Przedmiotem Zamówienia Jest Wykonanie Zadania Pn.: Budowa Świetlicy Wiejskiej W Gajkowicach. The Facility Is Located In Gajkowice At Ul. Łódzka, Plot No. 176/6, Precinct 0007 Gajkowice. The Building Of The Village Community Center Is Under Construction, Started In Accordance With The First Entry In The Construction Log On May 10, 2018. To Date, Most Of The Construction Works Have Been Completed, Including: Foundations, Walls, Roof, Windows And Part Of Doors Installed, Under-Plaster Electrical Installation, Underfloor Heating And Approaches For Central Heating Radiators, A Gas Furnace And A Gas Cylinder With External Installation, Water And Sewage Installation. Podtynkową, Tynki,Wylewki Na Posadzkach, Wykonano Ocieplenie Sufitów, Wykonano Częściowo Wentylację Mechaniczną. The Subject Of The Order Includes The Performance Of All Other Works Necessary To Obtain An Occupancy Permit By The Ordering Party, Including In Particular Those Listed In The Bill Of Quantities Constituting An Annex To The Swz. Przedmiar Ten Ma Charakter Pomocniczy I Nie Zmienia Ryczałtowego Charakteru Wynagrodzenia Wykonawcy. 3. Szczegółowy Zakres Przedmiotu Zamówienia:3.1. The Material Scope Includes, Among Others: The Following Works: 1) Construction Works: A) Foundation Works (Including, Among Others, Excavation Of Foundations, Insulation Of Walls With Eps 100 Gr. 10 Cm Polystyrene On Bituminous Mortar, Execution Of Vertical Bituminous Coating Moisture-Proof Insulation, Backfilling Of Excavations And Compaction Of Excavations), B) Floors (Including, Among Others, Making Floors Of Tiles And Panels With Plinths And Strips),C) Wall Finishing (Including, Among Others, Construction Of Suspended Gkf Ceilings, Manual Impregnation Of Steel Roof Beams With A Fire Retardant, Construction Of Ceilings Filled With Mineral Wool Boards, Gk Partition Walls, Casing Of Columns With Gkf Boards, Priming, Filling And Painting Walls, Laying Tiles, Handrails For Stairs And Mezzanines),D) Joinery (Including Window Sills, Installation Of System Walls, Door Joinery), E) Roof (Including, Among Others, Supplementing Horizontal Chimney Sweep Benches, Downpipes, Soffit Along With The Structure For Its Installation), F) Insulation Of External Walls With Plastering, G) Band Around The Building, 2) Sanitary Installations: A) Hydrant + Fire-Fighting Water Installation, B) Sewerage, C) Water And Sewage, D) Ventilation, 3) Installations Electrical,4) Tests, Checks, As-Built Documentation: A) Water Testing, B) Lighting Intensity Measurements, C) Preparation Of As-Built Inventory, D) Preparation Of Fire Safety Instructions Along With An Evacuation Plan And Installation Of Fire Extinguishers And Pictograms Resulting From The Instructions, E) Preparation Of As-Built Documentation For Individual Industries In Accordance With Point 3.5.3.2. A Detailed Description Of The Subject Of The Order Was Included In The Design Documentation: Construction Design With Replacement Documentation, Bill Of Quantities And Techni