GTR 105419014
Quotation Are Invited For Construction Work At The Faya Slaughterhouse
ICB — International Competitive Bid
Closed
Central Africa
Tender Information
GTR Reference
105419014
Tendering Authority
Subscribe to view
Tender No
30000016003
Financer Name
International Organization for Migration (IMO)
Work Title
Quotation Are Invited For Construction Work At The Faya Slaughterhouse
Bid Type
ICB — International Competitive Bid
Country
Subscribe to view
Geographical Region
Central Africa
Political Region
African Solidarity Fund (FSA),African Union
Last Date of Bid Submission
30-11-2025
Closed
Work Detail
Quotation are invited for Construction Work at the Faya Slaughterhouse The work consists of constructing a slaughtering area measuring 24m x 12m, equipped with a 7m x 0.8m slaughtering table, a liquid waste drainage channel ending in a 2m x 3m x 2m pit, and a 1.5m x 1.5m x 1.5m reinforced concrete incinerator for solid waste. It also includes a 400m perimeter wall, a water tower with a 5m³ tank, and a 6m x 5m sanitary inspection area. The following infrastructure is to be built within the slaughtering area: - The main building, including the slaughtering area shed, an office, a store, a cold storage room, and a toilet; - Two latrine blocks; - A waste sump; - An incinerator; - 5m³ water tower; - 400m perimeter wall; - Inspection area The material specifications are as follows: 1. Logging shed with office Measuring 24m x 12m, the shed will include the following details: Excavations will be dug to a depth of 200cm to secure the 100mm I-beams; The 100mm I-beams will be set in concrete with a mix of 350kg/m³; The frame will consist of double angle metal trusses (70x70mmx7mm), with 50mm square tubing for the purlins; The roof will be made of corrugated metal sheets with hooks, including all necessary accessories; Construct a 110cm high concrete block wall around the perimeter of the shed, then pour a 10cm thick reinforced concrete slab with a mix of 350kg/m³; Construct a drainage channel of a specified length, made of concrete blocks with interior and exterior plastering and a 2% slope; Finally, construct three 2m x 2m IPN 80 steel frames and install 12mm steel hooks spaced 60cm apart on the frames. 2. Reinforced Concrete Tables Construction of two reinforced concrete tables, each measuring 7m x 0.6m and 1.30m high. The supports will be 15cm x 15cm and 1.20m high, made of reinforced concrete with a mix of 350kg/m³. The table thickness will be 10cm. HA 10 and HA 6 rebar will be used for reinforcement. 3. Construction of a 3m x 2m x 2m pit The pit will be excavated and constructed using 15cm concrete blocks with interior plastering; The posts will be 15cm x 15cm, the capping beam 10cm x 15cm, and two 1.5m x 1m x 0.08m reinforced concrete slabs (350kg/m³ mix) will be used to cover the entire length of the pipeline. 2. Foundations: Excavation: Excavations will be carried out according to the dimensions and depths specified in the construction drawings. Footings: The footings will be made of reinforced concrete (350kg/m³ mix), with dimensions adapted to the buildings structural loads. Foundation Wall: The foundation wall will be constructed of 20cm concrete blocks, with a height of 40cm above the natural ground level. The mortar for the joints will have a mix ratio of 300kg/m³. 3. Walls: Masonry: The walls will be constructed of 15cm concrete blocks, with a mortar mix ratio of 300kg/m³. Columns and Tie Beams: The columns and tie beams will be made of reinforced concrete with a mix ratio of 350kg/m³, with HA10 reinforcement for the columns and HA6 reinforcement for the stirrups. Render: The interior and exterior render will be applied with a cement mortar mix ratio of 300kg/m³, with a thickness of 2.5cm. 4. Roof: Framing: The roof structure will be a metal truss, composed of IPN80 beams as purlin supports and 50 mm square tubing as purlins, assembled with metal connectors. Roofing: The roof will be made of corrugated metal sheets, fixed to the framing with self-drilling screws. Insulation: Thermal insulation will be installed under the metal sheets to reduce heat inside the rooms. 5. Floors: Slab: The slab will be made of reinforced concrete with a mix of 350 kg/m³, with a thickness of 10 cm. A 5 cm thick finishing screed will be laid with a mortar mix of 300 kg/m³. Flooring: The floors of the rooms will be covered with non-slip ceramic tiles. 6. Doors and Windows: Doors: The doors will be metal, measuring 1.2 m x 2.10 m as indicated in the plans. [Disclaimer: The above text is machine translated. For accurate information kindly refer the original document.] Tender Link : https://www.iom.int/procurement-opportunities
Key Value
Tender Value
Ref. Document
Tender Documents
Global Tender Document
56a376be-01c7-483f-a473-f4359f5293a1.htm
Attachments
Additional Details Available on Click
- Tendering Authority
- Publication Document (Tender Document / Tender Notice)
Disclaimer
We take all possible care for accurate & authentic tender information. However, users are requested to refer to the original Tender Notice / Tender Document published by the Tender Issuing Agency before taking any decision regarding this tender.