Tender For Annual Maintenance Water Supply Scheme Bhageswari , Distt Charkhi Dadri Repair Of Water Tank Of Ohsr , P F Of Expension Joint Ci Df Duct Bend , Ms Stair , Water Level Recorder Etc . At Village Bhageshwari And All Other Works Contingent Ther, PHED Charkhi Dadri-Haryana

Public Health Engineering Department-PHED has published Tender For Annual Maintenance Water Supply Scheme Bhageswari , Distt Charkhi Dadri Repair Of Water Tank Of Ohsr , P F Of Expension Joint Ci Df Duct Bend , Ms Stair , Water Level Recorder Etc . At Village Bhageshwari And All Other Works Contingent Ther. Submission Date for this Tender is 30-08-2019. Water Supply Project Tenders in PHED Charkhi Dadri Haryana. Bidders can get complete Tender details and download the document.




Tender Notice

21488123
Tender For Annual Maintenance Water Supply Scheme Bhageswari , Distt Charkhi Dadri Repair Of Water Tank Of Ohsr , P F Of Expension Joint Ci Df Duct Bend , Ms Stair , Water Level Recorder Etc . At Village Bhageshwari And All Other Works Contingent Ther
Open Tender
Indian
Haryana
PHED Charkhi Dadri
30-08-2019

Tender Details

Tender For Annual Maintenance Water Supply Scheme Bhageswari , Distt Charkhi Dadri Repair Of Water Tank Of Ohsr , P F Of Expension Joint Ci Df Duct Bend , Ms Stair , Water Level Recorder Etc . At Village Bhageshwari And All Other Works Contingent Thereto .

Key Value

Document Fees
INR 500 /-
EMD
INR 4780.0 /-
Tender Value
Refer document

BOQ Items

Name of Work: Sonf DNIT Independent Water Work for Water Supply Scheme Sonf Tehsil Charkhi Dadri Tehsil Charkhi Dadri. Construction of Raw Water pumping station RCC Sump Pump Chamber, Laying of rising main 1 No. SS Tank, 1 No. RCC Suction well for raw water, 1 no. RCC Suction well for clear water tank, 1 No. RCC high level tank, 1 No. RCC clear water tank,3 No. RCC filter bed, 1 No. pump chamber boundary wall, laying of distribution system and Raw water pumping machinery at Canal, laying of pipe line at head works, Supplying, Installing and Commissioning of pumping machinery for raw water, clear water including all required electrical & mechanical equipment, maintenance of civil works and distribution system for Five years after three month trail run period and all other works contingent thereto
Sl. No. Item Description Item Code / Make Quantity Units
1 1 Sub Head No. 1 (Hire charges)\nA) Scaffolding charges including loading, unloading and cartage charges \n2 No. 22x 10 x 2 = 440 No. BI01010001010000000000000515BI0100001113 440 Each
2 2 B) 10’ long (Horizontal) at a discharge of 3’6”\n11 x 34 x 2 = 748 No.\n BI01010001010000000000000515BI0100001114 748 Each
3 3 C) inner side Scaffolding\n12’ long (Vertical) 12 x 8 = 96 No\n\n BI01010001010000000000000515BI0100001115 96 Each
4 4 D) 10’ long (Horizontal) at a distance of 3’6” \n6 x 28 x 2 = 336 No.\n BI01010001010000000000000515BI0100001116 336 Each
5 5 E) Assuming 12 No. Mazdoor will prepares Scaffolding in 5 days removed in 2 days= 7 days BI01010001010000000000000515BI0100001117 7 Day Each
6 6 F) Charges of Lift machine 1 No. for 2 days BI01010001010000000000000515BI0100001118 2 Day Each
7 7 G) Charges of Chakri Bhooni BI01010001010000000000000515BI0100001119 1 Per Job
8 8 Sub Head No. 2 (Cost of Material) \nOuter side\nA) Rassa Coconut (22+22) x 34 = 1496 Nos.\n BI01010001010000000000000515BI0100001120 1496 Each
9 9 B) Rassa Coconut 24 x 28 = 672 No. BI01010001010000000000000515BI0100001121 672 Each
10 10 C) Cost of other material i.e. Cement, Chemical etc BI01010001010000000000000515BI0100001122 1 Job
11 11 D) PVC Rassa ¾” BI01010001010000000000000515BI0100001123 100 Rft.
12 12 E) Cost of cement plaster inside of tank wall & bed of dome \nInside – 1x22/7x20x16 = 1006 Sft\nOn dome – 1x22/7x22x20x1/4 = 314 Sft\nTotal = 1320 Sft Or 37 Sqm Say 40.00 Sqm\n BI01010001010000000000000515BI0100001124 40 Sqm
13 13 Sub Head No. 3 ( Labour Work) \nA) Forman for 10 days \n BI01010001010000000000000515BI0100001125 10 Each
14 14 B) Mason-II for 10 days BI01010001010000000000000515BI0100001126 10 Each
15 15 C) Mazdoor 8 Nos. for 10 days BI01010001010000000000000515BI0100001127 8 Each
16 16 Sub Head No. 4 (Repair work) \nA) Dismantling of floor of inside tank & reconstruction of same to its original condition \n BI01010001010000000000000515BI0100001128 40 Sqm
17 17 B) Providing and fixing of 6” i/d expansion joint including cost of labour of removing the old joint complete in all respect BI01010001010000000000000515BI0100001129 4 Each
18 18 C) Providing and fixing of C.I double Duct foot bend complete as per IS standard complete in all respect \n150mm i/d\n BI01010001010000000000000515BI0100001130 4 Each
19 19 100mm i/d BI01010001010000000000000515BI0100001131 4 Each
20 20 D) Providing and fixing of MS water reader Gauge of standard size complete in all respect BI01010001010000000000000515BI0100001132 1 Each
21 21 E) Providing and fixing of Angle Iron Grip complete in all respect BI01010001010000000000000515BI0100001133 10 Rft.
22 22 F) Providing and fixing of Air Ventilation 30 x 60cm BI01010001010000000000000515BI0100001134 4 Each
23 23 G) Providing and fixing of railing BI01010001010000000000000515BI0100001135 200 Kg
24 24 H) Providing and fixing of Can wall gate & Cantilever BI01010001010000000000000515BI0100001136 100 Kg
25 25 I) Providing and fixing of CI D/F pipe complete in all respect \n150mm dia 2.75 Mtr length = 11 No.\n BI01010001010000000000000515BI0100001137 540 Kg
26 26 J) 100mm dia 2.75 Mtr length = 11 No. BI01010001010000000000000515BI0100001138 540 Kg
Disclaimer :
We takes all possible care for accurate & authentic tender information, however Users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender.
Tell us about your Product / Services,
We will Find Tenders for you

Copyright © 2024 · All Rights Reserved. Terms of Usage | Privacy Policy

For Tender Information Services Visit : TenderDetail