BRR : 8482836
Tender Brief : GENERAL-PVIP Action Plan 2025-26-Rectification of Vadavucode MD between ch: 1.740 km and ch: 1.760 km for the year 2025-26-General Civil Work -- 1 Rectification 2 2.31:Clearing jungle including uprooting of rank vegetation, grass, brush wood, trees and saplings of girth up to 30 cm measured at a height of 1 m above ground level and removal of rubbish up to a distance of 50 m outside the periphery of the area cleared 3 2.6.1:Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including... Read More
Tender Value
₹
5,70,161
Contract Value
₹ 4,96,036
Saving / Difference
₹ 74,125
▲
Submission Date
09-10-2025
Contract Date
05-11-2025
Completion Date
180 days
Participated Bidder List
2 No of Bidder(s)
| Sr No. | Bidder Name | Bid Analytics | Technical Bid | Financial Bid | AOC | Bid Value | Rank |
|---|---|---|---|---|---|---|---|
| 1 | cnet-technologies | Bid Analytics | 5,06,874.27 | L2 | |||
| 2 | cnet-technologies | Bid Analytics | 4,96,036 | L1 |
Work Detail
general-pvip action plan 2025-26-rectification of vadavucode md between ch: 1.740 km and ch: 1.760 km for the year 2025-26-general civil work -- 1 rectification 2 2.31:clearing jungle including uprooting of rank vegetation, grass, brush wood, trees and saplings of girth up to 30 cm measured at a height of 1 m above ground level and removal of rubbish up to a distance of 50 m outside the periphery of the area cleared 3 2.6.1:earth work in excavation by mechanical means (hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including getting out and disposal of excavated earth lead upto 50 m and lift upto 1.5 m, as directed by engineer-in-charge.all kinds of soil 4 4.3.1:centering and shuttering including strutting, propping etc. and removal of form work for:foundations, footings, bases for columns 5 4.1.8:providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - all work up to plinth level:1:4:8 (1 cement : 4 coarse sand (zone-iii) derived from natural sources : 8 graded stone aggregate 40 mm nominal size derived from natural sources) 6 5.1.3:providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - all work up to plinth level:1:2:4 ( 1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size derived from natural sources) 7 5.22.2:steel reinforcement for r.c.c work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelhard drawn steel wire 8 50.2.25.1:filling with contractors own earth ( excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20 cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift up to 1.5 m as per direction of site engineer-in-charge 9 60.6:pvc weep holes- providing weep holes using 75mm dia. pvc pipes working pressure 4kg /sq.cm including cost of materials, conveyance, labour charges etc. complete.
View Original Notice/Document
Result Documents
Tender Documents
Disclaimer
We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender
✦ ✦ ✦
Awarded Bidder(s)
1
cnet-technologies
Rank : L1 (Lowest)
Bid Amount :
₹
1,00,00,000
Similar Tenders Results