| 1 | Material Part of LT line (TS No. 61/2025-26 WBS No. D-25-1334) |
| 2 | Prov. ACC Conductor 7/3.15mm (50mm sq.) |
| 3 | MS angle iron (75x75x6mm) length 1500 |
| 4 | MS angle iron knee bracing (75x75x6mm) length 600 |
| 5 | Shackle insulator |
| 6 | D-iron |
| 7 | Prov. L.T. Stay set Complete |
| 8 | Prov. Stay wire(7/3.15mm)(6.0Kg per stay) |
| 9 | Full Clamp |
| 10 | Half clamp |
| 11 | Earth hook |
| 12 | LT Earthing set (preferbly coil earthing) |
| 13 | Prov. Nut & Bolts of various sizes (Galvanised / Coated ) [Preferable 16 mm Ø or more (With flat and spring washers )] |
| 14 | Prov. Red oxide |
| 15 | Prov. Aluminium Paint |
| 16 | Distribution Box LTABThree Phase I/C- 1, O/G-2-4 (140 -200 A, 0.415kV) |
| 17 | MCCB LT 250A 35 KA |
| 18 | Erection Part of LT Line (TS No. 61/2025-26 WBS No. D-25-1334) |
| 19 | Erection of LT steel poles 8/9 Mtrs long, shackle insulator with D-iron eye hook, digging of pole pit size 1.20x0.80x1.35 filling and ramming and painting etc complete in all respect |
| 20 | Erection of LT stay set, stay clamp, egg insulator, stay wire, stay thimble, nozzeling and tightening, digging of stay pit size 1.20*.80*.1.50 mtr, filling and ramming of pit complete in all respect |
| 21 | Erection of LT earthing (pipe earthing) set complete in all respect, digging of earth pit, filling of pit with required material and ramming complete in all respect. |
| 22 | Erection AAAC 7/3.15 (50mm2) i/c laying, stringing, sagging, binding with insulators and jumpering etc. complete in all respect. (Single Conductor P/kM) |
| 23 | Erection of LT Distribution Box |
| 24 | Laying of G.I. Wire 6/8SWG i/c stringing, sagging and binding with earth hook bolt for continous earth wire complete in all respect. |
| 25 | Manual carriage for above material (Av. Lead 0.100 Km.) Please Enable Macros to View BoQ information |