| 1 | Dismantaling of building |
| 2 | Clearing and grubbing road land including oprooting wild vegetation, grass, bushes, shrubs, sapling and trees of girth up to 300mm, removai of stumps of such trees cut earlier and disposal of unserviceable materials and stacking of serviceable to be used or auctioned up to a lead of 1000m including removal and disposal of top prganic soil not exceeding 150 mm in thickness as Technical Specification Clause 201 |
| 3 | Excavation in foundation in black cotton /kanker mixed soil including filling lift up to 1.50 m and lead up tto 30 m & including filling, watering and ramming of excavated each in to trenchs or into space between the building and the side of foundation trenchs or plinth and removal and disposal of surplus earth as directed by the Engineer -in-charge up to a distance of 30 m from the foundation trenches including all T&P phowarah and basked etc complete S I N0 252 |
| 4 | cement concrete with 4 cm, gauge approved stone ballast, approved coarse sand and cement in the proportion of 8:4:1 including supply of all material, labour and T&P etc, required for proper completion S I N0 281 |
| 5 | R.C.R.Stone masonary work in 1:4 cementt coarse sand mortar including all material labour t&p etc compt up to plinth |
| 6 | E/Work in cutting or embankment in mixed soil /black cotton soil , excavation to be in the from or regular pits not exceeding 0.50 m in depth and earth work in embankment to be in 20 cm layer, including ramming & dressing the surface to required llevels and slopes and also including lift up to 1.50 m and lead up to 30 m The earth cutting to be used in making embankment or to be deposited as spoil by the banks within 30 m distance as directed by Engineer -in -charg S I N0 253 |
| 7 | Supply and laying of Local sand filling |
| 8 | Proving and injecting chemical for pre constructional anti termite treatment and creating chemical barrier around and under the coloumn pits ,wall trenches, base ment excavation,top surface if plinth filling, junction of wall and floor , along the external perimeter of binding ,expansion joints surrounding of pipes and conduit etccomplete( plinth area of the building at ground floor ony shall be measured as per IS 6313 PART II 1981) Aldrine emulsifiable concentrate or any other approved material such as Hepthchlor of Chlordane will be used as per PWD plinth area rate SOR |
| 9 | 1st class brick work in 4:1 fine sand and cement of 1.25 finesness modulus mortar in super structure including supply of all material, labour and tools and plants, required for proper completion of work S I N0 (305) |
| 10 | 1st class brick work in 4:1 fine sand and cement of 1.25 finesness modulus mortar in super structure including supply of all material, labour and tools and plants, required for proper completion of work S I N0 (305+309+310) |
| 11 | RCC work with cement approved coarse sand and 2Cm. Gauge approved stone ballast in the proportion of 1:2:4 in lintels of doors & window excluding including all material labour and T&P etc. as per Sl. No. 283 |
| 12 | RCC work with cement approved coarse sand and 2 cm gauge approved stone ballast in proportion of 1:1.5:3 in slab excluding its fixing snd binding the same with 24B.G.G.I.binding wire and including necessary centering and shuttering etc. And also including supply of all material required for proper completion of the wor, Binding wire to be supplied by contractor free of cost S I No 284(a) |
| 13 | RCC work with cement approved coarse sand and 2 cm gauge approved stone ballast in proportion of 1:2:4 in lintel fo doors and window excluding its fixing snd binding the same with 24B.G.G.I.binding wire and including necessary centering and shuttering etc. And also including supply of all material required for proper completion of the wor, Binding wire to be supplied by contractor free of cost S I No 285 |
| 14 | RCC work with cement approved coarse sand and 2 cm gauge approved stone ballast in proportion of 1:2:4 in lintel fo doors and window excluding its fixing snd binding the same with 24B.G.G.I.binding wire and including necessary centering and shuttering etc. And also including supply of all material required for proper completion of the wor, Binding wire to be supplied by contractor free of cost S I No 288 |
| 15 | Mild steel iron work in plain work such as reinforced concrete or reinforced brick work (when not includeed in over all rates ) wrought to required shape as necessary including bending , and also including, supply of steel and wastages and overlapping and hooks required for completion of the work S I N0 504 |
| 16 | 12 mm thiick plaster with cement mortar in consisting of 6:1 cement and approved coarse sand of minimum thickness not to be less 10 mm including supply of all materials, labour T&P etc required for proper completion of work S I N0 586+596 |
| 17 | 12 mm thiick plaster with cement mortar in consisting of 6:1 cement and approved coarse sand of minimum thickness not to be less 10 mm including supply of all materials, labour T&P etc required for proper completion of work S I N0 586 |
| 18 | 12mm thick monolythic plaster on roof in 1:3 cement and Coarse sand mortar I/c all material T&P etc. as per Sl. No. 13.1 (1) |
| 19 | Making groovess 10to12 mm wide & 8mm deep in plaster of the wall or ceiling vertically or horizontially as required S I No 598 |
| 20 | Finishing of wall with putty (birla or j &k or equivalent brand )one coat including all material labour t&p etc |
| 21 | Wall painting with (two coat) plastic emulsion paint of firet quality approved brand and manfacture on undecorated wall surface to give an even shade including throughly broushing the surface free from mortar dropping and other foreign matter and sand prepared smooth |
| 22 | Mild steel or iron work in heavy size such as trusses, built up gates, door frame, record racks roof work , gates etc riveting or welding where necessary, and also including supply of steel, bolts, nuts and wastages etc and their fixing required for completion of the work S I N0 503 |
| 23 | Fixing of M.S. Door & Window Chaukat in position excluding cost of all fixtures. New Item 18.14 |
| 24 | Painting or varnishing on iron work in small areas on new wood work with one coat of ready mixed priming paint and two coat of approved superior quality ready mixed paint of clear synthetic varnish including supply of all material, labour and T & P etc required for proper completion of the work Paint to be used should conform to the I.S I.N0 103-1950 S I N0641 642 |
| 25 | S/f of Fan Box as per Sl.No. 18.16 (N.I.) |
| 26 | Cement concrete with20mm gauge stone ballast, approved coarse sand and cement in proportion of 4:2:1 including supply of all materials, labour and T&P etc. Required for proper completion of work S I No 279A |
| 27 | Providing and laying vitrified floor ttiles Kerro brand or equivalent brand of qualitty in different size of approved make in colour & shade laid on 20 mm thick cement mortar 1:4 ( 1 cement 4 coarse sand )including grouting the joints with white cement and pigment etc complete ( size of tiles 600x600 mm) CPWD11:41:1 |
| 28 | Supply and fixing of mosquito proof jali having 5 mesh each cm. Made of 24 B.W.G wire heavy quality and including cost of 25x5 mm. flat iron around the jali , welding etc complte NS2 |
| 29 | Providing & fixing mineral fiber false ceiling as per DSR 26:27:2 |
| 30 | Providing & fixing wall pvc in hall (MR) |
| 31 | Sign Board |
| 32 | Add Electrifiction work 12% of Cost |
| 33 | Add Plumbring work 8% of Cost |
| 34 | Add Furnitur work 12% of Cost |
| 35 | Add 18% GST Please Enable Macros to View BoQ information |