Tiruppur District Sfc 2019-20 More Than 1Km Kangeyam Block Pkg No 28 1 . Strengthening The Road From Pattampalayam Ele . School Karichipalayam ( Upto Boundary ) Km0/0-1/0 2 . Strengthening The Road From Tirupur Kunnathur Road To Thoravalur Via Abdul
Tender Overview
Project Description
Tiruppur District Sfc 2019-20 More Than 1Km Kangeyam Block Pkg No 28 1 . Strengthening The Road From Pattampalayam Ele . School Karichipalayam ( Upto Boundary ) Km0/0-1/0 2 . Strengthening The Road From Tirupur Kunnathur Road To Thoravalur Via Abdulkalam Nagar Km0/02/0 Tirupur Block
BOQ
| Name of Work : 1.Strengthening of the road from Pattampalayam Ele.School Karichipalayam (upto District boundary) Km0/0-1/0 2.Strengthening the road from Tirupur Kunnathur road to Thoravalur via Abdulkalam Nagar KM0/0-2/0 | |||||
|---|---|---|---|---|---|
| Sl.No. | Item Description | Unnamed: 2 | Quantity | Units | |
| 1 | 1 | 1.Strengthening of the road from Pattampalayam Ele.School Karichipalayam (upto District boundary) Km0/0-1/0 | 1 | nos | |
| 2 | 2 | Clearing light Jungles including all labour charges for burrying and burning etc., complete., | 1 | nos | |
| 3 | 3 | Km 1/0-1/0 | 1440 | sqm | |
| 4 | 4 | Earthwork excavation for foundation in all soils and sub soil to full depth as may be directed except in hard rock requiring blasting but inclusive of shoring strutting and requiring the sides of foundation | 1 | nos | |
| 5 | 5 | Km 1/0-1/0 | 270 | cum | |
| 6 | 6 | Collection and supply of gritty gravel from appd quarry including cost and conveyance of all materials to site including all labour charges for spreading etc., complete Shoulders | 1 | nos | |
| 7 | 7 | Km 0/0-1/0 | 140 | cum | |
| 8 | 8 | Picking the Existing BT Surface Including all labour Charges etc.. Complete as Per Standard Specification | 1 | nos | |
| 9 | 9 | Km 1/0-1/0 | 1257.08 | Sqm | |
| 10 | 10 | Providing and laying 63mm compacted thick WBM Gr.III using 1 cum of 63 mm to 11.20 mm IRC HBG metal and 0.24 cum of Gravel for blindage for 10sqm. Of 63mm compacted thick (the blindage material shall have PI value less than 6%) including cost and conveyance of all materials from approved quarry to worksite and stacking to departmental gauge for pre-measurement as directed by the departmental officers including labour for spreading metal and gravel hand packing to camber and grade lines blinding with required quantity of gravel forming edge bunds watering with all leads for good water slurrying rolling and consolidation by power roller and finishing has per MOST 404 (III revision) including hire and fuel charges for power roller and water sprinkler and all other tools and plants employed therefor and all other incidental charges etc., complete for top layer. | 1 | nos | |
| 11 | 11 | Km 0/0-1/0 | 282.85 | cum | |
| 12 | 12 | Applying Tack coat over WBM Surface using 4Kg of bituminous binder for 10sqm area including cost of bituminous binder at the site including labour charges for preparing the surface and applying the required quantity of bituminous binder as tack coat including hire charges and fuel charges for bitumen boiler and all other tools and plants employed etc,. complete as per clause 503 of MOST specification | 1 | nos | |
| 13 | 13 | Km 0/0-1/0 | 3771.25 | sqm | |
| 14 | 14 | Providing and laying premix carpet 20mm thickness using 0.18 cum of 13.20 IRC machine crushed chips and 0.09cum of 11.20mm IRC machine crushed chips with 13.14 kg of bitumen for pre mixing 10sqm of premix carpet and laying separately seal coat type A using 0.09 cum of 6.70 mm conveyance of materials to the departmental metric gauge for pre-measurement heatinh the bitumen boiler heating the aggregate and mixing them with bitumen in mini hot mix plant for premix carpet and rolling by 80-100KN power roller including labour charges for spreading hire and fuel charges for mini hot mix plant, bitumen boiler, all other tools and plants employed etc, complete | 1 | nos | |
| 15 | 15 | Km 1/0-1/0 | 3771.25 | sqm | |
| 16 | 16 | Provision for KM stones | 1 | no | |
| 17 | 17 | Provision for HM stones | 4 | no | |
| 18 | 18 | 2.Strengthening the road from Tirupur Kunnathur road to Thoravalur via Abdulkalam Nagar KM0/0-2/0 | 1 | nos | |
| 19 | 19 | Clearing light Jungles including all labour charges for burrying and burning etc., complete., | 1 | nos | |
| 20 | 20 | Km 1/0-1/8 | 1080 | sqm | |
| 21 | 21 | Earthwork excavation for foundation in all soils and sub soil to full depth as may be directed except in hard rock requiring blasting but inclusive of shoring strutting and requiring the sides of foundation | 1 | nos | |
| 22 | 22 | Km 1/0-1/8 | 270 | cum | |
| 23 | 23 | Collection and supply of gritty gravel from appd quarry including cost and conveyance of all materials to site including all labour charges for spreading etc., complete Shoulders | 1 | nos | |
| 24 | 24 | Km 0/0-1/0 | 150 | cum | |
| 25 | 25 | Km 1/0-1/8 | 101.25 | cum | |
| 26 | 26 | Picking the Existing BT Surface Including all labour Charges etc.. Complete as Per Standard Specification | 1 | nos | |
| 27 | 27 | Km 1/0-1/8 | 1250 | Sqm | |
| 28 | 28 | Providing and laying 63mm compacted thick WBM Gr.III using 1 cum of 63 mm to 11.20 mm IRC HBG metal and 0.24 cum of Gravel for blindage for 10sqm. Of 63mm compacted thick (the blindage material shall have PI value less than 6%) including cost and conveyance of all materials from approved quarry to worksite and stacking to departmental gauge for pre-measurement as directed by the departmental officers including labour for spreading metal and gravel hand packing to camber and grade lines blinding with required quantity of gravel forming edge bunds watering with all leads for good water slurrying rolling and consolidation by power roller and finishing has per MOST 404 (III revision) including hire and fuel charges for power roller and water sprinkler and all other tools and plants employed therefor and all other incidental charges etc., complete for top layer. | 1 | nos | |
| 29 | 29 | Km 0/0-1/0 | 56.25 | cum | |
| 30 | 30 | Km 0/0-1/8 | 225 | cum | |
| 31 | 31 | Applying Tack coat over WBM Surface using 4Kg of bituminous binder for 10sqm area including cost of bituminous binder at the site including labour charges for preparing the surface and applying the required quantity of bituminous binder as tack coat including hire charges and fuel charges for bitumen boiler and all other tools and plants employed etc,. complete as per clause 503 of MOST specification | 1 | nos | |
| 32 | 32 | Km 0/8-1/8 | 3750 | sqm | |
| 33 | 33 | Applying Tack coat over BT Surface using 3Kg of bituminous binder for 10sqm area including cost of bituminous binder at the site including labour charges for preparing the surface and applying the required quantity of bituminous binder as tack coat including hire charges and fuel charges for bitumen boiler and all other tools and plants employed etc,. complete as per clause 503 of MOST specification | 1 | nos | |
| 34 | 34 | Km 0/8-1/8 | 2833.75 | sqm | |
| 35 | 35 | Providing and laying premix carpet 20mm thickness using 0.18 cum of 13.20 IRC machine crushed chips and 0.09cum of 11.20mm IRC machine crushed chips with 13.14 kg of bitumen for pre mixing 10sqm of premix carpet and laying separately seal coat type A using 0.09 cum of 6.70 mm conveyance of materials to the departmental metric gauge for pre-measurement heatinh the bitumen boiler heating the aggregate and mixing them with bitumen in mini hot mix plant for premix carpet and rolling by 80-100KN power roller including labour charges for spreading hire and fuel charges for mini hot mix plant, bitumen boiler, all other tools and plants employed etc, complete | 1 | nos | |
| 36 | 36 | Km 0/0-1/0 | 3771.25 | sqm | |
| 37 | 37 | Km 0/0-1/8 | 2812.5 | sqm | |
| 38 | 38 | Provision for KM stones | 1 | no | |
| 39 | 39 | Provision for HM stones | 7 | no | |
| 40 | 40 | Provision for Name boards | 1 | no | |
| 41 | 41 | GST Amount for providing Service to Government Contract Works for the above Construction & Maintenance Works. { GST Amount is the Total GST Amount for overall quoted amount (Both Construction and Maintenance) above this row in column \"BB\" for all works in this package}\n(Refer Clause 13.2 & 13.3 of Section 2 of Instruction to Bidders (ITB) of SBD) | 1 | GST Amount |
AI Tender Summary
Tender Timeline
Tender Published
Tender notice published.
CompletedBid Submission Deadline
Online submission via eProcurement portal.
CompletedBid Opening Date
Technical bids will be opened and evaluated.
CompletedTender Documents
Download All (ZIP) ↓We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender