| 1 | Survey, Supply, Transportation, Carriage, Erection, Testing and Commissioning for erection of 11KV line on 9 mtr long ST poles, with 30 mm sq ACSR Weasel conductor for Creation of 25 KVA Sub Station alongwith HT/LT Network at Badyal Mohalla W.No. 05 Mand West in Udhampur |
| 2 | 9 mtr. Long ST Poles(ST-410 SP-33) |
| 3 | GI V Cross -arm with top Bracket including clamps |
| 4 | GI Channel X-arm including clamps and Angle for braces |
| 5 | 11KV GO,AB Switch 3 Phase,3 Pole 200 Amp Vertical |
| 6 | 30mm² ACSR Weasel Conductor |
| 7 | 11 KV Polymer composite Pin Insulator 12 KV, 5 KN, lighting impulse 75 KV Positive and 80 KV Negative, Creepage distance 320mm. |
| 8 | 11 KV Polymeric Composite Disc insulator 12 KV, min failing load 45 kn, lightening impulse 75KV Positive and 80 KV Negative, creepage distance 320mm with fitting |
| 9 | Galvanized Nuts and Bolts |
| 10 | Earthing complete by GI Rod 20 mm, 2.5 mtr long through G.I. Strip 25X3 mm |
| 11 | Painting of ST poles 9 mtr. Long with 1 coat of Red oxide & 2 coat of Aluminum paint. |
| 12 | Cement Bottoming 1:2:4 ,ix as per REC Standards 0.5cum per pole |
| 13 | Galvanised Stay Set with 50x8mm stay clamp, guy insulator (2Nos.), anchor plate (200x 200 x 6 mm), nut-bolts, 2 Nos turn-buckles, 1.8m long, 16 mm diameter solid GS stay rod & 7/3.15 mm dia GI stranded wire complete |
| 14 | Survey, Supply, Transportation, Carriage, Erection, Testing and Commissioning for erection of LT line on 8 mtr long ST poles, with 30 mm sq ACSR Weasel conductor for Creation of 25 KVA Sub Station alongwith HT/LT Network at Badyal Mohalla W.No. 05 Mand West in Udhampur |
| 15 | 8 mtr. Long ST Poles(ST-410 SP-15) |
| 16 | GI M Clamps for shackle insulator |
| 17 | 30mm² ACSR Weasel Conductor |
| 18 | Shackle insulator |
| 19 | Galvanized Nuts and Bolts |
| 20 | Earthing complete by GI Rod 20 mm, 2.5 mtr long through G.I. Strip 25X3 mm |
| 21 | Survey, Supply, Transportation, Carriage, Erection, Testing and Commissioning for Creation of 25 KVA Sub Station alongwith HT/LT Network at Badyal Mohalla W.No. 05 Mand West in Udhampur |
| 22 | 11/0.433kV, 3-phase Distribution Transformers 25 KVA Aluminium wound distribution transformer of latest energy efficiency level 2 newISI 1180 PART I as per latest upto date amendment |
| 23 | Gapless surge Arrestor, 9 kv, 10 KA , LA with polymer housing stn. Type |
| 24 | 11 KV GO AB Switch 3 phase, 3 pole, 200 Amp, vertical |
| 25 | 11 KV Horn gap fuse set 3 phase 200 A |
| 26 | 70 mm²(1ckt)1.1 KV Grade, PVC insulated stranded conductor FRLS Type |
| 27 | 9 mtr. Long ST Poles(ST-410 SP-33) |
| 28 | 11 KV Polymeric Composite Disc insulator 12 KV, min failing load 45 kn, lightening impulse 75KV Positive and 80 KV Negative, creepage distance 320mm with fitting |
| 29 | Galvanized Nuts and Bolts |
| 30 | Danger Plates with Clamps |
| 31 | GI Channel /Angle/flat of sizes including clamps |
| 32 | Painting of ST poles 9 mtr. Long with 1 coat of Red oxide & 2 coat of Aluminum paint. |
| 33 | Cement Bottoming 1:2:4 ,ix as per REC Standards 0.5cum per pole |
| 34 | LT Fuse Switch made of angle iron 50x50x6 with Aluminium bus bar strip 50x6 mm fixed on busbar insulator including clamps for fixing of switch |
| 35 | Earthing of sub stn. Excavation of earth pit of dia 650mm & depth 3000mm installation of earthing pipe of 40mm Nominal bore & 4mm wall thickness & length 2.5 mtr. Long as per IS 1239. G.I Strip for neutral earthing of size 25mmx3mm for connection of transforemr body, GO Set & lightening arrestor as per IS 2629/85, GI Nuts & bolts refilled with earth enhancement materials and earth chamber with RCC Slab cover |
| 36 | Galvanised Stay Set with 50x8mm stay clamp, guy insulator (2Nos.), anchor plate (200x 200 x 6 mm), nut-bolts, 2 Nos turn-buckles, 1.8m long, 16 mm diameter solid GS stay rod & 7/3.15 mm dia GI stranded wire complete |
| 37 | Supply of 2 ton Chain block to Divisional Store ED Udhampur Please Enable Macros to View BoQ information |