| 1 | Boring of 30cm dia piles of single under reamed of 50cm dia of bulb and 3.5 metre depth in black cotton soil with hand operated auger machine including all labour T&P etc. for proper completion of work. |
| 2 | R.C.C. work in Pile Foundation in 1:2:4 cement, sand and 20mm mortar including supply of all materials, labour and T&P etc. required for proper completion of work as per E/I |
| 3 | S/F M.S. Square Pipe 50x50x5mm Including S/o material, including All complition of work |
| 4 | Supply and fixing Galvanized corrugated iron roofing 24 B.W.C. in position including supply of materials, labour and tools and plants etc. required for proper completion of the work and including wastage.S.I. No 536 |
| 5 | Supplying and fixing 22 B.W.G. ridges valley and gutters for iron roofing fixed with J or U 10 mm (3/8\\") dia, with G.I. Umpet and bitumen washers complete including supply of all materials, labour and tools and plants etc. required for proper completion of the work including wastage.SI No.537 |
| 6 | Jungle Cleaning |
| 7 | Earth work in excavation in Foundation in B.C. soil including lead 30m & lift up to 1.52 mtr |
| 8 | Sand Filling in foundation Including supply of all materials, labour T&P etc. |
| 9 | Laying C.C. with 1:4:8 cement sand & 40mm gauge S.S.B. |
| 10 | R.C.C. work with 1:1.5:3 cement sand & 20mm G.S.B. Column above P.L. to Top |
| 11 | Class-150 brick work 1:4 with cement, sand, mortar.Including supply of all materials, labour T&P etc. |
| 12 | Class-150 brick work 1:6 with cement, sand, mortar.Including supply of all materials, labour T&P etc. |
| 13 | R.C.C. work with 1:2:4 cement sand & 20mm G.S.B. Plinth Beam. |
| 14 | R.C.C. work with 1:2:4 cement sand & 20mm G.S.B. Lintle Beam. |
| 15 | PCC Work in flooring in 1:2:4 with cement, sand and 20 mm gauge, stone grit. Including supply of all materials, labour T&P etc. |
| 16 | 12mm thick plaster in 1:4 cement sand mortar. |
| 17 | R.C.C. work with 1:2:4 cement sand & 20mm G.S.B. in Slab |
| 18 | M.S. Work such as plain R.C.C. wrough to required necessary shape, cutting, bending & Binding etc. |
| 19 | Distempering two coat over one priming coat complete |
| 20 | M.S. Iron Sheet Shutters,Door,Window and Gate |
| 21 | Painting tow coat over one priming coat |
| 22 | Earth work in Filling,cartge by Tractor Trolly Complete |
| 23 | Providing and laying of Rubble moulded Zig - Zag Interlocking concrete block pavements having tickness 800 as per drawings and Techical specification clause 1504 Please Enable Macros to View BoQ information |