1. The Subject Of The Order Is The Execution Of The Task Entitled: Construction Of A Village Community Center In Gajkowice. The Facility Is Located In Gajkowice At Ul. Łódzka, Plot No. 176/6, Precinct 0007 Gajkowice. The Building Of The Village Community Center Is Under Construction, Started In Accordance With The First Entry In The Construction Log On May 10, 2018. To Date, Most Of The Construction Works Have Been Completed, Including: Foundations, Walls, Roof, Windows And Part Of The Door Installed, Under-Wall Electrical Installation, Underfloor Heating And Approaches For Central Heating Radiators, A Gas Furnace And A Gas Cylinder With An External Installation Were Installed (The Building Permit Was Amended To Change The Method Of Heating The Building From Solid Fuel To Gas - Internal Gas Installation And A Tank Installation For Liquid Gas With Above-Ground Gas Tank With A Capacity Of 4,850 Dm3), - Water And Sewage Installation. Under Plaster, Plasters, Screeds On Floors, Ceilings Were Insulated, Mechanical Ventilation Was Partially Installed. The Subject Of The Order Includes The Performance Of All Other Works Necessary To Obtain An Occupancy Permit By The Ordering Party, Including In Particular Those Listed In The Bill Of Quantities Constituting An Annex To The Swz. This Bill Of Quantities Is Of An Auxiliary Nature And Does Not Change The Lump-Sum Nature Of The Contractors Remuneration. 2. Detailed Scope Of The Subject Of The Order: 2.1. The Material Scope Includes, Among Others: The Following Works: 1) Construction Works: A) Foundation Works (Including, Among Others, Excavation Of Foundations, Insulation Of Walls With Eps 100 Gr. 10 Cm Polystyrene On Bituminous Mortar, Execution Of Vertical Bituminous Coating Moisture-Proof Insulation, Backfilling Of Excavations And Compaction Of Excavations), B) Floors (Including, Among Others, Making Floors Of Tiles And Panels With Plinths And Strips),C) Wall Finishing (Including, Among Others, Construction Of Suspended Gkf Ceilings, Manual Impregnation Of Steel Roof Beams With A Fire Retardant, Construction Of Ceilings Filled With Mineral Wool Boards, Gk Partition Walls, Casing Of Columns With Gkf Boards, Priming, Filling And Painting Walls, Laying Tiles, Handrails For Stairs And Mezzanines),D) Joinery (Including Window Sills, Installation Of System Walls, Door Joinery), E) Roof (Including, Among Others, Supplementing Horizontal Chimney Sweep Benches, Downpipes, Soffit Along With The Structure For Its Installation), F) Insulation Of External Walls With Plastering, G) Band Around The Building, 2) Sanitary Installations: A) Hydrant + Fire-Fighting Water Installation, B) Sewerage, C) Water And Sewage, D) Ventilation, 3) Installations Electrical,4) Tests, Checks, As-Built Documentation: A) Water Testing, B) Lighting Intensity Measurements, C) Preparation Of As-Built Inventory, D) Preparation Of Fire Safety Instructions Along With An Evacuation Plan And Installation Of Fire Extinguishers And Pictograms