Schedule A-Items of works that are not covered by the USSOR 2011.
3376050.00
2
1
0
1400.00
Sqm
231.00
323400.00
AT Par
323400.00
Rs.
3
ItemDescription:- Girder Bridges - Preparing the surface with sand paper , cleaning with cotton waste ,\rremoving rust if any and applying two coats of Aluminium paint conforming to IS 2339 over Girder Bridges as\rgiven in Annexure including painting the sleeper seating by shifting the sleepers and refixing in position under\rtraffic conditions using necessary scaffolding or ladder arrangements etc. complete as directed by the Engineer\rin charge of the work . All labour, tools and plants, materials, consumables, lead and lifts etc. by the contractor .
4
2
0
850.00
Sqm
1407.00
1195950.00
AT Par
1195950.00
Rs.
5
ItemDescription:- Girder Bridges - Removing the existing paint, rust etc. up to the parent metal by Sand\rblastingandapplying twocoatsof 2 components Aliphatic Polyurethine Nitocote UR -512 /Cera coat APU\r/equavalant as anti corrosive protective Epoxy coating followed by one finishing coat of Aluminium paint to IS\r2339 over steel girders of Bridges as given in Annexure under traffic conditions using necessary scaffolding or\rladder arrangements etc. complete as directed by the Engineer in charge of the work . All labour, tools and\rplants, materials, consumables, lead and lifts etc. bythe contractor .
6
3
0
2900.00
Sqm
451.50
1309350.00
AT Par
1309350.00
Rs.
7
ItemDescription:- OTHER STEEL STRUCTURES - Scraping and removing the existing paint, rust etc. by\rmeansofsteel/wool/wirebrushesorbyanyotherapprovedmeansasindicatedinSouthernRailway\rSpecification of Works and applying on the prepared surface one coat of ready mixed Zinc chromate primer to IS\r104followed by one coat of ready mixed Red oxide Zinc chromate to IS2074 followed by two finishing coats of\rAluminium paint to IS 2339 overall steel structures given in the Annexure using necessary scaffolding or ladder\rarrangements etc. complete as directed by the Engineer in charge of the work . All labour, tools and plants,\rmaterials, consumables, lead and lifts etc. by the contractor .
8
4
0
2450.00
Sqm
220.50
540225.00
AT Par
540225.00
Rs.
9
Item Description:- OTHER STEEL STRUCTURES - Preparing the surface with sand paper , cleaning with cotton\rwaste , removing rust if any and applying two coats of Aluminium paint conforming to IS 2339 over Steel\rStructures as given in Annexure using necessary scaffolding or ladder arrangements etc. complete as directed by\rthe Engineer in charge of the work . All labour, tools and plants, materials, consumables, lead and lifts etc. by the\rcontractor .
We takes all possible care for accurate & authentic tender information, however Users
are requested to refer Original source of Tender Notice / Tender Document published by
Tender Issuing Agency before taking any call regarding this tender.