Military Engineer Services-MES has published Repair And Maintenance Of Pump Sets Starter Ats Apfc Lt Panel Swimming Pool Pipe Line And Connected Works Under Age E And M Subathu. Submission Date for this Tender is 05-09-2019. Electromechanical Work Tenders in SUBATHU Himachal Pradesh. Bidders can get complete Tender details and download the document.
Name of Work: REPAIR / MAINT OF PUMP SETS, STARTER , ATS, APFC, LT PANEL, SWIMMING POOL, PIPE LINE AND CONNECTED WORKS UNDER AGE E/M SUBATHU | |||||
---|---|---|---|---|---|
Sl. No. | Item Description | Item Code / Make | Quantity | Units | |
1 | 0.01 | Schedule 'A' Section - I | |||
2 | 1 | Disconnecting the electrical connections of motor, water supply to the Pump and taking out pump after disconnecting both motor and pump mechanically 100/125 HP capacity (Make Crompton Greaves ) capacity - 45 Cum at 315 metres head installed at Gamber Pump House Subathu and transporting the same to an authorized workshop for following repairs:- 'Dismantling the complete pump carefully, taking out all impellers, impeller housings, bush bearings, oil rings, shaft with keys, shaft sleeves with nuts, balancing valve, com seating bush, neck rings and bushes, coupling set, gland and gland packing, logging ring, oil filter plug, water thrower, suction and delivery covers etc complete all as specified and as directed by Engineer-in-Charge and recommended by the manufacturer. After repairs the pump set is to be brought back at Pump house and installed, coupled with motor. All electrical, water and mechanical connections to be re-done all as directed. Note:- All spares to be replaced shall be measured and paid separately under respective items. | 1 | Each Job | |
3 | 1.01 | Bush bearing made out of bronze No 6318 for Srl Item No 1 | 1 | Each | |
4 | 1.02 | Oil ring made out of brass for Srl Item No 1 | 2 | Each | |
5 | 1.03 | Shaft sleeve with nuts made out of stainless steel 410 grade for Srl Item No 1 | 4 | Each | |
6 | 1.04 | Balancing valve made out of PCuSn7 for Srl Item No 1 | 1 | Each | |
7 | 1.05 | Com Seating Bush made out of bronze for Srl Item No 1 | 1 | Each | |
8 | 1.06 | Neck ring made out of bronze for Srl Item No 1 | 4 | Each | |
9 | 1.07 | Neck bush made out of bronze for Srl Item No 1 | 4 | Each | |
10 | 1.08 | Set of pins and Gaskets made out of Mild Steel for Srl Item No 1 | 1 | Each Set | |
11 | 1.09 | Coupling set made out of Cast Iron including bolts, nuts, washers & rubber bushes for Srl Item No 1 | 1 | Each | |
12 | 1.1 | Gland box made out of Cast Iron including gland box studs with nuts and washers for Srl Item No 1 | 2 | Each | |
13 | 1.11 | Gland packing made out of Gr. Cotton for Srl Item No 1 | 2 | Each Job | |
14 | 1.12 | Logging ring made out of bronze for Srl Item No 1 | 1 | Each | |
15 | 1.13 | Metal (bronze) filling in the worn out portion of impellers, turning and grinding the metal filled portions. Balancing the impeller by means of precision lathe machine for Srl Item No 1 | 4 | Each Job | |
16 | 1.14 | S&F Shaft with keys made out of steel 410 grade for Srl Item No 1 | 1 | Each | |
17 | 2 | Attending emergency breke down and disconnecting the electrical connections of motor, and taking out pump after disconnecting both motor and pump mechanically 20/25 HP capacity (Make-Mather & Polatt) capacity - 45 Cum at 70 metres head and transporting the same to an authorized workshop for following repairs:- | 2 | Each Job | |
18 | 2.01 | Dismantling the complete pump carefully, taking out all impellers, impeller housings, bush bearings, oil rings, shaft with keys, shaft sleeves with nuts, balancing valve, com seating bush, neck rings and bushes, coupling set, gland and gland packing, logging ring, oil filter plug, water thrower, suction and delivery covers etc complete all as specified and as directed by Engineer-in-Charge and recommended by the manufacturer. After repairs the pump set is to be brought back at Pump house and installed, coupled with motor. All electrical, water and mechanical connections to be re-done all as directed. Note:- All spares to be replaced shall be measured and paid separately under respective items. | |||
19 | 2.02 | Shaft sleeve with nuts made out of stainless steel 410 grade for Srl Item No 2 | 2 | Each | |
20 | 2.03 | Set of pins and Gaskets made out of Mild Steel for Srl Item No 2 | 1 | Each Set | |
21 | 2.04 | Coupling set made out of Cast Iron including bolts, nuts, washers & rubber bushes for Srl Item No 2 | 2 | Each | |
22 | 2.05 | Gland box made out of Cast Iron including gland box studs with nuts and washers for Srl Item No 2 | 2 | Each | |
23 | 2.06 | Gland packing made out of Gr. Cotton for Srl Item No 2 | 1 | Each Job | |
24 | 2.07 | Driving End bearing for Srl Item No 2 | 1 | Each | |
25 | 2.08 | Non Driving End bearing for Srl Item No 2 | 2 | Each | |
26 | 3 | All as per Srl item No. 2.00 above but for 20 HP capacity (Make-Mather & Platt, Model 65/32 SK - Non Clog) capacity - 68 Cum at 35 metres head installed at Pump House Gamber | 1 | Each Job | |
27 | 3.01 | S&F Shaft with keys made out of steel 410 grade for Srl Item No 3 | 1 | Each | |
28 | 3.02 | Shaft sleeve with nuts made out of stainless steel 410 grade for Srl Item No 3 | 2 | Each | |
29 | 3.03 | Set of pins and Gaskets made out of Mild Steel for Srl Item No 3 | 2 | Each Set | |
30 | 3.04 | Coupling set made out of Cast Iron for Srl Item No 3 | 2 | Each | |
31 | 3.05 | Spacer for coupling set made out of Cast Aluminium including rubber bushes (ring type) for Srl Item No 3 | 1 | Each | |
32 | 3.06 | Gland box made out of Cast Iron including gland box studs with nuts and washers for Srl Item No 3 | 1 | Each | |
33 | 3.07 | Gland packing made out of Gr. Cotton for Srl Item No 3 | 1 | Each Job | |
34 | 3.08 | Impeller made out of cast Iron duly balanced by means of precision lathe machine for Srl Item No 3 | 1 | Each Job | |
35 | 3.09 | Driving End bearing for Srl Item No 3 | 2 | Each | |
36 | 3.1 | Non Driving End bearing for Srl Item No 3 | 2 | Each | |
37 | 4 | All as per Srl item No. 3.00 here-in-before but for 10 to 15 HP capacity (Make-mather & Platt / Kirloskar, capacity - 45 Cum at 35 metres head. | 3 | Each Job | |
38 | 4.01 | S&F Shaft with keys made out of steel 410 grade for Srl Item No 4 | 2 | Each | |
39 | 4.02 | Shaft sleeve with nuts made out of stainless steel 410 grade for Srl Item No 4 | 1 | Each | |
40 | 4.03 | Set of pins and Gaskets made out of Mild Steel for Srl Item No 4 | 2 | Each Set | |
41 | 4.04 | Coupling set made out of Cast Iron including bolts, nuts, washers & rubber bushes for Srl Item No 4 | 2 | Each | |
42 | 4.05 | Gland box made out of Cast Iron including gland box studs with nuts and washers for Srl Item No 4 | 2 | Each | |
43 | 4.06 | Gland packing made out of Gr. Cotton for Srl Item No 4 | 2 | Each Job | |
44 | 4.07 | Impeller made out of cast Iron duly balanced by means of precision lathe machine for Srl Item No 4 | 1 | Each Job | |
45 | 4.08 | Driving End bearing for Srl Item No 4 | 3 | Each | |
46 | 4.09 | Non Driving End bearing for Srl Item No 4 | 3 | Each | |
47 | 5 | All as per Srl item No. 4.00 here-in-before but for 5 to 7.5 HP capacity (Make-Mather & Platt, Model-ET ISO 9 capacity - 13 Cum at 35 metres head) installed at Capts Colony Pump House/ filter plant . | 2 | Each Job | |
48 | 5.01 | S&F Shaft with key made out of steel 410 grade for Srl Item No 5 | 1 | Each | |
49 | 5.02 | Shaft sleeve with nuts made out of stainless steel 410 grade for Srl Item No 5 | 1 | Each | |
50 | 5.03 | Set of pins and Gaskets made out of Mild Steel for Srl Item No 5 | 2 | Each Set | |
51 | 5.04 | Coupling set made out of Cast Iron including bolts, nuts, washers & rubber bushes for Srl Item No 5 | 2 | Each | |
52 | 5.05 | Gland box made out of Cast Iron for Srl Item No 5 | 1 | Each | |
53 | 5.06 | Gland packing made out of Gr. Cotton for Srl Item No 5 | 4 | Each Job | |
54 | 5.07 | Metal (bronze) filling in the worn out portion of impellers, turning and grinding the metal filled portions. Balancing the impeller by means of precision lathe machine for Srl Item No 5 | 1 | Each Job | |
55 | 6 | Supply & fixing in repairs MS base frame for Motor and pump set suitable for 7.5 to 15 HP Kirloskar pump set including grouting of necessary fasteners in floors and PCC complete all as specified. Note:- Dismantling the pump set and after repair the base pump set installed in same position rate are deemed are including item. | 2 | Each Job | |
56 | 7 | Supply & fixing in repairs MS base frame for Motor and pump set suitable for 20 HP Kirloskar pump set including grouting of necessary fasteners in floors and PCC complete all as specified. | 2 | Each Job | |
57 | 8 | Supply & fixing in repairs MS base frame for Motor and pump set suitable for 25 HP Kirloskar pump set including grouting of necessary fasteners in floors and PCC complete all as specified. | 1 | Each Job | |
58 | 9 | Disconnecting the electrical and mechanical connections of motor, and taking out motor,100/125HP capacity. Transporting the same to an authorized workshop for following repairs:-(a) Dismantling burnt AC 3 Phase, 50 Hz, motor, 100/125 HP taking out all coils and re-winding the motor complete with same gauge of wire and same nos of turns. Heating, Baking and varnishing the winding complete. Re-assembling the motor and fixing back in position complete all as specified and as directed by Engr-in-Charge and recommended by the manufacturer. | 1 | Each Job | |
59 | 10 | Disconnecting the electrical and mechanical connections of motor, and taking out motor,20HP capacity. Transporting the same to an authorized workshop for following repairs:-(a) Dismantling burnt AC 3 Phase, 50 Hz, motor, 20 HP taking out all coils and re-winding the motor complete with same gauge of wire and same nos of turns. Heating, Baking and varnishing the winding complete. Re-assembling the motor and fixing back in position complete all as specified and as directed by Engr-in-Charge and recommended by the manufacturer. | 1 | Each Job | |
60 | 11 | Disconnecting the electrical and mechanical connections of motor, and taking out motor,15 HP capacity. Transporting the same to an authorized workshop for following repairs:-(a) Dismantling burnt AC 3 Phase, 50 Hz, motor,15 HP taking out all coils and re-winding the motor complete with same gauge of wire and same nos of turns. Heating, Baking and varnishing the winding complete. Re-assembling the motor and fixing back in position complete all as specified and as directed by Engr-in-Charge and recommended by the manufacturer. | 1 | Each Job | |
61 | 12 | Disconnecting the electrical and mechanical connections of motor, and taking out motor,7.5/10 HP capacity. Transporting the same to an authorized workshop for following repairs:-(a) Dismantling burnt AC 3 Phase, 50 Hz, motor,7.5/15 HP taking out all coils and re-winding the motor complete with same gauge of wire and same nos of turns. Heating, Baking and varnishing the winding complete. Re-assembling the motor and fixing back in position complete all as specified and as directed by Engr-in-Charge and recommended by the manufacturer. | 1 | Each Job | |
62 | 13 | Disconnecting the electrical and mechanical connections of motor, and taking out motor,5 HP capacity. Transporting the same to an authorized workshop for following repairs:-(a) Dismantling burnt AC 3 Phase, 50 Hz, motor,5 HP taking out all coils and re-winding the motor complete with same gauge of wire and same nos of turns. Heating, Baking and varnishing the winding complete. Re-assembling the motor and fixing back in position complete all as specified and as directed by Engr-in-Charge and recommended by the manufacturer. | 1 | Each Job | |
63 | 14 | Supply & fixing in repairs Volt Meter Digital, 96 x 96 mm, 0-500 Volts, Class 1, AC. Make: L&T, Model - WDS301FEV00 or equivalent of AE/Kappa | 6 | Each | |
64 | 15 | Supply & fixing in repairs Amp Meter Digital, 96 x 96 mm, 0-100 Amps, Class 1, AC. Make: L&T, Model - WDS301OCA00 or equivalent of AE/Kappa | 6 | Each | |
65 | 16 | PCC 1:3:6 type C-2 (using 40 mm graded stone aggregate) for anchorage blocks for pipe line/making good the cut portion of roads/paths/hard standings etc including necessary form work where required complete to support the pipe line where required complete all as specified and as directed. | 2 | Cum | |
66 | 17 | Taking out old & unserviceable power contactor and Supply & fix power contactor for auto transformer starter (BCH Make) 3 pole, 265 Amps for AC 3 rating 415 volts, 140 kW 50 Hz supply including control coil, 6 fixed & 3 moving contacts, contact springs, spring retainers and arc runners complete all as specified and as directed. Make: BCH, Model Duros Freedom SeriesMCE15S0N3 7 | 1 | Each | |
67 | 18 | Taking out old & unserviceable power contactor and Supply & fix power contactor for S/Dr starter 125 HP (BCH Make) 3 pole, 140/150 Amps for AC 3 rating 415 volts, 75 kW 50 Hz supply including control coil, 6 fixed & 3 moving contacts, contact springs, spring retainers and arc runners complete all as specified and as directed. Make: BCH, Model - BCH15NT.3.11.220 | 2 | Each | |
68 | 19 | Taking out old & unserviceable power contactor and Supply & fix power contactor for S/D starter 100 HP (BCH Make) 3 pole, 80/95 Amps for AC 3 rating 415 volts, 40 kW 50 Hz supply including control coil, 6 fixed & 3 moving contacts, contact springs, spring retainers and arc runners complete all as specified and as directed. Make: BCH, Model - MCE15LN3 | 2 | Each | |
69 | 20 | Taking out old & unserviceable power contactor and Supply & fix power contactor for S/D starter 40 HP (BCH Make) 3 pole, 32/40 Amps for AC 3 rating 415 volts, 15 kW 50 Hz supply including control coil, 6 fixed & 3 moving contacts, contact springs, spring retainers and arc runners complete all as specified and as directed. Make: BCH, Model - MV10DN22 | 3 | Each | |
70 | 21 | Supply & fixing in repairs Magnetic Coil for BCH 54 contactor complete all as specified. Make - BCH, Model - B51 | 1 | Each | |
71 | 22 | Supply & fixing in repairs Magnetic Coil for BCH 15NT contactor complete all as specified. Make - BCH, Model - B51 | 1 | Each | |
72 | 23 | Supply & fixing in repairs Magnetic Coil for MCE 15LN3 contactor complete all as specified. Make - BCH, Model - 9-2268 | 1 | Each | |
73 | 24 | Supply & fixing in repairs Magnetic Coil for C4NE22 contactor complete all as specified and as directed. \nMake - BCH, Model - 9-2267 | 1 | Each | |
74 | 25 | Supply & fixing in repairs Microprocessor based Electronic Over current Relay for protection against Motor Over current, Under current, Phase Loss, Phase Reverse, Locked Rotor, Phase Unbalance Make- BCH, Model- BOCR 3DE inbuilt display type (415 volts) including 1 No CT Cl-1.0 15VA Resin Cast, complete all as specified. Make - BCH | 2 | Each | |
75 | 26 | Supply and Laying XLPE insulated, screened PVC bedded ,galvanised steel strip or wire armoured, electric power cables(heavy duty) with aluminium conductor,11000 Volts grade(earthed) cross sectional area 95 sq. mm 3 core with fixing material laid in trenches fixed on poles, walls or under floor etc. complete all as specified. | 110 | RM | |
76 | 27 | M&L lightening arrestor expulsion type for out door use complete with all fitting transmission class discharge capacity 65 kilo Amps suitable for 11000 volts including brackets, clamps, nuts and washers and connecting to earth wire 4 mm dia GI wire complete all as specified. | 1 | Set of \nthree | |
77 | 28 | Supply and fixing Non Return valve heavy duty cast iron of 100 mm nominal bore, , both ends flanged (size of flanges 300 mm x 40 mm with 12 holes for 25 mm dia bolts) complete all as specified and directed. Note :- Rate deemed to be included for joints with 125 mm x 25 mm bolts, nuts, washers and 3 mm thick fibre gaskets complete. Make: Kirloskar / L&T / Audco | 1 | Each | |
78 | 29 | S&F in repairs single phasing preventor 415 Volt complete all as specified. Make - L&T , CAT No - MA51BC Series SM 301 | 2 | Each | |
79 | 30 | S&F Push Button 22.5 mm with push knob flush type having 1 NO & 1 NC illuminated type for putting on / off complete all as specified. Make - BCH | 10 | Each | |
80 | 31 | S&F LED indicating light surge and low voltage protected 220 / 240 Volts AC, Colour R/Y/G/A for LT Panels Make - BCH, CAT No - HFB2SP complete all as specified. | 10 | Each | |
81 | 32 | S&F Timer ( 1 to100) DQR 220V -10 Amp complete all as specified. Make - BCH, | 2 | Each | |
82 | 33 | Maintenance of Swimming Pool & keeping the water clear by using alum sulphate for floculation of silt/dirt etc, cleaning the pool time to time by suction sweeper to remove settled silt/dirt/flocs. Back washing of filter shell. Add disinfactant to make water fit for bath, testing the water of pool by means of chlorine testing kit, to keep water bathable from 0600 hrs to 2000 hrs. Note : (i) After the swimming pool is closed for bathing, the pool shall be cleaned again to make it fit for bathing next morning. (ii) Contractor's labours shall be responsible for repair/maintenance of pipe lines, valves, pumps, panels/starters etc & general cleanlibess in swimming pool and filter plant room. Following T & P shall be provided by the contractor for maint of pool without any extra cost to the deptt :- '(a) Leaf net (deep bag type) - 1 No (b) Telescopic pole - 1 No (c) Algae brush Stainless steel bristles - 1 No (d) Chlorine testing kit - 1Nos (e) Digital pH meter - 1 No, (f) suction sweeper rope - as required (g) suction sweeper hose - as required (h) Trolly mounted suction Sweeper self priming pump with suction head (900 x 200 x 150) - 1 Set (j) Open jaw spanners (6 to 32) - 02 Sets (k) Ring spanners (6 to 32) - 02 Sets (l) Plastic buckets, mugs for mixing chemicals (m) Any other tools/accessories required for routine maint of pool. | 180 | Per Day | |
83 | 34 | Supply and mixing alum sulphate (crystal) of best quality complete all as specified. | 300 | KGs | |
84 | 35 | Supply and mixing copper sulphate of best quality complete all as specified. | 10 | KGs | |
85 | 36 | Supply and mixing chlorine based granular powder TCCA 90 % concentrated complete all as specified. Make: NISSAN or equivalent as approved. | 300 | KGs | |
86 | 37 | Supply and mixing Soda- Ash to control the pH value of water complete all as specified. Make: Tata or equivalent as approved. | 10 | KGs | |
87 | 38 | Supply only Aquafit (Calcium Hypo Chloride) high strength granular disinfactant for treatment of drinking water complete all as specified. | 300 | KGs | |
88 | 39 | Supply only Poly Aluminium Chloride in powder form inorganic polymer effective in both high and low turbidity complete all as specified. | 100 | KGs | |
89 | 40 | Cutting down leaking piece of pipe 100mm. Cut down the rusted & leaking portion , providing (i) new piece of GI pipe 100 mm medium grade upto 0.50 metre long (ii) New union socket 100 mm - 1 Nos. (iii) Jointing the new pipe with existing old pipe by means of welding to make it leakproof including testing on completion complete all as specified and as directed. Note:- Unit rate quoted shall be included for (a) Necessary excavation/earth work (b) New GI pipe 100 mm upto 0.50 metre length (c) union socket 100mm - 1 Nos. (d) welding etc complete including testing on completion. | 1 | Each Job | |
90 | 41 | Cutting down leaking piece of pipe 80mm. Cut down the rusted & leaking portion , providing (i) new piece of GI pipe 80 mm medium grade upto 0.50 metre long (ii) New union socket 80 mm - 1 Nos. (iii) Jointing the new pipe with existing old pipe by means of welding to make it leakproof including testing on completion complete all as specified and as directed. Note:- Unit rate quoted shall be included for (a) Necessary excavation/earth work (b) New GI pipe 80 mm upto 0.50 metre length (c ) union socket 80mm - 1 Nos. (d) welding etc complete including testing on completion. | 1 | Each Job | |
91 | 42 | Cutting down leaking piece of pipe 50mm. Cut down the rusted & leaking portion , providing (i) new piece of GI pipe 50 mm medium grade upto 0.50 metre long (ii) New union socket 50 mm - 1 Nos. (iii) Jointing the new pipe with existing old pipe by means of welding to make it leakproof including testing on completion complete all as specified and as directed. Note:- Unit rate quoted shall be included for (a) Necessary excavation/earth work (b) New GI pipe 50 mm upto 0.50 metre length (c ) union socket 50mm - 1 Nos. (d) welding etc complete including testing on completion. | 1 | Each Job | |
92 | 43 | Cutting down leaking piece of pipe 20mm. Cut down the rusted & leaking portion , providing (i) new piece of GI pipe 20 mm medium grade upto 0.50 metre long (ii) New union socket 20 mm - 1 Nos. (iii) Jointing the new pipe with existing old pipe by means of welding to make it leakproof including testing on completion complete all as specified and as directed. Note:- Unit rate quoted shall be included for (a) Necessary excavation/earth work (b) New GI pipe 20 mm upto 0.50 metre length (c ) union socket 20mm - 1 Nos. (d) welding etc complete including testing on completion. | 1 | Each Job | |
93 | 44 | Supply and fix in repairs gun metal gate valve 50 mm bore with iron wheel head screwed both ends for iron pipes and fixed complete in existing location complete all as specified and as directed. Make : Zoloto/ Neta/Leader/Bir | 1 | Each | |
94 | 45 | All as per Srl item No. 44.00 above but for 20 mm bore pipe. | 2 | Each | |
95 | 46 | All as per Srl item No. 44.00 above but for 15 mm bore pipe. | 2 | Each | |
96 | 47 | Dismantling and taking out old u/s worn out MS/CI pipe line flanged type/ spigot socket/ lead joint 150 mm bore including fittings complete with nuts, bolts, washers and gaskets etc and removing from the site complete all as specified and as directed by Engineer-in-charge. Note:- New pipes shall be laid first at spring area and old ones to be taken out later. | 60 | RM | |
97 | 48 | M&L steel water tubing galvanised 150 mm bore medium grade pipe with flanged in trenches/under roads/floors etc with bend , union, flang and all fittings complete all as specified and as directed. Make : Jindal/Tata/Prakash | 60 | RM | |
98 | 49 | PCC 1:3:6 type C-2 (using 40 mm graded stone aggregate) for anchorage blocks for pipe line/making good the cut portion of roads/paths/hard standings etc including necessary form work where required complete to support the pipe line where required complete all as specified and as directed | 1 | Cum | |
99 | 50 | Excavation in trenches in hard/dense soil n.exc 1.5 mtr wide & 1.5 mtr in depth getting out and forming bottom surfaces to required gradient complete all as specified and as directed. | 30 | Cum | |
100 | 51 | Returning filling in with earth obtained from excavation including, spreading, levelling, watering well ramming in layers n.exc 25 cm thick after the pipe have been laid and tested complete all as specified. | 25 | Cum | |
101 | 52 | Removing of surplus soil obtained after item No 3 above to a distance n.exc 50 mtr and depositing where directed at a level n.exc 1.5 mtr above starting point complete all as specified and as directed. | 5 | Cum | |
102 | 53 | Taking up or down 40mm bore steel water tubing pipe removing from site for various area & M&L steel water tubing galvanised 40 mm bore medium grade in trenches/under roads/floors etc with bend , union , flang and all fittings complete all as specified and as directed. Make: Jindal/Tata/Prakash | 30 | RM | |
103 | 54 | All as per Srl item No. 53.00 above but size of pipe 25 mm bore. | 120 | RM | |
104 | 55 | All as per Srl item No. 53.00 above but size of pipe 20 mm bore. | 130 | RM | |
105 | 56 | Amount of credit of Rs. 60791.00 for retrived old material as mentioned in Schedule 'A' section-II of tender document in pdf form, will be deducted offline while acceptence of tender. |