Paranthenmadu Kodi Road Culvert
Tender Value
8.61 Lakhs
Estimated cost
Bid Submission
15 Nov 2019
0 days left
EMD
21750
Bank guarantee accepted
Document Fee
1740
Non-refundable
Tender Type
Online
Tender Overview
Organization
Tender ID
Competition Type
NCB
Bidding Type
Tender
Location / State
Cheruvathur → Kerala
EMD Exemption
Not Available
Quantity
Not Available
Website
Contact Person
Address
Project Description
Paranthenmadu Kodi Road Culvert
BOQ
| Work Name:CGP.2019-20 Pr.No.173/20 Paranthenmad Kodi Road Culvert Construction | |||||
|---|---|---|---|---|---|
| Sl.No. | Item Description | Item Code / Make | Quantity | Units | |
| 1 | 1 | culvert | BI01010001010000000000000515BI0100001113 | ||
| 2 | 1.001 | 60.1.1 : RING BUND Type-I-Putting up ring bund as per approved shape 2.5m bottom width, 1m top width using empty gunny/polythene bags filled with earth placed in 2 rows at 0.6m apart and filled in between with puddle clay to form bund for an average height 2.00m including labour dismantling the bund after completion of the work etc. complete. | BI01010001010000000000000515BI0100001114 | 8 | metre |
| 3 | 1.002 | 60.2.2 : Bailing out water Using 5HP Pump- Bailing out water with 5HP engine and pump set including conveyance to site and erection,cost of fuel, lubrication oil and other stores, pay of staff etc complete | BI01010001010000000000000515BI0100001115 | 120 | hour |
| 4 | 1.003 | 60.64.1 : Coconut Pile - Supplying and stacking well matured straight coconut post for driving down throug various strata bellow bed level including cost coveyance labour charges etc complete. | BI01010001010000000000000515BI0100001116 | 96 | metre |
| 5 | 1.004 | 60.64.4 : Coconut Pile - Driving down coconut pile to lines and levels through variuos strata including all hire charges and labour for fixing , staging platform and all other appliances necessary for pile driving down after pointing the bottom end | BI01010001010000000000000515BI0100001117 | 96 | metre |
| 6 | 1.005 | 60.64.6 : Cutting and removing the excess length of wooden piles to lines and levels and removing the cut end of piles and stacking within 150m | BI01010001010000000000000515BI0100001118 | 16 | each |
| 7 | 1.006 | 2.8.1 : Earth work in excavation by mechanical means (Hydraulic excavator) /manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m.All kinds of soil | BI01010001010000000000000515BI0100001119 | 18 | cum |
| 8 | 1.007 | 4.1.8 : Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40 nominal size) | BI01010001010000000000000515BI0100001120 | 3 | cum |
| 9 | 1.008 | 4.3.1 : Centering and shuttering including strutting, propping etc. and removal of form work for:Foundations, footings, bases for columns | BI01010001010000000000000515BI0100001121 | 10.24 | sqm |
| 10 | 1.009 | 4.3.2 : Centering and shuttering including strutting, propping etc. and removal of form work for:Retaining walls, return walls, (any thickness) including attached pilasters, buttresses, plinth and string courses fillets, kerbs and steps etc. | BI01010001010000000000000515BI0100001122 | 77.48 | sqm |
| 11 | 1.01 | 4.1.5 : Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 20 mm nominal size) | BI01010001010000000000000515BI0100001123 | 5.256 | cum |
| 12 | 1.011 | 4.1.6 : Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:3:6 ( 1 cement : 3 coarse sand : 6 graded stone aggregate 40 mm nominal size) | BI01010001010000000000000515BI0100001124 | 49.186 | cum |
| 13 | 1.012 | 5.9.3 : Centering and shuttering including strutting, etc. and removal of form for:Suspended floors, roofs, landings, balconies and access platform | BI01010001010000000000000515BI0100001125 | 21.624 | sqm |
| 14 | 1.013 | 5.1.2 : Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level:1:1:5:3 (1 cement 1.5 coarse sand :3 graded stone aggregate 20 mm nominal size | BI01010001010000000000000515BI0100001126 | 9.518 | cum |
| 15 | 1.014 | 5.22.6 : Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more | BI01010001010000000000000515BI0100001127 | 1401 | kilogram |
| 16 | 1.015 | 13.1.2 : 12 mm cement plaster of mix:1:6 (1 cement : 6 fine sand). | BI01010001010000000000000515BI0100001128 | 30 | sqm |
| 17 | 1.016 | 60.7.2 : DR PACKING Under foundation - Dry stone packing under foundation with good quality blasted rubble including conveyance of material and labour charges etc. complete as per direction of departmental officers at site. | BI01010001010000000000000515BI0100001129 | 14.25 | cum |
| 18 | 1.017 | 60.7.1 : DRY RUBBLE MASONRY _ Dry rubble without concrete levelling course masonry with good quality blasted rubble including packing to compactness to lines and levels cost and conveyance of all materials labour charges etc. complete as per direction of Departmental officers at site | BI01010001010000000000000515BI0100001130 | 32.8 | cum |
| 19 | 1.018 | 50.2.26.1 : Filling with contractor own earth (excluding rock) in open areas in layers not exceeding 20 cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift up to 1.5 m as per direction of site Engineer-in-charge. | BI01010001010000000000000515BI0100001131 | 64 | cum |
AI Tender Summary
Tender Timeline
Nov 08, 2019
11:30 IST
Tender Published
Tender notice published.
CompletedNov 15, 2019
17:00 IST
Bid Submission Deadline
Online submission via eProcurement portal.
CompletedNov 18, 2019
Bid Opening Date
Technical bids will be opened and evaluated.
CompletedTender Documents
Download All (ZIP) ↓
Disclaimer
We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender