| 1 | 1.01 | Dismantling the pressed tiles and weathering course in the open terrace area , including cost of all Labour ,lead lift etc | Item1 | 188 | Sqm |
|---|
| 2 | 1.02 | Dismantling Damaged RCC Sunshades including cost of all Labour lead lift etc | Item2 | 2 | Cum |
|---|
| 3 | 1.03 | Dismantling existing cement Flooring work including cost of all Labour lead lift etc complete | Item3 | 165 | Sqm |
|---|
| 4 | 1.04 | Supplying erecting steel centering for Roofslabs beams Lintels Sunshades Staircase waist Slab , Landing Slab etc including cost of all materials leads lift labour etc complete | Item4 | 41 | Sqm |
|---|
| 5 | 1.05 | RCC in 1:1 ½:3 using 12 to 20 mm HBG Jelly excluding cost of all materilas lead lit labour curing etc complete | Item5 | 2 | Cum |
|---|
| 6 | 1.06 | Supplying Fabricating and placing in position of TMT rods for reinforcement for RCC works including cutting bending placing in position and tieing as per standard specification including cost of steel,binding wire etc | Item6 | 300 | Kg |
|---|
| 7 | 1.07 | Plastering with cement mortar 1:5 12 mm thick for brick wall surface for outside and inside for all floors at all levels including cost of all materials lead lift labour T&Ps curing etc complete | Item7 | 133.5 | Sqm |
|---|
| 8 | 1.08 | Flooring with First Quality Design Ceramic tiles of Jhonson Make or its equivalent of size 305X305X6 mm to set in cement mortar 1:3 including cost of tiles , all leads lifts labours for laying fixing and finishing neatly as per standard specification including cost of all materials lead lift labour T&Ps curing etc complete | Item8 | 165 | Sqm |
|---|
| 9 | 1.09 | Flooring with First Quality Design Ceramic tiles of Jhonson Make or its equivalent of size 305X305X6 mm to set in cement mortar 1:3 including cost of tiles , all leads lifts labours for laying fixing and finishing neatly as per standard specification including cost of all materials lead lift labour T&Ps curing etc complete | Item9 | 40 | Sqm |
|---|
| 10 | 1.1 | Weathering course made up of concrete broken brick jelly 20mm size in pure slaked lime over RCC roof slab (the proportion being 32:12.5) for required depth of 80mm for giving required slope and thickness to roof as required well beaten with wooden beaters and terrace flooring with one course of pressed tiles 20cm X20cm X 20mm using cement and pointed with same oiled mortar including cost of all materials lead lift labour T&Ps curing etc complete | Item10 | 190 | Sqm |
|---|
| 11 | 1.11 | Supply and fixing of Solid PVC door shutters using 19 guage 19 mm MS Square tubes for stiles and outer frames ,15mm MS Square tubes for top lock and bottom rails and the steel tubes shall be covered with 5 mm thick solid PVC sheets. (The overall size of style’s shall be 50 mm X 30mm and of frames shall be 50 mm X 45 mm , with suitable rebate for housing the shutter . The Overall size of top rail lock rail and bottom rail shall be 75mm X 30mm) and fixing shutter using 5mm thick solid PVC sheets for paneling shall be rigidly fixed in position including cost of all materials necessary furniture and fittings ,lead ,lift etc complete.(Door size 0.75 X2.10m) | Item11 | 4.8 | Sqm |
|---|
| 12 | 1.12 | White washing two coats for ceiling with white cement including thorough scrapping clean removal of dirt etc including cost of all materials labour lewad lift labours scaffolding brush etc complete | Item12 | 155 | Sqm |
|---|
| 13 | 1.13 | Painting two coats withready mixed plastic Emulsion of first class quality paint and of approved colour over one coat of white cement and one coat of primer including thorough scrapping clean removal of dirt etc in all floor including cost of all materials including necessary plaster of paris putty wherever required leads lifts labours scaffolding brush etc complete. | Item13 | 640 | Sqm |
|---|
| 14 | 1.14 | Painting Old wood work with two coats of synthetic enamel paint over a coat of red oxide primer including cost of all materials leads lift labour etc complete | Item14 | 70 | Sqm |
|---|
| 15 | 1.15 | Supplying ALIGNING AND FIXING OF 110MM pvc Rain Water downfall pipe (4 Kg /Sqcm) with necessary specials including fixing to wall with necessary clamps and screws with necessary scaffolding , including cost of all materials labour T&Ps lead lift etc complete | Item15 | 24 | RM |
|---|