Position After Dechoking, Including Cutting And Fixing Suitable Size. 314 Dia ½ To 1 315 Dia 1½ 316 Dia 2 317 Dia 4 318 Dia 6 319 Dia 8 320 Hose Connection & Disconnection Job Hose Connection And Disconnection Job Involves Transportation Of Hoses From The Owners Storage To Worksite, Opening The Roll And Laying The Hose, Cutting If Required, Joining Them Properly, Connection Of Ends To Specified Locations / Equipment / Supply Points As Per Production Requirement, Tying The Hose Wherever Required, Opening Of End Connections And Removal Of Hose After Job Completion, Rolling The Same And Shifting To Scrap Yard / Storage Point As Per Direction Of Eic. The Job Also Covers Lowering, Lifting, Handling Of Hoses, Erection / Removal Of Steel Scaffolding, Area Preparation, Area Cleaning And Compliance To All Safety Norms And Work Permit Systems. Note: The Rates Shall Be Applicable For Working And Connection At All Elevation. The Hoses, Clamps And Bolts Shall Be Supplied By Iocl Free Of Charge. This Item Shall Be Operative Only If Hose Connection / Disconnection Is Required By Production / Maintenance And Is Not Related To Execution Of Any Of The Item. Only Hose Connection Or Dis-Connection Shall Be Treated As Half Activity. 321 Preparatory Jobs For Hot Work The Job Includes Opening Of Flanges, Blinding / Deblinding By Bolting / Debolting Etc. Fabrication Of Tail Blinds, Cover Plate Connections Fittings Etc., Elbow Reversing, Opening And Fixing Of Plugs From The Furnace Tube Etc., Making Hose Connections And All Other Arrangements As Required For Flushing The Lines Including Wedge Opening, Dewatering After Flushing, Decoking, Isolation Etc., Boxing Up The Lines With New Gaskets And Hot Bolting Of All The Joints During Hot Circulation And Complete The Job With Supply Of Tools, Tackles, Labours And Consumables Etc. As Per Direction Of The Engineer-In-Charge. 322 15 Mm 323 20 Mm 324 25 Mm 325 40 Mm 326 50 Mm 327 80 Mm 328 100 Mm 329 150 Mm 330 200 Mm 331 250 Mm 332 600 Mm 333 Stainless Steel Piping ( Gr. Ss 400 ) Joints Transportation Of All Piping Items From Owners Storage Points To Work Site And / Or Pre-Fabrication Yard And To Site After Pre-Fabrication; Cutting, Grinding, Edge Preparation Of Pipes And Fittings, Like Flanges, Elbows, Tees, Reducers Etc. To Match The Mating Edges Of Different Thickness; Fit-Up, Bending, Welding Using Approved Welding Electrodes As Per Owners Quality Requirements Etc. As Per Codes / Specifications, Drawing Etc., Threading, Laying, Erection And Alignment Of Pipes At Ground Level I.E. Upto A Height Of 5 Meters On Sleepers, Pipe Racks Etc. Or Upto 5 Meters Depth In Trenches; Anchoring Wherever Required, Connecting With Equipment, Nozzles, Steam Traps, Strainers, Orifice Assemblies ( Including Tapping Upto First Block Valve ) , Spray Nozzles Rotameters; Tapping For Instrument Connections Like Pressure Gauges, Thermowells, Sample Connections, Vents, Drains Etc. Including Fixing Of All Types Of Sw Valves, Gaskets, Nuts And Bolts, All Inline Instruments, Elbows, Tees, Flanges, Reducers, Full Coupling Or Half Coupling, Earthing Strip Wherever Required; Welding Prefabricated Shoes And Supports ( Including Alignment ) As Per The Drawings, Including Preparation Of Small Bore Isometric Upto 1.5 Inch Nb, Specifications, Codes Etc. And As Per The Instructions Of The Engineer-In-Charge To His Entire Satisfaction Including Supplying Of All Types Of Tools And Tackles, Lifting Arrangements, Equipment, Machineries, All Consumables A Nd Labour Etc. To Complete The Work In All Respects In A Workman Like Manner Including Area Preparation For Hot Jobs, Area Cleaning After Completion Of Work, Flushing Wherever Required, Cleaning Of Pipes Externally Off All Foreign Materials Like Weld Beads, Clamps Fixtures Etc. Used In Fabrication As Directed By The Engineer-In-Charge. Note : Proper Safety Arrangements For Carrying Out The Job Is Under Contractors Scope And The Same Has To Be Complied With As Per The Dire Ctions Of The Engineer- In-Charge. Note: For Piping Beyond 5 Mtr. Elevation Above And Below Ground Piping And Upto 10Mtr. Rates Is To Be Escalated By 20%. For More Than 10 Mtr. But Upto 15 Mtr. Rates Is To Be Escalated By 30%. For More Than 15 Mtr But Upto 20 Mtr. Rates To Be Escalated By 40% Respectively. Requirement Of Scaffolding To Be Envisaged And Decided By Engineer In Charge As Per Site Requirement And Scaffolding Item To Be Paid Separately. Note: For Piping Where Tig Welding Is Used For Root Run Only, The Rates To Be Escalated By 15% And Where Tig Welding Is Used For Entire Joints The Rates To Be Escalated By 20%. Note: Payment Of Tapping Points Will Also Be Made Extra On Joint Basis, As The Measurement Is On Joint Basis. 334 15 Mm Nb, Schedule More Than 40 But Upto 80 335 20 Mm Nb, Schedule More Than 40 But Upto 80 336 25 Mm Nb, Schedule More Than 40 But Upto 80 337 40 Mm Nb, Schedule More Than 40 But Upto 80 338 50 Mm Nb, Schedule More Than 40 But Upto 80 339 80 Mm Nb, Schedule More Than 40 But Upto 80 340 100 Mm Nb, Schedule Upto 40 341 150 Mm Nb, Schedule Upto 40 342 200 Mm Nb, Schedule Upto 40 343 Scrap Removal Collection Of Metallic Scrap / Unwanted Materials Such As Valves, Pipes, Bends, Plates, Structural, Gasket Sheets, Hoses, Fasteners Etc., From Different Location And Elevations And Transporting Them To Scrap Yard Or Any Other Place As Per Instruction Of Engineer-In-Charge. Job Includes Supplying Of All Types Of Tools And Tackles, Lifting Arrangements, Hydra / Crane, Tractor Trolley And Equipment, Machineries All Consumables And Labour. All Jobs Are To Be Carried Out As Per The Instruction And To The Full Satisfaction Of The Engineer-In-Charge. Note: If Cutting Is Required As Per Site Requirement The Same Shall Be Paid Separately. 344 Material Handling Within Refinery Handling, Shifting, Stacking Etc. Of Piping And Structural Material As Per Job Requirement At Elevation And As Per Instruction Of En Gineer-In-Charge. This Item To Be Operated In Case Of Lifting And Lowering Of Piping / Plates / Structural For Repair Job To Safe Working Site Where Fire Permit Can Be Given, Redundant Material Removal From Position And Transporting To Store / Scrap Yard Etc. Supply Of Labour, Tools And Tackles, Lifting Arrangements, Hydra / Crane, Tractor Trolley, Equipment, Consumables Etc. Will Be In Contractors Scope. All Jobs Are To Be Carried Out As Per The Instruction And To The Full Satisfaction Of The Engineer-In-Charge. ( Item Should Not Be Operated For Area Scrap Removal ) . 345 Installation / Removal Of Level Troll, Fire Hydrant, Monitors, Safety Valves Etc. The Job Involves Opening Of Flanged And Removal Of All Types Of Level Troll, Fire Hydrant And Monitor By Debolting / Cold / Hot Cutting Of Fasteners Wherever Required, Cleaning, Or Flange Facing, Lapping Of Rtj Rings, Level Troll, Fire Hydrant, Monitor, In Position With Correct Direction And Providing New Gasket ( Iocl Supplied ) Including Cutting Of Gaskets If Required And Finally Tightening Of The Gland To Ensure Zero Leak Including Hot Bolting Wherever Applicable. 346 Installation ( Same As 7.1 ) 347 Removal ( Same As 7.2 ) 348 Handling / Erection Of Fabricated Pipes / Coil Assemblies The Job Includes Getting The Materials Issued, Transportation To Work-Site, Handling And Care At Work-Site, Erecting The Fabricated Item At Position And Fixing, Aligning And Making Connections To The Companion Pipe Etc. And Complete In All Respect With All Labour, Tools, Tackles And Supervision Etc. As Per The Direction Of The Engineer-In-Charge. 349 Transportation From Owners Storage Points To Work Site And / Or Pre-Fabrication Yard And To Site After Pre-Fabrication; Cutting, Gr Inding, Edge Preparation As Per The Instructions Of The Engineer-In-Charge To His Entire Satisfaction Including Supplying Of All Types Of Tools And Tackles, Lifting Arrangements, Equipment, Machineries, All Consumables And Labour Etc. To Complete The Work In All Respects In A Workman Like Manner Including Area Preparation For Hot Jobs, Area Cleaning After Completion Of Work, Pneumatic Testing, Cleaning Of Pipes Externally Off All Foreign Materials Like Weld Beads, Clamps Fixtures Etc. Used In Fabrication As Directed By The Engineer-In-Charge. Note : Proper Safety Arrangements For Carrying Out The Job Is Under Contractors Scope And The Same Has To Be Complied With As Per The Dire Ctions Of The Engineer- In-Charge. 350 Branch Size 2 Inch 351 Branch Size 3 Inch 352 Branch Size 4 Inch 353 Branch Size 6 Inch 354 Branch Size 8 Inch 355 Branch Size 10 Inch 356 Branch Size 12 Inch 357 Branch Size 14 Inch 358 Branch Size 16 Inch 359 Branch Size 18 Inch 360 Alloy Steel Piping ( Astm A335 Gr. P1, P2, P11 & P12 ) Joints Transportation Of All Piping Items From Owners Storage Points To Work Site And / Or Pre-Fabrication Yard And To Site After Pre-Fabrication; Cutting, Grinding, Edge Preparation Of Pipes And Fittings, Like Flanges, Elbows, Tees, Reducers Etc. To Match The Mating Edges Of Different Thickness; Fit-Up, Bending, Welding Using Approved Welding Electrodes As Per Owners Quality Requirements Etc. As Per Codes / Specifications, Drawings Etc. ( Alloy Steel Joints Shall Be Welded By Doing Root Run Using Tig Welding Followed By Filler Passes By Manual / Semi-Automatic Arc Welding. The Job Is To Be Pre-Heated Prior To Welding And All Joints To Be Stress Relieved And Fully Radiographed, However, Charges For Stress Relieving And Radiography Shall Be Paid Separately ) , Threading, Laying, Erection And Alignment Of Pipes At Ground Level I.E. Upto A Height Of 5 Meters On Sleepers, Pipe Racks Etc. Or Upto 5 Meters Depth In Trenches, Anchoring Wherever Required, Connecting With Equipment, Nozzles, Steam Traps, Strainers, Orifice Assemblies ( Including Tapping Upto First Block Valve ) , Spray Nozzles Rotameters; Tapping For Instrument Connections Like Pressure Gauges, Thermowells, Sample Connections, Vents, Drains Etc. Including Fixing Of All Types Of Sw Valves, Gaskets, Nuts And Bolts, All Inline Instruments, Elbows, Tees, Flanges, Reducers, Full Coupling Or Half Coupling, Earthing Strip Wherever Required; Welding Prefabricated Shoes And Supports ( Including Alignment ) As Per The Drawings Including Preparation Of Small Bore Isometric Upto 1.5 Inch Nb, Specifications, Codes Etc. And As Per The Instructions Of The Engineer-In-Charge To His Entire Satisfaction Including Supplying Of All Types Of Tools And Tackles, Lifting Arrangements, Equipment, Machineries, All Consumables And Labour Etc. To Complete The Work In All Respects In A Workman Like Manner Including Area Preparation For Hot Jobs, Area Cleaning After Completion Of Work, Flushing Wherever Required, Cleaning Of Pipes Externally Off All Foreign Materials Like Weld Beads, Clamps Fixtures Etc. Used In Fabrication As Directed By The Engineer-In-Charge. Note : Proper Safety Arrangements For Carrying Out The Job Is Under Contractors Scope And The Same Has To Be Complied With As Per The Dire Ctions Of The Engineer- In-Charge. Note: For Piping Beyond 5 Mtr. Elevation Above And Below Ground Piping And Upto 10Mtr. Rates Is To Be Escalated By 20%. For More Than 10 Mtr. But Upto 15 Mtr. Rates Is To Be Escalated By 30%. For More Than 15 Mtr But Upto 20 Mtr. Rates To Be Escalated By 40% Respectively. Requirement Of Scaffolding To Be Envisaged And Decided By Engineer In Charge As Per Site Requirement And Scaffolding Item To Be Paid Separately. Note: For Piping Where Tig Welding Is Used For Root Run Only, The Rates To Be Escalated By 15% And Where Tig Welding Is Used For Entire Joints The Rates To Be Escalated By 20%. Note: Payment Of Tapping Points Will Also Be Made Extra On Joint Basis, As The Measurement Is On Joint Basis. 361 15 Mm Nb, Schedule Upto 80 362 15 Mm Nb, Schedule Above 80 363 20 Mm Nb, Schedule Upto 80 364 20 Mm Nb, Schedule Above 80 365 25 Mm Nb, Schedule Upto 80 366 25 Mm Nb, Schedule Above 80 367 40 Mm Nb, Schedule Upto 40 368 40Mm Nb, Schedule Above 40 But Upto 80 369 40 Mm Nb, Schedule Above 120 370 50 Mm Nb, Schedule Upto 40 371 50Mm Nb, Schedule Above 40 But Upto 80 372 50 Mm Nb, Schedule Above 120 373 80 Mm Nb, Schedule Upto 40 374 80Mm Nb, Schedule Above 40 But Upto 80 375 80 Mm Nb, Schedule Above 120 376 100Mm Nb, Schedule Upto 40 377 100Mm Nb, Schedule Above 40 But Upto 80 378 100Mm Nb, Schedule Above 120 379 150 Mm Nb, Schedule Upto 40 380 150 Mm Nb, Schedule More Than 40 But Upto 80 381 150 Mm Nb, Schedule Above 120 382 200 Mm Nb, Schedule Upto 20 383 200 Mm Nb, Schedule Above 20 But Upto 40 384 200 Mm Nb, Schedule More Than 40 But Upto 80 385 200 Mm Nb, Schedule Above 120 386 250 Mm Nb, Schedule Upto 20 387 250 Mm Nb, Schedule Above 20 But Upto 40 388 250 Mm Nb, Schedule More Than 40 But Upto 80 389 250 Mm Nb, Schedule Above 120 390 300 Mm Nb, Schedule Upto 20 391 300 Mm Nb, Schedule Above 20 But Upto 40 392 300 Mm Nb, Schedule More Than 40 But Upto 80 393 300 Mm Nb, Schedule Above 120 394 350 Mm Nb, Schedule Upto 20 395 350 Mm Nb, Schedule Above 20 But Upto 40 396 350 Mm Nb, Schedule More Than 40 But Upto 80 397 350 Mm Nb, Schedule Above 120 398 Provision Of Reinforcement Pad For P-1, P-2, P-11 And P-12 Transportation From Owners Storage Points To Work Site And / Or Pre-Fabrication Yard And To Site After Pre-Fabrication; Cutting, Gri Nding, Edge Preparation As Per The Instructions Of The Engineer-In-Charge To His Entire Satisfaction Including Supplying Of All Types Of Tools And Tackles, Lifting Arrangements, Equipment, Machineries, All Consumables And Labour Etc. To Complete The Work In All Respects In A Workman Like Manner Including Area Preparation For Hot Jobs, Area Cleaning After Completion Of Work, Pneumatic Testing, Cleaning Of Pipes Externally Off All Foreign Materials Like Weld Beads, Clamps Fixtures Etc. Used In Fabrication As Directed By The Engineer-In-Charge. Note : Proper Safety Arrangements For Carrying Out The Job Is Under Contractors Scope And The Same Has To Be Complied With As Per The Dire Ctions Of The Engineer- In-Charge. 399 Branch Size 2 Inch 400 Branch Size 3 Inch 401 Branch Size 4 Inch 402 Branch Size 6 Inch 403 Branch Size 8 Inch 404 Branch Size 10 Inch 405 Branch Size 12 Inch 406 Branch Size 14 Inch 407 Extra For Ibr Grade Alloy Steel Piping ( Astm A335 Gr.P1, P2, P11 & 12 ) Joints Extra For Ibr Grade Alloy Steel Piping ( Astm A335 Gr. P1, P2, P11 And 12 ) Joints. For Ibr Piping Jobs, The Scope Of Contractor Shall Be Liasoning With Ibr Authorities Including Approval Of Drawings / Documents From Ibr Authorities And Also Getting The Final Approval Of The Job From Ibr Authorities Including Payment Of Any Fee Or Charges To Ibr Authorities For This Purpose. 408 15 Mm Nb, Schedule Upto 80 409 15 Mm Nb, Schedule Above 80 410 20 Mm Nb, Schedule Upto 80 411 20 Mm Nb, Schedule Above 80 412 25 Mm Nb, Schedule Upto 80 413 25 Mm Nb, Schedule Above 80 414 40 Mm Nb, Schedule Upto 40 415 40Mm Nb, Schedule Above 40 But Upto 80 416 40 Mm Nb, Schedule Above 120 417 50 Mm Nb, Schedule Upto 40 418 50Mm Nb, Schedule Above 40 But Upto 80 419 50 Mm Nb, Schedule Above 120 420 80 Mm Nb, Schedule Upto 40 421 80Mm Nb, Schedule Above 40 But Upto 80 422 80 Mm Nb, Schedule Above 120 423 100Mm Nb, Schedule Upto 40 424 100Mm Nb, Schedule Above 40 But Upto 80 425 100Mm Nb, Schedule Above 120 426 150 Mm Nb, Schedule Upto 40 427 150 Mm Nb, Schedule More Than 40 But Upto 80 428 150 Mm Nb, Schedule Above 120 429 200 Mm Nb, Schedule Upto 20 430 200 Mm Nb, Schedule Above 20 But Upto 40 431 200 Mm Nb, Schedule More Than 40 But Upto 80 432 200 Mm Nb, Schedule Above 120 433 250 Mm Nb, Schedule Upto 20 434 250 Mm Nb, Schedule Above 20 But Upto 40 435 250 Mm Nb, Schedule More Than 40 But Upto 80 436 250 Mm Nb, Schedule Above 120 437 300 Mm Nb, Schedule Upto 20 438 300 Mm Nb, Schedule Above 20 But Upto 40 439 300 Mm Nb, Schedule More Than 40 But Upto 80 440 300 Mm Nb, Schedule Above 120 441 350 Mm Nb, Schedule Upto 20 442 350 Mm Nb, Schedule Above 20 But Upto 40 443 350 Mm Nb, Schedule More Than 40 But Upto 80 444 350 Mm Nb, Schedule Above 120 445 Alloy Steel Piping ( Astm A335 Gr. P22 ) Transportation Of All Piping Items From Owners Storage Points To Work Site And / Or Pre-Fabrication Yard And To Site After Pre-Fabrication; Cutting, Grinding, Edge Preparation Of Pipes And Fittings, Like Flanges, Elbows, Tees, Reducers Etc. To Match The Mating Edges Of Different Thickness; Fit-Up, Bending, Welding Using Approved Welding Electrodes As Per Owners Quality Requirements Etc. As Per Codes / Specifications, Drawings Etc. ( Alloy Steel Joints Shall Be Welded By Doing Root Run Using Tig Welding Followed By Filler Passes By Manual / Semi-Automatic Arc Welding. The Job Is To Be Pre-Heated Prior To Welding And All Joints To Be Stress Relieved And Fully Radiographed, However, Charges For Stress Relieving And Radiography Shall Be Paid Separately ) , Threading, Laying, Erection And Alignment Of Pipes At Ground Level I.E. Upto A Height Of 5 Meters On Sleepers, Pipe Racks Etc. Or Upto 5 Meters Depth In Trenches, Anchoring Wherever Required, Connecting With Equipment, Nozzles, Steam Traps, Strainers, Orifice Assemblies ( Including Tapping Upto First Block Valve ) , Spray Nozzles Rotameters; Tapping For Instrument Connections Like Pressure Gauges, Thermowells, Sample Connections, Vents, Drains Etc. Including Fixing Of All Types Of Sw Valves, Gaskets, Nuts And Bolts, All Inline Instruments, Elbows, Tees, Flanges, Reducers, Full Coupling Or Half Coupling, Reinforcement Pads, Earthing Strip Wherever Required; Welding Prefabricated Shoes And Supports ( Including Alignment ) As Per The Drawings Including Preparation Of Small Bore Isometric Upto 1.5 Inch Nb, Specifications, Codes Etc. And As Per The Instructions Of The Engineer-In-Charge To His Entire Satisfaction Including Supplying Of All Types Of Tools And Tackles, Lifting Arrangements, Equipment, Machineries, All Consumables And Labour Etc. To Complete The Work In All Respects In A Workman Like Manner Including Area Preparation For Hot Jobs, Area Cleaning After Completion Of Work, Flushing Wherever Required, Cleaning Of Pipes Externally Off All Foreign Materials Like Weld Beads, Clamps Fixtures Etc. Used In Fabrication As Directed By The Engineer-In-Charge. Note : Proper Safety Arrangements For Carrying Out The Job Is Under Contractors Scope And The Same Has To Be Complied With As Per The Dire Ctions Of The Engineer- In-Charge. Note: For Piping Beyond 5 Mtr. Elevation Above And Below Ground Piping And Upto 10Mtr. Rates Is To Be Escalated By 20%. For More Than 10 Mtr. But Upto 15 Mtr. Rates Is To Be Escalated By 30%. For More Than 15 Mtr But Upto 20 Mtr. Rates To Be Escalated By 40% Respectively. Requirement Of Scaffolding To Be Envisaged And Decided By Engineer In Charge As Per Site Requirement And Scaffolding Item To Be Paid Separately. Note: For Piping Where Tig Welding Is Used For Root Run Only, The Rates To Be Escalated By 15% And Where Tig Welding Is Used For Entire Joints The Rates To Be Escalated By 20%. 446 15 Mm Nb, Schedule Upto 80 447 15 Mm Nb, Schedule Above 80 448 20 Mm Nb, Schedule Upto 80 449 20 Mm Nb, Schedule Above 80 450 25 Mm Nb, Schedule Upto 80 451 25 Mm Nb, Schedule Above 80 452 40 Mm Nb, Schedule Upto 40 453 40Mm Nb, Schedule Above 40 But Upto 80 454 40 Mm Nb, Schedule Above 120 455 50 Mm Nb, Schedule Upto 40 456 50Mm Nb, Schedule Above 40 But Upto 80 457 50 Mm Nb, Schedule Above 120 458 80 Mm Nb, Schedule Upto 40 459 80Mm Nb, Schedule Above 40 But Upto 80 460 80 Mm Nb, Schedule Above 120 461 100Mm Nb, Schedule Upto 40 462 100Mm Nb, Schedule Above 40 But Upto 80 463 100Mm Nb, Schedule Above 120 464 150 Mm Nb, Schedule Upto 40 465 150 Mm Nb, Schedule More Than 40 But Upto 80 466 150 Mm Nb, Schedule Above 120 467 200 Mm Nb, Schedule Upto 20 468 200 Mm Nb, Schedule Above 20 But Upto 40 469 200 Mm Nb, Schedule More Than 40 But Upto 80 470 200 Mm Nb, Schedule Above 120 471 250 Mm Nb, Schedule Upto 20 472 250 Mm Nb, Schedule Above 20 But Upto 40 473 250 Mm Nb, Schedule More Than 40 But Upto 80 474 250 Mm Nb, Schedule Above 120 475 300 Mm Nb, Schedule Upto 20 476 300 Mm Nb, Schedule Above 20 But Upto 40 477 300 Mm Nb, Schedule More Than 40 But Upto 80 478 300 Mm Nb, Schedule Above 120 479 350 Mm Nb, Schedule Upto 20 480 350 Mm Nb, Schedule Above 20 But Upto 40 481 350 Mm Nb, Schedule More Than 40 But Upto 80 482 350 Mm Nb, Schedule Above 120 483 Fabrication & Fixing Of Fabric Bellow The Job Involves Removal Of Old Fabric Bellow From The Expansion Joint, Cleaning Of The Bellow And Fixing Of New Fabric Bellow With Bellow As Per Instruction Of Engineer-In-Charge Including Tools And Tackles And All Manpower. Dismantling / Erection Of Bellow Assembly And Supply Of New Fabric Bellow Shall Be In The Scope Of Iocl. 484 Cutting Various Sizes Of Gaskets Job Involves Collection Of Gasket Sheets From Materials Dept, Bringing Them To Drum Plant Or Wherever The Gasket Machine Is Available, Install The Die Required, Cut The Reqd Quantities Of Gaskets, As Advised By The Engineer-In-Charge. 485 25 Mm 486 40 Mm 487 50 Mm 488 80 Mm 489 100 Mm 490 150 Mm 491 200 Mm 492 250 Mm 493 300 Mm 494 350 Mm 495 400 Mm 496 450 Mm 497 500 Mm 498 600 Mm 499 700 Mm 500 750 Mm 501 Flame Heating Brg, Hub And Furnace Plug Etc. Heating Of Bearings, Hubs, Furnace Header Etc. By Gas At Different Elevations As Per Requirement And Instruction Of The Engineer-In-Charge. Including Supply Of All Tools, Tackles, Equipment#S, Labour, Consumables Etc. 502 B Dismatnling / Installation Of Valves 503 Removal Of Flanged / Rtj Valves Dismantling And Removal Of All Types Of Flanged Including Rtj Valves From Pipelines At Ground Level I.E. Up To A Height Of 5 Meters On Sleepers, Pipe Racks Etc. Or Up To 5 Meters Depth In Trenches Including Removal Of Gaskets, Nut Bolts Etc. And Transportation Either To Owners Storage Point / Workshop And / Or Scrapyard Including Loosening Of Studs, Disconnecting Earthing Protection All Complete As Per Direction Of The Engineer-In-Charge Including All Labour, Tools, Tackles, Consumables And Supervision Etc. 504 Installation Of Flanged / Rtj Valves Transportation Of All Types Of Flanged / Rtj Valves, Gaskets, Nut Bolts Etc. Either From Owners Storage Point To Workshop And / Or Worksite And Installation Of Valves At Ground Level I.E. Up To A Height Of 5 Meters On Sleepers, Pipe Racks Etc. Or Up To 5 Meters Depth In Trenches Including Assembly Of Valve Accessories, Cleaning Of Flanged Faces, Lapping Of Rtj Rings, Cutting The Gaskets To Proper Size, Placing The Gaskets / Rtj Ring Properly, Tightening Of Studs, Providing Earthing Protection By Way Of Fixing Strips, All Complete As Per Drawings And Direction Of The Engineer-In-Charge Including All Labour, Tools, Tackles, Consumables And Supervision Etc. 505 For Valves ( Other Than Rtj ) 506 For Rtj Valves 507 Extra For Over Head Installation / Removal Of Flanged / Rtj Valves At Additional Heights Extra For Overhead Installation / Removal Of Flanged Valves Of All Metallurgies For Every Additional Height Of Ten Metres Or Part Thereof. Note: Since Lift-Kg Unit Is Not Available In Sap, Hence For Estimate Unit Is To Be Taken As Kg. 508 Installation 509 Removal 510 C Steel Scaffolding Jobs 511 <H><U>Scaffolding Jobs To Be Done As Follows:-< / >< / > <H>1 ) For Normal Jobs, ( 100% ) Cup-Lok Type Of Scaffolding To Be Erected At Site.< / > <H>2 ) Only In Exceptional Cases, Where Erection Of Cup-Lok Type Of Scaffolding Is Not Possible At Site Due To In Accessibility Or Any Other Reason, Normal Scaffolding Pipes With Clamp Arrangement May Be Allowed After Clearance From Eic As Described< / >. 512 Steel Scaffloding Materials In Contractors Scope The Job Includes Transportation Of Scaffolding Materials In Contractors Scope Of Supply, Erection Of Scaffolding At Site Covering The Areas Specified Including Providing Vertical Posts Of Pipes At Inter Distance Of 1.5 M And Horizontal Numbers At A Inter Distance Of 0.5 To 0.75 M, Providing Tie Rods At Corners To Give Sufficient Strength To The Structure, Placing The Wooden / Steel Planks / Frp Gratings On Top For Making Sufficient Area. Dismantling Scaffolding After Completion Of Job And Returning The Scaffolding Material To Specified Place Including All Tools, Tackles, Consumables, Labours And Contractors Supervision As Directed By The Engineer-In-Charge 1. For Measurement In Sqm: 2 ( Length + Width ) X Height Area Covered By The Scaffolding Is To Be Taken. 2. Scaffolding Measurement To Be Done By Breaking The Height Into Parts As Per Height Slab Mentioned Below And Adopting Respective Rates Against Mentioned Height Slabs. 513 Upto 6 M 514 Above 6 M Upto 10 M 515 Above 10 M Upto 20 M 516 Above 20 M Upto 30 M 517 Above 30 M Upto 40 M 518 Above 40 M Upto 50 M 519 Intermediate Plate Form 520 D Dismanlting Of Structure 521 Dismantling Of Structurals Like Pipe Support / Stairway / Devit Etc. Removal Of Existing Platforms / Pipe Supports / Davits / Stairways Etc. Along With Adjacent Fittings / Members By Cutting / Debolting Or By Any Other Means Without Damaging The Remaining Unit And Lowering Down To The Ground Including Erection Of Scaffolding, Retrieving Of All The Usable Materials And Transportation To The Storage Point As Directed By The Engineer-In-Charge. 522 Fabrication And Erection Of Pipe Support / Platforms / Devits / Stair Case Etc. The Job Includes Getting The Materials Issued, Transportation To Work Site And Handling At Site, Fabrication At The Required Size And Shape Using Steel Pipes, Ms Structural / Plates Etc. By Cutting, Bevelling And Welding Including Fixing Of Ms Gratings / Chequered Plates On Platform At All Elevation By Welding, Bolting Or Otherwise To Existing Members Or Equipment. This Also Includes Fabrication And Fixing Of Pipe Clamps, Non-Standard Bolts Etc. Inclusive Of Labour, Consumables, Tools And Tackles And Materials Required For U-Clamps, J-Bolts Etc. And Applying One Coat Of Primer And Two Coats Of High Built Black Bituminous Paint And Complete In All Respect As Per Drawings, Specifications And Instructions Of The Engineer-In-Charge. ( Excluding Cost Of Structural Steel ) . 523 Installation Of Vessels / Columns / Drums / Filters Upto 5 Mt Transportation Of Vessel / Columns / Filters / Drums Etc. From Owners Storage Point To Worksite, Assembly Of Parts, Sub-Assemblies ( Including Internals ) , Erection At All Elevations, Aligning, Tightening Of Bolts, Grouting, Cleaning, Hydrotesting And Flushing By Water, Draining, Drying By Compressed Air And Installation Of All Mountings And Completing The Works In All Respects Including Earthing Protection By Way Of Fixing Strips And Electrodes As Per Drawings And Specifications. Job Also Includes Supplying Of All Types Of Tools, Tackles, Lifting Arrangements, Cranes, Tractor Trolley And Equipment, Machineries All Consumables And Labour To Complete The Job In A Workman Like Manner, Erection And Removal Of Steel Scaffolding Wherever Required, Area Preparation For Hot Job And Area Cleaning After Completion Of Work Including Blinding, Deblinding, Removal Of Insulation, Gas Cutting Of Bolts, Chipping Of Foundation, Flushing Wherever Required. All Jobs Are To Be Carried Out As Per The Instruction And To The Full Satisfaction Of The Engineer-In-Charge. 524 Installation Of Vessels / Columns / Drums / Filters More Than 5 Mt And Upto 10 Mt Transportation Of Vessel / Columns / Filters / Drums Etc. From Owners Storage Point To Worksite, Assembly Of Parts, Sub-Assemblies ( Including Internals ) , Erection At All Elevations, Aligning, Tightening Of Bolts, Grouting, Cleaning, Hydrotesting And Flushing By Water, Draining, Drying By Compressed Air And Installation Of All Mountings And Completing The Works In All Respects Including Earthing Protection By Way Of Fixing Strips And Electrodes As Per Drawings And Specifications. Job Also Includes Supplying Of All Types Of Tools, Tackles, Lifting Arrangements, Cranes, Tractor Trolley And Equipment, Machineries All Consumables And Labour To Complete The Job In A Workman Like Manner, Erection And Removal Of Steel Scaffolding Wherever Required, Area Preparation For Hot Job And Area Cleaning After Completion Of Work Including Blinding, Deblinding, Removal Of Insulation, Gas Cutting Of Bolts, Chipping Of Foundation, Flushing Wherever Required. All Jobs Are To Be Carried Out As Per The Instruction And To The Full Satisfaction Of The Engineer-In-Charge. 525 E Shutdown Factor 526 Shutdown Factor-25%
Basic Detail
Tender No BN20AD011
Bidding Type Tender
Location
City BGR, Dhaligaon
State Assam
Key Dates
Publish Date 28 Jan 2020
Submission Date 04 Feb 2020
Open Date 05 Feb 2020
Finance
Tender Value 1.32 Crore
Tender Fee Ref. Documents
EMD 1.32 Lakhs
Exemption Not Available
Document List
Tendernotice_1.pdf
13E19C07-1965-421B-BFAE-DAB039B02155.html
BOQ_122300.xls
GCC.pdf
FAQs-IOCL-Online-EMD.pdf
Tender-Acceptance-Format.pdf
TenderBN20AD011.rar
Special_Instructions_to_the_Bidders_20190325.pdf

Unlock Full AI Tender Summary

Get instant access to the complete AI-generated analysis — scope, eligibility, timeline & more.

Instant Access Secure Free
Your details are secure and used only for document delivery.

Tender Timeline

Jan 28, 2020
11:30 IST

Tender Published

Tender notice published.

Completed
Feb 04, 2020
17:00 IST

Bid Submission Deadline

Online submission via eProcurement portal.

Completed
Feb 05, 2020

Bid Opening Date

Technical bids will be opened and evaluated.

Completed

Tender Documents

Download All (ZIP) ↓
pdf

Tendernotice_1.pdf

html

13E19C07-1965-421B-BFAE-DAB039B02155.html

xls

BOQ_122300.xls

pdf

GCC.pdf

pdf

FAQs-IOCL-Online-EMD.pdf

pdf

Tender-Acceptance-Format.pdf

rar

TenderBN20AD011.rar

pdf

Special_Instructions_to_the_Bidders_20190325.pdf

Disclaimer

We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender

TenderDetail
Loading tenders