Name of Work: Dry Stone boulder Pitching on U/S slope of Both (Left/Right) bank of Kanhar Dam
Sl.No.
Item Description
Item Code / Make
Quantity
Units
1
1
Earth works filling for maintaining U/S & D/S slope of Kanhar Dam from borrow area with all lead-lift, labour charges and T&P etc with proper compaction including cost of soil etc. Complete.
36800
Cum.
2
2
Preparation of sub-grade for laying graded filter including cost of labour charges etc. Complete.
95300
Sqm.
3
3
Supplying and laying of fine sand from approved quarry as filter material including all cost of material, royalty and cost of labour, T&P etc. for proper completion of work as per direction of Engineer-in-charge.
21400
Cum.
4
4
Supplying and laying of coarse sand (FM>2) as filter material including all cost of material, royalty and cost of labour and T&P etc. for proper completion of work as per direction of Engineer-in-charge.
22200
Cum.
5
5
Supplying and laying well graded crushed hard stone grit 4.75 to 20 mm. including all cost fo material, labour and T&P etc. for proper completion of work as per direction of Engineer-in-charge.
20700
Cum.
6
6
Supplying and laying well graded crushed hard stone ballast 20 mm. to 80 mm. size including all cost fo material, labour and T&P etc. for proper completion of work as per direction of Engineer-in-charge.
27400
Cum.
7
7
Supplying and laying dry stone boulder pitching including all cost of material, royalty, labour and T&P etc. for proper completion of work as per direction of Engineer-in-charge.
45300
Cum.
8
8
Earth work in excavation of foundation with all types of soil, including all lead and lift, labours, T&P etc. required and filling sides of the foundation trenches and disposal of surplus excavated earth as per direction of Engineer-in-charge.
1430
Cum.
9
9
Providing & Laying C.C. 1:3:6 Concrete with stone ballast 25-50 mm size with coarge sand i/c cost of all material labour etc. Complete but excluding cost of Cement.
350
Cum.
10
10
Providing & Laying R.R. stone Masonary in 1:3 CM with cement, coarse sand and stone Boulder including cost of all material, labour, T&P but excluding cost of cement etc. required for proper completion of work as per direction of Engineer-in-charge.
We takes all possible care for accurate & authentic tender information, however Users
are requested to refer Original source of Tender Notice / Tender Document published by
Tender Issuing Agency before taking any call regarding this tender.