Estimate For Construction Of Masonry Field Channel Of Section (250 Mm. X 325 Mm.) For Distribution Of Irrigation Water From Source To Field At Jagannathpur Major Rli Scheme At Berhampore Block Under Berhampore(Am) Sub Division In Rkvy Programme, Yr.-2018-
Tender Overview
Project Description
Estimate For Construction Of Masonry Field Channel Of Section ( 250 Mm. X 325 Mm. ) For Distribution Of Irrigation Water From Source To Field At Jagannathpur Major Rli Scheme At Berhampore Block Under Berhampore ( Am ) Sub Division In Rkvy Programme, Yr.-2018-19.
BOQ
| Name of Work: ESTIMATE FOR CONSTRUCTION OF MASONRY FIELD CHANNEL OF SECTION (250 mm. x 325 mm.) FOR DISTRIBUTION OF IRRIGATION WATER FROM SOURCE TO FIELD AT JAGANNATHPUR MAJOR RLI SCHEME AT BERHAMPORE BLOCK UNDER BERHAMPORE(AM) SUB DIVISION IN RKVY PROGRAMME, YR.-2018-19. | |||||
|---|---|---|---|---|---|
| Sl.No. | Item Description | Item Code / Make | Quantity | Units | |
| 1 | 1 | Earthwork in excavation of foundation trenches or drains in all sorts of soil (including mixed soil but excluding laterite and sand stone), including removing, spreading or stacking the spoils within alead of 75 m. as directed.The item includes necessary trimming the sides of trenches, levelling, dressing and ramming the bottom, bailing out water as required complete. Depth of excavation not exceeding 1500 mm. | BI01010001010000000000000515BI0100001112 | 85.65 | %Cu.M. |
| 2 | 2 | Earth work in filling in foundation trenches or plinth with good earth in layer not exceeding 150 mm. including watering and ramming etc. layer by layer complete. (Payment tobe made on the basis of measurement of finished quantity of work)\na) with earth obtained from excavation of foundation. | BI01010001010000000000000515BI0100001113 | 59.2 | %Cu.M. |
| 3 | 3 | Single brick flat soling of picked jhama bricks including ramming & dressing bed to proper level & filling joints with powdred earth or local sand. | BI01010001010000000000000515BI0100001114 | 260.45 | Sq.M. |
| 4 | 4 | Cement Concrete with graded stone ballast (40mm. Size excluding shuttering) \n In Ground Floor. (A) [Pakur Variety]\n(a) 1 : 3 : 6 proportion.\n | BI01010001010000000000000515BI0100001115 | 26.045 | Cu.M. |
| 5 | 5 | Ordinary Cement concrete (mix 1:2:4) with graded stone chips (6mm nominal size) excluding shuttering and reinforcement,if any, in gound floor as per relevant IS codes.\ni) Pakur variety | BI01010001010000000000000515BI0100001116 | 3.4 | Cu.M. |
| 6 | 6 | Hire and labour charges for shuttering with centreing and necessary staging upto 4 metre using approved stout props and thick hard wood planks of approved thickness with required bracing for concrete slabs, beams,columns, lintels curved or straight including fitting, fixing and striking out after completion of works (upto roof of ground floor). \n(a) 25 mm. to 30 mm. thick wooden shuttering as per decision & direction of EIC. | BI01010001010000000000000515BI0100001117 | 160.475 | Sq.M. |
| 7 | 7 | 125 mm. thick brickwork with 1st class bricks in cement mortar (1 : 4) in ground floor | BI01010001010000000000000515BI0100001118 | 297.8 | Sq.M. |
| 8 | 8 | Brick work with 1st class bricks in cement mortar (1:6)\n(a) In foundation and plinth | BI01010001010000000000000515BI0100001119 | 6.8 | Cu.M. |
| 9 | 9 | Plaster (to wall, floor, ceiling etc.) with sand and cement mortar including rounding off or chamfering corners, as directed and racking out joints including throating, nosing and drip course ,scaffolding/staging where necessary at ground floor. [Excluding cost of chipping over concrete surface]\n(i) with (1:6) cement mortar.\n(b) 20 mm. thick plaster. | BI01010001010000000000000515BI0100001120 | 475 | Sq.M. |
| 10 | 9.01 | (c) 15 mm. thick plaster. | BI01010001010000000000000515BI0100001121 | 398.15 | Sq.M. |
| 11 | 10 | Neat cement punning about 1.5 mm. thick in wall dado, floor, drain, door and window sill etc. complete. NOTE:Cement 0.152 cu.m per100 sq.m. | BI01010001010000000000000515BI0100001122 | 873.15 | Sq.M. |
| 12 | 11 | Add GST @ 12% | BI01010001010000000000000515BI0100001123 | 0.12 | Each |
| 13 | 12 | Add Labour welfare cess @ 1% | BI01010001010000000000000515BI0100001124 | 0.01 | Each |
AI Tender Summary
Tender Timeline
Tender Published
Tender notice published.
CompletedBid Submission Deadline
Online submission via eProcurement portal.
CompletedBid Opening Date
Technical bids will be opened and evaluated.
CompletedTender Documents
Download All (ZIP) ↓We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender