Civil Aviation Boards / Undertakings / PSU Closing in 0 days TDR #21236267

Annual Maintenance Contract Of Electrical Installations At Juhu Airport Arsr Phhl Qtrs Tx Station Andheri Rrstation Dahisar And Om Vashi Mumbai For The Year 2019 21

Issued by Boards / Undertakings / PSU · Juhu Airport, Maharashtra
Tender Value
73.86 Lakhs
Estimated cost
Bid Submission
13 Aug 2019
0 days left
EMD
1.47 Lakhs
Bank guarantee accepted
Document Fee
1120
Non-refundable
Tender Type
Online

Tender Overview

Competition Type
NCB
Bidding Type
Tender
Location / State
Juhu Airport → Maharashtra
EMD Exemption
Not Available
Quantity
Not Available

Project Description

Annual Maintenance Contract of Electrical Installations at Juhu Airport ARSR PHHL Qtrs Tx Station Andheri RRStation Dahisar and OM Vashi Mumbai for the year 2019 21 , ( sh-i ) amc for 1 st year providing 3 nos . computer operator ( highly skilled manpower ) for office records upkeep / computer operation on all days excluding sunday . , hiring of unskilled labour during monsoon season 8 hours per day in all working days ( including sundays ) , rewinding of following monoblock pumps motor with suitable gauge of copper wire i / c dismantling , cutting of burnt wire including replacing of insulator & varnishing , baking transportation etc . , as required . ( credit towards dismantled copper wire & damage parts which are replaced to be consider while quoting the rate ) . capacity: 0 . 5 hp to 1 . 5 hp , capacity: 3 hp to 5 hp , capacity: 7 . 5 hp , rewinding of following submersible pumps motor with suitable gauge of copper wire i / c dismantling , cutting of burnt wire including replacing of insulator , baking transportation etc . , as required . ( credit towards dismantled copper wire & damage parts which are replaced to be consider while quoting the rate ) . capacity: 10 hp , servicing repairing rewinding and replacement of defective part like bearing , bushing etc . and also transportation from site to contractors workshop & back to site , testing and commissioning etc . complete as per site requirement for the following motors ( dismantle material belongs to contractor ) 600 mm sweep exhaust fan , 1200 mm sweep ceiling fan , scrubbing , cleaning and then painting of street light poles with bracket upto 9 mtrs height with one coat of red-oxide and two coats of silver enamel paint etc . as required . , scrubbing , cleaning and then painting of lt panels , outdoor feeder pillars at various locations of juhu airport , andheri transmitting station , rr station dahisar , outer marker vashi with one coat of red-oxide and two coats of enamel paint as directed by engineer in charge etc . as required . , replacement of loop in loop out box for street light poles ( sintax make ) of following sizes , including dip rail for mounting of mcbs / connectors , making interconnections as required . 240 x 130 x 95 ( model no gs-jb-2817 ) , making base foundation for the existing old street light pole including dismantling of old base & old cable etc . , with cement concrete 1:2:4 ratio collar of size 0 . 4 mtr . dia at a height of 0 . 5 mtr . from the ground level 0 . 5 mtr height & pcc flat form of 0 . 5 mtr x 0 . 4 x 0 . 4 mtr . in the ground level around the steel light poles as required . , filtration of 200kva / 250kva , 11kv / 0 . 415 kv transformer oil , i / c dehydration of oil & breather etc . as per requirement , breakdown strength of oil should be 40kv after filtration i / c submission of test report for the oil filtration and test report for re- commissioning of transformer to be arranged by contractor . , supply of transformer oil as per is 335 for topping of existing transformer i / c initial filtration to attain breakdown strength of 40kv as per is-335 . , comprehensive annual maintenance contract of 11 kv ht vcb panel make kirloskar of following relays , comprising of incomer / outgoing including fault rectification as and when required and carrying out preventive maintenance as per schedule , replacement of minor spares like control fuses and neutral links etc , job includes carrying out preventive maintenance checks , attending breakdowns , including calibration of relays etc . as required . 630a , 1 incoming + 1 outgoing 11 kv ht panel - 1 set at andheri transmitting station , d n . nagar . , 800a , 1 incoming + 2 outgoing , 11 kv ht panel - 1 set at arsr radar , juhu airport . , locating & pinpoint the cable fault in pvc insulated pvc sheathed power cable of following sizes with necessary machine and instruments etc . as required . , comprehensive maintenance contract of water purifier eureka forbes model-hi / low machines with pre-cooler attachment ( at least monthly service to be done by authorized service purchaser ) including replacement of parts etc . as required . ( atleast monthly service must be done ) ( quantity 8 nos purifier for 12 months hence rate is for 1 year ) , earthing with g . i . earth pipe 2 . 5 meter long , 40 mm dia including accessories , and providing masonry enclosure with cover plate having locking arrangement and watering pipe etc . with charcoal / coke and salt as required . , hiring of 12 meter height , truck mounted boom lift including diesel for 8 working hours excluding lunch break of 1 hr . , hiring of 45 meter height , truck mounted boom lift including diesel for 8 working hours excluding lunch break of 1 hr . , hiring of 200 hp submersible pump for 24 x 7 operation including installation , control panel , rope , pipe and cable ( capacity of pump will be between 20 hp to 35 hp ) for monsoon season , providing of following materials for celebration of yoga day at juhu offices as per the requirements shown below . 1 . hiring & erection of 15x10 stage ( 1 . 5 feet ) + white back drop . 2 . hiring and erection of side covering ( masking length ) length 90 meters , height 10 . 3 . hiring and erection of full half carpeting + white chadar ( 30 metre x 20 metre ) 4 . hiring and erection of outside area gate covering ( masking length ) length 10 metres . 5 . hiring of pedestal 15 nos . fans with installation 6 . hiring and erection of 15 nos table + cover + frills 7 . hiring and erection of 10 nos vip chairs . 8 . hiring and erection of music system , 2 cordless mics and speakers etc . 9 . hiring and erection of 1 no podium . 10 . hiring 1 no air cooler with installation 11 . hiring of 10 nos led lights with installation , decoration of juhu offices with led serial lighting and rgb pattern lighting on special occasions / nationally important days as per the requirements shown below . 1 . hiring and erection of 20 x 14 stage -1 no 2 . hiring and eretion of steps - 2 nos 3 . hiring and erection of 20 x 8 back drop - 1 no 4 . hiring and erection of 30 x 8 . 5 stage covering - 1 no 5 . hiring and erection of steel sofas with coverings - 6 nos 6 . hiring and erection of chairs - 200 nos 7 . hiring and erection of tables with coverings - 10 nos 8 . hiring and erection of 150 x 6 woollen carpet - 1 no 9 . hiring and erection of white led lights ( 100 w flood light ) - 10 nos 10 . hiring and erection of sound system colour led for stage - 1 no 11 . hiring and erection of balloons - 1000 nos 12 . hiring and erection of pedestal fans - 20 nos 13 . hiring and erection of vip chairs - 10 nos 14 . hiring and erection of led series light not less than 500 meters ( starting from 18 . 00 hrs on day before independence day to 6 . 00 hrs on the day after independence day ) 15 . hiring and erection of halogen / flood light in tri colour theme ( saffron , white & green ) - at main gate , juhu office and sahar hangar ( starting from 18 . 00 hrs on day before independence / republlic day to 6 . 00 hrs on the day after independence / republlic day ) , decoration of juhu offices with led series lighting with rgb pattern lighting on aai foundation day ( starting from 18 . 00 hrs on day before foundation day to 6 . 00 hrs on the day after foundatio

BOQ

Sl.No. Item Description Item Code / Make Quantity Units
1 1.1 (SH-I) AMC for 1 st Year Providing 3 nos. Computer Operator (Highly Skilled Manpower) for office records upkeep / computer operation on all days excluding Sunday. 12 Month
2 1.2 Hiring of unskilled labour during monsoon season 8 hours per day in all working days (including sundays) 120 days
3 1.3 Rewinding of following Monoblock pump's motor with suitable gauge of copper wire i/c dismantling, cutting of burnt wire including replacing of insulator & varnishing, baking transportation etc., as required. (Credit towards dismantled copper wire & damage parts which are replaced to be consider while quoting the rate). Capacity: 0.5 HP to 1.5 HP 2 Job
4 1.4 Capacity: 3 HP to 5 HP 2 Job
5 1.5 Capacity: 7.5 HP 2 Job
6 1.6 Rewinding of following Submersible pump's motor with suitable gauge of copper wire i/c dismantling, cutting of burnt wire including replacing of insulator, baking transportation etc., as required. (Credit towards dismantled copper wire & damage parts which are replaced to be consider while quoting the rate). Capacity: 10 HP 2 Job
7 1.7 Servicing repairing rewinding and replacement of defective part like bearing, bushing etc. and also transportation from site to contractors workshop & back to site, testing and commissioning etc. complete as per site requirement for the following motors (Dismantle material belongs to Contractor) 600 mm sweep exhaust fan 15 JOB
8 1.8 1200 mm sweep Ceiling Fan 25 JOB
9 1.9 Scrubbing, Cleaning and then painting of Street light poles with bracket upto 9 mtrs height with one coat of red-oxide and two coats of silver enamel paint etc. as required. 150 Job
10 2 Scrubbing, Cleaning and then painting of LT Panels, Outdoor Feeder Pillars at various locations of Juhu Airport, Andheri Transmitting Station, RR Station Dahisar, Outer Marker Vashi with one coat of red-oxide and two coats of enamel paint as directed by Engineer in Charge etc. as required. 80 sq. mtr
11 2.1 Replacement of loop in loop out box for Street light poles (Sintax Make) of following sizes, including DIP rail for mounting of MCB's / connectors, making interconnections as required. 240 X 130 X 95 (Model No GS-JB-2817) 30 Job
12 2.2 Making base foundation for the existing old street light pole including dismantling of old base & old cable etc., with cement concrete 1:2:4 ratio collar of size 0.4 mtr. dia at a height of 0.5 mtr.from the ground level 0.5 mtr height & PCC flat form of 0.5 mtr x 0.4 x 0.4 mtr. in the ground level around the steel light poles as required. 20 Job
13 2.3 Filtration of 200KVA / 250KVA,11KV / 0.415 KV Transformer oil , i/c dehydration of oil & breather etc. as per requirement, breakdown strength of oil should be 40KV after filtration i/c submission of test report for the oil filtration and test report for re- commissioning of Transformer to be arranged by contractor. 3 Job
14 2.4 Supply of transformer oil as per IS 335 for topping of existing transformer i/c initial filtration to attain breakdown strength of 40KV as per IS-335. 200 Litres
15 2.5 Comprehensive Annual maintenance contract of 11 KV HT VCB panel make Kirloskar of following relays, comprising of incomer/outgoing including fault rectification as and when required and carrying out preventive maintenance as per schedule, replacement of minor spares like control fuses and neutral links etc, job includes carrying out preventive maintenance checks, attending breakdowns, including calibration of relays etc. as required. 630A, 1 incoming + 1 outgoing 11 KV HT panel - 1 set at Andheri Transmitting Station, D N. Nagar. 1 Job
16 2.6 800A, 1 incoming + 2 outgoing, 11 KV HT panel - 1 set at ARSR Radar, Juhu Airport. 3 Job
17 2.7 Locating & Pinpoint the cable fault in PVC insulated PVC sheathed Power cable of following sizes with necessary machine and instruments etc. as required. 7 Each
18 2.8 Comprehensive Maintenance Contract of water purifier \"Eureka Forbes\" model-Hi / low machines with pre-cooler attachment (at least monthly service to be done by Authorized Service Purchaser) including replacement of parts etc. as required.(atleast monthly service must be done) (Quantity 8 nos Purifier for 12 Months hence rate is for 1 year) 13 Each
19 2.9 Earthing with G.I. earth pipe 2.5 meter long, 40 mm dia including accessories, and providing masonry enclosure with cover plate having locking arrangement and watering pipe etc. with charcoal/coke and salt as required. 10 Set
20 3 Hiring of 12 Meter Height, truck mounted boom lift including Diesel for 8 working hours excluding lunch break of 1 hr. 10 day
21 3.1 Hiring of 45 Meter Height, truck mounted boom lift including Diesel for 8 working hours excluding lunch break of 1 hr. 2 day
22 3.2 Hiring of 200 HP Submersible Pump for 24 X 7 operation including installation, control panel, rope, pipe and cable (Capacity of pump will be between 20 HP to 35 HP) for Monsoon Season 3 Months
23 3.3 Providing of following materials for Celebration of Yoga day at Juhu Offices as per the requirements shown below.\n1. Hiring & Erection of 15'x10' stage (1.5 feet) + white back drop.\n2. Hiring and Erection of side covering (masking length) length 90 meters, height 10'.\n3. Hiring and Erection of full half carpeting + white chadar (30 metre X 20 metre)\n4. Hiring and Erection of outside area gate covering (masking length) length 10 metres.\n5. Hiring of Pedestal 15 nos. fans with installation\n6. Hiring and Erection of 15 nos table + cover + frills\n7. Hiring and Erection of 10 nos VIP chairs.\n8. Hiring and erection of Music system, 2 cordless mics and speakers etc. \n9. Hiring and Erection of 1 no Podium.\n10. Hiring 1 no Air Cooler with Installation\n11. Hiring of 10 nos LED lights with Installation\n 1 Job
24 3.4 Decoration of Juhu Offices with LED serial lighting and RGB pattern lighting on special occasions / nationally important days as per the requirements shown below.\n1. Hiring and erection of 20' X 14' stage -1 No\n2. Hiring and eretion of steps - 2 Nos\n3. Hiring and erection of 20' X 8' Back Drop - 1 No\n4. Hiring and erection of 30 X 8.5 stage covering - 1 No\n5. Hiring and erection of steel sofas with coverings - 6 Nos\n6. Hiring and erection of chairs - 200 Nos\n7. Hiring and erection of Tables with coverings - 10 Nos\n8. Hiring and erection of 150 X 6 woollen carpet - 1 No\n9. Hiring and erection of White LED Lights (100 w Flood Light) - 10 Nos\n10. Hiring and erection of Sound System colour LED for stage - 1 No\n11. Hiring and erection of Balloons - 1000 Nos\n12. Hiring and erection of Pedestal Fans - 20 Nos\n13. Hiring and erection of VIP Chairs - 10 Nos\n14. Hiring and erection of LED series light not less than 500 Meters (Starting from 18.00 hrs on day before independence day to 6.00 hrs on the day after Independence day)\n15. Hiring and erection of Halogen / Flood Light in Tri Colour Theme (Saffron, White & Green) - at Main Gate, Juhu Office and Sahar Hangar (Starting from 18.00 hrs on day before independence/Republlic day to 6.00 hrs on the day after Independence/Republlic day) 2 Job
25 3.5 Decoration of Juhu Offices with LED series lighting with RGB pattern lighting on AAI Foundation day (Starting from 18.00 hrs on day before foundation day to 6.00 hrs on the day after foundation day) Each occasion in an year.\n1. Hiring and erection of LED series light not less than 500 Meters 1 Job
26 3.6 Decoration of Juhu Offices with with LED serial lighting and RGB pattern lighting on special occasions / festival days as per the requirements shown below.\n1. Hiring and erection of LED series light not less than 500 Meters (Starting from 18.00 hrs on day before Diwali day to 6.00 hrs on the day after Bhai Dhuj day)\n2. Hiring and Erection of Diwali Kandil / Lantern including lamp holder and connecting wire complete as required - Not Less than 50 Nos ( four days - starting from 18:00 hrs on day before Diwali, Diwali day, Bhai Dhooj Day and till 6:00 hrs on day after Bhai Dhooj day)\n 1 Job
27 3.7 Decoration of Juhu Offices with with LED serial lighting and RGB pattern lighting on Chrisrmas & New Year as per the requirements shown below.\n1. Hiring and erection of LED series light not less than 500 Meters (Starting from 18.00 hrs on day before Christmas i.e. 24th December to 6.00 hrs on the day after 1st January day)\n2. Hiring and Erection of Star Kandil / Lantern including lamp holder and connecting wire complete as required - Not Less than 50 Nos. 1 Job
28 3.8 Execution of Complete items from (Chapter 1 to Chapter 15) of CPWD Delhi schedule of rates (electrical) 2018. [Up to a ceiling limit of Rs. 7,00,000.00]. The materials used for executing the DSR items shall be as per the approved make list of AAI. (Rates Shall be quoted in multipules e.g. 0.99 or 1.01 Above / Below) 700000 Job
29 3.9 Hiring of JCB including Diesel for 9 working hours including lunch break of 1 hr. 30 Job
30 4 Hire charges for providing One Number Bolero/TUV 300+/ (Air-conditioned) or Equivalent Vehicle along with driver, fuel, insurance, all consumables etc. for all days including sunday and holidays. monthly usage is limited to 1500 Kms and period of useage is 11 Hrs per day [9.00 Hrs to 20.00 Hrs.) 12 Months
31 4.1 Supply of following type batteries for DG sets and other installations. All the batteries shall have a warranty of at least two years. 12V, 150 Ah, lead acid battery 2 Nos
32 4.2 12V, 180 Ah, lead acid battery 2 Nos
33 4.3 (SH-II)AMC for 2 nd Year Providing 3 nos. Computer Operator (Highly Skilled Manpower) for office records upkeep / computer operation on all days excluding Sunday. 12 Month
34 4.4 Hiring of unskilled labour during monsoon season 8 hours per day in all working days (including sundays) 120 days
35 4.5 Rewinding of following Monoblock pump's motor with suitable gauge of copper wire i/c dismantling, cutting of burnt wire including replacing of insulator & varnishing, baking transportation etc., as required. (Credit towards dismantled copper wire & damage parts which are replaced to be consider while quoting the rate). Capacity: 0.5 HP to 1.5 HP 2 Job
36 4.6 Capacity: 3 HP to 5 HP 2 Job
37 4.7 Capacity: 7.5 HP 2 Job
38 4.8 Rewinding of following Submersible pump's motor with suitable gauge of copper wire i/c dismantling, cutting of burnt wire including replacing of insulator, baking transportation etc., as required. (Credit towards dismantled copper wire & damage parts which are replaced to be consider while quoting the rate). Capacity: 10 HP 2 Job
39 4.9 Servicing repairing rewinding and replacement of defective part like bearing, bushing etc. and also transportation from site to contractors workshop & back to site, testing and commissioning etc. complete as per site requirement for the following motors (Dismantle material belongs to Contractor) 600 mm sweep exhaust fan 15 JOB
40 5 1200 mm sweep Ceiling Fan 25 JOB
41 5.1 Scrubbing, Cleaning and then painting of Street light poles with bracket upto 9 mtrs height with one coat of red-oxide and two coats of silver enamel paint etc. as required. 150 Job
42 5.2 Scrubbing, Cleaning and then painting of LT Panels, Outdoor Feeder Pillars at various locations of Juhu Airport, Andheri Transmitting Station, RR Station Dahisar, Outer Marker Vashi with one coat of red-oxide and two coats of enamel paint as directed by Engineer in Charge etc. as required. 80 sq. mtr
43 5.3 Replacement of loop in loop out box for Street light poles (Sintax Make) of following sizes, including DIP rail for mounting of MCB's / connectors, making interconnections as required. 240 X 130 X 95 (Model No GS-JB-2817) 30 Job
44 5.4 Making base foundation for the existing old street light pole including dismantling of old base & old cable etc., with cement concrete 1:2:4 ratio collar of size 0.4 mtr. dia at a height of 0.5 mtr.from the ground level 0.5 mtr height & PCC flat form of 0.5 mtr x 0.4 x 0.4 mtr. in the ground level around the steel light poles as required. 20 Job
45 5.5 Filtration of 200KVA / 250KVA,11KV / 0.415 KV Transformer oil , i/c dehydration of oil & breather etc. as per requirement, breakdown strength of oil should be 40KV after filtration i/c submission of test report for the oil filtration and test report for re- commissioning of Transformer to be arranged by contractor. 3 Job
46 5.6 Supply of transformer oil as per IS 335 for topping of existing transformer i/c initial filtration to attain breakdown strength of 40KV as per IS-335. 200 Litres
47 5.7 Comprehensive Annual maintenance contract of 11 KV HT VCB panel make Kirloskar of following relays, comprising of incomer/outgoing including fault rectification as and when required and carrying out preventive maintenance as per schedule, replacement of minor spares like control fuses and neutral links etc, job includes carrying out preventive maintenance checks, attending breakdowns, including calibration of relays etc. as required. 630A, 1 incoming + 1 outgoing 11 KV HT panel - 1 set at Andheri Transmitting Station, D N. Nagar. 1 Job
48 5.8 800A, 1 incoming + 2 outgoing, 11 KV HT panel - 1 set at ARSR Radar, Juhu Airport. 3 Job
49 5.9 Locating & Pinpoint the cable fault in PVC insulated PVC sheathed Power cable of following sizes with necessary machine and instruments etc. as required. 7 Each
50 6 Comprehensive Maintenance Contract of water purifier \"Eureka Forbes\" model-Hi / low machines with pre-cooler attachment (at least monthly service to be done by Authorized Service Purchaser) including replacement of parts etc. as required.(atleast monthly service must be done) (Quantity 8 nos Purifier for 12 Months hence rate is for 1 year) 13 Each
51 6.1 Earthing with G.I. earth pipe 2.5 meter long, 40 mm dia including accessories, and providing masonry enclosure with cover plate having locking arrangement and watering pipe etc. with charcoal/coke and salt as required. 10 Set
52 6.2 Hiring of 12 Meter Height, truck mounted boom lift including Diesel for 8 working hours excluding lunch break of 1 hr. 10 day
53 6.3 Hiring of 45 Meter Height, truck mounted boom lift including Diesel for 8 working hours excluding lunch break of 1 hr. 2 day
54 6.4 Hiring of 200 HP Submersible Pump for 24 X 7 operation including installation, control panel, rope, pipe and cable (Capacity of pump will be between 20 HP to 35 HP) for Monsoon Season 3 Months
55 6.5 Providing of following materials for Celebration of Yoga day at Juhu Offices as per the requirements shown below.\n1. Hiring & Erection of 15'x10' stage (1.5 feet) + white back drop.\n2. Hiring and Erection of side covering (masking length) length 90 meters, height 10'.\n3. Hiring and Erection of full half carpeting + white chadar (30 metre X 20 metre)\n4. Hiring and Erection of outside area gate covering (masking length) length 10 metres.\n5. Hiring of Pedestal 15 nos. fans with installation\n6. Hiring and Erection of 15 nos table + cover + frills\n7. Hiring and Erection of 10 nos VIP chairs.\n8. Hiring and erection of Music system, 2 cordless mics and speakers etc. \n9. Hiring and Erection of 1 no Podium.\n10. Hiring 1 no Air Cooler with Installation\n11. Hiring of 10 nos LED lights with Installation\n 1 Job
56 6.6 Decoration of Juhu Offices with LED serial lighting and RGB pattern lighting on special occasions / nationally important days as per the requirements shown below.\n1. Hiring and erection of 20' X 14' stage -1 No\n2. Hiring and eretion of steps - 2 Nos\n3. Hiring and erection of 20' X 8' Back Drop - 1 No\n4. Hiring and erection of 30 X 8.5 stage covering - 1 No\n5. Hiring and erection of steel sofas with coverings - 6 Nos\n6. Hiring and erection of chairs - 200 Nos\n7. Hiring and erection of Tables with coverings - 10 Nos\n8. Hiring and erection of 150 X 6 woollen carpet - 1 No\n9. Hiring and erection of White LED Lights (100 w Flood Light) - 10 Nos\n10. Hiring and erection of Sound System colour LED for stage - 1 No\n11. Hiring and erection of Balloons - 1000 Nos\n12. Hiring and erection of Pedestal Fans - 20 Nos\n13. Hiring and erection of VIP Chairs - 10 Nos\n14. Hiring and erection of LED series light not less than 500 Meters (Starting from 18.00 hrs on day before independence day to 6.00 hrs on the day after Independence day)\n15. Hiring and erection of Halogen / Flood Light in Tri Colour Theme (Saffron, White & Green) - at Main Gate, Juhu Office and Sahar Hangar (Starting from 18.00 hrs on day before independence/Republlic day to 6.00 hrs on the day after Independence/Republlic day) 2 Job
57 6.7 Decoration of Juhu Offices with LED series lighting with RGB pattern lighting on AAI Foundation day (Starting from 18.00 hrs on day before foundation day to 6.00 hrs on the day after foundation day) Each occasion in an year.\n1. Hiring and erection of LED series light not less than 500 Meters 1 Job
58 6.8 Decoration of Juhu Offices with with LED serial lighting and RGB pattern lighting on special occasions / festival days as per the requirements shown below.\n1. Hiring and erection of LED series light not less than 500 Meters (Starting from 18.00 hrs on day before Diwali day to 6.00 hrs on the day after Bhai Dhuj day)\n2. Hiring and Erection of Diwali Kandil / Lantern including lamp holder and connecting wire complete as required - Not Less than 50 Nos ( four days - starting from 18:00 hrs on day before Diwali, Diwali day, Bhai Dhooj Day and till 6:00 hrs on day after Bhai Dhooj day)\n 1 Job
59 6.9 Decoration of Juhu Offices with with LED serial lighting and RGB pattern lighting on Chrisrmas & New Year as per the requirements shown below.\n1. Hiring and erection of LED series light not less than 500 Meters (Starting from 18.00 hrs on day before Christmas i.e. 24th December to 6.00 hrs on the day after 1st January day)\n2. Hiring and Erection of Star Kandil / Lantern including lamp holder and connecting wire complete as required - Not Less than 50 Nos. 1 Job
60 7 Execution of Complete items from (Chapter 1 to Chapter 15) of CPWD Delhi schedule of rates (electrical) 2018. [Up to a ceiling limit of Rs. 7,00,000.00]. The materials used for executing the DSR items shall be as per the approved make list of AAI. (Rates Shall be quoted in multipules e.g. 0.99 or 1.01 Above / Below) 700000 Job
61 7.1 Hiring of JCB including Diesel for 9 working hours including lunch break of 1 hr. 30 Job
62 7.2 Hire charges for providing One Number Bolero/TUV 300+/ (Air-conditioned) or Equivalent Vehicle along with driver, fuel, insurance, all consumables etc. for all days including sunday and holidays. monthly usage is limited to 1500 Kms and period of useage is 11 Hrs per day [9.00 Hrs to 20.00 Hrs.) 12 Months
63 7.3 Supply of following type batteries for DG sets and other installations. All the batteries shall have a warranty of at least two years. 12V, 150 Ah, lead acid battery 2 Nos
64 7.4 12V, 180 Ah, lead acid battery 2 Nos

AI Tender Summary

OUR REF NO 21236267
AUTHORITY Boards / Undertakings / PSU
TENDER VALUE 73.86 Lakhs
LAST DATE 13-08-2019
Authority
Authority Name Airports Authority Of India
Work Description Annual Maintenance Contract of Electrical Installations at Juhu Airport ARSR PHHL Qtrs Tx Station Andheri RRStation Dahisar and OM Vashi Mumbai for the year 2019 21 , ( sh-i ) amc for 1 st year providing 3 nos . computer operator ( highly skilled manpower ) for office records upkeep / computer operation on all days excluding sunday . , hiring of unskilled labour during monsoon season 8 hours per day in all working days ( including sundays ) , rewinding of following monoblock pumps motor with suitable gauge of copper wire i / c dismantling , cutting of burnt wire including replacing of insulator & varnishing , baking transportation etc . , as required . ( credit towards dismantled copper wire & damage parts which are replaced to be consider while quoting the rate ) . capacity: 0 . 5 hp to 1 . 5 hp , capacity: 3 hp to 5 hp , capacity: 7 . 5 hp , rewinding of following submersible pumps motor with suitable gauge of copper wire i / c dismantling , cutting of burnt wire including replacing of insulator , baking transportation etc . , as required . ( credit towards dismantled copper wire & damage parts which are replaced to be consider while quoting the rate ) . capacity: 10 hp , servicing repairing rewinding and replacement of defective part like bearing , bushing etc . and also transportation from site to contractors workshop & back to site , testing and commissioning etc . complete as per site requirement for the following motors ( dismantle material belongs to contractor ) 600 mm sweep exhaust fan , 1200 mm sweep ceiling fan , scrubbing , cleaning and then painting of street light poles with bracket upto 9 mtrs height with one coat of red-oxide and two coats of silver enamel paint etc . as required . , scrubbing , cleaning and then painting of lt panels , outdoor feeder pillars at various locations of juhu airport , andheri transmitting station , rr station dahisar , outer marker vashi with one coat of red-oxide and two coats of enamel paint as directed by engineer in charge etc . as required . , replacement of loop in loop out box for street light poles ( sintax make ) of following sizes , including dip rail for mounting of mcbs / connectors , making interconnections as required . 240 x 130 x 95 ( model no gs-jb-2817 ) , making base foundation for the existing old street light pole including dismantling of old base & old cable etc . , with cement concrete 1:2:4 ratio collar of size 0 . 4 mtr . dia at a height of 0 . 5 mtr . from the ground level 0 . 5 mtr height & pcc flat form of 0 . 5 mtr x 0 . 4 x 0 . 4 mtr . in the ground level around the steel light poles as required . , filtration of 200kva / 250kva , 11kv / 0 . 415 kv transformer oil , i / c dehydration of oil & breather etc . as per requirement , breakdown strength of oil should be 40kv after filtration i / c submission of test report for the oil filtration and test report for re- commissioning of transformer to be arranged by contractor . , supply of transformer oil as per is 335 for topping of existing transformer i / c initial filtration to attain breakdown strength of 40kv as per is-335 . , comprehensive annual maintenance contract of 11 kv ht vcb panel make kirloskar of following relays , comprising of incomer / outgoing including fault rectification as and when required and carrying out preventive maintenance as per schedule , replacement of minor spares like control fuses and neutral links etc , job includes carrying out preventive maintenance checks , attending breakdowns , including calibration of relays etc . as required . 630a , 1 incoming + 1 outgoing 11 kv ht panel - 1 set at andheri transmitting station , d n . nagar . , 800a , 1 incoming + 2 outgoing , 11 kv ht panel - 1 set at arsr radar , juhu airport . , locating & pinpoint the cable fault in pvc insulated pvc sheathed power cable of following sizes with necessary machine and instruments etc . as required . , comprehensive maintenance contract of water purifier eureka forbes model-hi / low machines with pre-cooler attachment ( at least monthly service to be done by authorized service purchaser ) including replacement of parts etc . as required . ( atleast monthly service must be done ) ( quantity 8 nos purifier for 12 months hence rate is for 1 year ) , earthing with g . i . earth pipe 2 . 5 meter long , 40 mm dia including accessories , and providing masonry enclosure with cover plate having locking arrangement and watering pipe etc . with charcoal / coke and salt as required . , hiring of 12 meter height , truck mounted boom lift including diesel for 8 working hours excluding lunch break of 1 hr . , hiring of 45 meter height , truck mounted boom lift including diesel for 8 working hours excluding lunch break of 1 hr . , hiring of 200 hp submersible pump for 24 x 7 operation including installation , control panel , rope , pipe and cable ( capacity of pump will be between 20 hp to 35 hp ) for monsoon season , providing of following materials for celebration of yoga day at juhu offices as per the requirements shown below . 1 . hiring & erection of 15x10 stage ( 1 . 5 feet ) + white back drop . 2 . hiring and erection of side covering ( masking length ) length 90 meters , height 10 . 3 . hiring and erection of full half carpeting + white chadar ( 30 metre x 20 metre ) 4 . hiring and erection of outside area gate covering ( masking length ) length 10 metres . 5 . hiring of pedestal 15 nos . fans with installation 6 . hiring and erection of 15 nos table + cover + frills 7 . hiring and erection of 10 nos vip chairs . 8 . hiring and erection of music system , 2 cordless mics and speakers etc . 9 . hiring and erection of 1 no podium . 10 . hiring 1 no air cooler with installation 11 . hiring of 10 nos led lights with installation , decoration of juhu offices with led serial lighting and rgb pattern lighting on special occasions / nationally important days as per the requirements shown below . 1 . hiring and erection of 20 x 14 stage -1 no 2 . hiring and eretion of steps - 2 nos 3 . hiring and erection of 20 x 8 back drop - 1 no 4 . hiring and erection of 30 x 8 . 5 stage covering - 1 no 5 . hiring and erection of steel sofas with coverings - 6 nos 6 . hiring and erection of chairs - 200 nos 7 . hiring and erection of tables with coverings - 10 nos 8 . hiring and erection of 150 x 6 woollen carpet - 1 no 9 . hiring and erection of white led lights ( 100 w flood light ) - 10 nos 10 . hiring and erection of sound system colour led for stage - 1 no 11 . hiring and erection of balloons - 1000 nos 12 . hiring and erection of pedestal fans - 20 nos 13 . hiring and erection of vip chairs - 10 nos 14 . hiring and erection of led series light not less than 500 meters ( starting from 18 . 00 hrs on day before independence day to 6 . 00 hrs on the day after independence day ) 15 . hiring and erection of halogen / flood light in tri colour theme ( saffron , white & green ) - at main gate , juhu office and sahar hangar ( starting from 18 . 00 hrs on day before independence / republlic day to 6 . 00 hrs on the day after independence / republlic day ) , decoration of juhu offices with led series lighting with rgb pattern lighting on aai foundation day ( starting from 18 . 00 hrs on day before foundation day to 6 . 00 hrs on the day after foundatio
Basic Detail
Tender No AAI/WR/AGM(E-E)/JUHU/01/19-20
Bidding Type Tender
Location
City Juhu Airport
State Maharashtra
Key Dates
Publish Date 31 Jul 2019
Submission Date 13 Aug 2019
Open Date 21 Aug 2019
Finance
Tender Value 73.86 Lakhs
Tender Fee 1120
EMD 1.47 Lakhs
Exemption Not Available
Document List
7000669_0_01082019.pdf
Tendernotice_1.pdf
BOQ_28342.xls
AECA658B-FA96-4E09-9AEF-531BCE6C0890.html

Unlock Full AI Tender Summary

Get instant access to the complete AI-generated analysis — scope, eligibility, timeline & more.

Instant Access Secure Free
Your details are secure and used only for document delivery.

Tender Timeline

Jul 31, 2019
11:30 IST

Tender Published

Tender notice published.

Completed
Aug 13, 2019
17:00 IST

Bid Submission Deadline

Online submission via eProcurement portal.

Completed
Aug 21, 2019

Bid Opening Date

Technical bids will be opened and evaluated.

Completed

Tender Documents

Download All (ZIP) ↓
pdf

7000669_0_01082019.pdf

pdf

Tendernotice_1.pdf

xls

BOQ_28342.xls

html

AECA658B-FA96-4E09-9AEF-531BCE6C0890.html

Disclaimer

We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender