| 1 | 1 | Only Labour work with all machine diesel its opreator and all Tool & Plants Etc. | BI01010001010000000000000515BI0100001112 | | |
|---|
| 2 | 2 | Earth work in exacavation in foundations in ordinary soil(loam clay or sand) including lift upto 1.5 m and lead upto 30m.and including filling watering and ramming of exacaveted earth into the trenches or into the space between the building and the sides of foundation trenches or into the plinth and removal disposal of surplus excavated earth as directed by the Engineer i/c with in a charge upto a distance of 30 m from the foundation trenches . | BI01010001010000000000000515BI0100001113 | 746.55 | Cum |
|---|
| 3 | 3 | Carted earth filling in floor & trench including supply of necessary quantity of earth includes cost of alla materials labour and .required for competion of the work .up to distance -5 km | BI01010001010000000000000515BI0100001114 | 251.91 | Cum |
|---|
| 4 | 4 | Labour work in lean cement concrete with 4 cm gauge approved stone ballast , approved coarse sand and cement in the proportion of 1:4:8 (1 cement :4 coarse sand :8 stone ballast ) and curing complete , excluding suply of all materials etc.required for proper completion of the work | BI01010001010000000000000515BI0100001115 | 162.94 | Cum |
|---|
| 5 | 6 | Sand filling in plinth including supply of necessary quantity of sand from a distance not exceeding 8 kms. from the site of work and including watering, dressing etc rate to including cost of all materials labour T & P etc required for proper completion of work. | BI01010001010000000000000515BI0100001116 | 109.82 | Cum |
|---|
| 6 | 7 | Labour charges for laying damp-proof course 40mm thick with cement concrete 1:2:4 (1 cement : 2 coarse sand (zone-III): 4 graded stone aggregate 12.5mm nominal size) | BI01010001010000000000000515BI0100001117 | 77.51 | Cum |
|---|
| 7 | 8 | Providing & applying a coat of residual petroleum bitumen of grade of VG-10 of approved quality using 1.7kg per square metre on damp proof course after cleaning the surface with brushes and finally with a piece of cloth lightly soaked in kerosene oil. | BI01010001010000000000000515BI0100001118 | 77.51 | Sqm |
|---|
| 8 | 9 | Labour work in R.C.C. work with cement approved coarse sand and 20 mm. guage approved stone grit in M-20 (1:1.5:3 ) nominal mix in Slab excluding supply of reinforcement and its fixing and binding the same with 24 BWG binding wire etc, required for proper completion of the works.[Ground Floor ] | BI01010001010000000000000515BI0100001119 | 107.13 | Cum |
|---|
| 9 | 10 | Labour work in R.C.C. work with cement approved coarse sand and 20 mm. guage approved stone grit in M-20 (1:1.5:3 ) nominal mix in Beam excluding supply of reinforcement and its fixing and binding the same with 24 BWG binding wire etc, required for proper completion of the works.[Ground floor] | BI01010001010000000000000515BI0100001120 | 150.42 | cum |
|---|
| 10 | 11 | Labour work in R.C.C. work with cement approved coarse sand and 20 mm. guage approved stone grit in M-20 (1:1.5:3 ) nominal mix in raft footing excluding supply of reinforcement and its fixing and binding the same with 24 BWG binding wire etc, required for proper completion of the works. | BI01010001010000000000000515BI0100001121 | 245.49 | Cum |
|---|
| 11 | 12 | Labour work in Cement Concrete work with cement approved coarse sand and 20 mm. guage approved stone grit in M-20 nominal mix in column footing excluding supply of reinforcement and its fixing and binding the same with 24 BWG binding wire etc, required for proper completion of the works.[Ground Floor] | BI01010001010000000000000515BI0100001122 | 52.6 | Cum |
|---|
| 12 | 13 | Labour work in M-150 class brick work in 1:4 cement and coarse sand of 2.25 fineness modulus mortar in foundation and plinth excluding supply of all materials etc. required for proper completion of the work. (Ground Floor ) | BI01010001010000000000000515BI0100001123 | 100.52 | Cum |
|---|
| 13 | 14 | Labour work in TMT Bar Fe- 500 in plain work such as R.C.C.Work including bending for proper shape and excluding supply of steeel & its wastage ,bend ,hooks authorised over lapping shall be measured and excluding cost of binding wire.[Ground Floor, First Floor,Second Floor and Third Floor] | BI01010001010000000000000515BI0100001124 | 500 | Qtl |
|---|