| 1 | Part A- Cost of Materials for 11 KV Cut Point with 90 Degree Angle- 2 No. |
| 2 | Supply & installation of WPB (GI) Pole 160x152 (11Mtr. Long,30.44KG/Mtr)(Total pole weight with base plate & stiffner = 334.84 Kg + 10.74 Kg = 345.58).Including excavation of pole pit in all king of soil with depth upto 1/6th of pole height. Complete in all respect as per the approved technical specification and direction of EIC. |
| 3 | Supply & installation of Straight Cross Arm 100X50X6mm, 9.56 KG/Mtr. each channel(GI) length 1.2 mtr, 4no's channel(GI) required =( 4x9.56x1.2). Complete in all respect as per the approved technical specification and direction of EIC. |
| 4 | Supply & installation of Fish Plate(GI) 50x6mm., 2.36 kg/Mtr. each 0.280 mtr length,16 no's required =(16x2.36x0.280).Complete in all respect as per the approved technical specification and direction of EIC. |
| 5 | Supply & installation of Straight Cross Arm 100X50X6mm, 9.56 KG/Mtr., each channel(GI) length 0.306 mtr. 4no's channel(GI) required =(4x9.56x0.306). Complete in all respect as per the approved technical specification and direction of EIC. |
| 6 | Supply and installation of Danger Plate,1 no's. Complete in all respect as per the approved technical specification and direction of EIC. |
| 7 | Supply and installation of Back Clamp for danger Plate 25X3 mm. flat(GI), 0.59Kg/Mtr. Flat(GI) of 0.510mtr length 1 no's= (1x0.59x 0.510) .Complete in all respect as per the approved technical specification and direction of EIC. |
| 8 | Supply & installation of GI barbed wire anticlimbing device 3 Kg. per support. Complete in all respect as per the approved technical specification and direction of EIC. |
| 9 | Supply & installation of Back Clamp for anticlimbing device 25X3 mm. flat(GI), 0.59Kg /Mtr. Flat(GI) of 0.510mtr length 4 no's =(4x0.59x0.510). Complete in all respect as per the approved technical specification and direction of EIC. |
| 10 | Supply & installation of 11 KV pin insulator polymer. Complete in all respect as per the approved technical specification and direction of EIC. |
| 11 | Supply & installation of H W fitting (B&S) 70KN,3Bolt. Complete in all respect as per the approved technical specification and direction of EIC. |
| 12 | Supply & installation of Disc insulator (B&S) 70 KN polymer. Complete in all respect as per the approved technical specification and direction of EIC. |
| 13 | Supply & installation of Earthing of support(Coil Type). Complete in all respect as per the approved technical specification and direction of EIC. |
| 14 | Supply & installation of No-8 GI wire (Dia 4.6mm) 0.131 KG/Mtr- 2Mtr for connecting pole with coil earthing. Complete in all respect as per the approved technical specification and direction of EIC. |
| 15 | Supply & installation of Wedge connector for 80SQMM AAA Conductor.Complete in all respect as per the approved technical specification and direction of EIC. |
| 16 | Supply & installation of Polycarbonate Bird Guard. Complete in all respect as per the approved technical specification and direction of EIC. |
| 17 | Supply and installation of H.T. Stay clamp, 50x8 mm. flat(GI), 3.14Kg/Mtr., 0.551 Mtr. Length, 2 no's qty. reguired(1 Pair) .Complete in all respect as per the approved technical specification and direction of EIC. |
| 18 | Supply & installation of H.T. Stay set (Complete). Complete in all respect as per the approved technical specification and direction of EIC. |
| 19 | Supply & installation of H.T. Stay Insulator Type-C . Complete in all respect as per the approved technical specification and direction of EIC. |
| 20 | Supply & installation of 7/10 SWG Stay Wire 15kg /stay. Complete in all respect as per the approved technical specification and direction of EIC. |
| 21 | Supply & installation of GI Nut, Bolt & Washer of different sizes (7.433 Kg each Cut Pole). Complete in all respect as per the approved technical specification and direction of EIC. |
| 22 | Supply and painting of Black paint(GIS Numbering & Zebra Stripping) as required and direction of EIC. |
| 23 | Supply and painting of Yellow colour paint(GIS Numbering & Zebra Stripping) for background as required and direction of EIC. |
| 24 | Part A- Cost of Civil Works. |
| 25 | Fixing of 11KV line Complete stay set includes 1) Turn Buckle Assembly 2) Stay Rod & Stay plate 3)Stay Insulator 4) Stay Wire. 5)Stay clamps with Nuts & bolts, including excvation, supply of 0.5 Cum cement concrete foundation 1:2:4 size (500mmx500mmx800mnm) using 20mm BHG metal with all labour and material .Complete in all respect as per TPCODL Drawing , Standard & as per the direction of EIC. |
| 26 | Concreting ratio 1:1.5:3 (500mmX500mm X1800mm) = 0.45Cu.mtr(Per pole).Complete in all respect as per the direction of EIC. |
| 27 | Couping ratio 1:1.5:3 (M-20 Grade) with dimension (500X 500X450)= 0.1125 Cumtr(per Pole). Complete in all respect as per the direction of EIC. |
| 28 | Part B- Cost of Materials for 11 KV Cut Point with 180 Degree Angle- 1 No. |
| 29 | Supply & installation of WPB (GI) Pole 160x152 (11Mtr. Long,30.44KG/Mtr)(Total pole weight with base plate & stiffner = 334.84 Kg + 10.74 Kg = 345.58).Including excavation of pole pit in all king of soil with depth upto 1/6th of pole height. ComComplete in all respect as per the approved technical specification and direction of EIC. |
| 30 | Supply & installation of Straight Cross Arm 100X50X6mm, 9.56 KG/Mtr. each channel(GI) length 1.2 mtr, 2no's channel(GI) required =( 2x9.56x1.2). Complete in all respect as per the approved technical specification and direction of EIC. |
| 31 | Supply & installation of Fish Plate(GI) 50x6mm., 2.36 kg/Mtr. each 0.280 mtr length,6 no's required =(6x2.36x0.280).Complete in all respect as per the approved technical specification and direction of EIC. |
| 32 | Supply & installation of Straight Cross Arm 100X50X6mm, 9.56 KG/Mtr., each channel(GI) length 0.306 mtr. 2no's channel(GI) required =(2x9.56x0.306). Complete in all respect as per the approved technical specification and direction of EIC. |
| 33 | Supply and installation of Danger Plate,1 no's. Complete in all respect as per the approved technical specification and direction of EIC. |
| 34 | Supply and installation of Back Clamp for danger Plate 25X3 mm. flat(GI), 0.59Kg/Mtr. Flat(GI) of 0.510mtr length 1 no's= (1x0.59x 0.510) .Complete in all respect as per the approved technical specification and direction of EIC. |
| 35 | Supply & installation of GI barbed wire anticlimbing device 3 Kg. per support. Complete in all respect as per the approved technical specification and direction of EIC. |
| 36 | Supply & installation of Back Clamp for anticlimbing device 25X3 mm. flat(GI), 0.59Kg /Mtr. Flat(GI) of 0.510mtr length 4 no's =(4x0.59x0.510). Complete in all respect as per the approved technical specification and direction of EIC. |
| 37 | Supply & installation of H W fitting (B&S) 70KN,3Bolt. Complete in all respect as per the approved technical specification and direction of EIC. |
| 38 | Supply & installation of Disc insulator (B&S) 70 KN polymer. Complete in all respect as per the approved technical specification and direction of EIC. |
| 39 | Supply & installation of Earthing of support(Coil Type). Complete in all respect as per the approved technical specification and direction of EIC. |
| 40 | Supply & installation of No-8 GI wire (Dia 4.6mm) 0.131 KG/Mtr- 2Mtr for connecting pole with coil earthing. Complete in all respect as per the approved technical specification and direction of EIC. |
| 41 | Supply & installation of Wedge connector for 80SQMM AAA Conductor.Complete in all respect as per the approved technical specification and direction of EIC. |
| 42 | Supply & installation of Polycarbonate Bird Guard. Complete in all respect as per the approved technical specification and direction of EIC. |
| 43 | Supply & installation of GI Nut, Bolt & Washer of different sizes (7.433 Kg each Cut Pole). Complete in all respect as per the approved technical specification and direction of EIC. |
| 44 | Supply and painting of Black paint(GIS Numbering & Zebra Stripping) as required and direction of EIC. |
| 45 | Supply and painting of Yellow colour paint(GIS Numbering & Zebra Stripping) for background as required and direction of EIC. |
| 46 | Part B- Cost of Civil Works. |
| 47 | Concreting ratio 1:1.5:3 (500mmX500mm X1800mm) = 0.45Cu.mtr(Per pole).Complete in all respect as per the direction of EIC. |
| 48 | Couping ratio 1:1.5:3 (M-20 Grade) with dimension (500X 500X450)= 0.1125 Cumtr(per Pole). Complete in all respect as per the direction of EIC. |
| 49 | Part C- Cost of Materials for 11 KV Pin Points With WPB - 0.209 CKM. |
| 50 | Supply & installation of WPB (GI) Pole 160x152 (11Mtr. Long,30.44KG/Mr.)(Total pole weight with base plate & stiffner = 334.84 Kg + 10.74 Kg = 345.58).Including excavation of pole pit in all king of soil with depth upto 1/6th of pole height. Complete in all respect as per the approved technical specification and direction of EIC. |
| 51 | Supply & installation of 11KV V cross Arm(GI) (10.2 Kg. each). Complete in all respect as per the approved technical specification and direction of EIC. |
| 52 | Supply & installation of Top bracket 100x50X6 mm Gl channel (2kg each).Complete in all respect as per the approved technical specification and direction of EIC. |
| 53 | Supply & installation of Danger Plate,1 no's. for each pole. Complete in all respect as per the approved technical specification and direction of EIC. |
| 54 | Supply & installation of Back Clamp for danger Plate 25X3 mm. flat(GI), 0.59Kg/Mtr. Flat(GI) of 0.510mtr length 1 no's =(1x0.59x0.510). Complete in all respect as per the approved technical specification and direction of EIC. |
| 55 | Supply & installation of GI barbed wire anticlimbing device 3 Kg. Per support. Complete in all respect as per the approved technical specification and direction of EIC. |
| 56 | Supply & installation of Back Clamp for anticlimbing device 25X3 mm. flat, 0.59Kg/Mtr. Flat of 0.510mtr Iength 4 no's =(4x0.59x0.510). Complete in all respect as per the approved technical specification and direction of EIC. |
| 57 | Supply & installation of 11 KV pin insulator polymer, 3 Nos. required for each support. Complete in all respect as per the approved technical specification and direction of EIC. |
| 58 | Supply & installation of Earthing of Support Coil Type. Complete in all respect as per the approved technical specification and direction of EIC. |
| 59 | Supply & installation of No-8 GI wire (Dia 4.6mm) 0.131 KG/ Mtr.- 2 Mtr. For connecting pole with Coil earthing. Complete in all respect as per the approved technical specification and direction of EIC. |
| 60 | Supply & installation of GI Nut, Bolt & Washer of different sizes (1.45 Kg/ Pin Point). Complete in all respect as per the approved technical specification and direction of EIC. |
| 61 | Supply & Stringing of 80 SQ.MM AAAC XLPE Covered Conductor. Complete in all respect as per the approved technical specification and direction of EIC. |
| 62 | Supply & installation of Polycarbonate Bird Guard. Complete in all respect as per the approved technical specification and direction of EIC. |
| 63 | Supply and painting of Black paint(GIS Numbering & Zebra Stripping) as required and direction of EIC. |
| 64 | Supply and painting of Yellow colour paint(GIS Numbering & Zebra Stripping) for background as required and direction of EIC. |
| 65 | Part C- Cost of Civil Works. |
| 66 | Concreting ratio 1:1.5:3 (500mmX500mm X1800mm) = 0.45Cu.mtr(Per pole).Complete in all respect as per the direction of EIC. |
| 67 | Couping ratio 1:1.5:3 with dimension (500X 500X450)= 0.1125 Cu mtr(Per pole).Complete in all respect as per the direction of EIC. |
| 68 | Part D- Cost of meterial for Line protecting Guarding for road crossing |
| 69 | Supply and Installation of Guarding Channel(GI) 75x40x4.8 mm, 7.14 KG/Mtr,, each Channe(GI) length 2.2 mtr., 4 no's Channel(Gl) required =( 4x7.14x2.2) ( For Single Pole). Complete in all respect as per the approved technical specification and direction of EIC. |
| 70 | Supply and Installation of No-6 GI wire (0.192 kg/mtr.) for Main String.Complete in all respect as per the approved technical specification and direction of EIC. |
| 71 | Supply and Installation of No-8 GI wire (0.131 kg/mtr.) for lacing.Complete in all respect as per the approved technical specification and direction of EIC. |
| 72 | Supply and Installation of Eye Bolt (236mm, 16mm dia, 1.577kg/mtr.). Complete in all respect as per the approved technical specification and direction of EIC. |
| 73 | Supply and Installation of GI pipe earthing 40mm ,3mtr long. Complete in all respect as per the approved technical specification and direction of EIC. |
| 74 | Supply and Installation of 50x6mm,Flat(GI) for earthing, 2.36kg/mtr,( 10.7 meter for rising) =10.7x2.36 .Complete in all respect as per the approved technical specification and direction of EIC. |
| 75 | Part -D : Cost of Civil Work |
| 76 | Construction Earthing chamber including installation of earthing pipe.Making earthing chamber including excavation, soil treatment with bentonide powder, calculation of earth resistance, including Installation of 3Mtr GI Pipe 40mm/ 50mm including welding of Flat(GI) around pipe.Complete in all respect as per the direction of EIC. |
| 77 | N.B: The bidders are required to Quote theire rates excluding of Goods & Service Tax (GST). GST as applicable will be paid extra. The existing rule of Govt. and any amendment made in future will be followed. Please Enable Macros to View BoQ information |