| 1 | Earth work in excavation by mechanical means (Hydraulic Excavator )/ manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan) including dressing of sides and ramming of bottoms, lift upto 1.5 m, including taking out the excavated soil and depositing and refilling of jhiri with watering & ramming and disposal of surplus excavated soil as directed with in a lead of 50 meter. All kinds of soils |
| 2 | Carriage of materials Earth, Sand, Lime, Morrum manure or sludge including all lead and lift and loading & unloading. Up to 5 KM |
| 3 | Random rubble dry stone Kharanja under floor. |
| 4 | Providing and laying in position cement concrete including curing, compaction etc. complete in specified grade excluding the cost of centering and shuttering - All work up to plinth level. |
| 5 | M10 grade Nominal Mix 1: 3: 6 (1 cement : 3 coarse sand : 6 graded stone aggregate 20mm nominal size). |
| 6 | Providing and laying in position specified grade of cement concrete for all RCC structural elements upto plinth level including curing, compaction, finishing with rendering in cement sand mortar 1:3 (1 cement: 3 coarse sand) and making good the joints and cost of plastizers( if required) excluding the cost of centering, shuttering and reinforcement. M20 grade Nominal Mix / Design Mix |
| 7 | Centering and Shuttering with plywood or steel sheets including strutting, propping bracing both ways and removal of formwork for foundation , footings, strap beam, raft , bases of columns etc. |
| 8 | Providing and fabricating reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding (including cost of binding wire) all complete up to floor five level. ('Original producers' who manufacture billet directly from iron ores and roll the bilets to produce steel conforming to IS:1786) |
| 9 | Rough Chisel dressed Sand stone 35 mm thick flooring of approved shade set over 20mm thick base of cement mortar 1:6 (1 cement : 6 coarse sand) and pointing with cement sand mortar 1:3 with pigment to match the shade of stone with joint thickness up to 15 mm complete in all respects : |
| 10 | Red sand stone (Karauli stone) |
| 11 | Providing and laying in position cement concrete including curing, compaction etc. complete in specified grade excluding the cost of centering and shuttering - All work up to plinth level. |
| 12 | M20 grade Nominal Mix 1: 1.5: 3 (1 cement : 1.5 coarse sand : 3 graded stone aggregate 20mm nominal size). |
| 13 | Providing and fixing 3-layer PP-R (Polypropylene random coplymer ) pipes SDR 7.4 UV stabilized and antimicrobial fusion welded, having thermal stability for hot & cold water supply including all PP-R plain & brass threaded Polypropylene random fittings and fixing the pipe with clamps at 1 metre spacing. This includes testing of joint complete as per direction of Engineer - in charge.( INTERNAL WORK- EXPOSED ON WALL) |
| 14 | PN-16 Pipe, 16 mm OD |
| 15 | PN-16 Pipe, 20 mm OD |
| 16 | P&F rigid PVC Pipe (IS:4985 mark) class II/ (4 Kg. /Cm2.) approved quality /make including joining the pipe with solvent cement rubber ring and lubricant. |
| 17 | 110 mm dia |
| 18 | Providing at site, lowering & laying in trenches, aligning & jointing of PVC-U pipes (SN 8) as per IS 15328 (amended up to date) and as per specifications with rubber rings with socket and spigot joint, (EPDM/SBR) for all depths for pipe length as per drawing and specification including hydraulic field testing (including the cost and conveyance of water to site for testing) and commissioning etc complete as directed by Engineer. Note : E/w to be measured and paid separately. Length of pipe shall be measured in between the outer wall of two manholes / Inspection chambers. Pipe in the manhole/inspection chamber’s wall shall deemed to be included in the item of manhole/inspection chamber shall not be payable. |
| 19 | 110 mm Nominal Dia |
| 20 | Demolishing cement concrete manually/ by mechanical means including disposal of material within 50 metres lead as per direction of Engineer-in-charge. |
| 21 | 1: 3: 6 or richer mix. Please Enable Macros to View BoQ information |