| 1 | Earth filling from boro pit ordinary soil within the 5 km lead and lift including and depositing the same at work site and spreading the same as per proper level etc. all complete as directed by the Engineer-in-charge. |
| 2 | Earthwork in ordinary soil in excavation of foundation trenches for columns, basement, tie beams, walls and steps in all kinds of soil including moorum, hard stoney earth and earth mixed with boulders except sheet rocks and boulders requiring blasting with all leads and lifts including dressing and leveling the bed sides up to required depth and depositing the excavated materials at places away from the work site with all leads and lifts, T&P for shoring, shuttering, dewatering if required etc. complete as per the drawing, designing including cost of all labour, T&P etc. as required for the work complete as directed by the Engineer-in-charge. |
| 3 | Supplying and filling in foundation and plinth with river Sand in layers including watering and rammed with cost, conveyance and royality of sand etc complete. |
| 4 | Supplying all labour,materials,T&P for Cement Concrete (1:4:8) in foundation using 4 cm size hard granite Hand Broken metal including cost of materials,royalty & conveyance charges with watering,curing all complete as per direction of Engineer-in-charge. |
| 5 | Providing & laying cement concrete of prop. (1:2:4) in foundation bed and floors using 12mm nominal size down graded, screened, washed hard black crusher broken granite Chips of approved quality & from approved quarry including laying in the layers not exceeding 150 mm thick, hoisting, lowering, laying, watering and curing etc. complete to the required levels including cost, conveyance, royalty and taxes of all materials, cost of all labour, T&P etc. as required for the work complete and as per direction of Engineer-in-charge. |
| 6 | Rigid smooth centring and shuttering for R.C.C. works including false work and dismantling then after casting including cost of materials all complete.(R.C.C. Foundation, Plinth Band, Footings, Column Base, Mass Concrete & Precast Slabs ) |
| 7 | Providing & laying of concrete paver block (80cm thick) of different size M-40 grade of concrete over 50mm thick compacted sand layer including cost, conveyance & royalty of all materials etc. |
| 8 | Supplying, Fitting & fixing Cement Concrete Bnech at the side Play Ground including cost, conveyance & royalty of all materials etc.(Four Seater Concrete Chair) |
| 9 | Supplying , Fitting & Fixing Transporancy Board Please Enable Macros to View BoQ information |