Construction Work Of 1 No . 132 Kv Sc 2-Phase Transmission Line From 132 Kv Gss Sadulpur To 132/25 Kv Tss At Sadulpur
Tender Value
6.02 Lakhs
Estimated cost
Bid Submission
04 Nov 2019
0 days left
EMD
12100
Bank guarantee accepted
Document Fee
1180
Non-refundable
Tender Type
Online
Tender Overview
Organization
Tender ID
Competition Type
NCB
Bidding Type
Tender
Location / State
Sadulpur → Rajasthan
EMD Exemption
Not Available
Quantity
Not Available
Website
Contact Person
Address
Project Description
Construction Work Of 1 No . 132 Kv Sc 2-Phase Transmission Line From 132 Kv Gss Sadulpur To 132 / 25 Kv Tss At Sadulpur
BOQ
| Name of Work: Construction of 132 KV S/C ,2- Phase (fit for D/C Tower ) Transmission Line from 132 KV GSS, RVPN Sadulpur to Proposed 132/25 KV Traction Sub-Station at Sadulpur (Under Deposit work of Railways( NWR Bikaner Division ) on labour rate contract (0.2Km) | |||||
|---|---|---|---|---|---|
| Sl.No. | Item Description | Item Code / Make | Quantity | Units | |
| 1 | 1 | Detail Survey as per tentative route- | BI01010001010000000000000515BI0100001112 | ||
| 2 | 1.01 | Which includes the following major activities-Pegging of line route, providing of survey pillar at an interval of 3-4 KM in the line route with required jungle clearance for survey, profile preparation of approved route on graph sheet and marking of offset on either side of line, marking of side clearance for hills, sand dunes etc, as per specification and tower scheduling. | BI01010001010000000000000515BI0100001113 | 0.2 | KM |
| 3 | 2 | Check survey as per approved route of line which includes-\nRe-checking of the line route as per approved profile, chainage, tower center marking, pit marking, bisection of angle tower as required at site. | BI01010001010000000000000515BI0100001114 | 0.2 | KM |
| 4 | 3 | Excavation-\nExcavation, excluding back filling, including shoring, shuttering, dewatering, etc. up to the required depth as per foundation specification/ drawings.\n(j) Any Soil, soft rock other than Hard rock\n | BI01010001010000000000000515BI0100001115 | 300 | Cum |
| 5 | 4 | Setting of Template & Stub/ Anchor Bolt :Setting of template & stub/ anchor bolt & removal after concreting, excluding cost of excavation and concreting but including back filling with excavated/ borrowed earth (with lead & lift) in layers with ramming and watering as per specification.\n(i)Towers including extension up to 9 Meters | BI01010001010000000000000515BI0100001116 | 1.9 | MT |
| 6 | 5 | Concreting:\nProviding and laying cement concrete for all types of foundation as per latest ISS:456 including cement, sand, stone aggregate 20mm nominal size, water etc., preparing surfaces, shuttering, mixing, placing, ramming, curing, finishing as per specification and drawings. | BI01010001010000000000000515BI0100001117 | ||
| 7 | 5.1 | (i)1:3:6 Mix | BI01010001010000000000000515BI0100001118 | 6 | Cum |
| 8 | 5.2 | (ii)1:1:5:3 Mix | BI01010001010000000000000515BI0100001119 | 18 | Cum |
| 9 | 6 | Steel Reinforcement:\nCutting, bending, welding of joints if required, fixing and placing of steel reinforcement as per specification and drawings including material. | BI01010001010000000000000515BI0100001120 | 2.2 | MT |
| 10 | 7 | Earthing:\n(A) Earthing of towers with pipe type earthing excluding the supply of pipes, wires, flats &connectors, but including coke/charcoal, etc., excavation, auguring and backfilling in all types of soil. | BI01010001010000000000000515BI0100001121 | 4 | Nos |
| 11 | 8 | Erection Of Towers:\nErection of super structures including D-shackles, ACD, Hangers, U-Bolts, step bolts, danger plate, phase plate, number plate etc. Also including tack welding of bolts & nuts up to bottom cross arm/beam level including application of Zinc Rich paint | BI01010001010000000000000515BI0100001122 | ||
| 12 | 8.1 | (i) Erection of Towers \n (with extension up to 9 Meters) | BI01010001010000000000000515BI0100001123 | 12 | MT |
| 13 | 9 | Conductor Stringing:\n(A) Stringing of ACSR Panther including hoisting of insulator string, laying, jointing & tensioning of conductor, clamping with Armor rods and fixing of vibration damper per route KM of the line. | BI01010001010000000000000515BI0100001124 | ||
| 14 | 9.1 | (i)Single Conductor | BI01010001010000000000000515BI0100001125 | 0.4 | KM |
| 15 | 10 | Earth wire Stringing :\n(A) Stringing of galvanized steel stranded wire including laying, jointing & tensioning, clamping, clipping and fixing vibration damper and earth bond etc. | BI01010001010000000000000515BI0100001126 | ||
| 16 | 10.1 | (i)One No. 7/3.15mm galvanized wire | BI01010001010000000000000515BI0100001127 | 0.2 | KM |
AI Tender Summary
Tender Timeline
Oct 23, 2019
11:30 IST
Tender Published
Tender notice published.
CompletedNov 04, 2019
17:00 IST
Bid Submission Deadline
Online submission via eProcurement portal.
CompletedNov 05, 2019
Bid Opening Date
Technical bids will be opened and evaluated.
CompletedTender Documents
Download All (ZIP) ↓
Disclaimer
We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender