| 1 | 1 | Clearing compound premises of shurbs, plants, jungles etc. by cutting and removing as directed (Specific permission of Engineer-in-Charge prior to execution will be necessary). | BI01010001010000000000000515BI0100001113 | 140 | sqm |
|---|
| 2 | 2 | Earth work in excavation of foundation trenches or drains, in all sorts of soil (including mixed soil but excluding laterite or sandstone) including removing, spreading or stacking the spoils within a lead of 75 m. as directed. The item includes necessary trimming the sides of trenches, levelling, dressing and ramming the bottom, bailing out water as required complete.(a) Depth of excavation not exceeding 1,500 mm. | BI01010001010000000000000515BI0100001114 | 4.5 | sqm |
|---|
| 3 | 3 | Providing and fixing at or near ground level precast cement concrete in kerbs (size: 450 mm x 350 mm x width 150 mm at bottom with bevelled nosing at top) of cement concreat M20 Grade without reinforcement, fixing as per approved pattern and setting in position at site after preparing the bed grade and slopes by laying Cement concrete with jhama khoa (1:4:8) as per specification and direction of Engineer-in- Charge including filling of joints with 10 mm thick cement morter (3:1) and back filling the vertical piece properly with earth duly compacted and curing the morter joints for atleast 3 days including cost and carriage of all materials complete. | BI01010001010000000000000515BI0100001115 | 25 | Mtr |
|---|
| 4 | 4 | Filling in foundation or plinth by silver sands in layers not exceeding 150mm, as directed and consolidating the same by thorough saturation with water, ramming complete including the cost of supply of silver sand. (payment to be made on the basis of measurement of finished quantity of work) (B) Do- by fine sand | BI01010001010000000000000515BI0100001116 | 42 | cum |
|---|
| 5 | 5 | M.S. structural works in columns, beams etc. with simple rolled structural members (e.g. joists, angle, channel sections conforming to IS: 226, IS: 808 & SP (6)- 1964 connected to one another with bracket, gussets, cleats as per design, direction of Engineer-incharge complete including cutting to requisite shape and length, fabrication with necessary bolting, metal arc welding conforming to IS: 816- 1969 & IS: 1995 using electrodes of approved make and brand conforming to IS:814- 2004, haulage, hoisting and erection all complete. The rate includes the cost of rolled steel section, consumables such as electrodes, gas and hire charge of all tools and plants and labour required for the work including all incidental chages such as electricity charges, labour insurance charges etcI) For structural members of specified sections weighing less than\n22.5 Kg./m | BI01010001010000000000000515BI0100001117 | 0.92 | MT |
|---|
| 6 | 6 | Ordinary Cement concrete (mix 1: 2: 4) with graded stone aggregate (20 mm nominal size) and reinforcement as specified excluding shuttering and reinforcement, if any, in ground floor as per relevant IS codes. | BI01010001010000000000000515BI0100001118 | 3 | cum |
|---|
| 7 | 7 | Supplying & laying as per IRC-SP:063-2004 paver unit of any shade of approved quality as per relevant IS code, laid in pattern as directed in pavement, footpath, driveway (paver block only), etc including necessary underlay complete in all respect with all labour and material. [Border concrete if necessary to be paid separately]. Note: Sub-grade CBR should not be less than 5.(c) 60 mm thick interlocking designer concrete paver block M- 35 grade for light-traffic (ii) Coloured Decorativezone,commercial & office complex,tourist resort as per IS: 15658-2006 (over 20-40 mm medium sand bed on 250mm thk WBM/ WMM base course & 250 mm thk bound gnaular /granular sub-base course including cost of sand for sand bed but excluding cost of base ,sub-base course & subgrade preparati | BI01010001010000000000000515BI0100001119 | 105 | sqm |
|---|
| 8 | 8 | Taking out existing CC interlocking paver blocks from footpath/ central verge, including removal of rubbish etc., disposal of unserviceable material to the dumping ground, for which payment shall be made separately and stacking of serviceable material within 50 metre lead and laying the same of any design/ shape laid in required line, level, curvature, colour and pattern over and including 50 mm thick compacted bed of coarse sand, filling the joints with fine sand etc. all complete as per the direction of Engineer-in-charge. (Old CC paver blocks shall be supplied by the department free of cost). | BI01010001010000000000000515BI0100001120 | 350 | sqm |
|---|
| 9 | 9 | Welding in M.S. structural work with gas or electric:(a) Tack weld | | 1136 | point |
|---|
| 10 | 10 | Scraping of moss, blisters etc.thoroughly from exterior surface of walls necessitating the use of scraper, wire brush etc.(Payment against this item will be made only when this has been done on the specific direction of the Engineer-in-charge) | | 56 | sqm |
|---|
| 11 | 11 | Applying Exterior grade Acrylic primer of approved quality and brand on plastered or cencrete surface old or new surface to receive decorative textured (matt finish) or smooth finish acrylic exterior emulsion paint including scraping and preparing the surface thoroughly complete as per manufacturer's specification and as per direction of the EIC(b) Two Coats | | 350 | sqm |
|---|
| 12 | 12 | Protective and Decorative Acrylic exterior emulsion paint of approved quality, as per manufacturer's specification and as per direction ofEngineer-in-Charge to be applied over acrylic primer as required. The rate includes cost of material, labour, scaffolding and all incidental charges but excluding the cost of primerb) Premium 100% Acrylic Emulsion | | 350 | sqm |
|---|
| 13 | 13 | Providing and stacking of Foxtail palm of ht. 120-150 cm bottom girth 15-20 cm well developed in big poly bags of size 25 cm as per direction of the officer-in-charge | | 71 | No |
|---|
| 14 | 14 | Maintanance of trees for one year (Avenue Plants) including watering, trimming, manuring, spraying insecticide and guarding as required. This includes supply of labour, tools & plants including materials | | 71 | Each per year |
|---|
| 15 | 15 | Planting of trees ( Avenue plants) in 0.60m dia holea, 1m deep dug in the ground, mixing the soil with decayed farm yard/sludge manure. This includes supply of labour, tools & plants including materials but excluding cost of tree. | | 71 | no |
|---|
| 16 | 16 | Supplying and laying Polythene Sheet (150gm / sq.m.) over damp proof course or below flooring or roof terracing or infoundation or in foundation trenches. | | 180 | no |
|---|
| 17 | 17 | Supplying fitting and fixing I.R.C. fabric mesh with covering battens including cost of screws etc complete (excluding the cost of battens). In ground floor. (j) 25mm x 25mm x 2.2mm x 2.2mm. | BI01010001010000000000000515BI0100001121 | 350 | sqm |
|---|