It Is A Revitalization Of The Mineral Spring, Which Is Very Used. It Is Essential That There Is A Quick Repair. It Is Currently A State Of Emergency. The Works Will Be Divided Into Three Basic Sections. Stage No. 1 - Bill Regeneration Will Be Completed No Later Than 60 Days From The Handover Of The Construction Site Stage 2 - Other Building Objects Bud Completed No Later Than 120 Days After The Handover Of The Construction Site Stage 3 - Fountain Is Assumed In The Duration Of 150 Days From The Handover Of The Construction Site, But Will Definitely Be Determined After The Approval Of The Artistic Design Of The Fountain With The Resolution Of All The Details Of The Work Of Art.