GTR 112789984

Tenders Are Invited For Kallioniemi Connection Terminal Construction Contract

ICB — International Competitive Bid Closed Western Europe
Tender Information
GTR Reference
112789984
Tendering Authority
Subscribe to view
Tender No
2026-048458
Financer Name
Self-Funded
Work Title
Tenders Are Invited For Kallioniemi Connection Terminal Construction Contract
Bid Type
ICB — International Competitive Bid
Country
Subscribe to view
Geographical Region
Western Europe
Political Region
European Union
Last Date of Bid Submission
21-05-2026 Closed
Work Detail
The Mikkeli City Housing And Operating Environment Service Area Requests Your Offer For The Construction Contract For The Kallioniemi Connection Pier According To The Attached Plan. The Kallioniemi Property Is Located At Kallioniementie 106, 52360, Someenjärvi (Appendix 1). The Offer Must Include All Materials According To The Plans (Appendix 2) As Well As Transport And Installation Work. In Addition, The Removal Of The Old Ship Pier And Temporary Anchoring To The Shore Of The Property Is Part Of The Contract. The Contract Includes The Obligations Of The Main Contractor As Defined By The Legislation. It Is Possible To Install The Pier In Place At The Earliest After Kallioniemis Restaurant Operations End In September 2026. The Pier Must Be Installed In Place By October 15, 2026. Furnishing Work Can Still Be Done On The Pier After That, However, So That The Work Is Completely Completed By October 30, 2026. It Is Impossible To Transport Massive Concrete Elements Along The Narrow Private Road To Kallioniemi. The Pier Elements Must Be Transported To Their Place Along The Waterway. The Contractor, At His Own Expense, Acquires An Appropriate Place From Where The Pier Elements Can Be Lifted Into The Waterway To Be Transported. The Contractor Obtains The Necessary Permits For His Activities. The Pier Will Be Equipped According To The Plan With 2 X 110 Mm Electrical Pipe Provisions. Deviating From The Plan, The 160 Mm Drain Provision For The Septic System Is Replaced By Two M63 Peh Pressure Drain Provisions. Pipe And Cable Provisions Have Already Been Installed On The Land. Pipe Joining Work Is Not Part Of This Contract. Possible Electrical And Lighting Bollards Are A Separate Purchase By The Customer. Matters To Be Considered When Performing The Work: 1. The Construction Work Must Be Carried Out As Continuously As Possible In Such A Way And At Such A Time That The Water Area And Its Use And Water Nature Are Caused As Little Harm And Disruption As Possible. 2. The Supplier Must Investigate Any Wires, Cables And Other Structures In The Work Area. The Project Must Be Carried Out Without Damaging Them.3. Clean Earth And Stone Materials Are Used For The Construction Of The Ground Support Of The Joint Bridge And The Possible Filling Of The Anchor Pits. 4. The Pier Must Be Placed Outside The Fairway In Such A Way That Its Attachment Anchors Do Not Violate The Fairways Digging Depth N2000 +73.20.5. The Locations And Stability Of The Pier Anchorages Must Be Checked After The Work Is Completed. Sufficient Water Depth On The Fairway Must Be Ensured By Measurements. 6. At The End Of The Construction Work, The Demolition Waste And Other Construction Waste Must Be Transported To An Appropriate Place That Has A Permit To Receive The Waste In Question. Construction Material And Demolition Waste That May Have Entered The Water Must Be Removed From The Water. 7. Any Excavated Materials Will Be Sent To The Area Of ​​The Property. 8. After The Work Is Finished, The Construction Sites Must Be Finished And Landscaped In A Way That Suits The Environment. 9. After The Installation Of The Pier, The Customer Must Be Provided With A How-It-Is-Built Drawing And Information About The Pier And Related Structures. A Total Price Offer Is Requested For The Kallioniemi Pier Construction Contract. The Bid Price Must Include The Pier And The Materials Shown In The Plan Installed In Place. The Supplier Who Gave The Cheapest Offer Is Selected As The Contractor. The Cheapest Offer Does Not Yet Constitute A Contract, But A Contract Is Created By Signing A Separate Contract. The Selected Contractor Prepares A Schedule Of Payment Installments For The Project, Which Is Approved By The Customers Representative. The Contract Terms Of Yse 1998 Apply To The Procurement. The Customer Reserves The Right To Reject All Offers If The Allocated Budget Is Exceeded. The Contractor Must Draw Up A Work Safety Plan For The Installation, Lifting And Transportation Of The Platform. The Tender Request Is Accompanied By A Security Document Prepared By The Customer (Appendix 3). The Supplier Is Responsible For All Occupational Safety Duties And Obligations Of The Main Contractor In Accordance With Vna 205/2009 And 523/2013. The Fine For Delay Is 0.5% For Each Working Day, As Opposed To Yse § 18, And Also Applies To Delays In Milestones.
Key Value
Tender Value
Ref. Document
Tender Documents
Global Tender Document
654ca8da-124c-4fcc-a590-f6ca2c6d474e.html
Attachments
Additional Details Available on Click
  • Tendering Authority
  • Publication Document (Tender Document / Tender Notice)
Disclaimer

We take all possible care for accurate & authentic tender information. However, users are requested to refer to the original Tender Notice / Tender Document published by the Tender Issuing Agency before taking any decision regarding this tender.

Tell us about your Product / Services,

We will Find Tenders for you

TenderDetail
Loading tenders