Tender Brief Bids Are invited for Operation And Maintenance Power House / Power Plant - Biannual Maintenance Contract For All Maintenance Activities In Electrical Maintenance Department At Rgppl- Site(2026-28) - Preventive Maintenance Of All Type Ht-Motors. , Ir-
City Ratnagiri
State Maharashtra
Document Fees Refer document
EMD INR 500000.0 /-
Tender Value INR 5.10 Crore /-
Tender Type Tender
Bidding Type Open Tender
Competition Type Indian

Tender Details

Bids Are invited for Operation And Maintenance Power House / Power Plant - Biannual Maintenance Contract For All Maintenance Activities In Electrical Maintenance Department At Rgppl- Site(2026-28) - Preventive Maintenance Of All Type Ht-Motors. , Ir-Checking Of All Type Ht-Motors. , Trouble-Shooting And Maintenance Of All Type Ht-Motors. , No-Load/Load Trial Of All Type Ht-Motors/Transformers. , Re-Greasing And Lube Oil Top-Up Of Both Side Bearings Of All Type Ht-Motors. , Lube Oil S Ling Of One Side Bearing Of All Type Ht-Motors. , Removal/Re-Fixing Of All Cable Terminals Of All Type Ht-Motors. , Maintenance And Repairing Of Power Cable Terminal Box/Heat Exchanger (Cooler)/Cooling Fan/Fan Enclos , Removal Of All Type Ht-Motors From Foundation. , Re-Fixing And Commissioning Of All Type Ht-Motors On Foundation. , Removal/Re-Fixing Of Heat Exchanger (Cooler)/Cooling Fan With Enclosure/Power Cable Terminal Box Of , De/Nde-Side Bearing/Water Cooler Replacement Of All Type Ht-Motors. , Preventive Maintenance Of Vacuum Circuit Breaker/Air Break Switch Including Complete Cubicle Section , Preventive Maintenance Of One Horizontal Bus-Bar Section Of Ht-Switchgears Except Vcbs , Trouble-Shooting And Maintenance Of All Type Ht-Switchgears. , Replacement Of Vcb/Air Break Switch/C.T./P.T. Of Ht-Switchgearsincluding Shifting Within Plant , Servicing Of Vacuum Circuit Breaker/Air Break Switch Including Complete Cubicle Section/Complete T.B , Preventive Maintenance Of All Type Lt-Motors Upto 30 Kw Rating. , Preventive Maintenance Of All Type Lt-Motors Above 30 Kw To 100 Kw Rating. , Preventive Maintenance Of All Type Lt-Motors Above 100 Kw To 200 Kw Rating. , Ir-Checking Of All Type Lt-Motors. , Trouble-Shooting And Maintenance Of All Type Lt-Motors. , No-Load/Load Trial Of All Type Lt-Motors. , Re-Greasing/Lube Oil Top-Up Of Both Side Bearings Of All Type Lt-Motors Upto 30 Kw Rating. , Re-Greasing/Lube Oil Top-Up Of Both Side Bearings Of All Type Lt-Motorsabove 30Kw To 200Kw Rating. , Removal/Re-Fixing Of All Cable Terminals Of All Type Lt-Motors Upto 30 Kw Rating. , Removal/Re-Fixing Of All Cable Terminals Of All Type Lt-Motors Above 30 Kw To 200 Kw Rating. , Maintenance/Replacement Of Cooling Fan/Fan Cover/Power Cable Terminal Box Of All Type Lt-Motors Upt , Maintenance/Replacement Of Cooling Fan/Fan Cover/Power Cable Terminal Box Of All Type Lt-Motors Abo , Removing Of All Type Lt-Motors From Foundation And Transporting From Location To Anywhere Within The , Removing Of All Type Lt-Motors From Foundation And Transporting From Location To Anywhere Within The , Removing Of All Type Lt-Motors From Foundation And Transporting From Location To Anywhere Within The , Re-Fixing And Commissioning Of All Type Lt-Motors On Foundation Including Transportation From Anywh , Re-Fixing And Commissioning Of Lt-Motors On Foundation Above 30 Kw To100 Kw Rating. , Re-Fixing And Commissioning Of Lt-Motors On Foundationabove 100 Kw To200 Kw Rating. , Overhauling Of All Type Horizontal/Vertical Lt-Motors Upto 3.0 Kw Rating. , Overhauling Of All Type Horizontal/Vertical Lt-Motors Above 3.0 Kw To 10 Kw Rating. , Overhauling Of All Type Horizontal/Vertical Lt-Motors Above 10 Kw To 50 Kw Rating. , Overhauling Of All Type Horizontal/Vertical Lt-Motors Above 50 Kw To 100 Kw Rating. , Overhauling Of All Type Horizontal/Vertical Lt-Motors Above 100 Kw To 200 Kw Rating. , Preventive Maintenance Of One Starter Module Including Complete Cubicle Section Of Lt-Mcc. , Preventive Maintenance Of Air Circuit Breaker Including Complete Cubicle Section Of Lt-Switchgears. , Pm Of One Bus-Bar Section Of Lt-Switchgears/Mcc Except Acbs/Starter Modules , Trouble-Shooting And Maintenance Of Lt-Switchgears/Mcc. , Replacement Of One Complete Starter Module Of Lt-Mcc. , Replacement Of Acb Of Lt-Switchgear Including Loading Unloading & Shifting Within The Plant Area. , Servicing Of One Complete Starter Module Of Lt-Mcc. , Servicing Of Air Circuit Breaker Including Complete Cubicle Section Of Lt-Switchgears. , New Electrical Panel Designing Assemblingcontrol Wiring Etc Of Panel Upto 1.0 Mtr X 2.0 Mtrs. , Electrical Insulating Mat Replacement Thickness: 3.0Mm Width: 1.0 Mtr. , Reading Measurement (Current Voltage Power Etc) Of Any Equipment Of Switchgear/Motor/Mcc Etc. , Replacement/New Electrical Panel Installation & Commissioning Etc.Of Size Upto 1.0 Mtr X 2.0 Mtrs. , Preventive Maintenance Of All Type Transformers Upto 4.0 Mva Rating Including All Accessories. , Preventive Maint. Of All Type Transformers Above 4Mva To 40 Mva Rating Including All Accessories. , Preventive Maint. Of All Type Transformers Above 40Mva To 400 Mva Rating Including All Accessories. , Trouble-Shooting And Maintenance Of All Type Transformers Upto 400 Mva Rating. , Removal/Re-Fixing Of Hv Lv & Neutral Connections Of All Type Transformers Upto 4.0 Mva Rating. , Removal/Re-Fixing Of Hv Lv & Neutral Connections Of All Type Transformers Above 4.0 Mva To 40 Mva R , Removal/Re-Fixing Of Hvlv & Neutral Connections Of All Type Transformers Above 40Mva To 400Mva Rati , Replacement Of Silicagel/Silicagel Breather/Surge Counter/Regeneration Of Silicagel Etc Of All Type , Protections And Interlocks Checking Of All Type Transformer Upto 40 Mva Rating. , Protections And Interlocks Checking Of All Type Transformer Above 40 Mva To 400 Mva Rating. , Testing Arrangement Including Assistance Required For Testing Of All Type Transformer Upto 4.0 Mva R , Testing Arrangement Including Assistance Required For Testing Of All Type Transformer Above 4.0 Mva , Testing Arrangement Including Assistance Required For Testing Of All Type Transformer Above 40 Mva T , Routine-Checking Including Thermography Of Gsu Uat & Sst Transformers. , Shifting Of Filter Machine/Oil Storage Tank/Bushing Stand/Transformer Bushing/L.A./Transformer Coole , Maintenance And Repairing Of Oil Filtration Machine/Oil Storage Tank/Platform Truck. , Transformer Oil S Le Collections Including Packing/Bdv-Testing In Em-Lab. , Transportation Of Transformer Oil S Le Bottles From Rgppl-Site To R&D (Netra)-Noida. , Transportation Of Transformer Oil S Le Bottles From R&D (Netra)-Noida To Rgppl-Site. , Transportation Of Testing Instrument/Oil S Le/Other Material Up To 25Kg Weight From Rgppl-Site To , Transportation Of Testing Instrument/Oil S Le/Other Material Up To 25Kg Weight From Mumbai/Pune/Ko , Oil Filtration Of All Type Transformer Upto 4.0 Mva Rating. , Oil Filtration Of All Type Transformer Above 4.0 Mva To 40 Mva Rating. , Oil Filtration Of All Type Transformer Above 40 Mva To 400 Mva Rating. , Oil Top-Up Including Filtration (Upto 2.0 Kl Qty) Of All Type Transformer. , Dismantling And Removing Of Distribution Transformers Upto 2.0 Mva Rating/Transformer Ngr Anywhere W , Installation And Commissioning Of Distribution Transformers Upto 2.0 Mva Rating/Transformer Ngr Anyw , Overhauling Of Distribution Transformers Upto 2.0 Mva Rating. , Preventive Maintenance Of All 3 Poles Of Circuit Breaker/Isolator With Earth-Switch Of Switchyard. , Preventive Maintenance Of All Three Poles Of C.T./ C.V.T./L.A./Bushings/ Wavetrap Of Switchyard & Tr , Preventive Maintenance Of All Type Marshalling Box/Control Panels/Air Compressors Of Switchyard. , Trouble-Shooting And Maintenance Of Control Circuit And Any Equipments Of Switchyard. , Routine Checking Including Thermography Of All Equipments Of Switchyard. , Sf6/N2 Gas Topping-Up In One Circuit Breaker Pole Of Switchyard & Transformer. , Alignment Of All Three Poles Isolator Of Switchyard. , Alignment Of All Three Poles Earthswitch Of Switchyard. , Removing & Dismantling Of One Pole Of Cb(Sf6)/Isolator With Earth Switch/Wavetrap/Ct/Cvt/La/Bushing , Refixing/New Erection&Commissioning Of Cb(Sf6) One Pole/ Isolator With Es/Wavetrap/Ct/Cvt/La/Bushing , Testing Arrangementassistance For Testing Of All 3 Poles Of Cb/Ct/Cvt/La/Isolator/Es/Wavetrap Etc. , Maintenance Of All Type Of Earth Pit , Earth Resistance Measurement Of All Electrical Equipments Of Plant & Bop Area. , Assistance/Support Service Required During Unit Start-Up/Shut-Down. , Replacement & Commissioning Of Air Compressor Assembly Of Switchyard Circuit Breaker. , Overhauling Of All Type Pneumatic Drive Of 400Kv Switchyard Circuit Breaker. , Overhauling Of One Pole Of All Type Isolator With Earth Switch Of Switchyard. , Overhauling Complete One Pole Of All Type Circuit Breaker Of Switchyard. , Preventive Maintenance Of Generator Upto 360 Mva Rating. , Pm Of All Three Phase Complete Busduct From Generator To Transformer Upto 15.75 Kv Rating. , Preventive Maintenance Of Bac Cubicle Compartments (Lci Excitation & Pt Complete Cubicles). , Pm Of Complete Cubicle Compartments Of Ppt-Transformer/89 Ss-Air Break Switch/Dc-Link Reactor Etc. , Ir-Checking Of Generator Busduct Lci Excitation & Accessories. , Trouble-Shooting And Maintenance Of Control Circuit And Any Equipment Generator And Accessories. , Routine Checking Of Lci Excitation Ppt-Fan & Cooling System Of Bac-Compartment. , Generator Line-Up For Air/Co2/Hydrogen Filling. , Replacement Of Carbon Brush/Brush Holder/Hydrogen Regulator Etc. , Removal Of Flexible Links Star Point Bus-Bar And Ngr Connections Of Generator. , Testing Arrangement Including Assistance Required For Testing Of Generator Busduct & Accessories. , Replacement Of Generator Neutral Connection Protection Ct/La/Flexible C Links/Ngr/Phe (Lci) Etc. , Testing Arrangement Including Assistance Required During Testing & Calibration , Trouble-Shooting And Maintenance Of Relay/Cards/Meters/Transducers/Abt-System/Ct/Pt Etc. , Replacement And Modification Of Relay/Cards/Meters/Transducers/Abt-System/Ct/Pt Etc. , Pm Of Lead Acid Type Complete Battery Bank (Rating From 125 Volts To 250 Volts/300 Ah To 1700 Ah). , Preventive Maintenance Of All Type Battery Charger/Distribuation Panel (Dc/Ac). , Trouble-Shooting And Maintenance Of Battery Charger/Battery Bank/Distribution Panel (Dc/Ac). , Routine Checking Of All Type Battery Banks And Chargers. , Lead Acid Battery Bank Replacementcommissioning &Testingrating 125 V To250 V/300 Ah To1700 Ah. , One Cell Replacementcommissioning & Testing Of La Battery Bank (125 V To250 V /300 Ah To 1700 Ah) , Replacementcommissioning & Testing Of Battery Charger Incl. Loading Unloading & Transportation. , Discharge Test Of All Type Complete Battery Bank Of Rating Upto 250 Volts/1700 Ah). , Shifting Of Scrap Battery/Acid Can Min.10 Nos Acid Can Of 40 Ltrs/20 Nos Vrla//Alkaline Batteries , Assistance/Support Services Required During Inspection Testing And Maintenance Of Equipments , Pm Of Complete Electrical System Of Eot/Gantry Crane Capacity Rating Upto 100 Tons. , Preventive Maintenance Of Complete Electric Hoists Unit Capacity Rating 2X35 Tons. , Troubleshooting And Maint. Of Electrical System Of Eot/Gantry Crane Electric Hoists & Stack-Lift. , Maintenance & Repairing/Replacement Of Control Panel/Resistance Box/Control Transformer/Motor Etc. , Arrangement Including Assistance Required For Load Testing Of Electric Hoists Unit (35 Tons) , Trouble-Shooting And Maintenance Of Overhead Distribution Lines. , Replacement Of All Type Insulators/Cl S/L.A. Etc Of Overhead Distribution Lines. , Replacement/New Installation Of Complete Kiosk Panel/G.O.D/Fuse Assembly Etc Of Oh Lines. , Removing/Laying Of Conductor Earth Wire Guard Wire Etc Of Overhead Distribution Lines. , Temporary Laying/Removing Of All Type Cables Including Shifting Cable Size Upto 50 Sq.Mm. , Temporary Laying/Removing Of All Type Cables Including Shifting Cable Size Above 50 To 120 Sq.Mm. , Permanent Laying Of Cables On Cable Tray Wall & Structure Etc.Cable Size Upto 50 Sq.Mm. , Permanent Laying Of Cables On Cable Tray Wall & Structure Etc.Cable Size Above 50 To 120 Sq.Mm. , Permanent Laying Of Single Core Cables On Cable Traywall & Structure Etc.Size > 120 To <240 Sqmm , Permanent Laying Of Single Core Cables On Cable Tray Wall & Structure Etc.Cable Size > 240 Sq.Mm. , Permanent Laying Of 3/4 Cores Cables On Cable Tray Wall & Structure Etc.Size > 120 To <240 Sqmm , Permanent Laying Of 3/4 Cores Cables On Cable Tray Wall & Structure Etc. Size Above 240 Sqmm , One End Lugging/Jointing Of All Type Lt-Cables (All Cores) Cable Size Upto 50 Sq.Mm. , One End Lugging/Jointing Of All Type Lt-Cables (All Cores) Cable Size Above 50 To 120 Sq.Mm. , One End Lugging/Jointing Of All Type Lt-Cables (All Cores) Cable Size Above 120 Sq.Mm. , Single Core Heat Shrinkable Cables Termination/Through Jointing Of Cables Size Upto 120 Sq.Mm. , Single Core Heat Shrinkable Cables Termination/Through Jointing Of Cablessize Above 120 To240 Sqmm , Single Core Heat Shrinkable Cables Termination/Straight Through Jointing Of Cables Above 240 Sqmm , Outer Insulation Repairing Of Cables From Heat Shrinkable Tubing/Sleeves (1Mtr Length). , Laying/Removing/Repairing Of Cable Tray( Above 0.5 Ft X 2.0 Ft) /Conduit Pipe(Above Dia:3 Inch) , Laying/Removing/Repairing Of Cable Tray( Upto 0.5 Ft X 2.0 Ft)/Conduit Pipe(Upto 3.0 Inch Dia.) , Earthing Strip Laying Or Removing Including Drilling Welding Jointing Cutting Etc. , Preventive Maintenance Of All Type Lighting Transformers/Lighting Distribution Panels. , Maintenance/Replacement Of Industrial Pole Lighting Fixture Upto 30 Feets Height , Maintenance/Replacement Of All Type Industrial Lighting Fixture. , Maintenance/Replacement/Servicing Of All Type Cooling Fans/Exhaust Fan Etc. , Maintenance/Replacement Of High Mast/Hrsg-Stacks Aviation Lighting Fixture. , Trouble-Shooting And Maintenance Of All Type Lighting/Cooling Fans/Lighting Transformers Etc. , Replacement/New Erection & Commissioning Of Lighting Pole With All Accessoriesheight Upto 15 Fts. , Replacement/New Erection & Commissioning Of Lighting Pole With Pole Height Above 15 To 30 Feets. , Maintenance/Replacement Of Lighting Pole Junction Box/Sdfu/Dol-Starter Etc. , Maintenance/Replacement Of All Type Mcb/Rccb/Elcb/Timer Etc. , Maintenance/Replacement Of Domestic Lighting System/Electrical Appliances , Revival Of One Room Complete Lighting System Of Any Buildings In Plant & Bop Area. , Arrangement Of Temporary Lights/Cooling Fans/Cable Connections Etc. , Overhauling Of Ceiling Fans/Table Fans/Exhaust Fans/Geyser Etc. , Preventive Maintenance Of Electrical System Of All Type Skids. , Ir-Checking Of All Type Skids. , Trouble-Shooting And Maintenance Of Electrical System Of All Type Skids. , Installation & Commissioning Of Any Type Complete Skid Anywhere Within The Plant Area. , Preventive Maintenance Of Electrical System Of Edg/Fire Pump. , Trouble-Shooting And Maintenance Of Electrical System Of Edg/Fire Pump. , Replacement Of Dc-Starter/Control Module Of Edg/Fire Pump. , New Fabrication And Erection Works Of Mild Steel Supporting Structure Or Frame At Rgppl-Site. , Providing Welder On Day Basis As Per Work Specifications. , Erection And Dismantling Of Scaffolding As Per Work Specifications. , Tarpaulin And Polythene Sheet Covering Before Monsoon Season/Removing After Monsoon Season. , Shifting Of Any Material From One Location To Other Location In The Plant Area Upto 250 Kg Weight. , Shifting Of Any Material From One Location To Other Location In The Plant Area >250 Kg To < 500Kg , Shifting Of Any Material From One Location To Other Location In The Plant Area >500 Kg To <750 Kg , Shifting Of Any Material From One Location To Other Location In The Plant Area >750 Kg To <1500 Kg , Shifting/Relocation Of Any Material From Inside The Power Block From Eot Cranes Above 1.0 Ton , Oil Drum (210 Ltr)Shifting From One Location To Other Location In The Plant Area. , Shift Electrical Maintenance Activities In Power Block & Bop Area As Per Scope Of Work , Operation Service Of Mobile Hydraulic Industrial Vehicles/Cranes As Per Scope Of Work. , Providing Skilled Workers On Day Basis As Per Scope Of Work. , Store Keeper In Electrical Lab/Store As Per Scope Of Work. , Providing Semiskilled Workers On Day Basis As Per Scope Of Work. , Shift Electrical Maintenance Activities In Township Area (Three Shifts Per Day) As Per Scope Of Work

Key Dates

Publish Date 22-05-2026
Last Date of Bid Submission 13-06-2026
Tender Opening Date 13-06-2026

Contact Information

Company Name Ratnagiri Gas And Power Private Limited
Address 415703,RATNAGIRI GAS AND POWER PRIVATE LTD. Anjanwel (PO), Guhagar Taluk Ratnagiri Dist.

BOQ Items

Sl. No. Item TitleItem Description
1Preventive maintenance of all type HT-motors.Preventive maintenance of all type HT-motors.
2IR-checking of all type HT-motors.IR-checking of all type HT-motors.
3Trouble-shooting and maintenance of all type HT-motors.Trouble-shooting and maintenance of all type HT-motors.
4No-load/load trial of all type HT-motors/transformers.No-load/load trial of all type HT-motors/transformers.
5Re-greasing and lube oil top-up of both side bearings of all type HT-motors.Re-greasing and lube oil top-up of both side bearings of all type HT-motors.
6Lube oil sampling of one side bearing of all type HT-motors.Lube oil sampling of one side bearing of all type HT-motors.
7Removal/re-fixing of all cable terminals of all type HT-motors.Removal/re-fixing of all cable terminals of all type HT-motors.
8Maintenance and repairing of power cable terminal box/heat exchanger (cooler)/cooling fan/fan enclosMaintenance and repairing of power cable terminal box/heat exchanger (cooler)/cooling fan/fan enclos
9Removal of all type HT-motors from foundation.Removal of all type HT-motors from foundation.
10Re-fixing and commissioning of all type HT-motors on foundation.Re-fixing and commissioning of all type HT-motors on foundation.
11Removal/re-fixing of heat exchanger (cooler)/cooling fan with enclosure/power cable terminal box ofRemoval/re-fixing of heat exchanger (cooler)/cooling fan with enclosure/power cable terminal box of
12DE/NDE-side bearing/water cooler replacement of all type HT-motors.DE/NDE-side bearing/water cooler replacement of all type HT-motors.
13Preventive maintenance of vacuum circuit breaker/air break switch including complete cubicle sectionPreventive maintenance of vacuum circuit breaker/air break switch including complete cubicle section
14Preventive maintenance of one horizontal bus-bar section of HT-switchgears except VCBsPreventive maintenance of one horizontal bus-bar section of HT-switchgears except VCBs
15Trouble-shooting and maintenance of all type HT-switchgears.Trouble-shooting and maintenance of all type HT-switchgears.
16Replacement of VCB/air break switch/C.T./P.T. of HT-switchgearsincluding shifting within plantReplacement of VCB/air break switch/C.T./P.T. of HT-switchgearsincluding shifting within plant
17Servicing of vacuum circuit breaker/air break switch including complete cubicle section/complete T.BServicing of vacuum circuit breaker/air break switch including complete cubicle section/complete T.B
18Preventive maintenance of all type LT-motors upto 30 kW rating.Preventive maintenance of all type LT-motors upto 30 kW rating.
19Preventive maintenance of all type LT-motors above 30 kW to 100 kW rating.Preventive maintenance of all type LT-motors above 30 kW to 100 kW rating.
20Preventive maintenance of all type LT-motors above 100 kW to 200 kW rating.Preventive maintenance of all type LT-motors above 100 kW to 200 kW rating.
21IR-checking of all type LT-motors.IR-checking of all type LT-motors.
22Trouble-shooting and maintenance of all type LT-motors.Trouble-shooting and maintenance of all type LT-motors.
23No-Load/Load trial of all type LT-motors.No-Load/Load trial of all type LT-motors.
24Re-greasing/lube oil top-up of both side bearings of all type LT-motors upto 30 kW rating.Re-greasing/lube oil top-up of both side bearings of all type LT-motors upto 30 kW rating.
25Re-greasing/lube oil top-up of both side bearings of all type LT-motorsabove 30kW to 200kW rating.Re-greasing/lube oil top-up of both side bearings of all type LT-motorsabove 30kW to 200kW rating.
26Removal/re-fixing of all cable terminals of all type LT-motors upto 30 kW rating.Removal/re-fixing of all cable terminals of all type LT-motors upto 30 kW rating.
27Removal/re-fixing of all cable terminals of all type LT-motors above 30 kW to 200 kW rating.Removal/re-fixing of all cable terminals of all type LT-motors above 30 kW to 200 kW rating.
28Maintenance/replacement of cooling fan/fan cover/power cable terminal box of all type LT-motors uptMaintenance/replacement of cooling fan/fan cover/power cable terminal box of all type LT-motors upt
29Maintenance/replacement of cooling fan/fan cover/power cable terminal box of all type LT-motors aboMaintenance/replacement of cooling fan/fan cover/power cable terminal box of all type LT-motors abo
30Removing of all type LT-motors from foundation and transporting from location to anywhere within theRemoving of all type LT-motors from foundation and transporting from location to anywhere within the
31Removing of all type LT-motors from foundation and transporting from location to anywhere within theRemoving of all type LT-motors from foundation and transporting from location to anywhere within the
32Removing of all type LT-motors from foundation and transporting from location to anywhere within theRemoving of all type LT-motors from foundation and transporting from location to anywhere within the
33Re-fixing and commissioning of all type LT-motors on foundation including transportation from anywhRe-fixing and commissioning of all type LT-motors on foundation including transportation from anywh
34Re-fixing and commissioning of LT-motors on foundation above 30 kW to100 kW rating.Re-fixing and commissioning of LT-motors on foundation above 30 kW to100 kW rating.
35Re-fixing and commissioning of LT-motors on foundationabove 100 kW to200 kW rating.Re-fixing and commissioning of LT-motors on foundationabove 100 kW to200 kW rating.
36Overhauling of all type horizontal/vertical LT-motors upto 3.0 kW rating.Overhauling of all type horizontal/vertical LT-motors upto 3.0 kW rating.
37Overhauling of all type horizontal/vertical LT-motors above 3.0 kW to 10 kW rating.Overhauling of all type horizontal/vertical LT-motors above 3.0 kW to 10 kW rating.
38Overhauling of all type horizontal/vertical LT-motors above 10 kW to 50 kW rating.Overhauling of all type horizontal/vertical LT-motors above 10 kW to 50 kW rating.
39Overhauling of all type horizontal/vertical LT-motors above 50 kW to 100 kW rating.Overhauling of all type horizontal/vertical LT-motors above 50 kW to 100 kW rating.
40Overhauling of all type horizontal/vertical LT-motors above 100 kW to 200 kW rating.Overhauling of all type horizontal/vertical LT-motors above 100 kW to 200 kW rating.
41Preventive maintenance of one starter module including complete cubicle section of LT-MCC.Preventive maintenance of one starter module including complete cubicle section of LT-MCC.
42Preventive maintenance of air circuit breaker including complete cubicle section of LT-switchgears.Preventive maintenance of air circuit breaker including complete cubicle section of LT-switchgears.
43PM of one bus-bar section of LT-switchgears/MCC except ACBs/starter modulesPM of one bus-bar section of LT-switchgears/MCC except ACBs/starter modules
44Trouble-shooting and maintenance of LT-switchgears/MCC.Trouble-shooting and maintenance of LT-switchgears/MCC.
45Replacement of one complete starter module of LT-MCC.Replacement of one complete starter module of LT-MCC.
46Replacement of ACB of LT-switchgear including loading unloading & shifting within the plant area.Replacement of ACB of LT-switchgear including loading unloading & shifting within the plant area.
47Servicing of one complete starter module of LT-MCC.Servicing of one complete starter module of LT-MCC.
48Servicing of air circuit breaker including complete cubicle section of LT-switchgears.Servicing of air circuit breaker including complete cubicle section of LT-switchgears.
49New electrical panel designing assemblingcontrol wiring etc of panel upto 1.0 mtr X 2.0 mtrs.New electrical panel designing assemblingcontrol wiring etc of panel upto 1.0 mtr X 2.0 mtrs.
50Electrical insulating mat replacement thickness: 3.0mm width: 1.0 mtr.Electrical insulating mat replacement thickness: 3.0mm width: 1.0 mtr.
51Reading measurement (current voltage power etc) of any equipment of switchgear/motor/mcc etc.Reading measurement (current voltage power etc) of any equipment of switchgear/motor/mcc etc.
52Replacement/new electrical panel installation & commissioning etc.of size upto 1.0 mtr X 2.0 mtrs.Replacement/new electrical panel installation & commissioning etc.of size upto 1.0 mtr X 2.0 mtrs.
53Preventive maintenance of all type transformers upto 4.0 MVA rating including all accessories.Preventive maintenance of all type transformers upto 4.0 MVA rating including all accessories.
54Preventive maint. of all type transformers above 4MVA to 40 MVA rating including all accessories.Preventive maint. of all type transformers above 4MVA to 40 MVA rating including all accessories.
55Preventive maint. of all type transformers above 40MVA to 400 MVA rating including all accessories.Preventive maint. of all type transformers above 40MVA to 400 MVA rating including all accessories.
56Trouble-shooting and maintenance of all type transformers upto 400 MVA rating.Trouble-shooting and maintenance of all type transformers upto 400 MVA rating.
57Removal/re-fixing of HV LV & neutral connections of all type transformers upto 4.0 MVA rating.Removal/re-fixing of HV LV & neutral connections of all type transformers upto 4.0 MVA rating.
58Removal/re-fixing of HV LV & neutral connections of all type transformers above 4.0 MVA to 40 MVA rRemoval/re-fixing of HV LV & neutral connections of all type transformers above 4.0 MVA to 40 MVA r
59Removal/re-fixing of HVLV & neutral connections of all type transformers above 40MVA to 400MVA ratiRemoval/re-fixing of HVLV & neutral connections of all type transformers above 40MVA to 400MVA rati
60Replacement of silicagel/silicagel breather/surge counter/regeneration of silicagel etc of all typeReplacement of silicagel/silicagel breather/surge counter/regeneration of silicagel etc of all type
61Protections and interlocks checking of all type transformer upto 40 MVA rating.Protections and interlocks checking of all type transformer upto 40 MVA rating.
62Protections and interlocks checking of all type transformer above 40 MVA to 400 MVA rating.Protections and interlocks checking of all type transformer above 40 MVA to 400 MVA rating.
63Testing arrangement including assistance required for testing of all type transformer upto 4.0 MVA rTesting arrangement including assistance required for testing of all type transformer upto 4.0 MVA r
64Testing arrangement including assistance required for testing of all type transformer above 4.0 MVATesting arrangement including assistance required for testing of all type transformer above 4.0 MVA
65Testing arrangement including assistance required for testing of all type transformer above 40 MVA tTesting arrangement including assistance required for testing of all type transformer above 40 MVA t
66Routine-checking including thermography of GSU UAT & SST transformers.Routine-checking including thermography of GSU UAT & SST transformers.
67Shifting of filter machine/oil storage tank/bushing stand/transformer bushing/L.A./transformer cooleShifting of filter machine/oil storage tank/bushing stand/transformer bushing/L.A./transformer coole
68Maintenance and repairing of oil filtration machine/oil storage tank/platform truck.Maintenance and repairing of oil filtration machine/oil storage tank/platform truck.
69Transformer oil sample collections including packing/BDV-testing in EM-Lab.Transformer oil sample collections including packing/BDV-testing in EM-Lab.
70Transportation of transformer oil sample bottles from RGPPL-site to R&D (Netra)-NOIDA.Transportation of transformer oil sample bottles from RGPPL-site to R&D (Netra)-NOIDA.
71Transportation of transformer oil sample bottles from R&D (Netra)-NOIDA to RGPPL-site.Transportation of transformer oil sample bottles from R&D (Netra)-NOIDA to RGPPL-site.
72Transportation of testing instrument/oil sample/other material up to 25kg weight from RGPPL-site toTransportation of testing instrument/oil sample/other material up to 25kg weight from RGPPL-site to
73Transportation of testing instrument/oil sample/other material up to 25kg weight from Mumbai/Pune/KoTransportation of testing instrument/oil sample/other material up to 25kg weight from Mumbai/Pune/Ko
74Oil filtration of all type transformer upto 4.0 MVA rating.Oil filtration of all type transformer upto 4.0 MVA rating.
75Oil filtration of all type transformer above 4.0 MVA to 40 MVA rating.Oil filtration of all type transformer above 4.0 MVA to 40 MVA rating.
76Oil filtration of all type transformer above 40 MVA to 400 MVA rating.Oil filtration of all type transformer above 40 MVA to 400 MVA rating.
77Oil top-up including filtration (upto 2.0 KL qty) of all type transformer.Oil top-up including filtration (upto 2.0 KL qty) of all type transformer.
78Dismantling and removing of distribution transformers upto 2.0 MVA rating/transformer NGR anywhere wDismantling and removing of distribution transformers upto 2.0 MVA rating/transformer NGR anywhere w
79Installation and commissioning of distribution transformers upto 2.0 MVA rating/transformer NGR anywInstallation and commissioning of distribution transformers upto 2.0 MVA rating/transformer NGR anyw
80Overhauling of distribution transformers upto 2.0 MVA rating.Overhauling of distribution transformers upto 2.0 MVA rating.
81Preventive maintenance of all 3 poles of circuit breaker/isolator with earth-switch of switchyard.Preventive maintenance of all 3 poles of circuit breaker/isolator with earth-switch of switchyard.
82Preventive maintenance of all three poles of C.T./ C.V.T./L.A./bushings/ wavetrap of switchyard & trPreventive maintenance of all three poles of C.T./ C.V.T./L.A./bushings/ wavetrap of switchyard & tr
83Preventive maintenance of all type marshalling box/control panels/air compressors of switchyard.Preventive maintenance of all type marshalling box/control panels/air compressors of switchyard.
84Trouble-shooting and maintenance of control circuit and any equipments of switchyard.Trouble-shooting and maintenance of control circuit and any equipments of switchyard.
85Routine checking including thermography of all equipments of switchyard.Routine checking including thermography of all equipments of switchyard.
86SF6/N2 gas topping-up in one circuit breaker pole of switchyard & transformer.SF6/N2 gas topping-up in one circuit breaker pole of switchyard & transformer.
87Alignment of all three poles isolator of switchyard.Alignment of all three poles isolator of switchyard.
88Alignment of all three poles earthswitch of switchyard.Alignment of all three poles earthswitch of switchyard.
89Removing & dismantling of one pole of CB(SF6)/isolator with earth switch/wavetrap/CT/CVT/LA/bushingRemoving & dismantling of one pole of CB(SF6)/isolator with earth switch/wavetrap/CT/CVT/LA/bushing
90Refixing/new erection&commissioning of CB(SF6) one pole/ isolator with ES/wavetrap/CT/CVT/LA/bushingRefixing/new erection&commissioning of CB(SF6) one pole/ isolator with ES/wavetrap/CT/CVT/LA/bushing
91Testing arrangementassistance for testing of all 3 poles of CB/CT/CVT/LA/isolator/ES/wavetrap etc.Testing arrangementassistance for testing of all 3 poles of CB/CT/CVT/LA/isolator/ES/wavetrap etc.
92Maintenance of all type of earth PitMaintenance of all type of earth Pit
93Earth resistance measurement of all electrical equipments of plant & BOP area.Earth resistance measurement of all electrical equipments of plant & BOP area.
94Assistance/support service required during unit start-up/shut-down.Assistance/support service required during unit start-up/shut-down.
95Replacement & commissioning of air compressor assembly of switchyard circuit breaker.Replacement & commissioning of air compressor assembly of switchyard circuit breaker.
96Overhauling of all type pneumatic drive of 400kV switchyard circuit breaker.Overhauling of all type pneumatic drive of 400kV switchyard circuit breaker.
97Overhauling of one pole of all type isolator with earth switch of switchyard.Overhauling of one pole of all type isolator with earth switch of switchyard.
98Overhauling complete one pole of all type circuit breaker of switchyard.Overhauling complete one pole of all type circuit breaker of switchyard.
99Preventive maintenance of generator upto 360 MVA rating.Preventive maintenance of generator upto 360 MVA rating.
100PM of all three phase complete busduct from generator to transformer upto 15.75 kV rating.PM of all three phase complete busduct from generator to transformer upto 15.75 kV rating.
101Preventive maintenance of BAC cubicle compartments (LCI excitation & PT complete cubicles).Preventive maintenance of BAC cubicle compartments (LCI excitation & PT complete cubicles).
102PM of complete cubicle compartments of PPT-transformer/89 SS-air break switch/DC-link reactor etc.PM of complete cubicle compartments of PPT-transformer/89 SS-air break switch/DC-link reactor etc.
103IR-checking of generator busduct LCI excitation & accessories.IR-checking of generator busduct LCI excitation & accessories.
104Trouble-shooting and maintenance of control circuit and any equipment Generator and accessories.Trouble-shooting and maintenance of control circuit and any equipment Generator and accessories.
105Routine checking of LCI Excitation PPT-fan & cooling system of BAC-compartment.Routine checking of LCI Excitation PPT-fan & cooling system of BAC-compartment.
106Generator line-up for air/Co2/hydrogen filling.Generator line-up for air/Co2/hydrogen filling.
107Replacement of carbon brush/brush holder/hydrogen regulator etc.Replacement of carbon brush/brush holder/hydrogen regulator etc.
108Removal of flexible links star point bus-bar and NGR connections of generator.Removal of flexible links star point bus-bar and NGR connections of generator.
109Testing arrangement including assistance required for testing of generator busduct & accessories.Testing arrangement including assistance required for testing of generator busduct & accessories.
110Replacement of generator neutral connection protection CT/LA/flexible c links/NGR/PHE (LCI) etc.Replacement of generator neutral connection protection CT/LA/flexible c links/NGR/PHE (LCI) etc.
111Testing arrangement including assistance required during testing & calibrationTesting arrangement including assistance required during testing & calibration
112Trouble-shooting and maintenance of relay/cards/meters/transducers/ABT-system/CT/PT etc.Trouble-shooting and maintenance of relay/cards/meters/transducers/ABT-system/CT/PT etc.
113Replacement and modification of relay/cards/meters/transducers/ABT-system/CT/PT etc.Replacement and modification of relay/cards/meters/transducers/ABT-system/CT/PT etc.
114PM of lead acid type complete battery bank (rating from 125 Volts to 250 Volts/300 Ah to 1700 Ah).PM of lead acid type complete battery bank (rating from 125 Volts to 250 Volts/300 Ah to 1700 Ah).
115Preventive maintenance of all type battery charger/distribuation panel (DC/AC).Preventive maintenance of all type battery charger/distribuation panel (DC/AC).
116Trouble-shooting and maintenance of battery charger/battery bank/distribution panel (DC/AC).Trouble-shooting and maintenance of battery charger/battery bank/distribution panel (DC/AC).
117Routine checking of all type battery banks and chargers.Routine checking of all type battery banks and chargers.
118Lead acid battery bank replacementcommissioning &testingrating 125 V to250 V/300 Ah to1700 Ah.Lead acid battery bank replacementcommissioning &testingrating 125 V to250 V/300 Ah to1700 Ah.
119ONE cell replacementcommissioning & testing of LA battery bank (125 V to250 V /300 Ah to 1700 Ah)ONE cell replacementcommissioning & testing of LA battery bank (125 V to250 V /300 Ah to 1700 Ah)
120Replacementcommissioning & testing of battery charger incl. loading unloading & transportation.Replacementcommissioning & testing of battery charger incl. loading unloading & transportation.
121Discharge test of all type complete battery bank of rating upto 250 Volts/1700 Ah).Discharge test of all type complete battery bank of rating upto 250 Volts/1700 Ah).
122Shifting of scrap battery/acid can min.10 nos ACID can of 40 ltrs/20 nos VRLA//Alkaline batteriesShifting of scrap battery/acid can min.10 nos ACID can of 40 ltrs/20 nos VRLA//Alkaline batteries
123Assistance/support services required during inspection testing and maintenance of equipmentsAssistance/support services required during inspection testing and maintenance of equipments
124PM of complete electrical system of EOT/gantry crane capacity rating upto 100 tons.PM of complete electrical system of EOT/gantry crane capacity rating upto 100 tons.
125Preventive maintenance of complete electric hoist's unit capacity rating 2X35 tons.Preventive maintenance of complete electric hoist's unit capacity rating 2X35 tons.
126Troubleshooting and maint. of electrical system of EOT/gantry crane electric hoist's & stack-lift.Troubleshooting and maint. of electrical system of EOT/gantry crane electric hoist's & stack-lift.
127Maintenance & repairing/replacement of control panel/resistance box/control transformer/motor etc.Maintenance & repairing/replacement of control panel/resistance box/control transformer/motor etc.
128Arrangement including assistance required for load testing of electric hoist's unit (35 tons)Arrangement including assistance required for load testing of electric hoist's unit (35 tons)
129Trouble-shooting and maintenance of overhead distribution lines.Trouble-shooting and maintenance of overhead distribution lines.
130Replacement of all type insulators/clamps/L.A. etc of overhead distribution lines.Replacement of all type insulators/clamps/L.A. etc of overhead distribution lines.
131Replacement/new installation of complete kiosk panel/G.O.D/fuse assembly etc of OH lines.Replacement/new installation of complete kiosk panel/G.O.D/fuse assembly etc of OH lines.
132Removing/laying of conductor earth wire guard wire etc of overhead distribution lines.Removing/laying of conductor earth wire guard wire etc of overhead distribution lines.
133Temporary laying/removing of all type cables including shifting cable size upto 50 sq.mm.Temporary laying/removing of all type cables including shifting cable size upto 50 sq.mm.
134Temporary laying/removing of all type cables including shifting cable size above 50 to 120 sq.mm.Temporary laying/removing of all type cables including shifting cable size above 50 to 120 sq.mm.
135Permanent Laying of cables on cable tray wall & structure etc.cable size upto 50 sq.mm.Permanent Laying of cables on cable tray wall & structure etc.cable size upto 50 sq.mm.
136Permanent Laying of cables on cable tray wall & structure etc.cable size above 50 to 120 sq.mm.Permanent Laying of cables on cable tray wall & structure etc.cable size above 50 to 120 sq.mm.
137Permanent Laying of single core cables on cable traywall & structure etc.size > 120 to <240 sqmmPermanent Laying of single core cables on cable traywall & structure etc.size > 120 to <240 sqmm
138Permanent Laying of single core cables on cable tray wall & structure etc.cable size > 240 sq.mm.Permanent Laying of single core cables on cable tray wall & structure etc.cable size > 240 sq.mm.
139Permanent Laying of 3/4 cores cables on cable tray wall & structure etc.size > 120 to <240 sqmmPermanent Laying of 3/4 cores cables on cable tray wall & structure etc.size > 120 to <240 sqmm
140Permanent Laying of 3/4 cores cables on cable tray wall & structure etc. size above 240 sqmmPermanent Laying of 3/4 cores cables on cable tray wall & structure etc. size above 240 sqmm
141One end lugging/jointing of all type LT-cables (all cores) cable size upto 50 sq.mm.One end lugging/jointing of all type LT-cables (all cores) cable size upto 50 sq.mm.
142One end lugging/jointing of all type LT-cables (all cores) cable size above 50 to 120 sq.mm.One end lugging/jointing of all type LT-cables (all cores) cable size above 50 to 120 sq.mm.
143One end lugging/jointing of all type LT-cables (all cores) cable size above 120 sq.mm.One end lugging/jointing of all type LT-cables (all cores) cable size above 120 sq.mm.
144Single core heat shrinkable cables termination/through jointing of cables size upto 120 sq.mm.Single core heat shrinkable cables termination/through jointing of cables size upto 120 sq.mm.
145Single core heat shrinkable cables termination/through jointing of cablessize above 120 to240 sqmmSingle core heat shrinkable cables termination/through jointing of cablessize above 120 to240 sqmm
146Single core heat shrinkable cables termination/straight through jointing of cables above 240 sqmmSingle core heat shrinkable cables termination/straight through jointing of cables above 240 sqmm
147Outer insulation repairing of cables from heat shrinkable tubing/sleeves (1mtr Length).Outer insulation repairing of cables from heat shrinkable tubing/sleeves (1mtr Length).
148Laying/removing/repairing of cable tray( above 0.5 ft x 2.0 ft) /conduit pipe(above dia:3 Inch)Laying/removing/repairing of cable tray( above 0.5 ft x 2.0 ft) /conduit pipe(above dia:3 Inch)
149Laying/removing/repairing of cable tray( upto 0.5 ft x 2.0 ft)/conduit pipe(upto 3.0 inch dia.)Laying/removing/repairing of cable tray( upto 0.5 ft x 2.0 ft)/conduit pipe(upto 3.0 inch dia.)
150Earthing strip laying or removing including drilling welding jointing cutting etc.Earthing strip laying or removing including drilling welding jointing cutting etc.
151Preventive maintenance of all type lighting transformers/lighting distribution panels.Preventive maintenance of all type lighting transformers/lighting distribution panels.
152Maintenance/replacement of industrial pole lighting fixture upto 30 feets heightMaintenance/replacement of industrial pole lighting fixture upto 30 feets height
153Maintenance/replacement of all type industrial lighting fixture.Maintenance/replacement of all type industrial lighting fixture.
154Maintenance/replacement/servicing of all type cooling fans/exhaust fan etc.Maintenance/replacement/servicing of all type cooling fans/exhaust fan etc.
155Maintenance/replacement of high mast/HRSG-stacks aviation lighting fixture.Maintenance/replacement of high mast/HRSG-stacks aviation lighting fixture.
156Trouble-shooting and maintenance of all type lighting/cooling fans/lighting transformers etc.Trouble-shooting and maintenance of all type lighting/cooling fans/lighting transformers etc.
157Replacement/new erection & commissioning of lighting pole with all accessoriesheight upto 15 fts.Replacement/new erection & commissioning of lighting pole with all accessoriesheight upto 15 fts.
158Replacement/new erection & commissioning of lighting pole with pole height above 15 to 30 feets.Replacement/new erection & commissioning of lighting pole with pole height above 15 to 30 feets.
159Maintenance/replacement of lighting pole junction box/SDFU/DOL-starter etc.Maintenance/replacement of lighting pole junction box/SDFU/DOL-starter etc.
160Maintenance/replacement of all type MCB/RCCB/ELCB/timer etc.Maintenance/replacement of all type MCB/RCCB/ELCB/timer etc.
161Maintenance/replacement of domestic lighting system/electrical appliancesMaintenance/replacement of domestic lighting system/electrical appliances
162Revival of one room complete lighting system of any buildings in plant & BOP area.Revival of one room complete lighting system of any buildings in plant & BOP area.
163Arrangement of temporary lights/cooling fans/cable connections etc.Arrangement of temporary lights/cooling fans/cable connections etc.
164Overhauling of ceiling fans/table fans/exhaust fans/geyser etc.Overhauling of ceiling fans/table fans/exhaust fans/geyser etc.
165Preventive maintenance of electrical system of all type skids.Preventive maintenance of electrical system of all type skids.
166IR-checking of all type skids.IR-checking of all type skids.
167Trouble-shooting and maintenance of electrical system of all type skids.Trouble-shooting and maintenance of electrical system of all type skids.
168Installation & commissioning of any type complete skid anywhere within the plant area.Installation & commissioning of any type complete skid anywhere within the plant area.
169Preventive maintenance of electrical system of EDG/fire pump.Preventive maintenance of electrical system of EDG/fire pump.
170Trouble-shooting and maintenance of electrical system of EDG/fire pump.Trouble-shooting and maintenance of electrical system of EDG/fire pump.
171Replacement of DC-starter/control module of EDG/fire pump.Replacement of DC-starter/control module of EDG/fire pump.
172New fabrication and erection works of mild steel supporting structure or frame at RGPPL-site.New fabrication and erection works of mild steel supporting structure or frame at RGPPL-site.
173Providing welder on day basis as per work specifications.Providing welder on day basis as per work specifications.
174Erection and dismantling of scaffolding as per work specifications.Erection and dismantling of scaffolding as per work specifications.
175Tarpaulin and polythene sheet covering before monsoon season/removing after monsoon season.Tarpaulin and polythene sheet covering before monsoon season/removing after monsoon season.
176Shifting of any material from one location to other location in the plant area upto 250 kg weight.Shifting of any material from one location to other location in the plant area upto 250 kg weight.
177Shifting of any material from one location to other location in the plant area >250 kg to < 500kgShifting of any material from one location to other location in the plant area >250 kg to < 500kg
178Shifting of any material from one location to other location in the plant area >500 kg to <750 kgShifting of any material from one location to other location in the plant area >500 kg to <750 kg
179Shifting of any material from one location to other location in the plant area >750 kg to <1500 kgShifting of any material from one location to other location in the plant area >750 kg to <1500 kg
180Shifting/relocation of any material from inside the power block from EOT cranes above 1.0 tonShifting/relocation of any material from inside the power block from EOT cranes above 1.0 ton
181Oil drum (210 ltr)shifting from one location to other location in the plant area.Oil drum (210 ltr)shifting from one location to other location in the plant area.
182Shift electrical maintenance activities in power block & BOP area as per scope of workShift electrical maintenance activities in power block & BOP area as per scope of work
183Operation service of mobile hydraulic industrial vehicles/cranes as per scope of work.Operation service of mobile hydraulic industrial vehicles/cranes as per scope of work.
184Providing skilled workers on day basis as per scope of work.Providing skilled workers on day basis as per scope of work.
185Store keeper in electrical lab/store as per scope of work.Store keeper in electrical lab/store as per scope of work.
186Providing semiskilled workers on day basis as per scope of work.Providing semiskilled workers on day basis as per scope of work.
187Shift electrical maintenance activities in township area (three shifts per day) as per scope of workShift electrical maintenance activities in township area (three shifts per day) as per scope of work

Other Detail

Information Source https://gem.gov.in/
Download FileName File Description File Size
Download 8611b2c8-3807-4b4a-ab72-282f3b39a876.pdf Tender Documents 0 KB
Download 1778927836.xlsx Tender Documents 0 KB
Download 1779448333.pdf Tender Documents 0 KB
Download 1779448352.pdf Tender Documents 0 KB
Disclaimer :
We takes all possible care for accurate & authentic tender information, however Users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender.