Power Boards / Undertakings / PSU Closing in 0 days TDR #22508604

Repairs To Office Shed, Laying Of Borewell, Construction Of Balance Compound Wall And Rectification Of Ac Sheets To Stores At Durshed In Karimnagar District

Issued by Boards / Undertakings / PSU · KARIMNAGAR, Telangana
Tender Value
57.35 Lakhs
Estimated cost
Bid Submission
03 Dec 2019
0 days left
EMD
1.15 Lakhs
Bank guarantee accepted
Document Fee
Ref. Documents
Non-refundable
Tender Type
Online

Tender Overview

Competition Type
NCB
Bidding Type
Tender
Location / State
KARIMNAGAR → Telangana
EMD Exemption
Not Available
Quantity
Not Available

Project Description

Repairs To Office Shed, Laying Of Borewell, Construction Of Balance Compound Wall And Rectification Of Ac Sheets To Stores At Durshed In Karimnagar District

BOQ

b'
S.No Subwork Name Specification Number Quantity UOM Rate(INR) Amount(INR)
1 Construction of Compoundwall at 132KV SS Durshed Taxes 0 LS 4800487.93 4800.49
GST at 18%on total value of civil works
2 Construction of Compoundwall at 132KV SS Durshed NAC 0.18 LS 4856135.05 874104.31
Corpus Fund towards NAC
3 Construction of Compoundwall at 132KV SS Durshed Charges 1.00 LS 55647.12 55647.12
Seignorage charges including SMET 2%
4 Construction of Compoundwall at 132KV SS Durshed Spl.Spec 5.00 One Sq 1017.62 5088.10
S&F of plain clear float glass 5mm thick including all labour charges for fixing the glass to window shutters etc., complete for finised item of work.
5 Construction of Compoundwall at 132KV SS Durshed Spl.Spec 50.00 One Sq 28.22 1411.00
Supply and fixing of G.I ?J? bolts / nuts 8mm dia /G.I plain washers /bitumen washers inplace of damaged or not available over the AC Roof sheets by proper fixing, nutting at site as per the directions of Engineer in charge including labour charges complete for finished item of work.
6 Construction of Compoundwall at 132KV SS Durshed Spl.Spec 60.00 One Sq 97.25 5835.00
Roofing with 6 mm thick corrugated asbestos cement sheets, fixing with G.I ?J? bolts & nuts 8mm dia G.I plain washers complete including seigniorage charges etc., complete for finished item of work, but excluding the cost of purlins, rafters, trusses & cost of conveyance of all
7 Construction of Compoundwall at 132KV SS Durshed Spl.Spec 32.00 One Sq 6.99 223.53
Dismantling of existing flooring plastering including clearing away the debris from site with all leads and lifts , labour complete as per the directions of the Engineer-in - charge for finished item of work.
8 Construction of Compoundwall at 132KV SS Durshed Spl.Spec 65.00 One Sq 343.85 22350.25
Supplying & Fixing of expansion joint filler board conforming to IS: 1838 for buildings, columns, beams and slabs 20 mm THICK of CC road in lateral and longitudinal direction complete as per the direction of the Engineer in charge for the finished item of work.
9 Construction of Compoundwall at 132KV SS Durshed Spl.Spec 170.00 One Cum 5665.94 963209.80
Construction of Plain Cement Concrete Road with M20 Nominal Mix (1:2:4) using 40mm & 20mm HBG metal (50% each), jointed at expansion and construction joint only, over a prepared sub base, with 43 grade cement (330 kgs per Cum) , coarse and fine aggregates conforming to IS : 383, maximum in a concrete mixer of not less than 0.2 cum capacity and appropriate weigh batcher using approved mix design, laid in approved fixed side formwork (steel channel, including levelling the formwork as per drawing),providing joint filler board, spreading the concrete with sholvels, rakes, compacted using needle, scareed and plate vibrators and finished in continuous operation including provision of contraction and expansion, construction joints,, curing of concrete for 14- days, complete as per as per drawing and as directed by the Engineer in charge for the finished item of work.(Technical Specification Clause 1501 MORD).
10 Construction of Compoundwall at 132KV SS Durshed Spl.Spec 90.00 One Cum 2005.92 180532.80
Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam specification including premixing the material with water at OMC in mechanical mixer (Pug Mill), carriage of mixed materiald by tipper to site, laying in uniform layers in sub-base/ base course on a well prepared sub-base and compacting with smooth wheel roller of 80 to 100 kN/ Vibratory Roller 80-100 kN weight to achive the desired density including lighting, barricading and maintenance of diversion, etc., as per tables 400.11 & 400.12 and technical specification clause 406 MORD/ MORTH.
11 Construction of Compoundwall at 132KV SS Durshed Spl.Spec 2.00 One No 4016.37 8032.74
Providing independent earthing by excavating a trench to a depth of 2.1m in all soils, as per size specified in the data, using 40mm dia \'B\' class GI pipe of 2.5m length with necessary accessories with hume pipe ring duly providing staggered holes including filling with equal proportion of salt and charcoal in layers and including giving connections and labour charges and cost of materials complete for small quarters as directed by the Engineer in charge for the finished item of work at all levels of building.
12 Construction of Compoundwall at 132KV SS Durshed Spl.Spec 150.00 One RM 64.10 9615.00
Supply and Laying of P.V.C casing and caping (Modi make or equivalent )(ISI MARK) with double locking arrangments with groover trunking of size not below 12.5mm height for the following sizes with all accessories, duly sealed at points and erected on Wall / Ceiling including cost of all materials and labour charges complete 32mm x 12.5mm height
13 Construction of Compoundwall at 132KV SS Durshed Spl.Spec 100.00 One RM 59.63 5963.00
Supply and Laying of P.V.C casing and caping (Modi make or equivalent )(ISI MARK) with double locking arrangments with groover trunking of size not below 12.5mm height for the following sizes with all accessories, duly sealed at points and erected on Wall / Ceiling including cost of all materials and labour charges complete 25mm x 12.5mm height
14 Construction of Compoundwall at 132KV SS Durshed Spl.Spec 80.00 One RM 52.92 4233.60
Supply and Laying of P.V.C casing and caping (Modi make or equivalent )(ISI MARK) with double locking arrangments with groover trunking of size not below 12.5mm height for the following sizes with all accessories, duly sealed at points and erected on Wall / Ceiling including cost of all materials and labour charges complete 19mm/20mm x 12.5mm height
15 Construction of Compoundwall at 132KV SS Durshed Spl.Spec 4.00 One No 8075.72 32302.88
Supply and fixing of 400W MH Flood light luminaire with Non- integral weather proof diecast aluminium housing with IP66 protection with control gear box (of make Wipro / G.E. Venture / Phillips / Bajaj / Crompton / Surya /Halonix) with 400W MH Lamp )of make Phillips / Osram / Crompton / Bajaj / Surya / HPL / Havells /Halonix) with 16A flush type Swich (of make GM G Home / Gold Medal Olive / Million Zoom / Anchor Penta Cherry / Great white Omega / HPL / Vimal / CPL) including cost of all materials and labour charges etc. complete as directed by the Engineer in charge for the finished item of work at all levels of building.
16 Construction of Compoundwall at 132KV SS Durshed Spl.Spec 3.00 One No 1186.52 3559.56
Supply and fixing of 20A SP plug and socket (Legrand/Schindler make) for air conditioners including earth connection all labour charges, complete for finished item of work.
17 Construction of Compoundwall at 132KV SS Durshed Spl.Spec 2.00 One No 885.00 1770.00
Supply and fixing in position 32A. Main Switch (Sputnik or equivalent make) and including giving connections and labour charges and cost of materials complete as directed by the Engineer in charge for the finished item of work at all levels of building.
18 Construction of Compoundwall at 132KV SS Durshed Spl.Spec 150.00 One RM 75.05 11257.50
Run 2 of 36/0.30 (2.5 Sqmm) FR PVC insulated flexible Copper Cable (Makes: Finolex / RR kabel / Havells / APAR EBXL / KEI / L&T / VGuard) in existing pipe for Mains from Distribution board to 15Amps 3 pin Power Plug including giving connections and labour charges and cost of materials complete as directed by the Engineer in charge for the finished item of work at all levels of building.
19 Construction of Compoundwall at 132KV SS Durshed Spl.Spec 150.00 One RM 113.93 17089.50
Run 2 of 56/0.30 (4.0Sqmm) FR PVC insulated flexible copper cable (Makes: Finolex / RR kabel / Havells / APAR EBXL / KEI / L&T / VGuard) in existing pipe for run of Mains from Main switch to Distribution board as per colour code of wires including giving connections and labour charges and cost of materials complete as directed by the Engineer in charge for the finished item of work at all levels of building.
20 Construction of Compoundwall at 132KV SS Durshed Spl.Spec 50.00 One RM 312.76 15638.00
Supply and Run 4 of 84/0.30 (6.0Sqmm) FR PVC insulated flexible Copper cable (Makes: Finolex / RR kabel / Havells / APAR EBXL / KEI / L&T / VGuard) in existing pipe for run of Mains from AC panel to 32Amps Main switch as per colour code of wires including giving connections and labour charges and cost of materials complete as directed by the Engineer in charge for the finished item of work at all levels of building.
21 Construction of Compoundwall at 132KV SS Durshed Spl.Spec 4.00 One No 3427.83 13711.32
Supply and fixing of 4 Way SPN DB with IP 20 Protection as per IS:13032 and suitable for 4Nos S.P out goings and for 1 No Incommer etc complete of makes Legrand / Schneider / Siemens / L&T / Cabtree Xpro make) with IP-20 protection suitable for single phase ELCB/RCCB/DP Isolator (Legrand-DX3 / Schneider-Acti9 / Siemens / L&T Exora /Cabtree) as incomer and 10KA SP MCBs (Legrand-DX3 / Schneider-Acti9 / Siemens / L&T Exora /Cabtree) as out-going including internal connection and labour charges and cost of materials complete as directed by the Engineer in charge for the finished item of work at all levels of building for surface/flush mounting.
22 Construction of Compoundwall at 132KV SS Durshed Spl.Spec 10.00 One No 253.51 2535.10
Supply and fixing of 6A/10A 3/2 pin modular socket of (Legrand Arteor / Schneider Zen celo / Honeywell Blenge Plus / Cabtree Amare / Logus Platina) etc with 6A modular switch control of same make on a common switch board with earth continuity including wire leads, earth connections along with all labour charges etc., complete as per the directions of the Engineer in charge at site.
23 Construction of Compoundwall at 132KV SS Durshed Spl.Spec 10.00 One No 362.81 3628.10
Supply and fixing of 16A /6 A, 1 way 2 Module Combi Socket with indicator lamp /fuse unit of (Legrand Arteor / Schneider Zen celo / Honeywell Blenge Plus / Cabtree Amare / Logus Platina.) etc with 16A modular switch control (same make.)on a common switch board with earth continuity including wire leads, earth connections along with all labour charges etc., complete as per the directions of the Engineer in charge at site.
24 Construction of Compoundwall at 132KV SS Durshed Spl.Spec 12.00 One No 249.58 2994.96
Supply and fixing of HID / batten holder / slanting holder (Wipro/G.E./Phillips) in lieu of ceiling rose of light point complete with all connections and all labour charges with 36 W CFL lamp (Phillips / Crompton / Bajaj / Surya / Havells / HPL / Halonix) (for new installation).
25 Construction of Compoundwall at 132KV SS Durshed Spl.Spec 20.00 One No 1064.87 21297.40
Supply and fixing of 1 x 28W Box type powder coated energy conserving tube light luminaire with Electronic ballast operating voltage range of 90 volts to 350 volts power factor > 0.98 current less than 130ma crest factor and total hormonic distortion shall be as per IS Specification with auto cut off at high voltage suitable for 36/40W tube with 5 years guarantee for luminaire. Makes: Trinic or its equivalent with all accessories including giving connections, all labour charges and cost of materials complete as directed by the Engineer in charge for the finished item of work.
26 Construction of Compoundwall at 132KV SS Durshed Spl.Spec 16.00 One No 1346.51 21544.16
Supply and fixing of 2 X 36/40 Box type tube light luminaire powder coated CRCA sheet steel housing with 2 Nos Electronic Ballast Chokes and all standard accessories of makes (Wipro / GE Venture / Phillips / Crompton / Bajaj) and 2 Nos 36/40W tube ( Phillips / Crompton / Bajaj / Surya make) on Teak Wood Block on ceiling or wall with all accessories including giving connections, all labour charges and cost of materials complete as directed by the Engineer in charge for the finished item of work.
27 Construction of Compoundwall at 132KV SS Durshed Spl.Spec 6.00 One No 3316.56 19899.36
Supply and fixing of 1200mm(48\") 230V, AC, 50Hz ceiling fan 5 star rated with 3 blades and double ball bearings of standard make (Crompton High Speed Decora / Bajaj Regal star / Havells Fusion 50 / Orient Summer Crown / Usha technix decorative) with suitable down rod covered with flexible pipe, Stepped type heavy duty electronic regulator (Anchor make) with all standard accessories including cost of all fittings and fixtures, labour for fixing at all positions of building giving electrical connections with necessary tools complete as directed by the Engineer in charge for finished item of work.
28 Construction of Compoundwall at 132KV SS Durshed Spl.Spec 80.00 One poi 665.33 53226.40
Wiring with 2 runs of 22/0.30(1.5 M2m) Fire Retardant (FR) P.V.C. insulated flexible copper cable (ISI MARK) (Finolex / RR kabel / Havells / APAR EBXL / KEI / L&T / VGuard make) in existing pipe with 6A Modular switch (Legrand Arteor / Schneider Zen celo / Honeywell Blenge Plus / Cabtree Amare / Logus Platina.make, Ceiling rose (Anchor make), Hot dip galvanizes metal (Modular) control box (Legrand Arteor / Schneider Zen celo / Honeywell Blenge Plus / Cabtree Amare / Logus Platina) and 6 Modular cover frame (Legrand Myrius /Million Tap-Wood / Gold Medal Curve /Anchor Roma viola / GM Four-Five / Salzar / Stanjo Amron / Havells Fabio / C&S / Benlo make) including all labour charges etc., complete for light, bell, fan and exhaust fan points in Non-Residential Buildings.
29 Construction of Compoundwall at 132KV SS Durshed Spl.Spec 3.00 One No 1447.36 4342.08
Supply and fixing of light weight 457.2mm x 457.2mm (1\'6\'\'x1\'6\'\') CI frame and cover of 20 Kg weight including cost and conveyance of all materials, labour charges complete as per the directions of the Engineer in charge for the finished item of work.
30 Construction of Compoundwall at 132KV SS Durshed Spl.Spec 1.00 One No 8382.38 8382.38
Providing & Placing on Terrace (at all floor levels) polyethylene water storage tank of 1000 Ltrs capacity with Double layer approved brand & manufacture (SINTEX or equalent ISI make) with cover and suitable locking arrangement & making necessary holes for inlet & outlets and over flow pipes but without fittings & base support for tanks including cost and conveyance of all materials, all fixtures, all leads and lifts complete as per the directions of the Engineer in charge for the finished item of work.
31 Construction of Compoundwall at 132KV SS Durshed Spl.Spec 4.00 One NO 260.00 1040.00
Supplying and fixing long body C.P. Taps including cost and conveyance, labour charges complete as per the directions of the Engineer in charge for the finished item of work.
32 Construction of Compoundwall at 132KV SS Durshed Spl.Spec 10.00 One RM 284.64 2846.40
Providing and fixing in position at all levels of the building under floors and against walls 110mm dia (4kg/cm2) PVC pipes of prince / sudhakar or any ISI brand make with specials such as junctions,couplers, bends/Tees etc., with or without access doors as required and with solvent jointing as per standard practice wherever necessary including excavation and refilling wherever required,, testing etc. complete as per the directions of the Engineer in charge for the finished item of work.
33 Construction of Compoundwall at 132KV SS Durshed Spl.Spec 30.00 One RM 164.30 4929.00
Supplying and fixing CPVC pipes of SDR 13.50 pipes Medium Grade as per IS 15778 of approved make for water supply line to toilets including cost and conveyance of pipe, specials such as elbows, Tees concealing same in walls and floors by cutting 25/ 20/ 15mm dia to be included grooves, packing, finishing after laying pipe in position as per the directions of the Engineer in charge for the finished item of work 15.90mm Outer dia pipe
34 Construction of Compoundwall at 132KV SS Durshed Spl.Spec 30.00 One RM 184.42 5532.60
Supplying and fixing CPVC pipes of SDR 13.50 pipes Medium Grade as per IS 15778 of approved make for water supply line to toilets including cost and conveyance of pipe, specials such as elbows, Tees concealing same in walls and floors by cutting 25/ 20/ 15mm dia to be included grooves, packing, finishing after laying pipe in position as per the directions of the Engineer in charge for the finished item of work 22.20mm outer dia pipe
35 Construction of Compoundwall at 132KV SS Durshed 1326 & 1327 2.00 One No 553.23 1106.46
Supplying and fixing TV Shape mirror with PVC frame size 609.6x457.2mm including cost & conveyance of materials and labour for fixing complete as per the directions of the Engineer in charge for the finished item of work.
36 Construction of Compoundwall at 132KV SS Durshed 1326 & 1327 1.00 One No 574.47 574.47
Supplying and fixing CP finish Brass Soap dish heavy type with NP Screws including cost & conveyance of materials and labour for fixing complete as per the directions of the Engineer in charge for the finished item of work.
37 Construction of Compoundwall at 132KV SS Durshed 1326 & 1327 2.00 One No 402.35 804.70
Supplying and fixing S&F CP finish steel towel rod of 600 mm long and 20 mm dia with brackets of Ist quality Jaquar/ Hindware/ Plumber/ Parryware/ H & R Johnsonas per the directions of the Engineer in charge for the finished item of work.
38 Construction of Compoundwall at 132KV SS Durshed 1326 & 1327 1.00 One No 902.78 902.78
Supplying and fixing white glazed flat back Bowl urinal basin (Indian type) of size 440x265x315mm of HSW/Parry/Neycer make including all fixtures, labour for fixing as per the directions of the Engineer in charge for the finished item of work.
39 Construction of Compoundwall at 132KV SS Durshed 1326 & 1327 1.00 One No 1199.24 1199.24
Supplying and fixing Pedestal for wash hand basin (HSW/Parry/Earthenware ) make including cost of all fixtures, labour for fixing as per the directions of the Engineer in charge for the finished item of work.
40 Construction of Compoundwall at 132KV SS Durshed 1326 & 1327 2.00 One No 1756.11 3512.22
Supplying & Fixing 550x400 mm- single C.P. Pillar cock Indian make Flat Back Wash Hand Basin (HSW/Parryware/ Neycer) 1st quality conforming to IS:2556-Part-4:1972 with waste fittings like rubber plug, chain, 32 mm nominal size C.P. Fitting with parallel pipe thread conforming to IS:2963-1979 and fitted with 15 mm nominal bore Chromium Plated Pillar Tap of 1st quality Indian make 400 grams Seiko/ Esso or equivalent complete with standard CI brackets including wooden block as per the directions of the Engineer in charge for the finished item of work.
41 Construction of Compoundwall at 132KV SS Durshed Spl.Spec 2600.00 One Kg 94.81 246506.00
Supply and fixing in position M.S. grills/Angles/gates of required size of approved design and quality. (for, gates, windows, hand railing in front of portico, retaining walls ,) and painting with two coats of synthetic enamel paint of approved quality, make, colour and shade over one coat of red oxide, complete as per the directions of the Engineer in charge for the finished item of work.
42 Construction of Compoundwall at 132KV SS Durshed Spl.Spec 40.00 One RM 4897.25 195890.00
Providing stainless steel hand railing by running with styles made with 50mm dia 304 Grade of 900mm long at 1m interval, horizontal supports of 3 Nos 19mm dia 304 Grade pipes and hand railing with 50 mm dia 304 Grade pipes, drilling the holes in the concrete in 1 RM cente to center to insert the spikes with plate welded to the stainless steel tubes and grouting including cost of all materials and labour charges for Fabrication of stainless steel railing works using stainless steel welding rods including buffing, polishing, lacquer finishing, to present seamless finish for finished item of work asper approved drawing and as directed by the Engineer-In - Charge.
43 Construction of Compoundwall at 132KV SS Durshed 1201.0 310.00 One Sqm 183.97 57030.70
Painting to External new walls with 2 coats of acrylic emulsion exterior grade having VOC(Volatile Organic Compound) content less than 50 gms/Ltr of approved brand ( Asian, Berger, Nippon ) and shade over a base coat of appropriate primer of grade I quality approved brand,making 3 coats in all to give an even shade after thourughly brushing the surface to remove all dirt and remains of loose powdered materials, including cost and conveyance of all materials to work site and all operational, incidental, labour charges etc.complete for finished item of work as per SS 912 for External walls
44 Construction of Compoundwall at 132KV SS Durshed 1201.0 550.00 One Sqm 124.70 68585.00
Painting to inner new walls with 2 coats of acrylic emulsion interior grade having VOC(Volatile Organic Compound) content less than 50 gms/Ltr of approved brand ( Asian, Berger, Nippon ) and shade over a base coat of appropriate Cement Primer of Interior grade I of approved brand,making 3 coats in all to give an even shade after thourughly brushing the surface to remove all dirt and remains of loose powdered materials, including cost and conveyance of all materials to work site and all operational, incidental, labour charges etc.complete for finished item of work as per SS 911 for internal walls
45 Construction of Compoundwall at 132KV SS Durshed 701& 707 25.00 One Sqm 1053.82 26345.50
Providing skirting to internal walls to 15 cm height/risers of steps with Nano polished soluble salt porcelain vitrified tiles screen printed of size 800 x 800 mm and thickness between 9-11 mm 1st quality confoRMTing to IS:13711, IS:13712, IS:13630 (Parts 1 to 15) of any colour and finish in all shades and designs length equal to flooring stones, set over base coat of CM (1:5) 12 mm thick with cement slurry of honey like consistency spread at the rate of 3.30 kgs per M2 and jointed with white cement paste mixed with pigment of matching shade to full depth, including cost of all materials like tiles, cement, sand and water including seigniorage charges, etc., complete as per the directions of the Engineer in charge for the finished item of work.
46 Construction of Compoundwall at 132KV SS Durshed 701& 707 50.00 One Sqm 1045.37 52268.50
Flooring with Nano polished soluble salt porcelain vitrified tiles screen printed of size 800 X 800 mm and thickness between 9-11 mm 1st quality conforming to IS:13711, IS:13712,IS:13630 (Parts 1 to 15) of any colour and finish in all in all shades and designs as directed by Engineer. in charge, set over base coat of cement mortar (1:8), 12 mm thick over CC bed already laid or RCC roof slab, including neat cement slurry of honey like consistency spread @ 3.3.kgs per sqm & jointed neatly with white cement paste to full depth mixed with pigment of matching shade, including cost of all materials like cement, sand water and tiles etc., complete, including seigniorage charges, etc., complete as per the directions of the Engineer in charge for the finished item of work.
47 Construction of Compoundwall at 132KV SS Durshed Spl.Spec 0.60 One Sqm 3799.17 2279.50
Supply, fabrication and erection of Anodized Aluminium glazed ventilator using section of size 81.25mmx38.10mmx1.75mm @ 1.093 Kg/m (Jindal Sec 14071) for frame and \'U\' seciton of size 12.50mmx12.50mmx1.00mm @ 0.133 Kg/m (Jindal Sec 17533) for louvers and inserting 5mm thick plain glass panes including cost & conveyance of all materials, labour charges and other incidental charges complete as per the drawing and as per the directions of Engineer-in-charge for finished item of work.
48 Construction of Compoundwall at 132KV SS Durshed Spl.Spec 2050.00 One Sqm 38.69 79314.50
White washing two coats with whiting / Suryacem of approved quality to give an even shade after thoroughly brushing the surface to remove all dirt and remains of loose powdered materials including cost of all materials, labour charges and incidental such as scaffolding, lift charges etc., complete for finished item of work
49 Construction of Compoundwall at 132KV SS Durshed 901 & 904 1200.00 One Sqm 218.22 261864.00
Plastering to Uneven surfaces of RR /CR, PCC with CM(1:5) 20mm. thick including cost & conveyance of all materials, labour charges, leads, lifts and curing complete as per the directions of the Engineer in charge for the finished item of work.
50 Construction of Compoundwall at 132KV SS Durshed 901 & 904 900.00 One Sqm 142.10 127890.00
Plastering with CM (1:5), 12 mm thick to the even wall surfaces including cost & conveyance of all materials, labour charges, leads, lifts , scaffolding and curing complete as per the directions of the Engineer in charge for the finished item of work.
51 Construction of Compoundwall at 132KV SS Durshed 402.0 2.00 One cum 5255.07 10510.14
Plain Cement concrete - Nominal Mix (1:3:6) with 12 to 20mm HBG metal for encasing/embedding the structural steel supportng \'Y\' angles with necessary form work including cost and conveyance of all materials, labour charges, water charges, tools and tackles, all leads & lifts etc., complete for finished item of work as per directions of the Engineer-in-charge. (IS-456)
52 Construction of Compoundwall at 132KV SS Durshed 501& 504 170.00 One Cum 5844.92 993636.40
Brick Masonry in CM (1:6) with common burnt clay bricks of class as per Table-1 of IS:1077-1992 Non-Modular or traditional size 23 x 11 x 7 cms of approved quality, including cost & conveyance of all materials, labour charges, scaffolding leads, lifts and curing complete as per the directions of the Engineer in charge for the finished item of work .
53 Construction of Compoundwall at 132KV SS Durshed 501& 504 200.00 One Cum 3750.89 750178.00
Construction of RR Masonry in CM (1:6) using hard CRS , rough granite stone and bond stones (0.16 cum) including cost and conveyance of all matreials., labour charges, water lead , Curing, all leads and lifts etc., complete for finished item of work as per directions of the Engineer-in-charge.
54 Construction of Compoundwall at 132KV SS Durshed 402.0 40.00 One Cum 3985.05 159402.00
Laying of Cement Concrete (1:4:8) mix using 40mm size HBG Machine crushed metal for foundations including cost and conveyance of all materials at all leads and lifts, ramming, consolidating, curing etc,complete. for finished item of work as per directions of the Engineer-in-charge.
55 Construction of Compoundwall at 132KV SS Durshed 308.0 160.00 One Cum 216.13 34580.80
Earthwork excavation in all types of soils (up to stone matrix)which can be excavated with pick axe and crow bars and do not require blasting in all conditions such as dry, wet and slushy etc. covering initial lead and lift etc and backfilling the foundations (after laying foundations) with excavated earth complete as per the the directions of the Engineer in charge for the finished item of work. .
56 Construction of Compoundwall at 132KV SS Durshed Spl.Spec 1.00 One Set. 29627.66 29627.66
Supplying & fixing 3 Phase 3HP motor , 30 to 35 stage (Crompton Greaves/texmo make) of approved type, as directed by Engineer in charge, submersible for 6.5\" dia bore well including cost & conveyance of all materials, labour charges, and fitted with L.T/L.K MK-1 DOL starter with panel board (Seimens/crompton/L&T) fitted with related fittings such as Ammeter , volt meter,capacitors and including nuts & bolts and GI sheet box for panel board complete as per the directions of the Engineer in charge for the finished item of work.
57 Construction of Compoundwall at 132KV SS Durshed Spl.Spec 400.00 One RM 129.65 51860.00
Supplying & fixing of 3 core 2.5 Sqmm PVC Insulated and FRLS round sheathed multi core copper cable of Finolex / Polycab /Gold Medal make and as approved by the Engineer in charge for submergible motor including cost & conveyance of all materials, labour charges, leads complete as per the directions of the Engineer in charge for the finished item of work.
58 Construction of Compoundwall at 132KV SS Durshed Spl.Spec 1.00 One No 150.00 150.00
Supply and fixing of MS clamps cover suitable for 1/4\" dia GI pipe including cost &b conveyance of all materials and fittings and leads complete as per the directions of the Engineer in charge for the finished item of work.
59 Construction of Compoundwall at 132KV SS Durshed Spl.Spec 1.00 One No 190.00 190.00
Supply and fixing of MS Bore cover duly painted suitable for 8\" dia casing pipe including cost &b conveyance of all materials and fittings and leads complete as per the directions of the Engineer in charge for the finished item of work.
60 Construction of Compoundwall at 132KV SS Durshed Spl.Spec 200.00 One RM 122.39 24478.00
Supplying & fixing 1 1/4\" (32 mm inner dia HDPE pipe (12.5kg/Sqcm) PE-100 grade of approved quality & make including nipples, bends, couplings etc., complete for finished item of work from bore well to delivery including cost & conveyance of all materials, specials/fixtures and fittings labour charges, leads, and lifts complete as per the directions of the Engineer in charge for the finished item of work.
61 Construction of Compoundwall at 132KV SS Durshed Spl.Spec 200.00 One RM 236.95 47390.00
Supplying and fixing CPVC pipes of SDR 13.50 pipes Medium Grade as per IS 15778 of approved make for water supply line to toilets including cost and conveyance of pipe, specials such as elbows, Tees concealing same in walls and floors by cutting 25/ 20/ 15mm dia to be included grooves, packing, finishing after laying pipe in position as per the directions of the Engineer in charge for the finished item of work - 28.6mm
62 Construction of Compoundwall at 132KV SS Durshed Spl.Spec 3.00 One RM 315.18 945.54
Supplying and fixing CPVC pipes of SDR 13.50 pipes Medium Grade as per IS 15778 of approved make for water supply line to toilets including cost and conveyance of pipe, specials such as elbows, Tees concealing same in walls and floors by cutting 25/ 20/ 15mm dia to be included grooves, packing, finishing after laying pipe in position as per the directions of the Engineer in charge for the finished item of work - 34.9mm
63 Construction of Compoundwall at 132KV SS Durshed Spl.Spec 30.00 One RM 716.41 21492.30
Supply& fixing of 180 mm dia 6 kg/cm2 PVC casing pipes for bore wells for potable water supply conforming to IS 12818-1992 as amended from time to time including transortation, QC inspection etc., complete. as per the directions of the Engineer in charge for the finished item of work
64 Construction of Compoundwall at 132KV SS Durshed Spl.Spec 120.00 One RM 369.60 44352.00
Drilling of bore well by down the hole hammer (DTH) drilling to the finished diameter of 163 mm (6 1/2\") in all formations to the depth as specified and remaining the bore to the required dia, flushing the bore walls at an average pressure of 7 Kg/Sqcm(100 PSI), conducting yield test, inclusive of transportation from point to point , crew charges, consumables , shifting of ring and all other charges etc., complete. The bore well should be true & vertical and work should be carried out to the amendments if any from time . The rate is inclusive of all taxes etc., complete as per the directions of the Engineer in charge for the finished item of work. Above 90 RM to any depth
65 Construction of Compoundwall at 132KV SS Durshed Spl.Spec 90.00 One RM 336.00 30240.00
Drilling of bore well by down the hole hammer (DTH) drilling to the finished diameter of 163 mm (6 1/2\") in all formations to the depth as specified and remaining the bore to the required dia, flushing the bore walls at an average pressure of 7 Kg/Sqcm(100 PSI), conducting yield test, inclusive of transportation from point to point , crew charges, consumables , shifting of ring and all other charges etc., complete. The bore well should be true & vertical and work should be carried out to the amendments if any from time . The rate is inclusive of all taxes etc., complete as per the directions of the Engineer in charge for the finished item of work. Up to 90 Running meters
66 Construction of Compoundwall at 132KV SS Durshed Spl.Spec 1.00 One Job 1200.00 1200.00
Job work for Geologist charges for site investigation for locating bore well points
67 Construction of Compoundwall at 132KV SS Durshed Spl.Spec 6000.00 One Sqm 3.36 20160.00
Clearing thick jungle growth (less than 50 percent open space) including bushes up to 30 cm /parthenium and other weeds including burning or disposing off the same as directed by Engineer in charge for the finished item of work.
'

AI Tender Summary

OUR REF NO 22508604
AUTHORITY Boards / Undertakings / PSU
TENDER VALUE 57.35 Lakhs
LAST DATE 03-12-2019
Authority
Authority Name Transmission Corporation of Telangana Limited
Work Description Repairs To Office Shed, Laying Of Borewell, Construction Of Balance Compound Wall And Rectification Of Ac Sheets To Stores At Durshed In Karimnagar District
Basic Detail
Tender No 22/2019-20 of CE/Civil/TSTransco/VS
Bidding Type Tender
Location
City KARIMNAGAR
State Telangana
Key Dates
Publish Date 15 Nov 2019
Submission Date 03 Dec 2019
Open Date 01 Jan 0001
Finance
Tender Value 57.35 Lakhs
Tender Fee Ref. Documents
EMD 1.15 Lakhs
Exemption Not Available
Document List
d3066b7a-ae69-4929-b359-f342a18b0601.html
Double packet Tender Spec.doc

Unlock Full AI Tender Summary

Get instant access to the complete AI-generated analysis — scope, eligibility, timeline & more.

Instant Access Secure Free
Your details are secure and used only for document delivery.

Tender Timeline

Nov 15, 2019
11:30 IST

Tender Published

Tender notice published.

Completed
Dec 03, 2019
17:00 IST

Bid Submission Deadline

Online submission via eProcurement portal.

Completed

Tender Documents

Download All (ZIP) ↓
html

d3066b7a-ae69-4929-b359-f342a18b0601.html

doc

Double packet Tender Spec.doc

Disclaimer

We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender