Goa Shipyard Limited has published Annual Rate Contract To Provide Painters , Helpers , Blaster Cum Spray Painters And Supervisor In Gsl. Submission Date for this Tender is 11-11-2019. Man Power Supply Tenders in GSL, Goa Goa. Bidders can get complete Tender details and download the document.
Name of Work: Annual rate contract to provide Painters, Helpers, Blaster cum spray painters and supervisor in GSL | |||||
---|---|---|---|---|---|
Sl. No. | Description | Item Code / Make | Qty | UOM | |
1 | 1 | Services required for 305 days with 12 nos Painters during normal working day (incl. saturdays)\nNote: Contractors required to cater welfare items (such as umbrellas/raincoats, uniforms, shoes/ sandals, PPEs,soaps etc) , safety gears to employees, labour welfare funds, statutory expenditures other than those not included in BOQ, paid leaves of employees, administrative charges & profit percentage in service charges. Cost of the same shall be included in the service charges quoted. | item1 | 3660 | man-day |
2 | 2 | Overtime rate per Painter per hour for working before and after 08 normal working hours (12 Painters x 95 hours per year x 1 years) (On as an when required basis) | item2 | 1140 | per hour |
3 | 3 | Rate for hiring Painter per manday for 8 hours on Holidays and Sundays. (12 Painters x 15 days) (On as and when required basis) | item3 | 180 | man-day |
4 | 4 | Payment against National Holidays for Painters (8 National Holidays per annum) (12 Painters x 8 days) | item4 | 96 | man-day |
5 | 5 | Bonus for 6 Painters (12 Painters x 305 days) (Yearly payment on actual atttendence) | item5 | 3660 | man-day |
6 | 6 | Services required for 305 days with 4 nos Blaster cum Spray Painters during normal working day (incl. saturdays)\nNote: Contractors required to cater welfare items (such as umbrellas/raincoats, uniforms, shoes/ sandals, soaps etc) , safety gears to employees, labour welfare funds, statutory expenditures other than those not included in BOQ, paid leaves of employees, administrative charges & profit percentage in service charges. Cost of the same shall be included in the service charges quoted. | item6 | 1220 | man-day |
7 | 7 | Overtime rate per Blaster cum Spray Painter per hour for working before and after 08 normal working hours (4 Blaster cum Spray Painters x 95 hours per year x 1 years) (On as an when required basis) | item7 | 380 | per hour |
8 | 8 | Rate for hiring Blaster cum SprayPainter per manday for 8 hours on Holidays and Sundays. (4 Blaster cum Spray Painters x 15 days) (On as and when required basis) | item8 | 60 | man-day |
9 | 9 | Payment against National Holidays for Blaster cum Spray Painters (8 National Holidays per annum) (4 Blaster cum Spray Painters x 8 days) | item9 | 32 | man-day |
10 | 10 | Bonus for 4 Blaster cum Spray Painters (4 Blaster cum Spray Paintersx 305 days) (Yearly payment on actual atttendence) | item10 | 1220 | man-day |
11 | 11 | Services required for 305 days with 7 nos Helpers (un-skilled) during normal working day (incl. saturdays) \nNote: Contractors required to cater welfare items (such as umbrellas/raincoats, uniforms, shoes/ sandals, soaps etc) , safety gears to employees, labour welfare funds, statutory expenditures other than those not included in BOQ, paid leaves of employees, administrative charges & profit percentage in service charges. Cost of the same shall be included in the service charges quoted. | item11 | 2135 | man-day |
12 | 12 | Overtime rate per Helper per hour for working before and after 08 normal working hours (7 Helpers x 95 hours per year x 1 years) (On as an when required basis) | item12 | 665 | per hour |
13 | 13 | Rate for hiring Helper per manday for 8 hours on Holidays and Sundays. (7 Helpers x 15 days) (On as and when required basis) | item13 | 105 | man-day |
14 | 14 | Payment against National Holidays for Helpers (8 National Holidays per annum) (7 Helpers x 8 days) | item14 | 56 | man-day |
15 | 15 | Bonus for 7 Helpers (7 Helpers x 305 days) (Yearly payment on actual atttendence) | item15 | 2135 | man-day |
16 | 16 | Service required for 305 days with 2 supervisors (highly skilled category) during the BRC period. Supervisor during normal working day (incl. saturdays)\nNote: Contractors required to cater welfare items (such as umbrellas/raincoats, uniforms, shoes/ sandals, soaps etc) , safety gears to employees, labour welfare funds, statutory expenditures other than those not included in BOQ, paid leaves of employees, administrative charges & profit percentage in service charges. Cost of the same shall be included in the service charges quoted. | item16 | 610 | man-day |
17 | 17 | OT rate per supervisor per hour for working before and after 08 normal working hours (2 supervisors x 95 hours per year x 1 years) (On as an when required basis) | item17 | 190 | per hour |
18 | 18 | Rate for Hiring supervisor per mandays for 08 hours on Holidays and Sundays (2 supervisor x 15 days) (On as an when required basis) | item18 | 30 | man-day |
19 | 19 | Payment against National Holidays for supervisor (8 National Holidays per annum) (2 supervisors x 8 days) | item19 | 16 | man-day |
20 | 20 | Bonus for 2 supervisors (2 supervisors x 305 days) (Yearly payment on actual atttendence) | item20 | 610 | man-day |