Border Security Force-BSF has published Repairing Of Wall Of Underground Sump Near Pump No . 1 At Bsf Campus Salbagan Under Ftr Hq Bsf Tripura. Submission Date for this Tender is 15-10-2019. Wall construction Tenders in BSF CAMPUS SALBAGAN Tripura. Bidders can get complete Tender details and download the document.
Name of Work: REPAIRING OF WALL OF UNDERGROUND SUMP NEAR PUMP NO 1 AT BSF CAMPUS SALBAGAN UNDER FTR HQ BSF TRIPURA | |||||
---|---|---|---|---|---|
Sl. No. | Item Description | Item Code / Make | Quantity | Units | |
1 | 1.01 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level :1:4:8 (1 Cement : 4 coarse sand (zone-III) : 8 graded stone aggregate 40 mm nominal size) | BI01010001010000000000000515BI0100001113 | 0.3 | cum |
2 | 1.02 | Providing and laying cement concrete in retaining walls, return walls, walls (any thickness) including attached pilasters, columns, piers, abutments, pillars, posts, struts, buttresses, string or lacing courses, parapets, coping, bed blocks, anchor blocks, plain window sills, fillets, sunken floor etc., up to floor five level, excluding the cost of centering, shuttering and finishing :1:2:4 (1 Cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size). | BI01010001010000000000000515BI0100001114 | 0.14 | cum |
3 | 1.03 | Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level :1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size). | BI01010001010000000000000515BI0100001115 | 0.88 | cum |
4 | 1.04 | Centering and shuttering including strutting, propping etc. and removal of form for:Foundations, footings, bases of columns, etc. for mass concrete | BI01010001010000000000000515BI0100001116 | 4.7 | sqm |
5 | 1.05 | Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete above plinth level. Cold twisted bars | BI01010001010000000000000515BI0100001117 | 65.65 | Kg |
6 | 1.06 | Brick work with common burnt clay F.P.S. (non modular) bricks of class designation 7.5 in foundation and plinth in: Cement mortar 1:4 (1 cement : 4 coarse sand) | BI01010001010000000000000515BI0100001118 | 7.2 | cum |
7 | 1.07 | 12 mm cement plaster of mix :1:6 (1 cement: 6 fine sand) | BI01010001010000000000000515BI0100001119 | 13.95 | sqm |
8 | 1.08 | 12 mm cement plaster finished with a floating coat of neat cement of mix : 1:4 (1 cement: 4 fine sand) | BI01010001010000000000000515BI0100001120 | 15.98 | sqm |
9 | 1.09 | 15 mm cement plaster on rough side of single or half brick wall finished with a floating coat of neat cement of mix : 1:4 (1 cement: 4 fine sand) | BI01010001010000000000000515BI0100001121 | 15.98 | sqm |
10 | 1.1 | Add Cost Index @ 74.51% on DSR Item 1.01 to 1.09 | BI01010001010000000000000515BI0100001141 | 1 |