| 1 | Safe cartage of centralised Material from central store to Work Site (Including Loading, Unloading in all Respect) |
| 2 | PCC Pole of 8.5/9 Mtr. |
| 3 | PCC Pole of 11 Mtr. |
| 4 | 250 KVA Transformer |
| 5 | Centeral Material |
| 6 | LT AB Cable(3x120+1x95+1x16) SQ MM |
| 7 | ABC(3x95+1x70+1x16)/ (3x50+1x35+1x16) |
| 8 | LT PVC Cable Al 1x240 Sq mm |
| 9 | LT PVC Cable Al 1x400 Sq mm |
| 10 | LT PVC Cable Al 1x630 Sq mm |
| 11 | LT PVC Lead 1x240/1x400Sq mm |
| 12 | Construction of Plinth in all respect According RESPO Norms of size 2x2x1.5 m (All required Decentralized material will be Provided by contractor for Construction of Plinth) |
| 13 | Installation of 250 KVA T/F on Plinth in all respect and energize after complete all work as RESPO Norms.(All required Decentralized material will be Provided by contractor) |
| 14 | According RESPO Norms laying LT AB Cable, mounting on Pole and Tying work Properly.(All required Decentralized material will be Provided by contractor) |
| 15 | Digging a pit and Placed 11 mtr PCC Pole in it with Instalation all Line Items, Properly Grouting of Pole and energized line.(Decentralized Item As Nut Bolt, Clamp, F Brackets, Stone pad and Material for grouting will be provide by Contractor) |
| 16 | Digging and Erection 8.5/9 Mtr PCC pole with grauting, earthing and Complete work as per RESPO Norms Including all of accessories (Decentralized Item As Clamp,Nut bolt Angel, Chanal etc will be provide by Contractor) |
| 17 | Installation of 3 Phase Distribution Box (Decentralized Item will be provide by Contractor) |
| 18 | Open Jar Jar Rabit/ Weasal/ABC from Pole, Lay down and collect safly |
| 19 | Work of Spread ABC, mounting and tying the wire on the pole with installation of all necessary line Item properly as RESPO Norms. (Decentralized Item As Nut Bolt, ALL Type Clamp, J huk, Angel will be provide by Contractor) |
| 20 | Work of Spread Wiseal, mounting and tying the wire on the pole with installation of all necessary line Item properly as RESPO Norms (Decentralized Item As Nut Bolt, Clamp will be provide by Contractor) |
| 21 | Weasal |
| 22 | Work of Plinth Repairing with Put TF on Safe Side with enerzation and After Mantinance of Plinth Put TF on Repaired Pinth and Enerzied (All required Decentralized material will be Provided by contractor for Construction of Plinth) |
| 23 | Paint work on Angale & Chanal As RESPO Norma |
| 24 | Chemical Earthing work as per requirment of Site & RESPO Norms Including all of accessories (All required Decentralized material will be Provided by contractor for Earthing) |
| 25 | Water Level Earthing work as per requirment of Site & RESPO Norms Including all of accessories (All required Decentralized material will be Provided by contractor for Earthing) |
| 26 | According RESPO Norms Instalation Stay Set |
| 27 | Work for Concerting of Stay (All Item As Cement, Sand etc for Concreting will be provided by Contractor) |
| 28 | According RESPO Norms Installation of danger board on pole(All required Decentralized material will be Provided by contractor) |
| 29 | According RESPO Norms Installation of barbed wire on pole(All required Decentralized material will be Provided by contractor) |
| 30 | According RESPO Norms Instalation 11 KV Fuse Set (All required Decentralized material as Nut bolt, Clamp, Chanal will be Provided by contractor for Fuse Set) |
| 31 | According RESPO Norms Wire Mesh Fencing size of 2x2x1.5 for Distributan T/F (All required Decentralized material will be Provided by contractor for Fancing) |
| 32 | According RESPO Norms for Safty of 250KVA T/F Instalation of Tell Less Unit with Structure In LT Side of T/F.(All required Decentralized material will be Provided by contractor for Tell Less Unit) |
| 33 | Work for Earthing of Pole With MS Earthing Road |
| 34 | Received Back Old/Damaged Material from Site to Store (Including Loading, Unloading, Cartage in all respect) |
| 35 | 100 KVA TF |
| 36 | Receive Back of ABC |
| 37 | Conducter Wire Please Enable Macros to View BoQ information |