| 1 | Excavating in trenches, not exceeding 1.5 m wide and not exceeding 1.5 m in depth; for foundation, etc. or for shafts, wells, cesspits, manholes, pier holes, cable, pipes etc. not exceeding 10 sqm on plan and not exceeding 1.5 m in depth and getting out in Soft/ Loose soil complete all as specified and as directed by Engineer-in- charge. |
| 2 | Returning, filling in, including spreading, leveling, watering and well ramming in layers not exc 25cm thick, in any type of soil complete all as spefied and as directed by Engineer-in-Charge. |
| 3 | Removing excavated material/soils to a distance not exceeding 50 mtr and depositing where directed at a level not exc.1.5 mtr above the starting point, complete all as spefied and as directed by Engineer-in-Charge. |
| 4 | Dismantling/taking out old rusted / blocked /corroded, unsvervicable GI/CI pipe line laid in trenches / fixed to walls and ceilings or laid in floors with complete fittings of following sizes of bores mentioed under respective serial item nos.4.01 ,4.02,4.03,4.04,4.05,4.06,4.07,4.08 & 4.09 of Schedule 'A' BoQNotes:(a) Earth work such as excavation, returning filling and removal for pipe line shall be measured and paid for separately under relevant items of Schedule 'A' BoQ.(b) Where old and new pipe lines are laid/relaid along the same alignment/location, earth work such as excavation, returning filling and removal shall be measured and paid only once. No duplicate measurement shall be admissible on this account. |
| 5 | Cast Iron pipe and GI pipe of 200 mm bore |
| 6 | Cast Iron pipe and GI pipe of 150 mm bore |
| 7 | Cast Iron pipe and GI pipe of 100 mm bore |
| 8 | Cast Iron pipe and GI pipe of 80 mm bore |
| 9 | GI pipe 50mm bore |
| 10 | GI pipe 40mm bore |
| 11 | GI pipe 25mm bore |
| 12 | GI pipe 20mm bore |
| 13 | GI pipe 15mm bore |
| 14 | Fixing and Testing only Cast Iron pipes ( retrived from serial item .4.01 ,4.02,4.03 & 4.04 here-in- before ) after removing rust and corrosion by thoroughly cleaning the surface of pipes with emery paper,and jointing with spun yarn/hemp and molten lead caulked joints (or approved rubber ring joints, wherever applicable) laid in trenches, for the following sizes/bores as mentioned under respective Serial Item Nos. 5.01, 5.02, 5.03 & 5.04 of Schedule 'A' BoQ complete all as specified and directed by the Engineer-in-Charge.Note: 1. The rate of removing rust and corrosion by throughly cleaning the surface of pipe with emery paper of old servicable pipes is included in this item and nothing shall be paid extra on this account.2. The rate for fixing of cast iron Pipes with spun yarn/hemp and molten lead caulked joints (or approved rubber ring joints, wherever applicable) is included in this item . Contractor shall quote his rate accordingly.Nothing shall be paid extra on this account.3. Cast Iron specials fittings of the pipes shall be measured and paid for separately under appropriate item of Schedule `A' BoQ.4 Earth work such as excavation, returning filling and removal for pipe line shall be measured and paid for separately under relevant items of Schedule 'A' BoQ.5. Where old and new pipe lines are laid/relaid along the same alignment/location, earth work such as excavation, returning filling and removal shall be measured and paid only once. No duplicate measurement shall be admissible on this account. |
| 15 | Cast Iron pipe of 200 mm bore |
| 16 | Cast Iron pipe of 150 mm bore |
| 17 | Cast Iron pipe of 100 mm bore |
| 18 | Cast Iron pipe and GI pipe of 80 mm bore Please Enable Macros to View BoQ information |
| 19 | Cast Iron pipe and GI pipe of 80 mm bore Please Enable Macros to View BoQ information |