| 1 | (-)Earthwork in all kinds of soil in excavation of foundation trenches for columns, basement, tie beams, walls and steps in all kinds of soil including moorum, hard stoney earth and earth mixed with boulders except sheet rocks and boulders requiring blasting with all leads and lifts including dressing and leveling the bed sides up to required depth and depositing the excavated materials at places away from the work site with all leads and lifts, T&P for shoring, shuttering, dewatering if required etc. complete as per the drawing, designing including cost of all labour, T&P etc. as required for the work complete as directed by the Engineer-in-charge |
| 2 | Supplying and filling in F and P with sand well watered and rammed including all cost, conveyance, royalities, T and P etc all complete as per direction of the EIC. |
| 3 | (-)Supplying all labour, materials, T&P for Cement Concrete (1:3:6) in foundation using 4 cm size hard granite Crusher Broken metal including cost of materials, royalty & conveyance charges with watering, curing all complete as per direction of Engineer-in-charge. |
| 4 | (-)R.C.C work of prop M20 having minimum compressive strength (in work test) 200kg/cm2 in 15cm cubes at 28days after mixing and test conducted in accordance with 1.S. 456 and 1.5. 516using 12mm to 20mm size (1/28 to Aȧ) crusher broken hard black granite chips of 20mm size (not to exceed 25%) of approved quality & from approved quarry including hosting, lowering, laying and compacting concrete with vibrator, watering and curing for 28days, cost of rigid and smooth centering & shuttering and finishing to exposed surface smooth providing, grooves or beads wherever necessary as per direction of the Engineer in charge including cost, conveyance, royalties & taxes of all materials and cost of all labour, T&P etc. as required for the work completion in all respects as per direction of Engineer in charge but excluding cost of M.S rod/Tor steel and |
| 5 | Straightening cutting, bending bent up of M.S. rods / Tor steels, including cranking, hooking, welding or jointing the M.S. rods or tor confirming to I.S. 432 (Plain) and 1785 (Tor) steel and binding, tying the grills, hoisting, lowering and placing in proper position required for R.C.C. works including cost, conveyance and taxes of M.S. rods or tor steel and binding wires of 18 to 20 gauge and cost of all labour with all T&P required for the work etc. |
| 6 | Rigid and smooth centering and Shuttering for RCC/CC work including false work and dismantlling after casting including cost of all labour, T & Petc all complete as per direction of EIC |
| 7 | Drain Wall |
| 8 | RCC Precast Slab |
| 9 | (-)Providing & laying cement concrete of prop. (1:2:4) in foundation bed and floors using 12mm nominal size down graded, screened, washed hard black crusher broken granite Chips of approved quality & from approved quarry including laying in the layers not exceeding 150 mm thick, hoisting, lowering, laying, watering and curing etc. complete to the required levels including cost, conveyance, royalty and taxes of all materials, cost of all labour, T&P etc as required for the work complete. |
| 10 | (-)Removal of excavated earth and dismantled materials away from the worksite to out site by Mechanical means upto 5Km lead etc all complete as per Idirection of the EIC |
| 11 | Provision of One Display Board Please Enable Macros to View BoQ information |