Group A Carrying Out Rate Contract For Reconnaissance Survey , Detailed Engineering Survey , Topographical Survey , Geotechnical Investigation , Soil Surveys In State Of Bihar , Jharkhand , Mp And Ap In 10 Gas Awarded To Iocl In 9Th And 10Th Round O, Bihar-Bihar

Indian Oil Corporation Limited-IOCL has published Group A Carrying Out Rate Contract For Reconnaissance Survey , Detailed Engineering Survey , Topographical Survey , Geotechnical Investigation , Soil Surveys In State Of Bihar , Jharkhand , Mp And Ap In 10 Gas Awarded To Iocl In 9Th And 10Th Round O. Submission Date for this Tender is 18-10-2019. Geotechnical Investigation Tenders in Bihar Bihar. Bidders can get complete Tender details and download the document.




Tender Notice

21892904
Group A Carrying Out Rate Contract For Reconnaissance Survey , Detailed Engineering Survey , Topographical Survey , Geotechnical Investigation , Soil Surveys In State Of Bihar , Jharkhand , Mp And Ap In 10 Gas Awarded To Iocl In 9Th And 10Th Round O
Open Tender
Indian
Bihar
Bihar
18-10-2019

Tender Details

Group A Carrying Out Rate Contract For Reconnaissance Survey , Detailed Engineering Survey , Topographical Survey , Geotechnical Investigation , Soil Surveys In State Of Bihar , Jharkhand , Mp And Ap In 10 Gas Awarded To Iocl In 9Th And 10Th Round Of Cgd Gp-A Carrying Out Rate Contract For Reconnaissance Survey , Detailed Engineering Survey , Topographical Survey , Geotechnical Investigation , Soil Surveys In State Of Bihar , Jharkhand , Mp And Ap In 10 Gas Awarded To Iocl In 9Th And 10Th Round Of Cgd

Key Value

Document Fees
Refer document
EMD
INR 353000.0 /-
Tender Value
Refer document

BOQ Items

Name of Work: Carrying out “Rate Rate contract for Reconnaissance Survey, Detailed Engineering Survey, Topographical Survey, Geotechnical Investigation, Soil Surveys in state of Bihar, Jharkhand, Madhya Pradesh & Andhra Pradesh (In 10 GAs ) awarded to IOCL in 9th & 10th round of CGD bidding by PNGRB’’ Group-A: In State of Bihar
Sl. No. Item Description Item Code / Make Quantity Units
1 2 GST % for the tender\nPlease Note that the rate selected shall be applicable for entire items of the Boq Item 0009
2 10 Survey Works-Mainline--Araria-Purnia-Kat Item 0010
3 10.01 Carrying out Reconnaissance Survey of the pipeline route including desktop study followed by verification of reconnaissance survey carried out earlier ( during DFR stage) as per SCC, Specification/Scope of work in the tender and instructions of Engineer-in-Charge and submission of four coloured drawings and report. The reconnaissance survey shall be carried out proposing minimum three or more feasible alternative routes and giving details of likely crossings and other constraints that is likely to be encountered during pipeline construction on each route, future development plans of land owning authorities like Municipal corporation, Gram Panchayat, PWD, NHAI , etc., availability of and including ownership details for setting up of CNG stations, DRS stations, potential Industrial consumers for PNG usage and recommending the best feasible route Item 0011 2 KM
4 10.02 DETAILED ENGINEERING SURVEY</></> Carrying out Detailed Engineering Survey and detailed Grid Line Survey along the entire proposed gas pipeline routes for a width of 30 meter on either side, in accordance with requirement of SCC, Scope of Work and Specification documents enclosed with the tender document and as per instructions of the Company’s representative including meeting all responsibilities and furnishing all documents for survey and all Reports and Drawings along with original editable CAD output including all data as per the detailed SCC, scope of work and Specifications of the tender document but not limited to following: (a),,Deploying Differential Global Positioning to provide DGPS control points at every 4 to 5 km interval based on WGS-84 UTM co-ordinate system; (b),,Deploying Total Stations for traverse control between DGPS stations; (c),,Establishing UTM co-ordinates of all TPs, IPs and Flag Control Points and other important points as desired by Owner; (d),,Taking all survey measurements, readings required for Planimetry, information and feature capturing and levels with respect to MSL; (e),,Obtaining base maps from authorised source (having clearance from Ministry of Defense/ Survey of India) of all districts and submission to Owner; (f),,Preparation & submission of Route Map, Profile Map, Crossing drawings, Planimetry, Alignment Sheets, etc.; (g),,Obtaining seismic fault line data & plotting of fault lines on Route Maps, Alignment sheets as well as on ground; (h),,DGPS survey details of forest area crossing in the pipeline route to be incorporated in the village maps. (i),,Collection of other details, including all labour, material, equipment etc. complete in all respects as per SCC, specifications and direction of Engineer-in-Charge/ Site Engineer; (j),,Integrating all survey details & deliverables, including base maps, into Owner's Arc GIS (ESRI) server to obtain seamless geo-referenced data. Item 0012
5 10.03 Along the entire steel pipeline route Item 0013 130 KM
6 10.04 SOIL RESISTIVITY SURVEY</></> Carrying out corrosion survey including measurement of soil resistivity at a depth of 1.0, 1.5 & 2.0 m interval at in pipeline route, and at station locations, collection of additional data related to cathodic protection as per specification including providing man power, tools, tackles, materials, soil resistivity testing equipment, pipe/cable locator & other supporting facilities etc. including mobilization & demobilization necessary for survey and associated works, including compilation and presentation of data in four sets of Corrosion Survey Report as per SCC, technical specification, drawings, implementation schedule and other provisions of the tender document and instructions of Engineer-in-charge including uploading all data on Owner's ArcGIS (ESRI) server Item 0014
7 10.05 IN PIPELINE ROUTE</></> Conducting soil resistivity survey at intervals of 500 meters along the pipeline route as per the detailed scope of work specified in SCC, Specifications of the tender document and direction of Engineer-in Charge/Site Engineer. Item 0015 130 KM
8 10.06 SOIL CHEMICAL ANALYSIS SURVEY</></> Conducting soil chemical analysis survey for determination of PH value, Chemical analysis for cations i.e. calcium, magnesium,sodium,potassium and Anions i.e Chloride, Sulphate, Sulphide, Carbonate, Bicarbonate, Nitrate, Phosphate,etc. as per SCC, specifications and direction of Engineer-in-Charge/Site Engineer & providing data in tabular form complete in all respect as per following schedule including uploading all data on Owner's ArcGIS server. Item 0016
9 10.07 IN PIPELINE ROUTE</></> Along the entire pipeline route at an interval of 1 km as per SCC, specification. Item 0017 130 KM
10 10.08 SOIL STRATIFICATION SURVEY</></> Conducting Soil Stratification Survey for determining stratification of Soil/ rock as per detailed scope of work specified in SCC, Specifications of the tender document and direction of Engineer-in-charge/Site Engineer including and providing all men, tools, tackles, materials, testing equipment & other equipment and other support facilities including mobilization and demobilization etc. as per tender document including providing the data in tabular form complete in all respect as per following schedule including uploading all data on Owner's ArcGIS server. Item 0018
11 10.09 )ALONG PIPELINE ROUTE</></> "Along the pipeline route, including river crossings (excluding flowing river), by boring 150 mm dia. using auger type equipments up to a depth of 3 m from ground/bed level or till rock is encountered, whichever is less, at an interval of 250 m and providing the results in tabular form as well as borelogs, ensuring atleast one borelog at the centre location of dry rivers, as per SCC, Specification and direction of Engineer-in-charge/Site Engineer. Note: The bank to bank width of flowing rivers shall be deducted from the total length for payment purpose, as payment for soil stratification at flowing river locations shall be under relevant item given below." Item 0019 130 KM
12 10.1 "At both the banks of flowing river by auguring up to a depth of 5 m from the ground level or till rock is encountered, whichever is less in the bank of river as per the SCC, specification and providing the result in tabular form. Note : Readings of two bore holes at both banks of the river shall be considered as One unit of reading for payment." Item 0020 3 EA
13 10.11 HYDROLOGICAL DATA COLLECTION/ GENERATION</></> Collection of Hydrological data such as High Flood Level (HFL), maximum flood discharge (Q), Average velocity of flow, extent of flood plains (based on previous floods), of all the rivers enroute, assessment of scour depth and flow pattern of rivers in the past 10 years. Relevant details shall be collected from the concerned Irrigation Deptt. office or other relevant sources. Other data based on hydrological survey of river crossings, as per details mentioned earlier, for design and installation of such crossings. Note: Unit 'EA' represents set of details for one river for purpose of payment. Item 0021
14 10.12 FOR ALL THE RIVERS ENROUTE Item 0022 3 EA
15 10.13 Deployment & Erection of Boring craft & Rig in each borehole location as per SCC, specifications, Scope of work and direction of Engineer in-charge. Item 0023
16 10.14 In land (other than Railway Crossings) Item 0024 10 EA
17 10.15 In land (for Railway Crossings) - <H>OPTIONAL</> Item 0025 4 EA
18 10.16 In Water Item 0026 8 EA
19 10.17 Conducting Boring of minimum 150 mm dia upto 25 meter of depth at Site in soil, Depth from GL/Bed level as per SCC, specifications, Scope of work and direction of Engineer in-charge. Item 0027
20 10.18 In land (other than Railway Crossings) Item 0028 210 M
21 10.19 In land(for Railway Crossings)-OPTIONAL Item 0029 60 M
22 10.2 In water Item 0030 180 M
23 10.21 Drilling through rock with Nx size double tube core barrel upto a depth of 10 meter below GL/bed level using TC bit/diamond bit as per SCC, specifications, Scope of work and direction of Engineer in-charge. Item 0031
24 10.22 In land (other than Railway Crossings) Item 0032 30 M
25 10.23 In land (for Railway Crossings)-OPTIONAL Item 0033 10 M
26 10.24 In Water <H><U>NOTE FOR ITEM NO. 010-0120</></> i) Boring depth shall be measured from Ground Level/River Bed level. Depth of actual soil strata bored / rock strata drilled shall be considered for payment. ii) Mere deployment of rig/ boring/drilling in river bed will not be considered as deployment / boring/drilling "in water" unless it is actually carried out in water. iii) Rate shall be inclusive of grouting back the boreholes as specified including cost for material, equipments and labour. iv) Core recovery >25 % shall be designated as rock. v) Recording of rock core characterstics shall be as per SCC, specification. Item 0034 20 M
27 10.25 Standard Peneteration Test</> at different depth as per SCC, specifications, Scope of work and direction of Engineer in-charge. Item 0035 220 EA
28 10.26 Collection of disturbed and undisturbed samples at different depth as per SCC, specifications, Scope of work and direction of Engineer in-charge. Item 0036
29 10.27 Collection of undisturbed samples</> at different depth as per SCC, specifications, Scope of work and direction of Engineer in-charge. Item 0037 140 EA
30 10.28 Collection of disturbed samples</> at different depth as per SCC, specifications, Scope of work and direction of Engineer in-charge. Item 0038 210 EA
31 10.29 Conducting <H>Laboratory Test</> on soil samples at an approved laboratory including preparation of soil samples to determine the following properties etc all complete as per SCC, specifications. Item 0039
32 10.3 Sieve analysis. Item 0040 150 EA
33 10.31 Hydrometer Analysis Item 0041 70 EA
34 10.32 Atterberg Limits Item 0042 140 EA
35 10.33 Natural Moisture Content Item 0043 140 EA
36 10.34 Bulk Density of Soil Item 0044 140 EA
37 10.35 Dry Density of Soil Item 0045 140 EA
38 10.36 Specific Gravity Item 0046 70 EA
39 10.37 Permeability Test Item 0047 40 EA
40 10.38 Consolidation Test Item 0048 40 EA
41 10.39 Uniaxial compressive strength of rock sample Item 0049 40 EA
42 10.4 Specific gravity test of rock sample Item 0050 40 EA
43 10.41 GROUND PENETRATING RADAR (OPTIONAL)</> Carrying out underground utility mapping using Ground Penetrating Radar (GPR) and other non-penetrating techniques up to 12 metre below the ground at railway crossing locations, including using of GPR equipment for recording the railroad bed crossing profile, Geological strata profiling, bedrock mapping, water table detection/mapping, burried pipe and cable mapping etc., for railway crossing locations, inclusive of all tools & tackles, manpower for carrying out the work as per the direction of Engineer in-charge (for HDD locations of railway crossing) Item 0051 2 EA
44 10.42 OBTAINING APPROVALS / PERMISSIONS</></> Obtaining approvals/ permissions from appropriate respective State/ National and other statutory authorities like Municpal corporation, Gram Panchayat or various land owning authorities using Google map or secondary maps or survey maps or crossing maps or any documents as applicable ( With authorisation from concerned agency) and submission to concerned land owning agencies in the required format and /or uploading in the website as required for applying of permission and submitting 4 copies of the applied permission drawings along with soft editable copies and CAD output on External Hard Disk to company /PMC as per detailed scope of work specified in SCC, specifications of the tender documents and direction of Engineer-in-Charge/ Site Engineer. All liasioning works including Integrating all details on Owner's Arc GIS (ESRI) server along the entire Pipeline Route for applying and obtaining secondary maps is included in this item. <H><U>Note:</></> 1) Payment shall be made for obtaining each permission. Cluster of crossings needing permission from same Authority shall be considered as one permission, for the purpose of payment 2) For Railway crossings, each crossing shall be treated as separate and payment shall be made on unit basis. 3) Payment will be made for the final approved route for which application has been made to the land agencies. 4) Item covers all works towards successful receipt of Permision for Laying Pipeline and stations from Concerned authorities & Land owners Item 0052
45 10.43 (a) All National Highways (NH)/Expressways Item 0053 1 EA
46 10.44 (b) All State Highways(SH) Item 0054 1 EA
47 10.45 (c) Other road crossings, any other road not designated as NH or SH, under each authority Item 0055 1 EA
48 10.46 (d) Railway Crossings ( for each individual crossing) Item 0056 1 EA
49 10.47 (e) All River crossings Item 0057 1 EA
50 10.48 (f) All Canal Crossings Item 0058 1 EA
51 10.49 (g) All other water bodies crossings like Pond, lakes etc. (excluding Rivers & Canals) Item 0059 1 EA
52 10.5 (h)All types of forest permission Item 0060 1 EA
53 20 Survey Works-Station-Araria-Purnia-Kat Item 0061
54 20.01 SOIL RESISTIVITY SURVEY</></> Carrying out corrosion survey including measurement of soil resistivity at a depth of 1.0, 1.5 & 2.0 m interval at in pipeline route, and at station locations, collection of additional data related to cathodic protection as per specification including providing man power, tools, tackles, materials, soil resistivity testing equipment, pipe/cable locator & other supporting facilities etc. including mobilization & demobilization necessary for survey and associated works, including compilation and presentation of data in four sets of Corrosion Survey Report as per SCC, technical specification, drawings, implementation schedule and other provisions of the tender document and instructions of Engineer-in-charge including uploading all data on Owner's ArcGIS (ESRI) server Item 0062
55 20.02 AT STATION LOCATIONS</></> Conducting Soil resistivity survey at station locations as per SCC, specifications & instructions of Engineer in charge/ Site Engineer complete in all respect. (1 set of reading per grid size of 35m x 35m) Note: Unit 'EA' represents set of readings at one location/point for purpose of payment. Item 0063
56 20.03 All Stations Locations Item 0064 1 EA
57 20.04 SOIL CHEMICAL ANALYSIS SURVEY</></> Conducting soil chemical analysis survey for determination of PH value, Chemical analysis for cations i.e. calcium, magnesium,sodium,potassium and Anions i.e Chloride, Sulphate, Sulphide, Carbonate, Bicarbonate, Nitrate, Phosphate,etc. as per SCC, specifications and direction of Engineer-in-Charge/Site Engineer & providing data in tabular form complete in all respect as per following schedule including uploading all data on Owner's ArcGIS server. Item 0065
58 20.05 AT STATION LOCATIONS</></> "At all station locations as per specifcations (1set of reading per grid of size 35m x 35m). Note: Unit 'EA' represents set of readings at one location/ grid for purpose of payment. " Item 0066
59 20.06 All Station locations Item 0067 1 EA
60 20.07 Topographical survey</></> Carrying out Topographic survey/contour survey including carrying out complete survey for the City Gas (CGS) & CNG station site of plot size 40mx50m in all respects as per SCC, drawing, technical specification and as per the direction of engineer -in-charge in all types of land involving contouring with advanced equipment (total station) at 0.50 meter intervals and spot level at 3.0 meter grid, plotting the existing underground and over ground facilities all complete as per SCC, specification and submission of all survey drawings, reports, contour maps made in Auto CAD in 4 (four) sets and copy of all drgs in External Hard Disk and the field book. Note: (1) Surveyors having adequate practical knowledge and experienced in survey works with advanced equipment is essential. Man and equipment required are to be arranged by the contractor at his own cost. Note:(2) The contractors shall include the cost towards mobilisation & de-mobilisation of equipment and men Note:(3) the contractor shall include the cost towards clearing of bushes/vegetation/cutting and removing tree branches (if required), in his quoted rates. Item 0068
61 20.08 At all Station locations Item 0069 2500 SQM
62 20.09 <H>Collection of Ground water samples</> & its chemical analysis as per SCC, specifications, scope of work and direction of Engineerin-charge (Only for Stations) Item 0070 1 EA
63 20.1 <H>Static Cone Penetration Test (SCPT)</> upto a depth of 30 meter as per SCC, specifications, Scope of Work and directions of Engineer-in-Charge (only for Station location) Item 0071 1 EA
64 20.11 Conducting <H>Laboratory Test</> on soil samples at an approved laboratory including preparation of soil samples to determine the following properties etc all complete as per SCC, specifications. Item 0072
65 20.12 Direct Shear Test(Only for Station locations) Item 0073 60 EA
66 20.13 Triaxial Shear Test (UD)(Only for Station locations) Item 0074 60 EA
67 20.14 Unconfined compression test(Only for Station locations) Item 0075 60 EA
68 20.15 Swelling pressure test(Only for Station locations) Item 0076 60 EA
69 20.16 Free swell index test(Only for Station locations) Item 0077 60 EA
70 20.17 Shrinkage limit test(Only for Station locations) Item 0078 60 EA
71 30 Survey Works-Mainline-Arwal Item 0079
72 30.01 Carrying out Reconnaissance Survey of the pipeline route including desktop study followed by verification of reconnaissance survey carried out earlier ( during DFR stage) as per SCC, Specification/Scope of work in the tender and instructions of Engineer-in-Charge and submission of four coloured drawings and report. The reconnaissance survey shall be carried out proposing minimum three or more feasible alternative routes and giving details of likely crossings and other constraints that is likely to be encountered during pipeline construction on each route, future development plans of land owning authorities like Municipal corporation, Gram Panchayat, PWD, NHAI , etc., availability of and including ownership details for setting up of CNG stations, DRS stations, potential Industrial consumers for PNG usage and recommending the best feasible route Item 0080 2 KM
73 30.02 DETAILED ENGINEERING SURVEY</></> Carrying out Detailed Engineering Survey and detailed Grid Line Survey along the entire proposed gas pipeline routes for a width of 30 meter on either side, in accordance with requirement of SCC, Scope of Work and Specification documents enclosed with the tender document and as per instructions of the Company’s representative including meeting all responsibilities and furnishing all documents for survey and all Reports and Drawings along with original editable CAD output including all data as per the detailed SCC, scope of work and Specifications of the tender document but not limited to following: (a),,Deploying Differential Global Positioning to provide DGPS control points at every 4 to 5 km interval based on WGS-84 UTM co-ordinate system; (b),,Deploying Total Stations for traverse control between DGPS stations; (c),,Establishing UTM co-ordinates of all TPs, IPs and Flag Control Points and other important points as desired by Owner; (d),,Taking all survey measurements, readings required for Planimetry, information and feature capturing and levels with respect to MSL; (e),,Obtaining base maps from authorised source (having clearance from Ministry of Defense/ Survey of India) of all districts and submission to Owner; (f),,Preparation & submission of Route Map, Profile Map, Crossing drawings, Planimetry, Alignment Sheets, etc.; (g),,Obtaining seismic fault line data & plotting of fault lines on Route Maps, Alignment sheets as well as on ground; (h),,DGPS survey details of forest area crossing in the pipeline route to be incorporated in the village maps. (i),,Collection of other details, including all labour, material, equipment etc. complete in all respects as per SCC, specifications and direction of Engineer-in-Charge/ Site Engineer; (j),,Integrating all survey details & deliverables, including base maps, into Owner's Arc GIS (ESRI) server to obtain seamless geo-referenced data. Item 0081
74 30.03 Along the entire steel pipeline route Item 0082 150 KM
75 30.04 <H><U>SOIL RESISTIVITY SURVEY</></> Carrying out corrosion survey including measurement of soil resistivity at a depth of 1.0, 1.5 & 2.0 m interval at in pipeline route, and at station locations, collection of additional data related to cathodic protection as per specification including providing man power, tools, tackles, materials, soil resistivity testing equipment, pipe/cable locator & other supporting facilities etc. including mobilization & demobilization necessary for survey and associated works, including compilation and presentation of data in four sets of Corrosion Survey Report as per SCC, technical specification, drawings, implementation schedule and other provisions of the tender document and instructions of Engineer-in-charge including uploading all data on Owner's ArcGIS (ESRI) server Item 0083
76 30.05 (a) IN PIPELINE ROUTE</></> Conducting soil resistivity survey at intervals of 500 meters along the pipeline route as per the detailed scope of work specified in SCC, Specifications of the tender document and direction of Engineer-in Charge/Site Engineer. Item 0084 150 KM
77 30.06 SOIL CHEMICAL ANALYSIS SURVEY</></> Conducting soil chemical analysis survey for determination of PH value, Chemical analysis for cations i.e. calcium, magnesium,sodium,potassium and Anions i.e Chloride, Sulphate, Sulphide, Carbonate, Bicarbonate, Nitrate, Phosphate,etc. as per SCC, specifications and direction of Engineer-in-Charge/Site Engineer & providing data in tabular form complete in all respect as per following schedule including uploading all data on Owner's ArcGIS server. Item 0085
78 30.07 IN PIPELINE ROUTE</></> Along the entire pipeline route at an interval of 1 km as per SCC, specification. Item 0086 150 KM
79 30.08 SOIL STRATIFICATION SURVEY</></> Conducting Soil Stratification Survey for determining stratification of Soil/ rock as per detailed scope of work specified in SCC, Specifications of the tender document and direction of Engineer-in-charge/Site Engineer including and providing all men, tools, tackles, materials, testing equipment & other equipment and other support facilities including mobilization and demobilization etc. as per tender document including providing the data in tabular form complete in all respect as per following schedule including uploading all data on Owner's ArcGIS server. Item 0087
80 30.09 ALONG PIPELINE ROUTE</></> "Along the pipeline route, including river crossings (excluding flowing river), by boring 150 mm dia. using auger type equipments up to a depth of 3 m from ground/bed level or till rock is encountered, whichever is less, at an interval of 250 m and providing the results in tabular form as well as borelogs, ensuring atleast one borelog at the centre location of dry rivers, as per SCC, Specification and direction of Engineer-in-charge/Site Engineer. Note: The bank to bank width of flowing rivers shall be deducted from the total length for payment purpose, as payment for soil stratification at flowing river locations shall be under relevant item given below." Item 0088 150 KM
81 30.1 "At both the banks of flowing river by auguring up to a depth of 5 m from the ground level or till rock is encountered, whichever is less in the bank of river as per the SCC, specification and providing the result in tabular form. Note : Readings of two bore holes at both banks of the river shall be considered as One unit of reading for payment." Item 0089 1 EA
82 30.11 <H><U>HYDROLOGICAL DATA COLLECTION/ GENERATION</></> Collection of Hydrological data such as High Flood Level (HFL), maximum flood discharge (Q), Average velocity of flow, extent of flood plains (based on previous floods), of all the rivers enroute, assessment of scour depth and flow pattern of rivers in the past 10 years. Relevant details shall be collected from the concerned Irrigation Deptt. office or other relevant sources. Other data based on hydrological survey of river crossings, as per details mentioned earlier, for design and installation of such crossings. Note: Unit 'EA' represents set of details for one river for purpose of payment. Item 0090
83 30.12 FOR ALL THE RIVERS ENROUTE Item 0091 1 EA
84 30.13 Deployment & Erection of Boring craft & Rig in each borehole location as per SCC, specifications, Scope of work and direction of Engineer in-charge. Item 0092
85 30.14 In land (other than Railway Crossings) Item 0093 3 EA
86 30.15 In land (for Railway Crossings) - <H>OPTIONAL</> Item 0094 4 EA
87 30.16 In Water Item 0095 2 EA
88 30.17 Conducting Boring of minimum 150 mm dia upto 25 meter of depth at Site in soil, Depth from GL/Bed level as per SCC, specifications, Scope of work and direction of Engineer in-charge. Item 0096
89 30.18 In land (other than Railway Crossings) Item 0097 50 M
90 30.19 In land(for Railway Crossings)-OPTIONAL Item 0098 60 M
91 30.2 In water Item 0099 50 M
92 30.21 Drilling through rock with Nx size double tube core barrel upto a depth of 10 meter below GL/bed level using TC bit/diamond bit as per SCC, specifications, Scope of work and direction of Engineer in-charge. Item 0100
93 30.22 In land (other than Railway Crossings) Item 0101 10 M
94 30.23 In land (for Railway Crossings)-OPTIONAL Item 0102 10 M
95 30.24 In Water <H><U>NOTE FOR ITEM NO. 010-0120</></> i) Boring depth shall be measured from Ground Level/River Bed level. Depth of actual soil strata bored / rock strata drilled shall be considered for payment. ii) Mere deployment of rig/ boring/drilling in river bed will not be considered as deployment / boring/drilling "in water" unless it is actually carried out in water. iii) Rate shall be inclusive of grouting back the boreholes as specified including cost for material, equipments and labour. iv) Core recovery >25 % shall be designated as rock. v) Recording of rock core characterstics shall be as per SCC, specification. Item 0103 10 M
96 30.25 Standard Peneteration Test</> at different depth as per SCC, specifications, Scope of work and direction of Engineer in-charge. Item 0104 80 EA
97 30.26 Collection of disturbed and undisturbed samples at different depth as per SCC, specifications, Scope of work and direction of Engineer in-charge. Item 0105
98 30.27 Collection of undisturbed samples</> at different depth as per SCC, specifications, Scope of work and direction of Engineer in-charge. Item 0106 50 EA
99 30.28 Collection of disturbed samples</> at different depth as per SCC, specifications, Scope of work and direction of Engineer in-charge. Item 0107 75 EA
100 30.29 Conducting <H>Laboratory Test</> on soil samples at an approved laboratory including preparation of soil samples to determine the following properties etc all complete as per SCC, specifications. Item 0108
101 30.3 Sieve analysis. Item 0109 50 EA
102 30.31 Hydrometer Analysis Item 0110 30 EA
103 30.32 Atterberg Limits Item 0111 50 EA
104 30.33 Natural Moisture Content Item 0112 50 EA
105 30.34 Bulk Density of Soil Item 0113 50 EA
106 30.35 Dry Density of Soil Item 0114 50 EA
107 30.36 Specific Gravity Item 0115 30 EA
108 30.37 Permeability Test Item 0116 10 EA
109 30.38 Consolidation Test Item 0117 10 EA
110 30.39 Uniaxial compressive strength of rock sample Item 0118 10 EA
111 30.4 Specific gravity test of rock sample Item 0119 10 EA
112 30.41 GROUND PENETRATING RADAR (OPTIONAL)</> Carrying out underground utility mapping using Ground Penetrating Radar (GPR) and other non-penetrating techniques up to 12 metre below the ground at railway crossing locations, including using of GPR equipment for recording the railroad bed crossing profile, Geological strata profiling, bedrock mapping, water table detection/mapping, burried pipe and cable mapping etc., for railway crossing locations, inclusive of all tools & tackles, manpower for carrying out the work as per the direction of Engineer in-charge (for HDD locations of railway crossing) Item 0120 2 EA
113 30.42 OBTAINING APPROVALS / PERMISSIONS</></> Obtaining approvals/ permissions from appropriate respective State/ National and other statutory authorities like Municpal corporation, Gram Panchayat or various land owning authorities using Google map or secondary maps or survey maps or crossing maps or any documents as applicable ( With authorisation from concerned agency) and submission to concerned land owning agencies in the required format and /or uploading in the website as required for applying of permission and submitting 4 copies of the applied permission drawings along with soft editable copies and CAD output on External Hard Disk to company /PMC as per detailed scope of work specified in SCC, specifications of the tender documents and direction of Engineer-in-Charge/ Site Engineer. All liasioning works including Integrating all details on Owner's Arc GIS (ESRI) server along the entire Pipeline Route for applying and obtaining secondary maps is included in this item. <H><U>Note:</></> 1) Payment shall be made for obtaining each permission. Cluster of crossings needing permission from same Authority shall be considered as one permission, for the purpose of payment 2) For Railway crossings, each crossing shall be treated as separate and payment shall be made on unit basis. 3) Payment will be made for the final approved route for which application has been made to the land agencies. 4) Item covers all works towards successful receipt of Permision for Laying Pipeline and stations from Concerned authorities & Land owners Item 0121
114 30.43 (a) All National Highways (NH)/Expressways Item 0122 1 EA
115 30.44 (b) All State Highways(SH) Item 0123 1 EA
116 30.45 (c) Other road crossings, any other road not designated as NH or SH, under each authority Item 0124 1 EA
117 30.46 (d) Railway Crossings ( for each individual crossing) Item 0125 1 EA
118 30.47 (e) All River crossings Item 0126 1 EA
119 30.48 (f) All Canal Crossings Item 0127 1 EA
120 30.49 (g) All other water bodies crossings like Pond, lakes etc. (excluding Rivers & Canals) Item 0128 1 EA
121 30.5 (h)All types of forest permission Item 0129 1 EA
122 40 Survey Works-Station-Arwal Item 0130
123 40.01 SOIL RESISTIVITY SURVEY</></> Carrying out corrosion survey including measurement of soil resistivity at a depth of 1.0, 1.5 & 2.0 m interval at in pipeline route, and at station locations, collection of additional data related to cathodic protection as per specification including providing man power, tools, tackles, materials, soil resistivity testing equipment, pipe/cable locator & other supporting facilities etc. including mobilization & demobilization necessary for survey and associated works, including compilation and presentation of data in four sets of Corrosion Survey Report as per SCC, technical specification, drawings, implementation schedule and other provisions of the tender document and instructions of Engineer-in-charge including uploading all data on Owner's ArcGIS (ESRI) server Item 0131
124 40.02 AT STATION LOCATIONS</></> Conducting Soil resistivity survey at station locations as per SCC, specifications & instructions of Engineer in charge/ Site Engineer complete in all respect. (1 set of reading per grid size of 35m x 35m) Note: Unit 'EA' represents set of readings at one location/point for purpose of payment. Item 0132
125 40.03 All Stations Locations Item 0133 1 EA
126 40.04 SOIL CHEMICAL ANALYSIS SURVEY</></> Conducting soil chemical analysis survey for determination of PH value, Chemical analysis for cations i.e. calcium, magnesium,sodium,potassium and Anions i.e Chloride, Sulphate, Sulphide, Carbonate, Bicarbonate, Nitrate, Phosphate,etc. as per SCC, specifications and direction of Engineer-in-Charge/Site Engineer & providing data in tabular form complete in all respect as per following schedule including uploading all data on Owner's ArcGIS server. Item 0134
127 40.05 AT STATION LOCATIONS</></> "At all station locations as per specifcations (1set of reading per grid of size 35m x 35m). Note: Unit 'EA' represents set of readings at one location/ grid for purpose of payment. " Item 0135
128 40.06 All Station locations Item 0136 1 EA
129 40.07 Topographical survey</></> Carrying out Topographic survey/contour survey including carrying out complete survey for the City Gas (CGS) & CNG station site of plot size 40mx50m in all respects as per SCC, drawing, technical specification and as per the direction of engineer -in-charge in all types of land involving contouring with advanced equipment (total station) at 0.50 meter intervals and spot level at 3.0 meter grid, plotting the existing underground and over ground facilities all complete as per SCC, specification and submission of all survey drawings, reports, contour maps made in Auto CAD in 4 (four) sets and copy of all drgs in External Hard Disk and the field book. Note: (1) Surveyors having adequate practical knowledge and experienced in survey works with advanced equipment is essential. Man and equipment required are to be arranged by the contractor at his own cost. Note:(2) The contractors shall include the cost towards mobilisation & de-mobilisation of equipment and men Note:(3) the contractor shall include the cost towards clearing of bushes/vegetation/cutting and removing tree branches (if required), in his quoted rates. Item 0137
130 40.08 At all Station locations Item 0138 2500 SQM
131 41.08 Collection of Ground water samples</> & its chemical analysis as per SCC, specifications, scope of work and direction of Engineerin-charge (Only for Stations) Item 0139 1 EA
132 42.08 Static Cone Penetration Test (SCPT)</> upto a depth of 30 meter as per SCC, specifications, Scope of Work and directions of Engineer-in-Charge (only for Station location) Item 0140 1 EA
133 43.08 Conducting Laboratory Test</> on soil samples at an approved laboratory including preparation of soil samples to determine the following properties etc all complete as per SCC, specifications. Item 0141
134 44.08 Direct Shear Test(Only for Station locations) Item 0142 60 EA
135 45.08 Triaxial Shear Test (UD)(Only for Station locations) Item 0143 60 EA
136 46.08 Unconfined compression test(Only for Station locations) Item 0144 60 EA
137 47.08 Swelling pressure test(Only for Station locations) Item 0145 60 EA
138 48.08 Free swell index test(Only for Station locations) Item 0146 60 EA
139 49.08 Shrinkage limit test(Only for Station locations) Item 0147 60 EA
140 50 Survey Works-Mainline-Bhagalpur Item 0148
141 50.01 Carrying out Reconnaissance Survey of the pipeline route including desktop study followed by verification of reconnaissance survey carried out earlier ( during DFR stage) as per SCC, Specification/Scope of work in the tender and instructions of Engineer-in-Charge and submission of four coloured drawings and report. The reconnaissance survey shall be carried out proposing minimum three or more feasible alternative routes and giving details of likely crossings and other constraints that is likely to be encountered during pipeline construction on each route, future development plans of land owning authorities like Municipal corporation, Gram Panchayat, PWD, NHAI , etc., availability of and including ownership details for setting up of CNG stations, DRS stations, potential Industrial consumers for PNG usage and recommending the best feasible route Item 0149 2 KM
142 50.02 DETAILED ENGINEERING SURVEY</></> Carrying out Detailed Engineering Survey and detailed Grid Line Survey along the entire proposed gas pipeline routes for a width of 30 meter on either side, in accordance with requirement of SCC, Scope of Work and Specification documents enclosed with the tender document and as per instructions of the Company’s representative including meeting all responsibilities and furnishing all documents for survey and all Reports and Drawings along with original editable CAD output including all data as per the detailed SCC, scope of work and Specifications of the tender document but not limited to following: (a),,Deploying Differential Global Positioning to provide DGPS control points at every 4 to 5 km interval based on WGS-84 UTM co-ordinate system; (b),,Deploying Total Stations for traverse control between DGPS stations; (c),,Establishing UTM co-ordinates of all TPs, IPs and Flag Control Points and other important points as desired by Owner; (d),,Taking all survey measurements, readings required for Planimetry, information and feature capturing and levels with respect to MSL; (e),,Obtaining base maps from authorised source (having clearance from Ministry of Defense/ Survey of India) of all districts and submission to Owner; (f),,Preparation & submission of Route Map, Profile Map, Crossing drawings, Planimetry, Alignment Sheets, etc.; (g),,Obtaining seismic fault line data & plotting of fault lines on Route Maps, Alignment sheets as well as on ground; (h),,DGPS survey details of forest area crossing in the pipeline route to be incorporated in the village maps. (i),,Collection of other details, including all labour, material, equipment etc. complete in all respects as per SCC, specifications and direction of Engineer-in-Charge/ Site Engineer; (j),,Integrating all survey details & deliverables, including base maps, into Owner's Arc GIS (ESRI) server to obtain seamless geo-referenced data. Item 0150
143 50.03 Along the entire steel pipeline route Item 0151 170 KM
144 50.04 SOIL RESISTIVITY SURVEY</></> Carrying out corrosion survey including measurement of soil resistivity at a depth of 1.0, 1.5 & 2.0 m interval at in pipeline route, and at station locations, collection of additional data related to cathodic protection as per specification including providing man power, tools, tackles, materials, soil resistivity testing equipment, pipe/cable locator & other supporting facilities etc. including mobilization & demobilization necessary for survey and associated works, including compilation and presentation of data in four sets of Corrosion Survey Report as per SCC, technical specification, drawings, implementation schedule and other provisions of the tender document and instructions of Engineer-in-charge including uploading all data on Owner's ArcGIS (ESRI) server Item 0152
145 50.05 (a) IN PIPELINE ROUTE</></> Conducting soil resistivity survey at intervals of 500 meters along the pipeline route as per the detailed scope of work specified in SCC, Specifications of the tender document and direction of Engineer-in Charge/Site Engineer. Item 0153 170 KM
146 50.06 SOIL CHEMICAL ANALYSIS SURVEY</></> Conducting soil chemical analysis survey for determination of PH value, Chemical analysis for cations i.e. calcium, magnesium,sodium,potassium and Anions i.e Chloride, Sulphate, Sulphide, Carbonate, Bicarbonate, Nitrate, Phosphate,etc. as per SCC, specifications and direction of Engineer-in-Charge/Site Engineer & providing data in tabular form complete in all respect as per following schedule including uploading all data on Owner's ArcGIS server. Item 0154
147 50.07 IN PIPELINE ROUTE</></> Along the entire pipeline route at an interval of 1 km as per SCC, specification. Item 0155 170 KM
148 50.08 SOIL STRATIFICATION SURVEY</></> Conducting Soil Stratification Survey for determining stratification of Soil/ rock as per detailed scope of work specified in SCC, Specifications of the tender document and direction of Engineer-in-charge/Site Engineer including and providing all men, tools, tackles, materials, testing equipment & other equipment and other support facilities including mobilization and demobilization etc. as per tender document including providing the data in tabular form complete in all respect as per following schedule including uploading all data on Owner's ArcGIS server. Item 0156
149 50.09 (a)ALONG PIPELINE ROUTE</></> "Along the pipeline route, including river crossings (excluding flowing river), by boring 150 mm dia. using auger type equipments up to a depth of 3 m from ground/bed level or till rock is encountered, whichever is less, at an interval of 250 m and providing the results in tabular form as well as borelogs, ensuring atleast one borelog at the centre location of dry rivers, as per SCC, Specification and direction of Engineer-in-charge/Site Engineer. Note: The bank to bank width of flowing rivers shall be deducted from the total length for payment purpose, as payment for soil stratification at flowing river locations shall be under relevant item given below." Item 0157 170 KM
150 50.1 "At both the banks of flowing river by auguring up to a depth of 5 m from the ground level or till rock is encountered, whichever is less in the bank of river as per the SCC, specification and providing the result in tabular form. Note : Readings of two bore holes at both banks of the river shall be considered as One unit of reading for payment." Item 0158 6 EA
151 50.11 HYDROLOGICAL DATA COLLECTION/ GENERATION</></> Collection of Hydrological data such as High Flood Level (HFL), maximum flood discharge (Q), Average velocity of flow, extent of flood plains (based on previous floods), of all the rivers enroute, assessment of scour depth and flow pattern of rivers in the past 10 years. Relevant details shall be collected from the concerned Irrigation Deptt. office or other relevant sources. Other data based on hydrological survey of river crossings, as per details mentioned earlier, for design and installation of such crossings. Note: Unit 'EA' represents set of details for one river for purpose of payment. Item 0159
152 50.12 FOR ALL THE RIVERS ENROUTE Item 0160 6 EA
153 50.13 Deployment & Erection of Boring craft & Rig in each borehole location as per SCC, specifications, Scope of work and direction of Engineer in-charge. Item 0161
154 50.14 In land (other than Railway Crossings) Item 0162 15 EA
155 50.15 In land (for Railway Crossings) - <H>OPTIONAL</> Item 0163 4 EA
156 50.16 In Water Item 0164 14 EA
157 50.17 Conducting Boring of minimum 150 mm dia upto 25 meter of depth at Site in soil, Depth from GL/Bed level as per SCC, specifications, Scope of work and direction of Engineer in-charge. Item 0165
158 50.18 In land (other than Railway Crossings) Item 0166 320 M
159 50.19 In land(for Railway Crossings)-OPTIONAL Item 0167 60 M
160 50.2 In water Item 0168 320 M
161 50.21 Drilling through rock with Nx size double tube core barrel upto a depth of 10 meter below GL/bed level using TC bit/diamond bit as per SCC, specifications, Scope of work and direction of Engineer in-charge. Item 0169
162 50.22 In land (other than Railway Crossings) Item 0170 40 M
163 50.23 In land (for Railway Crossings)-OPTIONAL Item 0171 10 M
164 50.24 In Water <H><U>NOTE FOR ITEM NO. 010-0120</></> i) Boring depth shall be measured from Ground Level/River Bed level. Depth of actual soil strata bored / rock strata drilled shall be considered for payment. ii) Mere deployment of rig/ boring/drilling in river bed will not be considered as deployment / boring/drilling "in water" unless it is actually carried out in water. iii) Rate shall be inclusive of grouting back the boreholes as specified including cost for material, equipments and labour. iv) Core recovery >25 % shall be designated as rock. v) Recording of rock core characterstics shall be as per SCC, specification. Item 0172 40 M
165 50.25 Standard Peneteration Test</> at different depth as per SCC, specifications, Scope of work and direction of Engineer in-charge. Item 0173 340 EA
166 50.26 Collection of disturbed and undisturbed samples at different depth as per SCC, specifications, Scope of work and direction of Engineer in-charge. Item 0174
167 50.27 <H>Collection of undisturbed samples</> at different depth as per SCC, specifications, Scope of work and direction of Engineer in-charge. Item 0175 210 EA
168 50.28 <H>Collection of disturbed samples</> at different depth as per SCC, specifications, Scope of work and direction of Engineer in-charge. Item 0176 315 EA
169 50.29 Conducting <H>Laboratory Test</> on soil samples at an approved laboratory including preparation of soil samples to determine the following properties etc all complete as per SCC, specifications. Item 0177
170 50.3 Sieve analysis. Item 0178 230 EA
171 50.31 Hydrometer Analysis Item 0179 110 EA
172 50.32 Atterberg Limits Item 0180 210 EA
173 50.33 Natural Moisture Content Item 0181 210 EA
174 50.34 Bulk Density of Soil Item 0182 210 EA
175 50.35 Dry Density of Soil Item 0183 210 EA
176 50.36 Specific Gravity Item 0184 110 EA
177 50.37 Permeability Test Item 0185 50 EA
178 50.38 Consolidation Test Item 0186 50 EA
179 50.39 Uniaxial compressive strength of rock sample Item 0187 50 EA
180 50.4 Specific gravity test of rock sample Item 0188 50 EA
181 50.41 GROUND PENETRATING RADAR (OPTIONAL)</> Carrying out underground utility mapping using Ground Penetrating Radar (GPR) and other non-penetrating techniques up to 12 metre below the ground at railway crossing locations, including using of GPR equipment for recording the railroad bed crossing profile, Geological strata profiling, bedrock mapping, water table detection/mapping, burried pipe and cable mapping etc., for railway crossing locations, inclusive of all tools & tackles, manpower for carrying out the work as per the direction of Engineer in-charge (for HDD locations of railway crossing) Item 0189 2 EA
182 50.42 OBTAINING APPROVALS / PERMISSIONS</></> Obtaining approvals/ permissions from appropriate respective State/ National and other statutory authorities like Municpal corporation, Gram Panchayat or various land owning authorities using Google map or secondary maps or survey maps or crossing maps or any documents as applicable ( With authorisation from concerned agency) and submission to concerned land owning agencies in the required format and /or uploading in the website as required for applying of permission and submitting 4 copies of the applied permission drawings along with soft editable copies and CAD output on External Hard Disk to company /PMC as per detailed scope of work specified in SCC, specifications of the tender documents and direction of Engineer-in-Charge/ Site Engineer. All liasioning works including Integrating all details on Owner's Arc GIS (ESRI) server along the entire Pipeline Route for applying and obtaining secondary maps is included in this item. <H><U>Note:</></> 1) Payment shall be made for obtaining each permission. Cluster of crossings needing permission from same Authority shall be considered as one permission, for the purpose of payment 2) For Railway crossings, each crossing shall be treated as separate and payment shall be made on unit basis. 3) Payment will be made for the final approved route for which application has been made to the land agencies. 4) Item covers all works towards successful receipt of Permision for Laying Pipeline and stations from Concerned authorities & Land owners Item 0190
183 50.43 All National Highways (NH)/Expressways Item 0191 1 EA
184 50.44 (b) All State Highways(SH) Item 0192 1 EA
185 50.45 (c) Other road crossings, any other road not designated as NH or SH, under each authority Item 0193 1 EA
186 50.46 (d) Railway Crossings ( for each individual crossing) Item 0194 1 EA
187 50.47 (e) All River crossings Item 0195 1 EA
188 50.48 (f) All Canal Crossings Item 0196 1 EA
189 50.49 (g) All other water bodies crossings like Pond, lakes etc. (excluding Rivers & Canals) Item 0197 1 EA
190 50.5 (h)All types of forest permission Item 0198 1 EA
191 60 Survey Works-Station-Bhagalpur Item 0199
192 60.01 SOIL RESISTIVITY SURVEY</></> Carrying out corrosion survey including measurement of soil resistivity at a depth of 1.0, 1.5 & 2.0 m interval at in pipeline route, and at station locations, collection of additional data related to cathodic protection as per specification including providing man power, tools, tackles, materials, soil resistivity testing equipment, pipe/cable locator & other supporting facilities etc. including mobilization & demobilization necessary for survey and associated works, including compilation and presentation of data in four sets of Corrosion Survey Report as per SCC, technical specification, drawings, implementation schedule and other provisions of the tender document and instructions of Engineer-in-charge including uploading all data on Owner's ArcGIS (ESRI) server Item 0200
193 60.02 AT STATION LOCATIONS</></> Conducting Soil resistivity survey at station locations as per SCC, specifications & instructions of Engineer in charge/ Site Engineer complete in all respect. (1 set of reading per grid size of 35m x 35m) Note: Unit 'EA' represents set of readings at one location/point for purpose of payment. Item 0201
194 60.03 All Stations Locations Item 0202 1 EA
195 60.04 <H><U>SOIL CHEMICAL ANALYSIS SURVEY</></> Conducting soil chemical analysis survey for determination of PH value, Chemical analysis for cations i.e. calcium, magnesium,sodium,potassium and Anions i.e Chloride, Sulphate, Sulphide, Carbonate, Bicarbonate, Nitrate, Phosphate,etc. as per SCC, specifications and direction of Engineer-in-Charge/Site Engineer & providing data in tabular form complete in all respect as per following schedule including uploading all data on Owner's ArcGIS server. Item 0203
196 60.05 <H><U>(b) AT STATION LOCATIONS</></> "At all station locations as per specifcations (1set of reading per grid of size 35m x 35m). Note: Unit 'EA' represents set of readings at one location/ grid for purpose of payment. " Item 0204
197 60.06 All Station locations Item 0205 1 EA
198 60.07 <H><U>Topographical survey</></> Carrying out Topographic survey/contour survey including carrying out complete survey for the City Gas (CGS) & CNG station site of plot size 40mx50m in all respects as per SCC, drawing, technical specification and as per the direction of engineer -in-charge in all types of land involving contouring with advanced equipment (total station) at 0.50 meter intervals and spot level at 3.0 meter grid, plotting the existing underground and over ground facilities all complete as per SCC, specification and submission of all survey drawings, reports, contour maps made in Auto CAD in 4 (four) sets and copy of all drgs in External Hard Disk and the field book. Note: (1) Surveyors having adequate practical knowledge and experienced in survey works with advanced equipment is essential. Man and equipment required are to be arranged by the contractor at his own cost. Note:(2) The contractors shall include the cost towards mobilisation & de-mobilisation of equipment and men Note:(3) the contractor shall include the cost towards clearing of bushes/vegetation/cutting and removing tree branches (if required), in his quoted rates. Item 0206
199 60.08 At all Station locations Item 0207 2500 SQM
200 60.09 <H>Collection of Ground water samples</> & its chemical analysis as per SCC, specifications, scope of work and direction of Engineerin-charge (Only for Stations) Item 0208 1 EA
201 60.1 <H>Static Cone Penetration Test (SCPT)</> upto a depth of 30 meter as per SCC, specifications, Scope of Work and directions of Engineer-in-Charge (only for Station location) Item 0209 1 EA
202 60.11 Conducting <H>Laboratory Test</> on soil samples at an approved laboratory including preparation of soil samples to determine the following properties etc all complete as per SCC, specifications. Item 0210
203 60.12 Direct Shear Test(Only for Station locations) Item 0211 60 EA
204 60.13 Triaxial Shear Test (UD)(Only for Station locations) Item 0212 60 EA
205 60.14 Unconfined compression test(Only for Station locations) Item 0213 60 EA
206 60.15 Swelling pressure test(Only for Station locations) Item 0214 60 EA
207 60.16 Free swell index test(Only for Station locations) Item 0215 60 EA
208 60.17 Shrinkage limit test(Only for Station locations) Item 0216 60 EA
209 70 Survey Works-Mainline-Muzaffarpur Item 0217
210 70.01 Carrying out Reconnaissance Survey of the pipeline route including desktop study followed by verification of reconnaissance survey carried out earlier ( during DFR stage) as per SCC, Specification/Scope of work in the tender and instructions of Engineer-in-Charge and submission of four coloured drawings and report. The reconnaissance survey shall be carried out proposing minimum three or more feasible alternative routes and giving details of likely crossings and other constraints that is likely to be encountered during pipeline construction on each route, future development plans of land owning authorities like Municipal corporation, Gram Panchayat, PWD, NHAI , etc., availability of and including ownership details for setting up of CNG stations, DRS stations, potential Industrial consumers for PNG usage and recommending the best feasible route Item 0218 2 KM
211 70.02 DETAILED ENGINEERING SURVEY</></> Carrying out Detailed Engineering Survey and detailed Grid Line Survey along the entire proposed gas pipeline routes for a width of 30 meter on either side, in accordance with requirement of SCC, Scope of Work and Specification documents enclosed with the tender document and as per instructions of the Company’s representative including meeting all responsibilities and furnishing all documents for survey and all Reports and Drawings along with original editable CAD output including all data as per the detailed SCC, scope of work and Specifications of the tender document but not limited to following: (a),,Deploying Differential Global Positioning to provide DGPS control points at every 4 to 5 km interval based on WGS-84 UTM co-ordinate system; (b),,Deploying Total Stations for traverse control between DGPS stations; (c),,Establishing UTM co-ordinates of all TPs, IPs and Flag Control Points and other important points as desired by Owner; (d),,Taking all survey measurements, readings required for Planimetry, information and feature capturing and levels with respect to MSL; (e),,Obtaining base maps from authorised source (having clearance from Ministry of Defense/ Survey of India) of all districts and submission to Owner; (f),,Preparation & submission of Route Map, Profile Map, Crossing drawings, Planimetry, Alignment Sheets, etc.; (g),,Obtaining seismic fault line data & plotting of fault lines on Route Maps, Alignment sheets as well as on ground; (h),,DGPS survey details of forest area crossing in the pipeline route to be incorporated in the village maps. (i),,Collection of other details, including all labour, material, equipment etc. complete in all respects as per SCC, specifications and direction of Engineer-in-Charge/ Site Engineer; (j),,Integrating all survey details & deliverables, including base maps, into Owner's Arc GIS (ESRI) server to obtain seamless geo-referenced data. Item 0219
212 70.03 Along the entire steel pipeline route Item 0220 230 KM
213 70.04 SOIL RESISTIVITY SURVEY</></> Carrying out corrosion survey including measurement of soil resistivity at a depth of 1.0, 1.5 & 2.0 m interval at in pipeline route, and at station locations, collection of additional data related to cathodic protection as per specification including providing man power, tools, tackles, materials, soil resistivity testing equipment, pipe/cable locator & other supporting facilities etc. including mobilization & demobilization necessary for survey and associated works, including compilation and presentation of data in four sets of Corrosion Survey Report as per SCC, technical specification, drawings, implementation schedule and other provisions of the tender document and instructions of Engineer-in-charge including uploading all data on Owner's ArcGIS (ESRI) server Item 0221
214 70.05 <H><U>(a) IN PIPELINE ROUTE</></> Conducting soil resistivity survey at intervals of 500 meters along the pipeline route as per the detailed scope of work specified in SCC, Specifications of the tender document and direction of Engineer-in Charge/Site Engineer. Item 0222 230 KM
215 70.06 <H><U>SOIL CHEMICAL ANALYSIS SURVEY</></> Conducting soil chemical analysis survey for determination of PH value, Chemical analysis for cations i.e. calcium, magnesium,sodium,potassium and Anions i.e Chloride, Sulphate, Sulphide, Carbonate, Bicarbonate, Nitrate, Phosphate,etc. as per SCC, specifications and direction of Engineer-in-Charge/Site Engineer & providing data in tabular form complete in all respect as per following schedule including uploading all data on Owner's ArcGIS server. Item 0223
216 70.07 (a) IN PIPELINE ROUTE</></> Along the entire pipeline route at an interval of 1 km as per SCC, specification. Item 0224 230 KM
217 70.08 <SOIL STRATIFICATION SURVEY</></> Conducting Soil Stratification Survey for determining stratification of Soil/ rock as per detailed scope of work specified in SCC, Specifications of the tender document and direction of Engineer-in-charge/Site Engineer including and providing all men, tools, tackles, materials, testing equipment & other equipment and other support facilities including mobilization and demobilization etc. as per tender document including providing the data in tabular form complete in all respect as per following schedule including uploading all data on Owner's ArcGIS server. Item 0225
218 70.09 (a)ALONG PIPELINE ROUTE</></> "Along the pipeline route, including river crossings (excluding flowing river), by boring 150 mm dia. using auger type equipments up to a depth of 3 m from ground/bed level or till rock is encountered, whichever is less, at an interval of 250 m and providing the results in tabular form as well as borelogs, ensuring atleast one borelog at the centre location of dry rivers, as per SCC, Specification and direction of Engineer-in-charge/Site Engineer. Note: The bank to bank width of flowing rivers shall be deducted from the total length for payment purpose, as payment for soil stratification at flowing river locations shall be under relevant item given below." Item 0226 230 KM
219 70.1 "At both the banks of flowing river by auguring up to a depth of 5 m from the ground level or till rock is encountered, whichever is less in the bank of river as per the SCC, specification and providing the result in tabular form. Note : Readings of two bore holes at both banks of the river shall be considered as One unit of reading for payment." Item 0227 6 EA
220 70.11 HYDROLOGICAL DATA COLLECTION/ GENERATION</></> Collection of Hydrological data such as High Flood Level (HFL), maximum flood discharge (Q), Average velocity of flow, extent of flood plains (based on previous floods), of all the rivers enroute, assessment of scour depth and flow pattern of rivers in the past 10 years. Relevant details shall be collected from the concerned Irrigation Deptt. office or other relevant sources. Other data based on hydrological survey of river crossings, as per details mentioned earlier, for design and installation of such crossings. Note: Unit 'EA' represents set of details for one river for purpose of payment. Item 0228
221 70.12 FOR ALL THE RIVERS ENROUTE Item 0229 6 EA
222 70.13 Deployment & Erection of Boring craft & Rig in each borehole location as per SCC, specifications, Scope of work and direction of Engineer in-charge. Item 0230
223 70.14 In land (other than Railway Crossings) Item 0231 18 EA
224 70.15 In land (for Railway Crossings) - <H>OPTIONAL</> Item 0232 18 EA
225 70.16 In Water Item 0233 23 EA
226 70.17 Conducting Boring of minimum 150 mm dia upto 25 meter of depth at Site in soil, Depth from GL/Bed level as per SCC, specifications, Scope of work and direction of Engineer in-charge. Item 0234
227 70.18 In land (other than Railway Crossings) Item 0235 390 M
228 70.19 In land(for Railway Crossings)-OPTIONAL Item 0236 250 M
229 70.2 In water Item 0237 520 M
230 70.21 Drilling through rock with Nx size double tube core barrel upto a depth of 10 meter below GL/bed level using TC bit/diamond bit as per SCC, specifications, Scope of work and direction of Engineer in-charge. Item 0238
231 70.22 In land (other than Railway Crossings) Item 0239 50 M
232 70.23 In land (for Railway Crossings)-OPTIONAL Item 0240 30 M
233 70.24 In Water <H><U>NOTE FOR ITEM NO. 010-0120</></> i) Boring depth shall be measured from Ground Level/River Bed level. Depth of actual soil strata bored / rock strata drilled shall be considered for payment. ii) Mere deployment of rig/ boring/drilling in river bed will not be considered as deployment / boring/drilling "in water" unless it is actually carried out in water. iii) Rate shall be inclusive of grouting back the boreholes as specified including cost for material, equipments and labour. iv) Core recovery >25 % shall be designated as rock. v) Recording of rock core characterstics shall be as per SCC, specification. Item 0241 60 M
234 70.25 <H>Standard Peneteration Test</> at different depth as per SCC, specifications, Scope of work and direction of Engineer in-charge. Item 0242 570 EA
235 70.26 Collection of disturbed and undisturbed samples at different depth as per SCC, specifications, Scope of work and direction of Engineer in-charge. Item 0243
236 70.27 <H>Collection of undisturbed samples</> at different depth as per SCC, specifications, Scope of work and direction of Engineer in-charge. Item 0244 350 EA
237 70.28 <H>Collection of disturbed samples</> at different depth as per SCC, specifications, Scope of work and direction of Engineer in-charge. Item 0245 525 EA
238 70.29 Conducting <H>Laboratory Test</> on soil samples at an approved laboratory including preparation of soil samples to determine the following properties etc all complete as per SCC, specifications. Item 0246
239 70.3 Sieve analysis. Item 0247 380 EA
240 70.31 Hydrometer Analysis Item 0248 190 EA
241 70.32 Atterberg Limits Item 0249 350 EA
242 70.33 Natural Moisture Content Item 0250 350 EA
243 70.34 Bulk Density of Soil Item 0251 350 EA
244 70.35 Dry Density of Soil Item 0252 350 EA
245 70.36 Specific Gravity Item 0253 180 EA
246 70.37 Permeability Test Item 0254 90 EA
247 70.38 Consolidation Test Item 0255 90 EA
248 70.39 Uniaxial compressive strength of rock sample Item 0256 90 EA
249 70.4 Specific gravity test of rock sample Item 0257 90 EA
250 70.41 GROUND PENETRATING RADAR (OPTIONAL)</> Carrying out underground utility mapping using Ground Penetrating Radar (GPR) and other non-penetrating techniques up to 12 metre below the ground at railway crossing locations, including using of GPR equipment for recording the railroad bed crossing profile, Geological strata profiling, bedrock mapping, water table detection/mapping, burried pipe and cable mapping etc., for railway crossing locations, inclusive of all tools & tackles, manpower for carrying out the work as per the direction of Engineer in-charge (for HDD locations of railway crossing) Item 0258 9 EA
251 70.42 OBTAINING APPROVALS / PERMISSIONS</></> Obtaining approvals/ permissions from appropriate respective State/ National and other statutory authorities like Municpal corporation, Gram Panchayat or various land owning authorities using Google map or secondary maps or survey maps or crossing maps or any documents as applicable ( With authorisation from concerned agency) and submission to concerned land owning agencies in the required format and /or uploading in the website as required for applying of permission and submitting 4 copies of the applied permission drawings along with soft editable copies and CAD output on External Hard Disk to company /PMC as per detailed scope of work specified in SCC, specifications of the tender documents and direction of Engineer-in-Charge/ Site Engineer. All liasioning works including Integrating all details on Owner's Arc GIS (ESRI) server along the entire Pipeline Route for applying and obtaining secondary maps is included in this item. <H><U>Note:</></> 1) Payment shall be made for obtaining each permission. Cluster of crossings needing permission from same Authority shall be considered as one permission, for the purpose of payment 2) For Railway crossings, each crossing shall be treated as separate and payment shall be made on unit basis. 3) Payment will be made for the final approved route for which application has been made to the land agencies. 4) Item covers all works towards successful receipt of Permision for Laying Pipeline and stations from Concerned authorities & Land owners Item 0259
252 70.43 All National Highways (NH)/Expressways Item 0260 1 EA
253 70.44 (b) All State Highways(SH) Item 0261 1 EA
254 70.45 (c) Other road crossings, any other road not designated as NH or SH, under each authority Item 0262 1 EA
255 70.46 (d) Railway Crossings ( for each individual crossing) Item 0263 1 EA
256 70.47 (e) All River crossings Item 0264 1 EA
257 70.48 (f) All Canal Crossings Item 0265 1 EA
258 70.49 (g) All other water bodies crossings like Pond, lakes etc. (excluding Rivers & Canals) Item 0266 1 EA
259 70.5 (h)All types of forest permission Item 0267 1 EA
260 80 Survey Works-Station-Muzaffarpur Item 0268
261 80.01 SOIL RESISTIVITY SURVEY</></> Carrying out corrosion survey including measurement of soil resistivity at a depth of 1.0, 1.5 & 2.0 m interval at in pipeline route, and at station locations, collection of additional data related to cathodic protection as per specification including providing man power, tools, tackles, materials, soil resistivity testing equipment, pipe/cable locator & other supporting facilities etc. including mobilization & demobilization necessary for survey and associated works, including compilation and presentation of data in four sets of Corrosion Survey Report as per SCC, technical specification, drawings, implementation schedule and other provisions of the tender document and instructions of Engineer-in-charge including uploading all data on Owner's ArcGIS (ESRI) server Item 0269
262 80.02 AT STATION LOCATIONS</></> Conducting Soil resistivity survey at station locations as per SCC, specifications & instructions of Engineer in charge/ Site Engineer complete in all respect. (1 set of reading per grid size of 35m x 35m) Note: Unit 'EA' represents set of readings at one location/point for purpose of payment. Item 0270
263 80.03 All Stations Locations Item 0271 1 EA
264 80.04 SOIL CHEMICAL ANALYSIS SURVEY</></> Conducting soil chemical analysis survey for determination of PH value, Chemical analysis for cations i.e. calcium, magnesium,sodium,potassium and Anions i.e Chloride, Sulphate, Sulphide, Carbonate, Bicarbonate, Nitrate, Phosphate,etc. as per SCC, specifications and direction of Engineer-in-Charge/Site Engineer & providing data in tabular form complete in all respect as per following schedule including uploading all data on Owner's ArcGIS server. Item 0272
265 80.05 AT STATION LOCATIONS</></> "At all station locations as per specifcations (1set of reading per grid of size 35m x 35m). Note: Unit 'EA' represents set of readings at one location/ grid for purpose of payment. " Item 0273
266 80.06 All Station locations Item 0274 1 EA
267 80.07 <H><U>Topographical survey</></> Carrying out Topographic survey/contour survey including carrying out complete survey for the City Gas (CGS) & CNG station site of plot size 40mx50m in all respects as per SCC, drawing, technical specification and as per the direction of engineer -in-charge in all types of land involving contouring with advanced equipment (total station) at 0.50 meter intervals and spot level at 3.0 meter grid, plotting the existing underground and over ground facilities all complete as per SCC, specification and submission of all survey drawings, reports, contour maps made in Auto CAD in 4 (four) sets and copy of all drgs in External Hard Disk and the field book. Note: (1) Surveyors having adequate practical knowledge and experienced in survey works with advanced equipment is essential. Man and equipment required are to be arranged by the contractor at his own cost. Note:(2) The contractors shall include the cost towards mobilisation & de-mobilisation of equipment and men Note:(3) the contractor shall include the cost towards clearing of bushes/vegetation/cutting and removing tree branches (if required), in his quoted rates. Item 0275
268 80.08 At all Station locations Item 0276 2500 SQM
269 80.09 Collection of Ground water samples</> & its chemical analysis as per SCC, specifications, scope of work and direction of Engineerin-charge (Only for Stations) Item 0277 1 EA
270 80.1 Static Cone Penetration Test (SCPT)</> upto a depth of 30 meter as per SCC, specifications, Scope of Work and directions of Engineer-in-Charge (only for Station location) Item 0278 1 EA
271 80.11 Conducting <H>Laboratory Test</> on soil samples at an approved laboratory including preparation of soil samples to determine the following properties etc all complete as per SCC, specifications. Item 0279
272 80.12 Direct Shear Test(Only for Station locations) Item 0280 60 EA
273 80.13 Triaxial Shear Test (UD)(Only for Station locations) Item 0281 60 EA
274 80.14 Unconfined compression test(Only for Station locations) Item 0282 60 EA
275 80.15 Swelling pressure test(Only for Station locations) Item 0283 60 EA
276 80.16 Free swell index test(Only for Station locations) Item 0284 60 EA
277 80.17 Shrinkage limit test(Only for Station locations) Item 0285 60 EA
278 90 Survey Works-Mainline-Khagaria Item 0286
279 90.01 Carrying out Reconnaissance Survey of the pipeline route including desktop study followed by verification of reconnaissance survey carried out earlier ( during DFR stage) as per SCC, Specification/Scope of work in the tender and instructions of Engineer-in-Charge and submission of four coloured drawings and report. The reconnaissance survey shall be carried out proposing minimum three or more feasible alternative routes and giving details of likely crossings and other constraints that is likely to be encountered during pipeline construction on each route, future development plans of land owning authorities like Municipal corporation, Gram Panchayat, PWD, NHAI , etc., availability of and including ownership details for setting up of CNG stations, DRS stations, potential Industrial consumers for PNG usage and recommending the best feasible route Item 0287 2 KM
280 90.02 DETAILED ENGINEERING SURVEY</></> Carrying out Detailed Engineering Survey and detailed Grid Line Survey along the entire proposed gas pipeline routes for a width of 30 meter on either side, in accordance with requirement of SCC, Scope of Work and Specification documents enclosed with the tender document and as per instructions of the Company’s representative including meeting all responsibilities and furnishing all documents for survey and all Reports and Drawings along with original editable CAD output including all data as per the detailed SCC, scope of work and Specifications of the tender document but not limited to following: (a),,Deploying Differential Global Positioning to provide DGPS control points at every 4 to 5 km interval based on WGS-84 UTM co-ordinate system; (b),,Deploying Total Stations for traverse control between DGPS stations; (c),,Establishing UTM co-ordinates of all TPs, IPs and Flag Control Points and other important points as desired by Owner; (d),,Taking all survey measurements, readings required for Planimetry, information and feature capturing and levels with respect to MSL; (e),,Obtaining base maps from authorised source (having clearance from Ministry of Defense/ Survey of India) of all districts and submission to Owner; (f),,Preparation & submission of Route Map, Profile Map, Crossing drawings, Planimetry, Alignment Sheets, etc.; (g),,Obtaining seismic fault line data & plotting of fault lines on Route Maps, Alignment sheets as well as on ground; (h),,DGPS survey details of forest area crossing in the pipeline route to be incorporated in the village maps. (i),,Collection of other details, including all labour, material, equipment etc. complete in all respects as per SCC, specifications and direction of Engineer-in-Charge/ Site Engineer; (j),,Integrating all survey details & deliverables, including base maps, into Owner's Arc GIS (ESRI) server to obtain seamless geo-referenced data. Item 0288
281 90.03 Along the entire steel pipeline route Item 0289 70 KM
282 90.04 SOIL RESISTIVITY SURVEY</></> Carrying out corrosion survey including measurement of soil resistivity at a depth of 1.0, 1.5 & 2.0 m interval at in pipeline route, and at station locations, collection of additional data related to cathodic protection as per specification including providing man power, tools, tackles, materials, soil resistivity testing equipment, pipe/cable locator & other supporting facilities etc. including mobilization & demobilization necessary for survey and associated works, including compilation and presentation of data in four sets of Corrosion Survey Report as per SCC, technical specification, drawings, implementation schedule and other provisions of the tender document and instructions of Engineer-in-charge including uploading all data on Owner's ArcGIS (ESRI) server Item 0290
283 90.05 <H><U>(a) IN PIPELINE ROUTE</></> Conducting soil resistivity survey at intervals of 500 meters along the pipeline route as per the detailed scope of work specified in SCC, Specifications of the tender document and direction of Engineer-in Charge/Site Engineer. Item 0291 70 KM
284 90.06 <H><U>SOIL CHEMICAL ANALYSIS SURVEY</></> Conducting soil chemical analysis survey for determination of PH value, Chemical analysis for cations i.e. calcium, magnesium,sodium,potassium and Anions i.e Chloride, Sulphate, Sulphide, Carbonate, Bicarbonate, Nitrate, Phosphate,etc. as per SCC, specifications and direction of Engineer-in-Charge/Site Engineer & providing data in tabular form complete in all respect as per following schedule including uploading all data on Owner's ArcGIS server. Item 0292
285 90.07 <H><U>(a) IN PIPELINE ROUTE</></> Along the entire pipeline route at an interval of 1 km as per SCC, specification. Item 0293 70 KM
286 90.08 <H><U>SOIL STRATIFICATION SURVEY</></> Conducting Soil Stratification Survey for determining stratification of Soil/ rock as per detailed scope of work specified in SCC, Specifications of the tender document and direction of Engineer-in-charge/Site Engineer including and providing all men, tools, tackles, materials, testing equipment & other equipment and other support facilities including mobilization and demobilization etc. as per tender document including providing the data in tabular form complete in all respect as per following schedule including uploading all data on Owner's ArcGIS server. Item 0294
287 90.09 <H><U>(a)ALONG PIPELINE ROUTE</></> "Along the pipeline route, including river crossings (excluding flowing river), by boring 150 mm dia. using auger type equipments up to a depth of 3 m from ground/bed level or till rock is encountered, whichever is less, at an interval of 250 m and providing the results in tabular form as well as borelogs, ensuring atleast one borelog at the centre location of dry rivers, as per SCC, Specification and direction of Engineer-in-charge/Site Engineer. Note: The bank to bank width of flowing rivers shall be deducted from the total length for payment purpose, as payment for soil stratification at flowing river locations shall be under relevant item given below." Item 0295 70 KM
288 90.1 "At both the banks of flowing river by auguring up to a depth of 5 m from the ground level or till rock is encountered, whichever is less in the bank of river as per the SCC, specification and providing the result in tabular form. Note : Readings of two bore holes at both banks of the river shall be considered as One unit of reading for payment." Item 0296 3 EA
289 90.11 HYDROLOGICAL DATA COLLECTION/ GENERATION</></> Collection of Hydrological data such as High Flood Level (HFL), maximum flood discharge (Q), Average velocity of flow, extent of flood plains (based on previous floods), of all the rivers enroute, assessment of scour depth and flow pattern of rivers in the past 10 years. Relevant details shall be collected from the concerned Irrigation Deptt. office or other relevant sources. Other data based on hydrological survey of river crossings, as per details mentioned earlier, for design and installation of such crossings. Note: Unit 'EA' represents set of details for one river for purpose of payment. Item 0297
290 90.12 FOR ALL THE RIVERS ENROUTE Item 0298 3 EA
291 90.13 Deployment & Erection of Boring craft & Rig in each borehole location as per SCC, specifications, Scope of work and direction of Engineer in-charge. Item 0299
292 90.14 In land (other than Railway Crossings) Item 0300 15 EA
293 90.15 In land (for Railway Crossings) - <H>OPTIONAL</> Item 0301 6 EA
294 90.16 In Water Item 0302 4 EA
295 90.17 Conducting Boring of minimum 150 mm dia upto 25 meter of depth at Site in soil, Depth from GL/Bed level as per SCC, specifications, Scope of work and direction of Engineer in-charge. Item 0303
296 90.18 In land (other than Railway Crossings) Item 0304 320 M
297 90.19 In land(for Railway Crossings)-OPTIONAL Item 0305 90 M
298 90.2 In water Item 0306 90 M
299 90.21 Drilling through rock with Nx size double tube core barrel upto a depth of 10 meter below GL/bed level using TC bit/diamond bit as per SCC, specifications, Scope of work and direction of Engineer in-charge. Item 0307
300 90.22 In land (other than Railway Crossings) Item 0308 40 M
301 90.23 In land (for Railway Crossings)-OPTIONAL Item 0309 10 M
302 90.24 In Water <H><U>NOTE FOR ITEM NO. 010-0120</></> i) Boring depth shall be measured from Ground Level/River Bed level. Depth of actual soil strata bored / rock strata drilled shall be considered for payment. ii) Mere deployment of rig/ boring/drilling in river bed will not be considered as deployment / boring/drilling "in water" unless it is actually carried out in water. iii) Rate shall be inclusive of grouting back the boreholes as specified including cost for material, equipments and labour. iv) Core recovery >25 % shall be designated as rock. v) Recording of rock core characterstics shall be as per SCC, specification. Item 0310 10 M
303 90.25 <H>Standard Peneteration Test</> at different depth as per SCC, specifications, Scope of work and direction of Engineer in-charge. Item 0311 240 EA
304 90.26 Collection of disturbed and undisturbed samples at different depth as per SCC, specifications, Scope of work and direction of Engineer in-charge. Item 0312
305 90.27 <H>Collection of undisturbed samples</> at different depth as per SCC, specifications, Scope of work and direction of Engineer in-charge. Item 0313 150 EA
306 90.28 <H>Collection of disturbed samples</> at different depth as per SCC, specifications, Scope of work and direction of Engineer in-charge. Item 0314 225 EA
307 90.29 Conducting <H>Laboratory Test</> on soil samples at an approved laboratory including preparation of soil samples to determine the following properties etc all complete as per SCC, specifications. Item 0315
308 90.3 Sieve analysis. Item 0316 160 EA
309 90.31 Hydrometer Analysis Item 0317 80 EA
310 90.32 Atterberg Limits Item 0318 150 EA
311 90.33 Natural Moisture Content Item 0319 150 EA
312 90.34 Bulk Density of Soil Item 0320 150 EA
313 90.35 Dry Density of Soil Item 0321 150 EA
314 90.36 Specific Gravity Item 0322 80 EA
315 90.37 Permeability Test Item 0323 40 EA
316 90.38 Consolidation Test Item 0324 40 EA
317 90.39 Uniaxial compressive strength of rock sample Item 0325 40 EA
318 90.4 Specific gravity test of rock sample Item 0326 40 EA
319 90.41 <H>GROUND PENETRATING RADAR (OPTIONAL)</> Carrying out underground utility mapping using Ground Penetrating Radar (GPR) and other non-penetrating techniques up to 12 metre below the ground at railway crossing locations, including using of GPR equipment for recording the railroad bed crossing profile, Geological strata profiling, bedrock mapping, water table detection/mapping, burried pipe and cable mapping etc., for railway crossing locations, inclusive of all tools & tackles, manpower for carrying out the work as per the direction of Engineer in-charge (for HDD locations of railway crossing) Item 0327 3 EA
320 90.42 <H><U>OBTAINING APPROVALS / PERMISSIONS</></> Obtaining approvals/ permissions from appropriate respective State/ National and other statutory authorities like Municpal corporation, Gram Panchayat or various land owning authorities using Google map or secondary maps or survey maps or crossing maps or any documents as applicable ( With authorisation from concerned agency) and submission to concerned land owning agencies in the required format and /or uploading in the website as required for applying of permission and submitting 4 copies of the applied permission drawings along with soft editable copies and CAD output on External Hard Disk to company /PMC as per detailed scope of work specified in SCC, specifications of the tender documents and direction of Engineer-in-Charge/ Site Engineer. All liasioning works including Integrating all details on Owner's Arc GIS (ESRI) server along the entire Pipeline Route for applying and obtaining secondary maps is included in this item. <H><U>Note:</></> 1) Payment shall be made for obtaining each permission. Cluster of crossings needing permission from same Authority shall be considered as one permission, for the purpose of payment 2) For Railway crossings, each crossing shall be treated as separate and payment shall be made on unit basis. 3) Payment will be made for the final approved route for which application has been made to the land agencies. 4) Item covers all works towards successful receipt of Permision for Laying Pipeline and stations from Concerned authorities & Land owners Item 0328
321 90.43 All National Highways (NH)/Expressways Item 0329 1 EA
322 90.44 (b) All State Highways(SH) Item 0330 1 EA
323 90.45 (c) Other road crossings, any other road not designated as NH or SH, under each authority Item 0331 1 EA
324 90.46 (d) Railway Crossings ( for each individual crossing) Item 0332 1 EA
325 90.47 (e) All River crossings Item 0333 1 EA
326 90.48 (f) All Canal Crossings Item 0334 1 EA
327 90.49 (g) All other water bodies crossings like Pond, lakes etc. (excluding Rivers & Canals) Item 0335 1 EA
328 90.5 (h)All types of forest permission Item 0336 1 EA
329 100 Survey Works-Station-Khagaria Item 0337
330 100.01 <H><U>SOIL RESISTIVITY SURVEY</></> Carrying out corrosion survey including measurement of soil resistivity at a depth of 1.0, 1.5 & 2.0 m interval at in pipeline route, and at station locations, collection of additional data related to cathodic protection as per specification including providing man power, tools, tackles, materials, soil resistivity testing equipment, pipe/cable locator & other supporting facilities etc. including mobilization & demobilization necessary for survey and associated works, including compilation and presentation of data in four sets of Corrosion Survey Report as per SCC, technical specification, drawings, implementation schedule and other provisions of the tender document and instructions of Engineer-in-charge including uploading all data on Owner's ArcGIS (ESRI) server Item 0338
331 100.02 <H><U>(b) AT STATION LOCATIONS</></> Conducting Soil resistivity survey at station locations as per SCC, specifications & instructions of Engineer in charge/ Site Engineer complete in all respect. (1 set of reading per grid size of 35m x 35m) Note: Unit 'EA' represents set of readings at one location/point for purpose of payment. Item 0339
332 100.03 All Stations Locations Item 0340 1 EA
333 100.04 <H><U>SOIL CHEMICAL ANALYSIS SURVEY</></> Conducting soil chemical analysis survey for determination of PH value, Chemical analysis for cations i.e. calcium, magnesium,sodium,potassium and Anions i.e Chloride, Sulphate, Sulphide, Carbonate, Bicarbonate, Nitrate, Phosphate,etc. as per SCC, specifications and direction of Engineer-in-Charge/Site Engineer & providing data in tabular form complete in all respect as per following schedule including uploading all data on Owner's ArcGIS server. Item 0341
334 100.05 <H><U>(b) AT STATION LOCATIONS</></> "At all station locations as per specifcations (1set of reading per grid of size 35m x 35m). Note: Unit 'EA' represents set of readings at one location/ grid for purpose of payment. " Item 0342
335 100.06 All Station locations Item 0343 1 EA
336 100.07 <H><U>Topographical survey</></> Carrying out Topographic survey/contour survey including carrying out complete survey for the City Gas (CGS) & CNG station site of plot size 40mx50m in all respects as per SCC, drawing, technical specification and as per the direction of engineer -in-charge in all types of land involving contouring with advanced equipment (total station) at 0.50 meter intervals and spot level at 3.0 meter grid, plotting the existing underground and over ground facilities all complete as per SCC, specification and submission of all survey drawings, reports, contour maps made in Auto CAD in 4 (four) sets and copy of all drgs in External Hard Disk and the field book. Note: (1) Surveyors having adequate practical knowledge and experienced in survey works with advanced equipment is essential. Man and equipment required are to be arranged by the contractor at his own cost. Note:(2) The contractors shall include the cost towards mobilisation & de-mobilisation of equipment and men Note:(3) the contractor shall include the cost towards clearing of bushes/vegetation/cutting and removing tree branches (if required), in his quoted rates. Item 0344
337 100.08 At all Station locations Item 0345 2500 SQM
338 100.09 <H>Collection of Ground water samples</> & its chemical analysis as per SCC, specifications, scope of work and direction of Engineerin-charge (Only for Stations) Item 0346 1 EA
339 100.1 <H>Static Cone Penetration Test (SCPT)</> upto a depth of 30 meter as per SCC, specifications, Scope of Work and directions of Engineer-in-Charge (only for Station location) Item 0347 1 EA
340 100.11 Conducting <H>Laboratory Test</> on soil samples at an approved laboratory including preparation of soil samples to determine the following properties etc all complete as per SCC, specifications. Item 0348
341 100.12 Direct Shear Test(Only for Station locations) Item 0349 60 EA
342 100.13 Triaxial Shear Test (UD)(Only for Station locations) Item 0350 60 EA
343 100.14 Unconfined compression test(Only for Station locations) Item 0351 60 EA
344 100.15 Swelling pressure test(Only for Station locations) Item 0352 60 EA
345 100.16 Free swell index test(Only for Station locations) Item 0353 60 EA
346 100.17 Shrinkage limit test(Only for Station locations) Item 0354 60 EA
Disclaimer :
We takes all possible care for accurate & authentic tender information, however Users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender.
Tell us about your Product / Services,
We will Find Tenders for you

Copyright © 2024 · All Rights Reserved. Terms of Usage | Privacy Policy

For Tender Information Services Visit : TenderDetail