| 1 | 1 | MAINTENANCE OF EXISTING MACHINE ROOM AND WORKSHED | | | |
|---|
| 2 | 1.01 | Demolishing works (LS) | | 1 | No |
|---|
| 3 | 1.02 | Supplying and fixing wood work for doors, windows and ventilators including cost of all materials and labour charge etc. complete | | 6 | Nos |
|---|
| 4 | 1.03 | Providing and fixing MS Grills of required pattern in frames of ventilator etc with MS flats square or round bars etc.including priming coat with approved steel primer all complete. Fixed to steel ventilator by welding | | 278.4 | kg |
|---|
| 5 | 1.04 | Plastering with MS 1:4 12mm thick for inside and outside the wall including cost of all material, labour charge etc | | 171.8 | m2 |
|---|
| 6 | 1.05 | Flooring in cement concrete 1:4:8 using 40mm brocken stone including cost of all material, labour charge etc. complete | | 4.24 | m3 |
|---|
| 7 | 1.06 | Floor plastering with cm1:3 12mm thick over the concrete including cost of all material, labour charge etc complete | | 42.44 | m2 |
|---|
| 8 | 1.07 | Cement washing one coat and white washing two coats over the wall including cost of all material, labour charge etc | | 171.8 | m2 |
|---|
| 9 | 1.08 | Steel workbuiltup tubular trusses etc including cutting , hoisting fixing position and applying a priming coat of steel primer, including welding and bolted with special shaped washers etc complete. Hot finished seamless type tubes | | 354.28 | kg |
|---|
| 10 | 1.09 | Roofing with GI Hard colour power coated triffod sheets 0.35mm thick or nearest available thickeness with overlap 150mm at ends and GI hook or crank CI bolts and nuts including plain washers and bitumin washers etc. complete | | 88.57 | m2 |
|---|
| 11 | 1.1 | Ridge caping with prepainted galvanized steel sheet .5mm thick 60cm wide including all cost and materials, conveyance, labour charges etc complete | | 11.05 | m |
|---|
| 12 | 1.2 | Electrification (LS) | | 1 | no |
|---|
| 13 | 2 | Workshed and rest Room, Existing workshed griil work, painting | | | |
|---|
| 14 | 2.01 | Earth work excavation in ordinary soil and despositing on bank with initial lead and lift etc complete for wbuilding work | | 17.71 | m3 |
|---|
| 15 | 2.02 | Random rubble masonary in CM 1 :6 for foundation and basement including cost of all material labour charge etc complete for foundation and basement | | 26.62 | m3 |
|---|
| 16 | 2.03 | Laterite massonary in CM 1:6 for super structure including cost of all material labour charge etc conmplete | | 26.02 | m3 |
|---|
| 17 | 2.04 | RCC 1:2:4 using 20 mm broken stone including cost alla material labour charge etc.complete | | 2.93 | m3 |
|---|
| 18 | 2.05 | Steel reinforcement for RCC work including straightening cutting, bending, placing in position and binding all complete up to plinth level | | 300 | kg |
|---|
| 19 | 2.06 | Supplying and fixing wood work for doors, windows and ventilators including cost of all materials and labour charge etc. complete | | 13 | nos |
|---|
| 20 | 2.07 | Providing and fixing MS Grills of required pattern in frames of ventilator etc with MS flats square or round bars etc.including priming coat with approved steel primer all complete. Fixed to steel ventilator by welding | | 31.2 | m2 |
|---|
| 21 | 2.08 | Plastering with MS 1:4 12mm thick for inside and outside the wall including cost of all material, labour charge etc | | 265.61 | m2 |
|---|
| 22 | 2.09 | Flooring in cement concrete 1:4:8 using 40mm brocken stone including cost of all material, labour charge etc. complete | | 6.77 | m3 |
|---|
| 23 | 2.1 | Floor plastering with cm1:3 12mm thick over the concrete including cost of all material, labour charge etc complete | | 67.91 | m2 |
|---|
| 24 | 2.11 | Cement washing one coat and white washing two coats over the wall including cost of all material, labour charge etc | | 265.61 | m2 |
|---|
| 25 | 2.12 | Steel workbuiltup tubular trusses etc including cutting , hoisting fixing position and applying a priming coat of steel primer, including welding and bolted with special shaped washers etc complete. Hot finished seamless type tubes | | 548.8 | kg |
|---|
| 26 | 2.13 | Roofing with GI Hard colour power coated triffod sheets 0.35mm thick or nearest available thickeness with overlap 150mm at ends and GI hook or crank CI bolts and nuts including plain washers and bitumin washers etc. complete | | 137.2 | m2 |
|---|
| 27 | 2.14 | Ridge caping with prepainted galvanized steel sheet .5mm thick 60cm wide including all cost and materials, conveyance, labour charges etc complete | | 18.2 | m |
|---|
| 28 | 2.15 | Electrification | | 1 | no |
|---|
| 29 | 3 | Existing workshed grill work, painting | | | |
|---|
| 30 | 3.01 | Providing and fixing MS Grills of required pattern in frames of ventilator etc with MS flats square or round bars etc.including priming coat with approved steel primer all complete. Fixed to steel ventilator by welding | | 39.26 | m2 |
|---|
| 31 | 3.02 | Cement washing one coat and white washing two coats over the wall including cost of all material, labour charge etc | | 103.11 | m2 |
|---|
| 32 | 3.03 | Electrification | | 1 | no |
|---|
| 33 | 4 | Restroom and toilet | | | |
|---|
| 34 | 4.01 | Earth work excavation in ordinary soil with in an intitial lead of 50k and lift 1.5m including labour charge etc. complete | | 7.68 | m3 |
|---|
| 35 | 4.02 | Random rubble masonary in CM 1 :6 for foundation and basement including cost of all material labour charge etc complete for foundation and basement | | 11.54 | m3 |
|---|
| 36 | 4.03 | Laterite massonary in CM 1:6 for super structure including cost of all material labour charge etc conmplete | | 14.44 | m3 |
|---|
| 37 | 4.04 | RCC 1:2:4 using 20 mm broken stone including cost of all material labour charge etc.complete | | 4.962 | m3 |
|---|
| 38 | 4.05 | Steel reinforcement for RCC work including straightening cutting, bending, placing in position and binding all complete up to plinth level | | 500 | kg |
|---|
| 39 | 4.06 | Supplying and fixing wood work for doors, windows and ventilators including cost of all materials and labour charge etc. complete | | 14 | nos |
|---|
| 40 | 4.07 | Plastering in CM 1:4 12mm thick for inside and outside the wall including cost of all material labour charge etc. complete | | 159 | m2 |
|---|
| 41 | 4.08 | Plastering with cm 1:4 12mm thick over the roof slab including cost of all material, labour charge etc. complete | | 38.37 | m2 |
|---|
| 42 | 4.09 | Plastering in CM 1:3 9mm for ceiling and sunshade including cost of all material labour charge etc complete | | 33.17 | m2 |
|---|
| 43 | 4.1 | Flooring in cement concrete 1:4:8 using 40mm brocken stone including cost of all material, labour charge etc. complete | | 1 | m3 |
|---|
| 44 | 4.11 | Floor plastering with cm1:3 12mm thick over the concrete including cost of all material, labour charge etc complete | | 20.02 | m2 |
|---|
| 45 | 4.12 | Cement washing one coat and white washing two coats over the wall including cost of all material, labour charge etc | | 192 | m2 |
|---|
| 46 | 4.13 | Electrification & water supply | | 1 | nos |
|---|
| 47 | 5 | Workshed goodown | | | |
|---|
| 48 | 5.01 | Earth work excavation in ordinary soil with in an intitial lead of 50m and lift 1.5m including labour charge etc. complete | | 7.91 | m3 |
|---|
| 49 | 5.02 | Random rubble masonary in CM 1 :6 for foundation and basement including cost of all material labour charge etc complete for foundation and basement | | 11 | m3 |
|---|
| 50 | 5.03 | Laterite massonary in CM 1:6 for super structure including cost of all material labour charge etc complete | | 4 | m3 |
|---|
| 51 | 5.04 | Supplying and fixing wood work for doors, windows and ventilators including cost of all materials and labour charge etc. complete | | 2 | m4 |
|---|
| 52 | 5.05 | Providing and fixing MS Grills of required pattern in frames of ventilator etc with MS flats square or round bars etc.including priming coat with approved steel primer all complete. Fixed to steel ventilator by welding | | 529 | kg |
|---|
| 53 | 5.06 | Plastering in CM 1:4 12mm thick for inside and outside the wall including cost of all material labour charge etc. complete | | 60 | m2 |
|---|
| 54 | 5.07 | Flooring in cement concrete 1:4:8 using 40mm brocken stone including cost of all material, labour charge etc. complete | | 3.1 | m3 |
|---|
| 55 | 5.08 | Floor plastering with cm1:3 12mm thick over the concrete including cost of all material, labour charge etc complete | | 31.04 | m2 |
|---|
| 56 | 5.09 | Cement washing one coat and white washing two coats over the wall including cost of all material, labour charge etc | | 352 | m2 |
|---|
| 57 | 5.1 | Steel workbuiltup tubular trusses etc including cutting , hoisting fixing position and applying a priming coat of steel primer, including welding and bolted with special shaped washers etc complete. Hot finished seamless type tubes | | 1046 | kg |
|---|
| 58 | 5.11 | Roofing with GI Hard colour power coated triffod sheets 0.35mm thick or nearest available thickeness with overlap 150mm at ends and GI hook or crank CI bolts and nuts including plain washers and bitumin washers etc. complete | | 261.47 | m2 |
|---|
| 59 | 5.12 | Ridge caping with prepainted galvanized steel sheet .5mm thick 60cm wide including all cost and materials, conveyance, labour charges etc complete | | 17.84 | m |
|---|
| 60 | 5.13 | Electrification | | 1 | no |
|---|
| 61 | 6 | Workshed | | | |
|---|
| 62 | 6.01 | Providing and fixing MS Grills of required pattern in frames of ventilator etc with MS flats square or round bars etc.including priming coat with approved steel primer all complete. Fixed to steel ventilator by welding | | 321 | kg |
|---|
| 63 | 6.02 | Cement washing one coat and white washing two coats over the wall including cost of all material, labour charge etc | | 118 | m2 |
|---|
| 64 | 6.03 | Steel work built up tubular trusses etc including cutting, hoisting fixing position and applying a priming coat of steel primer including welding and bolted with special shaped washers etc complete. Hot finished seamless type tubes | | 414 | kg |
|---|
| 65 | 6.04 | Roofing with GI Hard colour power coated triffod sheets 0.35mm thick or nearest available thickeness with overlap 150mm at ends and GI hook or crank CI bolts and nuts including plain washers and bitumin washers etc. complete | | 104 | m2 |
|---|
| 66 | 6.05 | Ridge caping with prepainted galvanized steel sheet .5mm thick 60cm wide including all cost and materials, conveyance, labour charges etc complete | | 17 | m |
|---|
| 67 | 6.06 | Electrification | | 1 | no |
|---|