Construction Of Boundary Wall Of Park -Textile Center Pilkhuwa Isthit O . H . T . Park Ki Boundaryboll Ka Nirman Karya .
Tender Value
13.83 Lakhs
Estimated cost
Bid Submission
25 Oct 2019
0 days left
EMD
69150
Bank guarantee accepted
Document Fee
1180
Non-refundable
Tender Type
Online
Tender Overview
Organization
Tender ID
Competition Type
NCB
Bidding Type
Tender
Location / State
HAPUR → Uttar Pradesh
EMD Exemption
Not Available
Quantity
Not Available
Website
Contact Person
Address
Project Description
Construction Of Boundary Wall Of Park -Textile Center Pilkhuwa Isthit O . H . T . Park Ki Boundaryboll Ka Nirman Karya .
BOQ
| Name of Work: VSDlVkby lSaVj fiy[kqok fLFkr vks0,p0Vh0 ikdZ dh ckm.Mªhoky ds fuekZ.k dk dk;ZA | |||||
|---|---|---|---|---|---|
| Sl.No. | Item Description | Item Code / Make | Quantity | Units | |
| 1 | 1 | Dismantling brick work or stone work in lime or cement mortar and including stacking of materials as directed be the engineer-in-charge within a distance of 60 meter (200 feet.). | BI01010001010000000000000515BI0100001113 | 102 | cum. |
| 2 | 2 | Deduction of cost of old brick obtained from dismantling of brick work. | BI01010001010000000000000515BI0100001114 | 23460 | No |
| 3 | 3 | Deduction of cost of old brick bats obtained from dismantling of brick work. | BI01010001010000000000000515BI0100001115 | 51 | Cum |
| 4 | 4 | Earthwork in Foundation in ordinary soil (loam, clay or sand) including lift upto 1.50m and lead upto 30m. and including filling watering and ramming of excavated earth into the trenches or into space between the building and the sides of foundation trenches or into the plinth and removal and disposal of surplus earth as directed by the Engineer-in-charge upto a distance of 30m from the foundation trenches. | BI01010001010000000000000515BI0100001116 | 52 | Cum |
| 5 | 5 | Cement concrete with 4 cm gauge approved stone ballast coarse sand & cement in the proportion of 8:4:1 including supply of all materials , labour, tools & plants etcc required for proper completion of the work.In bedding of RCC pipes,including cost of form work in the trenches | BI01010001010000000000000515BI0100001117 | 8 | Cum |
| 6 | 6 | RCC work with cement, approved Coarse sand and 20mm stone grit in proportion of 1:1.5:3 in raft foundation and footings excluding supply of reinforcement and its bending but including its fixing and binding the same with 24 B.W.G.G.I. binding wire and including necessary centering and shuttering etc. and supply of all materials, labour, T&P etc. required for proper completion of the work, including cost of binding wire. | BI01010001010000000000000515BI0100001118 | 12 | Cum. |
| 7 | 7 | RCC work with cement, approved Coarse sand and 20mm stone grit in proportion of 1:1.5:3 for column excluding supply of reinforcement and its bending but including its fixing and binding the same with 24 B.W.G.G.I. binding wire and including necessary centering and shuttering etc. and supply of all materials, labour, T&P etc. required for proper completion of the work, including cost of binding wire. | BI01010001010000000000000515BI0100001119 | 9.5 | Cum. |
| 8 | 8 | RCC work with cement, approved Coarse sand and 20mm stone grit in proportion of 1:1.5:3 excluding supply of reinforcement and its bending but including its fixing and binding the same with 24 B.W.G.G.I. binding wire and including necessary centering and shuttering etc. and supply of all materials, labour, T&P etc. required for proper completion of the work, including cost of binding wire. | BI01010001010000000000000515BI0100001120 | 23.5 | Cum. |
| 9 | 9 | M.S (tor steel or plain ) in work such as RCC or RB work including bending for proper shape and including supply of steel & its wastage, bend, hooks, and authories overlaping shall be measured and including cost of binding wire. | BI01010001010000000000000515BI0100001121 | 53 | Qtl |
| 10 | 10 | M-150 class brick work in 1:4 cement and coarse sand of 1.25 fineness modulus mortar in super structure including supply of all material, labour T&P etc. required for proper completion of the work as per direction of the work as per direction of Engineer-in-charge. (SI.No. 307-306+303+309+310) | BI01010001010000000000000515BI0100001122 | 96 | Cum. |
| 11 | 11 | 12mm thick plaster with cement and coarse sand in 1:4 over brick work minimum thickness not to be less than 10mm thick including supply of all materials, labour and T & P etc. required for proper completion of the work. | BI01010001010000000000000515BI0100001123 | 1244 | Sqm |
| 12 | 12 | Finishing wall with weather coat (asian or Berger Brand) of approved make and quality on new wood with two coat to give an even shade including supply of all materials, labour, T&P etc. required for proper completion of the work. | BI01010001010000000000000515BI0100001124 | 1244 | sqm. |
AI Tender Summary
Tender Timeline
Oct 12, 2019
11:30 IST
Tender Published
Tender notice published.
CompletedOct 25, 2019
17:00 IST
Bid Submission Deadline
Online submission via eProcurement portal.
CompletedOct 26, 2019
Bid Opening Date
Technical bids will be opened and evaluated.
CompletedTender Documents
Download All (ZIP) ↓
Disclaimer
We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender