| 1 | BOQ FOR RELEASE OF SERVICE CONNECTIONS OF NEW HT/LT LINE & LT SUB STATIONS AND OTHER WORK IN EDSD, JWALAPUR-I & II UNDER ELECTRICITY DISTRIBUTION DIVISION, JWALALPUR, HARIDWAR UNDER CAPITAL(NSC) HEAD AGAINST E-TENDER NO- 37/EDC(H)/2026-27 Bidder's Name & Address S.N. Work Unit Qty. Rate Amount (In Rs.) A Decentrlized Material |
| 2 | Holding Clamp with nut & bolt for ST Pole SP-23 |
| 3 | Holding Clamp with nut & bolt for ST Pole SP-33 |
| 4 | Holding Clamp with nut & bolt for ST Pole SP-55 |
| 5 | Holding Clamp with nut & bolt for PCC Pole. |
| 6 | Holding Clamp with nut & bolt for ST Pole SP-72. |
| 7 | Stay Clamp with nut & bolt for ST Pole SP-23 |
| 8 | Stay Clamp with nut & bolt for ST Pole SP-33 |
| 9 | Stay Clamp with nut & bolt for ST Pole SP-55 |
| 10 | Stay Clamp with nut & bolt for PCC Pole. |
| 11 | Stay Clamp with nut & bolt for ST Pole SP-72. |
| 12 | Earth Wire Clamp with nut & bolt for ST Pole SP-23 |
| 13 | Earth Wire Clamp with nut & bolt for ST Pole SP-33 |
| 14 | Earth Wire Clamp with nut & bolt for ST Pole SP-55 |
| 15 | Earth Wire Clamp with nut & bolt for PCC Pole. |
| 16 | Earth Clamp with nut & bolt for ST Pole SP-72. |
| 17 | LT Clamp with nut & bolt for ST Pole SP-23 |
| 18 | LT Clamp with nut & bolt for ST Pole SP-33 |
| 19 | LT Clamp with nut & bolt for ST Pole SP-55 |
| 20 | LT Clamp with nut & bolt for PCC Pole. |
| 21 | Bracing Clamp with nut & bolt for ST Pole SP-23 |
| 22 | Bracing Clamp with nut & bolt for ST Pole SP-33 |
| 23 | Bracing Clamp with nut & bolt for ST Pole SP-55 |
| 24 | Bracing Clamp with nut & bolt for PCC Pole. |
| 25 | PP & Clamp with nut & bolt for ST Pole SP-23 |
| 26 | PP & Clamp with nut & bolt for ST Pole SP-33 |
| 27 | PP & Clamp with nut & bolt for ST Pole SP-55 |
| 28 | PP & Clamp with nut & bolt for PCC Pole. |
| 29 | F' Clamp with nut & bolt for PCC Pole. |
| 30 | LT shackle Insulator. |
| 31 | Stay Insulator. |
| 32 | PG Clamp Rabbit to Rabbit conductor. |
| 33 | PG Clamp Dog to Dog conductor. |
| 34 | LT PRC |
| 35 | Suspension Clamp for AB Cable. |
| 36 | Cable Holding Clamp with nut & bolt for ST/PCC Pole. |
| 37 | Holding Clamp J/I-Hook for AB Cable |
| 38 | Dead End Clamp for AB Cable. |
| 39 | 3Ph.4W LT Distribution Box. |
| 40 | Al. Cable 1x35 Sqmm for energizing Distribution Box. |
| 41 | LConnecting Cable AB Cable to DB 1x25Sqmm. |
| 42 | Al. Lugs 120 Sqmm |
| 43 | Nut & Bolt off size. |
| 44 | GI Pipe 150mm 4mtr long |
| 45 | LT DB Holding Clamp with nut & bolt. |
| 46 | 11 KV Cable J/K 3x50 Sq.mm (O/D) |
| 47 | 11 KV Cable J/K 3x50 Sq.mm (I/D) |
| 48 | 11 KV Cable J/K 3x70 Sq.mm (O/D) |
| 49 | 11 KV Cable J/K 3x70 Sq.mm (I/D) 0.0 B LABOUR CHARGE |
| 50 | Cartage of following from store centre, Haridwar/JE Store to work site with loading, unloading at both ends. Dist. upto( 0-20) Km. (i) SP-10/21/23 No. 1.0 0.0 (ii) SP-33 No. 1.0 0.0 (iii) SP-55 No. 1.0 0.0 (iv) SP-72 No. 1.0 0.0 (v) PCC Pole No. 1.0 0.0 (vi) Petty material Qtl. 1.0 0.0 (vii) 25 KVA No. 1.0 0.0 (viii) 63 KVA No. 1.0 0.0 (ix) 100 KVA No. 1.0 0.0 (x) 250 KVA No. 1.0 0.0 (xi) 400/500 KVA No. 1.0 0.0 |
| 51 | Head load cartage of following from store centre, Haridwar/JE Store to work site with loading, unloading at both ends. Dist. upto( 0-1) Km. (i) SP-10/21/23 No. 1.0 0.0 (ii) SP-33 No. 1.0 0.0 (iii) SP-55 No. 1.0 0.0 (iv) SP-72 No. 1.0 0.0 (v) PCC Pole No. 1.0 0.0 (vi) Petty material Qtl. 1.0 0.0 (vii) 25 KVA No. 1.0 0.0 (viii) 63 KVA No. 1.0 0.0 (ix) 100 KVA No. 1.0 0.0 (x) 250 KVA No. 1.0 0.0 (xi) 400/500 KVA No. 1.0 0.0 |
| 52 | Cartage of 11KV metering cubical from ESC, Haridwar/Rishikesh/ Roorkee /JE store to work site with loading and unloading at both ends. Dist. upto( 0-20) Km |
| 53 | Cartage of 33KV metering cubical from ESC, Haridwar/Rishikesh/ Roorkee /JE store to work site with loading and unloading at both ends. Dist. upto( 0-20) Km |
| 54 | Cartage of 11KV VCB from ESC, Haridwar/Rishikesh/Roorkee /JE store to work site with loading and unloading at both ends. Dist. upto( 0-20) Km |
| 55 | Cartage of 33KV VCB from ESC, Haridwar/Rishikesh/Roorkee /JE store to work site with loading and unloading at both ends. Dist. upto( 0-20) Km |
| 56 | Cartage of 11KV CT-PT combined unit off size from ESC, Haridwar/Rishikesh/Roorkee /JE store to work site with loading and unloading at both ends. Dist. upto( 0-20) Km |
| 57 | Manual shifting/Pulling of 11KV/33KV metering cubical from existing site to plinth/nereby place with loading and unloading at both ends. Dist. Upto 200 Mtrs. |
| 58 | Manual shifting/Pulling of 11KV VCB from existing site to plinth/nereby place with loading and unloading at both ends.Dist. Upto 200 Mtrs. |
| 59 | Manual shifting/Pulling of 33KV VCB from existing site to plinth/nereby place with loading and unloading at both ends.Dist. Upto 200 Mtrs. |
| 60 | Manual shifting/Pulling of 11KV CT-PT combined unit off size from existing site to plinth/nereby place with loading and unloading at both ends.Dist. Upto 200 Mtrs. |
| 61 | Excavation of Earth for pole pit of size 0.9x0.6x1/6th of full length of pole for erection of pole in all type of soil complete work. |
| 62 | Erection of Single support pole in proper level and alignment including fixing of all accessories for HT/LT line as per Respo construction manual. (i) SP-10/21/23 No. 1.0 0.0 (ii) SP-33 No. 1.0 0.0 (iii) SP-55 No. 1.0 0.0 (iv) SP-72 No. 1.0 0.0 (v) PCC Pole No. 1.0 0.0 |
| 63 | Erection of double support pole in proper level and alignment alongwith fixing of all accessories for HT/LT line as per Respo construction manual. (i) SP-21/23 No. 1.0 0.0 (ii) SP-33 No. 1.0 0.0 (iii) SP-55 No. 1.0 0.0 (iv) SP-72 No. 1.0 0.0 (v) PCC Pole No. 1.0 0.0 |
| 64 | Erection of triple pole structure in proper level and alignment alongwith fixing of all accessories for HT/LT line as per Respo construction manual. (i) SP-55 No. 1.0 0.0 (ii) SP-72 No. 1.0 0.0 |
| 65 | Erection of Four pole structure in proper level and alignment alongwith fixing of all accessories for HT/LT line as per Respo construction manual. (i) SP-55 No. 1.0 0.0 (ii) SP-72 No. 1.0 0.0 |
| 66 | Grouting of pole in size 0.45x0.45x1/9th of the support in CC ratio 1:4:8 (1cement:4 graded stone 20mm naminal size:8 coarse sand) block including cost of material as per Respo construction manual. |
| 67 | Muffing of Poles size 0.45x0.60 cm radius with cc 1:3:6 block and 45 cm height from ground level including cost of material. |
| 68 | Fixing of bracket in LT. |
| 69 | Fixing of bracket in 11KV line. |
| 70 | Fabrication of MS Channel/Angle |
| 71 | Excavation of Earth for Stay pit of size 0.6x0.6x1.2mtr in all type of soil complete work. |
| 72 | Fixing, Binding , Nozzling of stay on required tension as per RESPO manual. (i) LT line. No. 1.0 0.0 (ii) 11KV line. No. 1.0 0.0 (iii) 33KV line. No. 1.0 0.0 |
| 73 | Grouting of Stay in size 0.6x0.6x0.3mtr in CC ratio 1:4:8 (1cement:4 graded stone 20mm naminal size:8 coarse sand) block including cost of material as per Respo construction mannual. |
| 74 | Earthing with M.S. Earth Rod of 2.5 mtr long by hammering of M.S. Earth rod to proper depth and connecting the earth electrode with the help of GI wire. |
| 75 | Laying, Spreading, Stringing and Sagging of HT line in 3 phase (3 Phase 4 wire) of the following wire as phase wire with G.I. earth wire complete including fixing of all accessories as per Respo Specn. (i) ACSR Weasel Conductor Km. 1.0 0.0 (ii) ACSR Rabbit Conductor Km. 1.0 0.0 (iii) ACSR Raccoon Conductor Km. 1.0 0.0 (iv) ACSR Dog Conductor Km. 1.0 0.0 (v) ACSR Panther Conductor Km. 1.0 0.0 |
| 76 | Laying, Spreading, Stringing and Sagging of LT lines of the following wire as phase wire with G.I. earth wire complete with binding and jumpering as per RESPO Specn. (A) ACSR Weasel Conductor (i) 3 Phase 5 wire length Ckt. Km. 1.0 0.0 (ii) 3 Phase 4 wire length Ckt. Km. 1.0 0.0 (iii) 2 Phase 3 wire length Ckt. Km. 1.0 0.0 (iv) 1 Phase 2 wire length Ckt. Km. 1.0 0.0 (B) ACSR Rabbit Conductor (i) 3 Phase 5 wire length Ckt. Km. 1.0 0.0 (ii) 3 Phase 4 wire length Ckt. Km. 1.0 0.0 (iii) 2 Phase 3 wire length Ckt. Km. 1.0 0.0 (iv) 1 Phase 2 wire length Ckt. Km. 1.0 0.0 (C) ACSR Raccoon Conductor (i) 3 Phase 5 wire length Ckt. Km. 1.0 0.0 (ii) 3 Phase 4 wire length Ckt. Km. 1.0 0.0 (iii) 2 Phase 3 wire length Ckt. Km. 1.0 0.0 (iv) 1 Phase 2 wire length Ckt. Km. 1.0 0.0 (D) ACSR Dog Conductor (i) 3 Phase 5 wire length Ckt. Km. 1.0 0.0 (ii) 3 Phase 4 wire length Ckt. Km. 1.0 0.0 (iii) 2 Phase 3 wire length Ckt. Km. 1.0 0.0 (iv) 1 Phase 2 wire length Ckt. Km. 1.0 0.0 |
| 77 | Laying, Spreading & Binding of LT AB cable off size. |
| 78 | Making Jumper on the double pole with PG Clamp complete as per RESPO |
| 79 | Painting of ST poles and fixture with scrapping of dust & rust applying one coat of primer Red oxide paint and two coats of synth enamel Al. paint. (i) ST Pole SP-21/23 No. 1.0 0.0 (ii) ST Pole SP-33 No. 1.0 0.0 (iii) ST Pole SP-55 No. 1.0 0.0 (iv) ST Pole SP-72 No. 1.0 0.0 |
| 80 | Digging of trench of size 0.60x0.15 mtr. and laying of under ground LT/11KV XLPE cable with making of brick housing and filling of sand including filling of earth with ramming. & repairing of road including cost of cement sand and stone blast. |
| 81 | Digging of trench of size 0.60x0.15 mtr. and laying of under ground 33KV XLPE cable with making of brick housing and filling of sand including filling of earth with ramming. & repairing of road including cost of cement sand and stone blast. |
| 82 | Filling & Fixing of 11KV Heat Shrinkable Cable Jointing Kit complete in all respect. |
| 83 | Filling & Fixing of 33KV Heat Shrinkable Cable Jointing Kit complete in all respect. |
| 84 | Installation of 11KV/33KV Metering cubical in the metering room with grouting complete in all respect. |
| 85 | Installation of 11KV VCB complete in all respect. |
| 86 | Installation of 33KV VCB complete in all respect. |
| 87 | Installation of 11KV CT-PT combined unit off size complete in all respect. |
| 88 | Earthing of Metering Cubical/VCB/11KV CT-PT combined unit off size with GI Strip 35x6mm complete in all respect. |
| 89 | Guarding of 11KV line as per RESPO specn. (Length of span 40 mtr.) including fabrication of guarding channel & angle & fixing on the pole & laying sagging GI 6 SWG wire in each and cross guard at a distance of 2 mtr in each span including binding. |
| 90 | Guarding of 33KV line as per RESPO specn. (Length of span 40 mtr.) including fabrication of guarding channel & angle & fixing on the pole & laying sagging GI 6/8 SWG wire in each and cross guard at a distance of 2 mtr in each span including binding. |
| 91 | Dismantling of following pole for HT/LT line complete in all respect . (A) Single Pole (i) SP-21/23 No. 1.0 0.0 (ii) SP-33 No. 1.0 0.0 (iii) SP-55 No. 1.0 0.0 (iv) SP-72 No. 1.0 0.0 (v) PCC Pole No. 1.0 0.0 (B) Double Pole (i) SP-21/23 No. 1.0 0.0 (ii) SP-33 No. 1.0 0.0 (iii) SP-55 No. 1.0 0.0 (iv) SP-72 No. 1.0 0.0 (v) PCC Pole No. 1.0 0.0 |
| 92 | Dismantling of ACSR/ABC Conductor of HT/LT line complete in all respect. (i) Weasel Ckt.Km. 1.0 0.0 (ii) Rabbit Ckt.Km. 1.0 0.0 (iii) Raccoon Ckt.Km. 1.0 0.0 (iv) Dog Ckt.Km. 1.0 0.0 (v) AB Cable off size Km. 1.0 0.0 |
| 93 | Dismantling of following T/F's from double pole/plinth including of all connections, circuits & earthing strip etc. (i) 25KVA No. 1.0 0.0 (ii) 63KVA No. 1.0 0.0 (iii) 100KVA No. 1.0 0.0 (iv) 250KVA No. 1.0 0.0 (v) 400KVA No. 1.0 0.0 |
| 94 | Safe carriage of dismantled T/F's from pit site to JE' store/ store center with loading & unloading both ends.Dist. Upto (0-20) km. (i) 25KVA No. 1.0 0.0 (ii) 63KVA No. 1.0 0.0 (iii) 100KVA No. 1.0 0.0 (iv) 250KVA No. 1.0 0.0 (v) 400KVA No. 1.0 0.0 |
| 95 | Dismantling of 11KV VCB/ 33KV Single feeder/ double feeder/ transformer single or double/ capacitor panel. |
| 96 | Dismantling of 33KV VCB complete in all respect. |
| 97 | Dismantling of 11KV/33KV Metering cubical. |
| 98 | Dismantling of TPMO/Fuse Set on double pole structure. |
| 99 | Dismantling of LT Fuse Set complete. |
| 100 | Mounting & Fixing of TPMO/Fuse Set on double pole structure including making of connections complete. |
| 101 | Mounting & Fixing of LT Fuse Set complete in all respect. |
| 102 | Fixing of L.A. on the double pole & earthing of the same as per RESPO specn. |
| 103 | Construction of T/F plinth with size 2x2x1.1m above ground level and 0.6mtr below ground level including the cost of material such as cement, brick, ballast, sand etc. complete in all respect. |
| 104 | Mounting of Transformer on Plinth/double pole and making all connections of HT/LT side complete in all respect. (i) 25KVA No. 1.0 0.0 (ii) 63KVA No. 1.0 0.0 (iii) 100KVA No. 1.0 0.0 (iv) 250KVA No. 1.0 0.0 (v) 400/500 KVA No. 1.0 0.0 |
| 105 | Laying of LT PVC/XLPE cables (upto 150 Sqmm). |
| 106 | Laying of LT PVC/XLPE cables (240 to 630 Sqmm). |
| 107 | Making of section pole of existing LT/HT line complete in all respect. |
| 108 | T-off Conection Complete 11 KV line complete in all respect. |
| 109 | T-off Conection Complete 33KV line complete in all respect. |
| 110 | Neutral Earthing of T/F by 1.5Mtr Delta Earthing including digging of pit 1.5x1.5x1 Mtr 3 no. 32 mm dia 3 mtr long MS round duly pointed at one and 500 mm below ground level jointing the neutral point of the T/F with the flat and earthing of T/F body of 2 points. |
| 111 | Cartage of LT PRMC from ESC store, Haridwar/JE store to pit site & installation on the double pole complete in all respect. |
| 112 | Route clearence by cutting of tree branches/proning, lopping and chopping of tree for HT/LT line complete in all respect. |
| 113 | Laying of overhead 11KV XLPE cable, off size. |
| 114 | Fixing of GI pipe complete in all respect. |
| 115 | Laying of 11KV Cable in HDPE Pipe complete after making trench with trenchless technology as per RESPO, including cost of HDPE pipe. |
| 116 | Laying of 33KV Cable in HDPE Pipe complete after making trench with trenchless technology as per RESPO, including cost of HDPE pipe. |
| 117 | Laying of LT/11KV Cable in Half Circle Hume Pipe of dia 150mm including cost of hume pipe in depth 1.5 meter. |
| 118 | Laying of 33KV Cable in Half Circle Hume Pipe of dia 150mm including cost of hume pipe in depth 1.5 meter. |
| 119 | Erection, providing and fixing of wire mesh fencing of size 50x35 mm around plinth and toe wall duly welded with frame of MS Angle iron 35x35x6mm and strip of size 35x6mm in mid of each side alongwith wire mesh (width of wiremesh 1.5 mtr)with the height of 0.5 mtr above the plinth and 2 mtr above the toe wall with 1 no. gate and locking arrangement in the toe wall size including grouting of 1no. legs in the ratio in block of size 0.25x0.25x0.45 mtr including gravelling of shingle of size 20 to 40mm and complete printing of wire mesh with aluminium paint with two coat(including cost of all material) |
| 120 | Providing and fixing of Danger Board/nunber plate complete with clamp. |
| 121 | Fixing of 3Ph. LT Distribution Box. |
| 122 | Laying of LT Service Cable from pole to consumer end. |
| 123 | Fixing of Single Phase Electronic Meter 10-60 Amp. complete in all respect.. |
| 124 | Fixing of Three Phase Electronic Meter 10-60 Amp. complete in all respect.. |
| 125 | Civil Work (i) Making and casting of equipment foundations as per site requirements and design report in brick work. Cu.mtr 1.0 0.0 |
| 126 | Road cutting Charges (i) BM/SDBC Road Cu.mtr 1.0 0.0 (ii) Premix Concrete/Painted Road Cu.mtr 1.0 0.0 (iii) WBM Surface Road Cu.mtr 1.0 0.0 (iv) Kacha Road Cu.mtr 1.0 0.0 (v) RWD Road Cu.mtr 1.0 0.0 Total (B) 0.0 Total (A+B) 0.0 Note :- GST will be paid extra as actuals. Company/Firm Name Name Designation Date |